Resiliency in Construction: Better Materials & Methods for High Performance — Transcript

by Matt Risinger · 11,935 words · 1,824 segments · language en · Watch on YouTube

Full transcript

  1. 0:00All
  2. 0:05>> [music]
  3. 0:07>> right, my friends. Welcome back to
  4. 0:09another episode of the Build Show
  5. 0:13webinar. That's right. This is our time
  6. 0:15to get together and go deep on a
  7. 0:17particular topic. And we are talking
  8. 0:19today about resiliency. And I'm going to
  9. 0:22show you a wall concept that I bet
  10. 0:24you've never seen before. I met these
  11. 0:26guys at the International Builder Show
  12. 0:28and it was a display very similar to
  13. 0:31this that I kind of ran across and I met
  14. 0:34Todd, the founder and the COO of this
  15. 0:36company and Todd and I immediately hit
  16. 0:39it off. I fired off a hundred questions
  17. 0:41that he answered right away and I was
  18. 0:44like, man, this is really, really
  19. 0:46compelling, especially with this theme
  20. 0:48that we're talking about today, disaster
  21. 0:50resilience. So Todd Wright, founder and
  22. 0:52CEO. I've also got with me uh Kyle
  23. 0:56Hintan. Hintley.
  24. 0:57>> Yeah, you said it right. It's a tough
  25. 0:59one, but he's our sales guy. He's going
  26. 1:01to help you out in the future when
  27. 1:02you've got some sales uh that you want
  28. 1:04to talk to these guys about.
  29. 1:06>> But on this theme of resilience that
  30. 1:08we're talking about today, this is a
  31. 1:09really big deal nationally for us, Todd.
  32. 1:12And it's a big deal because of this
  33. 1:14slide right here. I mean, this stuff is
  34. 1:16happening and is in the news all over
  35. 1:18the place, isn't it?
  36. 1:19>> Yeah, it is. I mean from California to
  37. 1:21Florida, we've had Palisade fires, we
  38. 1:24have hurricanes constantly um in Florida
  39. 1:27and also here in Texas. So, you know,
  40. 1:30we're just plagued with uh all kinds of
  41. 1:32issues from mother nature all across the
  42. 1:35country, earthquakes, fires, hurricanes,
  43. 1:38etc.
  44. 1:39>> For sure. And if you look at this mockup
  45. 1:41wall that we put up here, that is what I
  46. 1:43would consider traditional framing. I
  47. 1:45mean, this is how we've been building in
  48. 1:46America for hundreds of years. is maybe
  49. 1:49not with 2x4s for hundreds of years, but
  50. 1:51with wood construction since our log
  51. 1:53cabin days.
  52. 1:54>> My [clears throat] cousin owns a 250y
  53. 1:56old log cabin. By the way,
  54. 1:57>> wow, that's But you know, we've been
  55. 1:59building with wood for a long time. And
  56. 2:01wood is great
  57. 2:02>> except for when it isn't. Except for
  58. 2:04when there's a fire or except for when
  59. 2:06you've got some mold issues or mold size
  60. 2:08of clients or except for when the
  61. 2:09termites come uh for that house. So,
  62. 2:13with that being said, Todd, uh let's
  63. 2:15actually show these guys, jump right
  64. 2:17into the mockup because what you guys
  65. 2:19have done is very different uh than what
  66. 2:24most people think of. And actually, I'm
  67. 2:25going to hang on one sec. One quick sec.
  68. 2:27Will you guys meet me over at the uh at
  69. 2:29the display here? Sure. Cuz I want to I
  70. 2:30want to start with this demo of how your
  71. 2:34system holds up against uh fire in
  72. 2:38particular. So, let's actually roll this
  73. 2:40video as we're coming out here.
  74. 2:41>> Yeah. So, what are we looking at on this
  75. 2:43video, Tob?
  76. 2:45>> So, this is a fire test that we did last
  77. 2:47week uh at our uh location in Florida.
  78. 2:51>> We essentially took a frame pretty close
  79. 2:53to this one right here. We wrapped it in
  80. 2:56MGO inside outside full credo system and
  81. 3:00then uh we put about 10 pallets inside
  82. 3:03and outside around the around the
  83. 3:05building
  84. 3:05>> and you could see the fire burning
  85. 3:07raging fire inside and outside on your
  86. 3:09wall assembly, isn't it? It was was
  87. 3:11actually pretty hot. We were a little
  88. 3:12over 100° that day and uh the fire uh
  89. 3:15got to about 1100°.
