THE EDISON - A Modular Construction Time-lapse Film — Transcript

by Sam Forencich · 1,209 words · 173 segments · language en · Watch on YouTube

Full transcript

  1. 0:07I'm Nathan young owner of Maude's PDX
  2. 0:11Inc modular manufacturer and
  3. 0:14organ we
  4. 0:15finished the Edison the Edison is a
  5. 0:18building that we developed in a modular
  6. 0:20format to go in st. John's Oregon the
  7. 0:22concept of being modular was one that we
  8. 0:25knew we were gonna do from the very very
  9. 0:27beginning of the project and it was it's
  10. 0:30the only way we want to be building as
  11. 0:31we move forward the benefit of building
  12. 0:34modular is also that it's a circle
  13. 0:35environment so instead of standard
  14. 0:37construction that's very linear where
  15. 0:39you have to pour the foundation and then
  16. 0:40you frame it and then you do the next
  17. 0:42component we're actually working in
  18. 0:44tandem so you can see that the site is
  19. 0:46being constructed and the Foundation's
  20. 0:48going in at the same time that we're
  21. 0:49building the building in the factory so
  22. 0:51that the dynamics of having two
  23. 0:53different locations going at the same
  24. 0:54time really allows for us to have a
  25. 0:56speed that you can't get in a standard
  26. 0:59construction so in the factory we have
  27. 1:02several different framing stations where
  28. 1:04we frame up the walls in a certain area
  29. 1:06and utilize our overhead cranes so we
  30. 1:08have two different build sections where
  31. 1:09we're building the products away from
  32. 1:12where the floors actually are and then
  33. 1:13bringing them into position and so
  34. 1:15everything's getting framed up on
  35. 1:16framing tables and then we use overhead
  36. 1:19cranes and forklifts and move them
  37. 1:20around
  38. 1:21in the factory environment we work as a
  39. 1:24team so we don't have sub mentality
  40. 1:26where we'd have a guy that's coming in
  41. 1:28to work he's coming in to be part of a
  42. 1:31team which means anything that anybody
  43. 1:32can do in front of him
  44. 1:34they're gonna try to do to help
  45. 1:35facilitate his process the other benefit
  46. 1:39of working in doors is were not
  47. 1:41constrained by weather so if there's a
  48. 1:43really rainy day we're not going to be
  49. 1:45stopped in the factory we might be
  50. 1:46stopped on site but we're able to keep
  51. 1:48the production level moving even if it's
  52. 1:51snowing it doesn't snow inside the
  53. 1:52facility the modulars are finished to
  54. 1:56about 85 to 90 percent so the exterior
  55. 1:59we've got all the windows set the
  56. 2:01windows are trimmed the interiors are
  57. 2:03finished to about 90% so the hardwood
  58. 2:06floors are in the cabinets are in
  59. 2:07countertops are in everything Venom the
  60. 2:10appliances are actually in the units but
  61. 2:12they're still in the boxes so that we
  62. 2:14can get them installed which is a really
  63. 2:16nice deal on a second floor or any
  64. 2:18elevated structure because then you're
  65. 2:19not moving your appliances up the stairs
  66. 2:21so we try to get everything put into the
  67. 2:23boxes when they leave that you're gonna
  68. 2:25need to finish them up with the Edison
  69. 2:28we were very fortunate because we
  70. 2:29actually developed that project within
  71. 2:32about five miles of our site so as we
  72. 2:34started to look at transporting the mods
  73. 2:36we had very limited distance to travel
  74. 2:39but even in that limited distance that
  75. 2:42we had to travel we still had to
  76. 2:43navigate all the roads because the boxes
  77. 2:45are 15 foot 6 by 6 to 9 foot 2
  78. 2:48by 11 feet tall and they sit up on a
  79. 2:51trailer that makes them about 14 feet
  80. 2:53tall which is your max height so as
  81. 2:56we're moving them down the road we have
  82. 2:58to have a number of pilot cars that run
  83. 3:01in front and close down all the streets
  84. 3:03so that you're coming through an
  85. 3:05intersection because the boxes are so
  86. 3:07big you're taking up both lanes as you
  87. 3:10as you make your transportation routes
  88. 3:12you have to make sure that you can
  89. 3:13navigate all the corners and be able to
  90. 3:15get around a corner and that there's no
  91. 3:17cars parked there so there's quite a bit
