What Happens At A Pre-Construction Meeting? — Transcript
Full transcript
- 0:00What happens at a pre construction meeting? Well, what happens actually is if you start doing these,
- 0:05you'll start installing work right the first time and who doesn't want that? So stay with
- 0:10us for this cool outline.
- 0:22So what is the process for a good pre construction meeting? How do you
- 0:26make it not boring? What key step will make this meeting remarkable? Well, first, let's talk about
- 0:31the order. So we do not look at construction as individual tools. So like if you said, Hey, I am
- 0:38a Project Engineer or superintendent, whatever the position is, and hey, I do RFIs or you know,
- 0:44somebody's like, Hey, mister, missus, Project Engineer. What do you do? Well, I read our files,
- 0:49I review submittals. You know, I do subcontractor pay application approvals, right? So it's not
- 0:55wrong, was not right. You do, you are not a tool, doer or user, your job. And I want you to hear me
- 1:03on this because this is remarkable. Okay, so I'm excited that like your job is to oversee scopes of
- 1:09work, and support our trade partners. So they can plan build, finish, plan, build finish. So that
- 1:16means that we're going to go through a process. And it just so happens that the pre construction
- 1:21meeting is a key part of that process. So when you have bought out a trade partner, then you
- 1:28have what's called a pre mobilization meeting. That's where you ask for the requirements,
- 1:33the list the submittals, everything that they need, and you tell them the start date, and you
- 1:37schedule your pre construction meeting, your pre construction meeting is to gather the information,
- 1:41hold the meeting, and educate and align with the superintendent in the format and to leave with a
- 1:47visual that you can use to install quality in the field, then you can do your initial inspection,
- 1:52follow up inspections, and then your final and do your zone control walks based on those
- 1:58quality expectations. I will link you to the other video in this series that talks about the overall
- 2:04process and the concept of quality. But right now we're zoning in on the pre construction meeting
- 2:09itself. So step number one, you're going to gather the document and these are the requirements
- 2:15at a minimum. In the pre construction meeting, you're going to have the updated set of plans,
- 2:19the updated set of specs, and those two need to be highlighted by either you or the trade partner,
- 2:27superintendent and foreman or both. And I will say that these meetings you don't just show up
- 2:31to him. I remember when I was younger, and I was a assistant superintendent and Hensel Phelps,
- 2:37they did a little training and study that said, it typically takes about a day and a half to prepare
- 2:42for a really good pre construction meeting. So somebody is going to have to come having read
- 2:47these and highlighted exactly what we're going to be discussing in the meetings. So come with
- 2:53the right information. The other thing is, you will want by this time the approved submittals
- 2:58you better or else you're not going to have the materials on time. So you will want to
- 3:02review that write. Any other pertinent information that's required for the work, maybe installation
- 3:09instructions, you're going to collect like I said before, the safety manual and plan for the trade
- 3:15partner, you're going to collect the quality manual, you're going to collect any emergency
- 3:20contacts, any training certificates. Anything that you and your company require, we want that
- 3:25collected and put together in one common location so that you can review it in the meeting. That's
- 3:31step one. Step number two, if you have the plans and specs highlighted already, not a big deal,
- 3:36you can simply go through the highlights. But if you haven't, do not let the meeting proceed
- 3:42unless you've read the plans and specs that specifically goes to the superintendent and
- 3:46the foreman. So what I mean by this is you can either ask them to do it right then and there or
- 3:52you can because you've scheduled the meeting three weeks ahead of the work, say, hey, we need to do
- 3:57a little bit more prep. Let's cancel today and let's schedule this meeting in a week. That way,
- 4:03you can be sure that you've done the amount of prep required, so we can have a great meeting.
- 4:07So that way, if I schedule it three weeks in advance, I still have my two week backup and
- 4:12then if they still don't come prepared, I'm just gonna have to take the 15 minutes and study the
- 4:16plans and specs and get a mental frame, a mental context of the work that we're about to discuss,
- 4:22because here's the issue. Here's the method. And I want to make this clear, you are going
- 4:26through the requirements for the owner, and for the authority having jurisdiction as outlined in
- 4:32the plans and specs and you're going to find all of the major issues that could happen and you're
- 4:37going to discuss what you'll do about it and solve the problem by making sure that expectations are
- 4:44clear on your quality checklist or your quality feature of work bored, which I'll talk about in
- 4:49a minute. Step number three, if the owner is there, then you will ask what is super important to you
- 4:55about this work and they'll be like yeah, just so the plans and specs No, no, we're talking about
- 4:59flooring What is the biggest thing that you all deal with? What is the biggest thing your
- 5:03maintenance team has to deal with? What is your biggest frustration with your other buildings? Oh,
- 5:07I can tell you that, okay, it's when.... and you get them talking. And then those requirements,
- 5:12go into those checklists, or that visual feature of workforce. So that's key. Step number three,
- 5:18ask your owner what they want. Step number four, you're going to start to discuss some details
- 5:23here. So by this point, you should have not only the master schedule, but the actual work as shown
- 5:29in a pull plan as a part of the detailed sequence. And you should be able to pull up your zone maps,
- 5:34your logistics drawings, and any other pertinent information for how you're going to install this,
- 5:39even the model and basically go through how are we going to install it. So it's not just
- 5:44what does a good install look like? But what is a good sequence of install look like? Right? Like,
- 5:49for instance, if you're doing an exterior curtain wall, or you're doing cladding or something that's
- 5:53super crucial. The sequence of installation when you're talking about waterproofing, and flashing
- 5:59and cure times, is pretty darn important. So that's why in these meetings, we have to talk
- 6:03about those key items. How are you going to build it, enable the team to visualize that? So they can
- 6:08say, oh, no, before this flashing goes on, I need to... right? And then you're like, Oh,
- 6:13if we hadn't talked about the sequence, we wouldn't have gotten it right. So go through
- 6:17that overall plan. By the time that happens, you've read the plans. You've read the specs,
- 6:21you've asked what everybody wants, you know, previous pitfalls. Actually, some of the best
- 6:25companies that do this the best is they'll have historical documents checklist from before, say,
- 6:31hey, here, the normal pitfalls, right? Now you've gone through the actual sequence in the plan, how
- 6:36the builders are going to install it, you should now have a list of issues. So in your meeting,
- 6:41you're going to list these out, right? What are my issues and so every time an issue comes up
- 6:45that project manager or project engineer, write it on the board, oh, there's an issue, write it up,
- 6:49just fanatically like, so now you've got a list of issues, this is great. These are things that
- 6:55could possibly happen, and we're finding them before the work takes place. So now you do what
- 7:00Gina Whitman says in the book, traction, you IDS, identify, discuss and solve. Identify, discuss and
- 7:06solve. So once you discuss it in the meeting with the experts, now you have a solution. Where does
- 7:11that solution go? I guess we just not- No, no, no, no, this was the best part, your checklist
- 7:15or your visual, those solutions go on that for the crew to use later. That's the genius part.