  90. 3:17>> Oh my gosh.
  91. 3:18>> And um we let it run for about an hour
  92. 3:20and and then we put it out. But uh
  93. 3:22>> and then part two of this video that
  94. 3:24we're playing now is after how long this
  95. 3:26video is playing?
  96. 3:27>> Uh this is about I think 48
  97. 3:32maybe 48 to 55 minutes or so.
  98. 3:34>> Okay. So about an hour later.
  99. 3:36>> Yeah.
  100. 3:36>> Yeah. We're ready to do some barbecue in
  101. 3:38there. Don't you think? It looks like
  102. 3:39you're ashed over, but it looks to me
  103. 3:41like your wall is also solid still. I'm
  104. 3:43just still standing.
  105. 3:44>> Yeah. Yeah, it is. Um, you see that back
  106. 3:47wall inside, you know, that was engulfed
  107. 3:49with flames.
  108. 3:50>> Mhm.
  109. 3:50>> And um unlike a typical fire, we've got
  110. 3:53flames on the inside and the outside of
  111. 3:55the building simultaneously. So, we
  112. 3:57really, you know, we're putting it to
  113. 3:58the test.
  114. 3:59>> Yeah, you were big time.
  115. 4:00>> Yeah. So, that particular uh
  116. 4:02configuration has a 12-in webbased floor
  117. 4:06system.
  118. 4:07>> Okay. made of cold form steel. It has an
  119. 4:09MGO uh subflooring. It has half inch MGO
  120. 4:13on the inside and then it has the MX7
  121. 4:16board on the outside of the building.
  122. 4:18>> Okay. So, now that you've seen that
  123. 4:20demo, let's show you a very similar
  124. 4:22mockup to exactly what you saw in that
  125. 4:24fire test a second ago. And and just for
  126. 4:27the uh the understanding of some of the
  127. 4:29logos and such, let me let me explain to
  128. 4:31you real quick. Uh their company is
  129. 4:33called Performance Building Solutions,
  130. 4:35right? So when you look at their
  131. 4:36website, performancebuilding solutions,
  132. 4:38but Kratos build and the Kratos wall is
  133. 4:41what exactly, Todd?
  134. 4:42>> Yeah. So it's really our building
  135. 4:44system. U we branded the product
  136. 4:47separate from the company, right? So
  137. 4:49>> um the Kratos wall is what we're looking
  138. 4:52at here, which is your exterior wall.
  139. 4:54>> So when I look at this, I think this
  140. 4:56looks like a lot like a commercial
  141. 4:58building to me, right? We
  142. 4:59[clears throat] we're building with
  143. 5:00platform uh concrete platforms and then
  144. 5:03we've got infill between the red iron.
  145. 5:05This is what I would see. Steel studs.
  146. 5:07>> Exactly.
  147. 5:08>> And something that's fireproof on the
  148. 5:09outside.
  149. 5:10>> Exactly. That's what we've done. We're
  150. 5:11essentially taking commercial grade
  151. 5:13construction, best of breed materials,
  152. 5:16and then bringing that to the
  153. 5:17residential market,
  154. 5:19>> but doing it in a way where we're doing
  155. 5:20it in a factory, right, which is
  156. 5:22industrialized construction.
  157. 5:23>> So, in other words, this is in effect a
  158. 5:26SIP panel. You know, when I think of
  159. 5:28SIPs, I think of the acronym structural
  160. 5:30insulated panel. And so, their company
  161. 5:33builds these panels in a factory. We're
  162. 5:35going to get into that in a minute.
  163. 5:37Ships them to the job site and you put
  164. 5:39them together. Uh, no organics. You're
  165. 5:42going to not see any wood in this system
  166. 5:44at all. And in fact, there's not even
  167. 5:46any paper facing as well cuz they've
  168. 5:48used this magnesium oxide board on the
  169. 5:50inside and the outside. But also what's
  170. 5:53different about this than a traditional
  171. 5:54SIP is your cavities are open like
  172. 5:57you're seeing on this back wall. Right.
  173. 5:59>> Right. Right. I mean that's if you've
  174. 6:01worked with SIPS, which I know you have
  175. 6:03in the past. Right. Couple of the few u
  176. 6:05couple of the issues that we run into
  177. 6:07with SIPS is that we get a lot of
  178. 6:09complaints from the trades, all the MEP
  179. 6:11trades, the inspectors can't see in the
  180. 6:13wall. Connections are an issue. So, um,
  181. 6:17we set out to try to achieve what was
  182. 6:21already achievable with the SIP panel by
  183. 6:24eliminating the thermal bridging, which
  184. 6:25I know we're going to talk about, but at
  185. 6:27the same time address the issues and
  186. 6:29challenges that we have with traditional
  187. 6:31SIP. Yeah.