  92. 3:19of work that goes into into prepping
  93. 3:21that that day but it's also kind of the
  94. 3:23culmination of the whole the whole
  95. 3:25project when you get to move the boxes
  96. 3:27it's pretty exciting because you're
  97. 3:28moving 50 plus thousand-pound boxes down
  98. 3:31the road that are 70 feet long and
  99. 3:33people are a little amazed at seeing
  100. 3:35that transportation process happen so
  101. 3:40the big day of the set we've got all the
  102. 3:42boxes moved the night before the cranes
  103. 3:44getting into position and then we'll
  104. 3:47have a number of guys there that are
  105. 3:49doing different jobs whether they're
  106. 3:51doing what's called rigging so they're
  107. 3:52setting up all the rigging that's gonna
  108. 3:54actually sling the boxes into position
  109. 3:56on the Edison we actually had to spin
  110. 3:58the boxes in the air to get around a
  111. 4:00tree to bring them in because of the way
  112. 4:02we had to position them on the street so
  113. 4:05then there's there's guys that are doing
  114. 4:06the setting which are then positioned in
  115. 4:09the building right down onto the
  116. 4:10foundation and making sure that it's on
  117. 4:12the lines where it needs to go and then
  118. 4:14the next box is going to fit and we've
  119. 4:15got all the right connections done
  120. 4:19when you're running the crane the crane
  121. 4:22is fairly expensive so you want to make
  122. 4:24sure that everything's moving as quick
  123. 4:25as possible and so you have to have a
  124. 4:27well a well tuned group of people that
  125. 4:30have worked together we've worked with
  126. 4:31pj event level for a number of years
  127. 4:34setting the number of modulars and so
  128. 4:36all of our guys are very accustomed to
  129. 4:37what needs to happen and his guys are
  130. 4:39very very well trained which is very
  131. 4:42important when you're spending a fifty
  132. 4:44thousand plus pound box above your head
  133. 4:46and landing it within a quarter inch of
  134. 4:48where it needs to go and so you have to
  135. 4:51have good crane operators and everybody
  136. 4:52has to have very good communication
  137. 4:54skills once the Edison is set we had
  138. 5:01designed the Edison so that it would
  139. 5:02have a standard roof on it because one
  140. 5:05of the limitations with modular is
  141. 5:06height than transportation so you can't
  142. 5:08get a super tall roof so we designed the
  143. 5:11Edison to be fairly Craftsman type
  144. 5:16hipped roof and
  145. 5:18good overhangs on it we start to add the
  146. 5:20roof to it and bring the character of
  147. 5:22the finished product together you start
  148. 5:24to see the building take shape and it's
  149. 5:26no longer quite so boxy but that's done
  150. 5:29with with good design work and good
  151. 5:32attention to detail on-site the Edison
  152. 5:36is an is an interesting building because
  153. 5:38we wanted to help shift the paradigm a
  154. 5:40modular a lot of people think of modular
  155. 5:42as being something of a lesser
  156. 5:43construction techniques or lower quality
  157. 5:46materials the Edison has solid surface
  158. 5:49countertops quartz countertops real
  159. 5:50hardwood floors the building is built to
  160. 5:54essentially a passive house standard so
  161. 5:56it's very well constructed and we
  162. 5:58control air movement and minimize energy
  163. 6:01loads so the building will run 70% less
  164. 6:04energy than code which means over the
  165. 6:06long haul of the building the carbon
  166. 6:08footprint is significantly less which is
  167. 6:10another benefit of modular construction
  168. 6:12you have a lot less waste so if we can
  169. 6:14incorporate that less waste in the
  170. 6:16building process and then higher energy
  171. 6:20efficiencies we can essentially build a
  172. 6:22better product over and over again
  173. 6:23[Music]

About this transcript

This page contains the full transcript of THE EDISON - A Modular Construction Time-lapse Film by Sam Forencich, generated from the public captions YouTube serves with the video. The transcript has 1,209 words across 173 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.

Free YouTube transcript tool

YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, caption language selection, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.