- 7:22If I was doing well, actually, we are starting a construction company. And so in our company,
- 7:27we will have live Canva files with all of these visual quality checklists on them with pictures.
- 7:34And so as we're going through the meeting, I'll just pull the picture, put it right on there. Oh,
- 7:39there's another item type in and so this document is auto format it, well, we're manually putting it
- 7:44in, but it's formatting as we go. So that by the time we're done with the meeting,
- 7:48it's like Nope, that's what we're doing like this right here. And so also the in
- 7:53reference to this is what we're doing right here. Like these videos, this what you and I are doing,
- 7:57this is what we're doing right now, please like and subscribe to this video, like right now real
- 8:01time so that we can do this thing right here all the time together. So before we move on,
- 8:05I want to explain what a quality feature of workboard actually is. So imagine 11 by 17 paper,
- 8:11and it has the title of the feature of work that you're discussing, okay, and then on the actual
- 8:18sheet, and your company can format it however you want. On the actual sheet, it says okay,
- 8:23this is the goal of this installation. This is the how to steps for the installation. Here are
- 8:32pictures right here on this visual, showing what success looks like. Here are some key pitfalls,
- 8:39things that you do not do things to look out for. And you can add other content onto it. But don't
- 8:45have too many words, make it impactful. Bring out the stuff that people don't already know.
- 8:51And make it as visual as you possibly can. So what I'm saying is with these 11 by 17 documents, or
- 8:57you can make them eight and a half by 11, whatever you want, whenever you identify, discuss and solve
- 9:01a potential issue that can happen to the quality install, that solution goes on to that checklist
- 9:07or that visual, now, because it's being done real time. Now the crew will have it with crystal clear
- 9:14expectations. And so the genius of this meeting is that at the end, you've IDS, identified, discussed
- 9:20and solved all the issues, the solutions are now documented. Now the foremen and the crew can use
- 9:26it. Now all you have to do like we said in another video is actually use the visual in the field and
- 9:32inspect the work with the visual. That's all you have to do. It's amazing. And you can do that as
- 9:37a part of your zone control walks, in fact, on some projects and clients that we work with,
- 9:42they have a packet of these things or a link to all of them when the super is going around doing
- 9:46his or her zone control walks and saying hey, Mr., Mrs. Foreman, Hey, how are you doing? They
- 9:52can just pull it up right on their iPad, boom, like right there or their checklist or they have
- 9:56it on a little ring laminated in the field. Hey, let's look at yep, yep, yep. Okay, and finish the
- 10:02work as you go. This is remarkable. This is the way quality should have always been designed. And
- 10:07if you do it according to this process, you will install a quality product. And so when the foreman
- 10:12and supers leave, again, like I've said before, you say, hey, if I do this, will you be happy? Yeah,
- 10:18I'll be happy. Okay, well, I'm gonna go do this. expectations are clear and other foremen and the
- 10:23crew are committed to delivering it. And so the key to this whole step is the pre construction
- 10:28meeting was a waste of time. If you don't have an output, and if you don't use the darn thing. So
- 10:33once we have the darn thing, the expectations, use it in the field, inspect according to it,
- 10:39and deliver the product according to those expectations. That is the key. And so it's really
- 10:44a process. We don't run projects through guessing, we run them through standard processes. Remember,
- 10:49plan, build, finish. Plan that scope of work, build it right with that pre construction meeting
- 10:55and those visuals right, and then finish the work before you leave by inspecting it,
- 11:00this is how it's done in the description below. I'm going to link you to the quality process in
- 11:07a beautiful outline that I love to use myself that really really matters on project sites
- 11:13and delivers the results you want. So please go grab that document. You're going to love
- 11:18it and I think you'll find it simple enough to where you can start doing it tomorrow. On we go.
About this transcript
This page contains the full transcript of What Happens At A Pre-Construction Meeting? by Jason Schroeder, generated from the public captions YouTube serves with the video. The transcript has 2,222 words across 127 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.
What you can do with it
Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.
Free YouTube transcript tool
YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, caption language selection, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.