  188. 6:31>> So, this is like a hybrid ZIP. We call
  189. 6:33it a CIS, which is a structural
  190. 6:35insulated system. Gotcha.
  191. 6:37>> Because we don't just sell wall panels,
  192. 6:39>> right? We're trying to um do a holistic
  193. 6:42design and engineering of the entire
  194. 6:43building.
  195. 6:44>> I like it. So the Kratos the Kratos wall
  196. 6:47is the exterior wall but the Kratos
  197. 6:49build is the entire structure. So that's
  198. 6:51your exterior walls, your interior
  199. 6:52walls, columns, beams, floor trusses,
  200. 6:54roof trusses, flashings, fasteners,
  201. 6:57sealants, the whole thing essentially as
  202. 7:00a kit, right, that you're going to tilt
  203. 7:02up wall in the in the field.
  204. 7:03>> Gotcha. Now steel framing obviously
  205. 7:06moldproof, obviously termite proof, very
  206. 7:09floody, right? And if I had a flood that
  207. 7:11occurred in this wall back here and you
  208. 7:14see I've got some closed cell foam, all
  209. 7:16I'd have to do is pull that cavity
  210. 7:17insulation out. And if this is a
  211. 7:20magnesium oxide board, will you hand me
  212. 7:21that board right behind me? By the way,
  213. 7:23uh this is also one of their products.
  214. 7:26This magnesium oxide board won't absorb
  215. 7:28water. Uh it's naturally mold resistant
  216. 7:30because there's no organics. I could
  217. 7:32actually remove that panel, dry out the
  218. 7:36cavity, and move on. Well, not only we
  219. 7:39were in the ninth ward of Louisiana, we
  220. 7:41could survive, right?
  221. 7:42>> Exactly. We actually had that happen to
  222. 7:44a house there, but uh
  223. 7:46>> uh the other important aspect of that is
  224. 7:49you can actually put the same board back
  225. 7:51on.
  226. 7:51>> Oh, how about that? Yeah,
  227. 7:52>> that's awesome.
  228. 7:53>> Yeah. Yeah. So, you're not sending all
  229. 7:54that, you know, like you would typically
  230. 7:56gut the entire thing and send that
  231. 7:58chipboard to the landfill, right?
  232. 7:59>> So, it's a very lose it structural
  233. 8:02abilities by getting soaked or
  234. 8:03underwater for a day or two.
  235. 8:04>> No, it's not. We've had these panels
  236. 8:06outside for over a year at our factory
  237. 8:08just sitting outside being rained on
  238. 8:12constantly. So, we should send you a
  239. 8:13couple of those samples so you can look
  240. 8:15at it. Yeah.
  241. 8:15>> Now, here's the downside of steel in my
  242. 8:17mind, though. I'm worried that if I get
  243. 8:19air leakage in here, especially if I'm
  244. 8:21building a house in the south. You know,
  245. 8:23you guys are based in Florida. I'm based
  246. 8:25here in Texas. If I'm building a Florida
  247. 8:27coastal house with this, it's often hot
  248. 8:29and humid out. I'm worried if I get any
  249. 8:31air leakage in this cavity, this steel
  250. 8:33is going to be the same temperature as
  251. 8:35my air conditioner. Uh, and I'm going to
  252. 8:37have some condensation issues. But
  253. 8:39you've addressed that. How, Todd?
  254. 8:41>> Well, the first thing that we have to
  255. 8:43address is the thermal bridging, right?
  256. 8:45You I mean, you flew all the way to
  257. 8:47Australia, right?
  258. 8:48>> Saw steel framing steel framing and I
  259. 8:50was sure worried about it.
  260. 8:51>> Exactly. No, it was a great point. Uh,
  261. 8:53so I I I love that uh that episode. So
  262. 8:57one of the one of the first things that
  263. 8:58we need to do is we need to eliminate
  264. 9:00the thermal bridging right so that's
  265. 9:02going to eliminate that cond you know
  266. 9:04that temperature variation and the and
  267. 9:07the uh uh the condensation to form
  268. 9:10>> and there's you know for a long time
  269. 9:12there's been a lot of conversation about
  270. 9:14breathable walls right hey those walls
  271. 9:16need to breathe we see those comments
  272. 9:18all the time
  273. 9:19>> but in reality the walls need don't need
  274. 9:21to breathe people need to breathe right
  275. 9:23so what we need to do is we need to make
  276. 9:26that there is a way for that wall to um
  277. 9:29exchange humidity, right? And that's
  278. 9:32inside. So by, you know, there's a
  279. 9:35saying, right? Build tight, ventilate,
  280. 9:37right?
  281. 9:37>> That's right.
  282. 9:38>> Right. So that's what we're trying to
  283. 9:39do. So we want to stop that air
  284. 9:41infiltration or leakage on the outside
  285. 9:44and let the wall breathe inside with the
  286. 9:47controlled humidity
  287. 9:48>> and air conditioning inside the house.
  288. 9:50And the other thing you've done with
  289. 9:51this assembly is this magnesium oxide
  290. 9:54board that's bonded to insulation is
  291. 9:57their product. They call this the MX7
  292. 10:00panel. So this sheathing that's on the
  293. 10:02outside is mag oxide. And that sheathing
  294. 10:05is bonded to, in this case a half inch,
  295. 10:07but it could be greater if you wanted
  296. 10:09to. Uh EPS foam. So now when you look at
  297. 10:12this sandwich, actually Kyle, will you
  298. 10:13help me rotate the wall here a little
  299. 10:15bit?
  300. 10:15>> Absolutely. You're going to notice that
  301. 10:18that sandwich is actually glued on to
  302. 10:21the assembly. Okay, that's probably good
  303. 10:24for now because I want to be able to
  304. 10:24share this side. So, this sandwich is
  305. 10:27actually glued on. And you can see a
  306. 10:28little bit of that glue right there.
  307. 10:31It's probably, I would guess, a
  308. 10:32polyurethane glue. They have a patent on
  309. 10:34this, so we probably can't tell you all
  310. 10:35the secret sauce. Uh, but that assembly
  311. 10:38is glued on. And then if you look in the
  312. 10:40back here, then at the factory, they've
  313. 10:44sprayed in a couple of inches of closed
  314. 10:47cell foam on top of that. So that whole
  315. 10:50assembly is a structural panel. It's
  316. 10:53been insulated and it's got a thermal
  317. 10:55break at all these steel studs. But the
  318. 10:58cool part about that is I've got an open
  319. 11:00stud bay that I can bring the
  320. 11:02electrician in. I can bring the plumber
  321. 11:04in and run all those services inside of
  322. 11:06that service bay. And then if I want to
  323. 11:08add additional insulation, you see he's
  324. 11:10got some rockwool bats in here, let's
  325. 11:12say, or that could be fiberglass. That
  326. 11:14could be whatever you could add more
  327. 11:15spray foam if you want. Then I could add
  328. 11:17additional cavity insulation. But what's
  329. 11:20cool about this now? Let's complete the
  330. 11:22rotation cuz I want to show them this.
  331. 11:24>> They can actually go right over top of
  332. 11:26this mag oxide board with what, Todd?
  333. 11:30What are we looking at here? This green
  334. 11:31face.
  335. 11:32>> Uh, this is a synthetic elastoic struck
  336. 11:36uh stucco. Mhm.
  337. 11:37>> Um it's what we call direct apply. We're
  338. 11:39all familiar with the EF system.
  339. 11:41>> Uh so this is called the DEF system,
  340. 11:44direct apply finish system, DFS.
  341. 11:46>> And um with the MGO board like
  342. 11:49cementitious type board, we're able to
  343. 11:51go directly to that substrate.
  344. 11:54>> Uh the in this particular case,
  345. 11:56>> so in other words, this isn't
  346. 11:57traditional L and plaster stucco. This
  347. 12:00is basically something that's adhering
  348. 12:02right to that cementitiousbased board.
  349. 12:05>> That's right. And it becomes the air
  350. 12:06barrier to the water barrier and you've
  351. 12:09got a sanded kind of coat with an
  352. 12:11elasame paint in the front. That's
  353. 12:12right.
  354. 12:13>> So that's your finish as well.
  355. 12:14>> Right. In fact, it comes in color.
  356. 12:16>> So with this this particular
  357. 12:18application, your Let's talk about the
  358. 12:20layers, right? So your first layer of
  359. 12:22course is the boards already part of the
  360. 12:24panel. When you tilt that wall up,
  361. 12:26you've already solved seven issues or
  362. 12:28seven trades.
  363. 12:29>> Okay. What are those?
  364. 12:30>> That's that's why you have the seven,
  365. 12:32right? So, you have your there's
  366. 12:33actually a few more, but essentially
  367. 12:35you've got your structural frame,
  368. 12:37>> you have your insulation, you have all
  369. 12:39your hold downs, okay? You have your
  370. 12:41exterior um continuous insulation, your
  371. 12:45CI,
  372. 12:46>> you've also got your exterior sheathing.
  373. 12:48>> You've got your fire rating.
  374. 12:50>> Okay. And
  375. 12:51>> what is the fire rating on this?
  376. 12:52>> So, this particular uh panel is the 1 in
  377. 12:56MX7.
  378. 12:57>> We rotate.
  379. 12:58>> So, it's 1 hour.
  380. 13:00>> It's a 1 hour. 1 hour. Yeah, the 1/2 in
  381. 13:02MGO is a 1 hour.
  382. 13:04>> So, you know, I actually have a big
  383. 13:06lighter over here and I was thinking
  384. 13:08about uh you know, putting this big
  385. 13:10lighter. I don't know if this is legal
  386. 13:11at the
  387. 13:12>> Oh, no. No. To see if this would
  388. 13:15actually catch fire.
  389. 13:16>> No, no, we don't want that. We want
  390. 13:17this.
  391. 13:18>> Oh, what do we got?
  392. 13:20>> Come on.
  393. 13:21>> All right. So,
  394. 13:22>> let's crank it up. So, we got the MX
  395. 13:25panel
  396. 13:26>> and we've applied it to wood framing
  397. 13:30instead of uh steel studs.
  398. 13:34>> Yeah.
  399. 13:36>> Check that out. That's pretty legit.
  400. 13:40>> It's up full blast.
  401. 13:43>> So, we're I don't know 1,000° or so on
  402. 13:46that magnesium oxide board. But you
  403. 13:49notice this is this is being applied to
  404. 13:51standard wood framing which they'll sell
  405. 13:53you just the magnesium oxide board.
  406. 13:55>> Wood's not going anywhere right in the
  407. 13:57Northeast everybody's using wood frame.
  408. 14:00>> Very little light gauge steel going on.
  409. 14:02Um
  410. 14:03it's it's coming down the pike but it's
  411. 14:05not there yet. So this is a great option
  412. 14:07here. You have your continuous
  413. 14:08insulation MGO panel. So you have your
  414. 14:10fire rated panel. You have it's water
  415. 14:13resistant. It's uh pest resistant. It's
  416. 14:15mold and mildew resistant. So, allin-one
  417. 14:18and your continuous insulation.
  418. 14:19>> It's pretty compelling.
  419. 14:21>> And Todd, when I met you at the
  420. 14:22International Builder Show, you had a
  421. 14:24sample uh of this MX7 board going with a
  422. 14:28torch that it looked like it had been
  423. 14:29sitting there for a while. This wasn't a
  424. 14:31two-minute demo like this.
  425. 14:33>> Yeah. In fact, we brought it with us.
  426. 14:35So, this ran about 3 hours. Uh what's
  427. 14:38impressive about this is that um it's
  428. 14:41only the half inch version. So, it's
  429. 14:43only rated to an hour. So you started
  430. 14:44this at 1, you know, 130, let's say, ran
  431. 14:47it for 3 hours, and that's how much
  432. 14:49damage was done to the face. It does not
  433. 14:51look like this has been structurally
  434. 14:53damaged.
  435. 14:54>> A little charring. You can
  436. 14:56>> And this is um
  437. 14:58>> Yeah. So this is
  438. 14:59>> technically this is only a 1hour fire
  439. 15:01rated wall, though.
  440. 15:02>> Right. Right. Technically,
  441. 15:03>> and part of that is because a little bit
  442. 15:04of the heat transferred through, right?
  443. 15:07>> And the EPS foam a little bit on the
  444. 15:09back melted. Now, not very much,
  445. 15:11frankly, and not a lot of damage.
  446. 15:14But that's not bad for three times what
  447. 15:16it's rated life at.
  448. 15:17>> Yeah. Yeah. And what I thought was
  449. 15:18interesting was one, you know, the EPS
  450. 15:21has air bubbles in it, right? So there's
  451. 15:23no offging or anything like that, but I
  452. 15:26thought it was interesting that the size
  453. 15:29of this area pretty much matched.
  454. 15:31>> Yeah. This,
  455. 15:32>> you know, so we didn't have a lot of
  456. 15:33propagation
  457. 15:35>> of the heat beyond the the the initial
  458. 15:38or direct impact of the flame. I thought
  459. 15:40that was
  460. 15:40>> was kind of interesting. Now, that
  461. 15:42coupled with wood framing is going to
  462. 15:44meet your, let's say, 1 hour rating if
  463. 15:46you're in a WOOI zone. Um, but we can
  464. 15:49also meet two or three hour ratings by
  465. 15:51doing what, guys?
  466. 15:52>> Well, so you have different thicknesses
  467. 15:53of the boards, right? So, you can go
  468. 15:55from/ inch to 5/8, right? Uh, and then
  469. 15:58you can also get a higher R value if
  470. 16:01you're doing EPS foam on the back if
  471. 16:02you're using the MX7 board. And you can
  472. 16:05do/ inch, 5/8, all the way up to an
  473. 16:08inch,
  474. 16:09>> three up to 3/4 in ongo.
  475. 16:11>> And do you guys have Oh, okay. So So we
  476. 16:13could go even a 3/4 MGO board.
  477. 16:16>> And so you guys in other parts of the
  478. 16:17world, didn't I hear you have an islands
  479. 16:19project going that has a three-hour
  480. 16:21rated fire?
  481. 16:21>> Yeah, we do. Yeah, we have a we have a
  482. 16:23project right now in the Bahamas that
  483. 16:25requires a three-hour fire rating
  484. 16:27because of the proximity of the
  485. 16:28buildings, uh, according to the Bohemian
  486. 16:30building code.
  487. 16:30>> How about that? So they're limited in
  488. 16:34being able to build with wood maximum
  489. 16:37two stories. Gotcha.
  490. 16:38>> And then they were limited to building
  491. 16:39with the CMU block and cast in place
  492. 16:42because of the cost and the weight.
  493. 16:44>> And so the light gauge steel system fit
  494. 16:46perfectly because it's non-combustible.
  495. 16:48We could go up to four stories
  496. 16:50>> and um also provided three-hour
  497. 16:53firewall. So looking at all the
  498. 16:55different building technologies, we
  499. 16:57really fit, you know, perfecting
  500. 16:59>> for that particular build. Now, let's uh
  501. 17:02explain to these guys from the bottom to
  502. 17:03the top real quick.
  503. 17:05>> Sure.
  504. 17:05>> Uh what you've got going on. So, first
  505. 17:07off, this floor framing system is also
  506. 17:10[snorts] like gauge steel and comes out
  507. 17:12of your factory.
  508. 17:13>> And what are we seeing in here when we
  509. 17:15look in this cavity?
  510. 17:16>> Yeah, we wanted to leave it open so you
  511. 17:17could see one I mean whether you're
  512. 17:19using a mineral wool or a bad insulation
  513. 17:21really, you know, doesn't matter. But if
  514. 17:23you look back in there, you'll see a
  515. 17:24solid sea joist.
  516. 17:26>> Okay. So we have equipment that can take
  517. 17:28the coils of steel and uh either you
  518. 17:32know roll stud or truss profiles or deep
  519. 17:34sea joist
  520. 17:36>> um you know which are
  521. 17:38>> well right and the nice thing about it
  522. 17:39when you do the rim tracks with the sea
  523. 17:41joist
  524. 17:42>> you can typically span a little further.
  525. 17:44>> Yeah.
  526. 17:44>> Um you don't have the assembly aspect in
  527. 17:47the factory so they're a little less
  528. 17:48expensive.
  529. 17:50>> Uh but on the other hand they're
  530. 17:51restrictive in that we really can only
  531. 17:53go 14 in. So 14, 12, or 10.
  532. 17:56>> Okay.
  533. 17:57>> So when we're looking at maybe a floor
  534. 17:59system that needs to be 24 in or even
  535. 18:02greater depending on the span, we'll
  536. 18:04need to uh resort to the web based
  537. 18:07>> trusses. Trusses.
  538. 18:08>> Yeah. Gotcha. And then what is this
  539. 18:09subfloor that's on top of this?
  540. 18:11>> This is a 3/4 in uh tongue and groove
  541. 18:16uh MGO board.
  542. 18:17>> Ah, so we also have a fire rating with
  543. 18:19that as well.
  544. 18:20done in condos or
  545. 18:22>> multifamily or mixed use residential
  546. 18:25commercial. This would also help us with
  547. 18:27our fire.
  548. 18:28>> Right. Right. And the interesting thing
  549. 18:29about this, this is a a product also
  550. 18:32that we make with one of our partner
  551. 18:34companies
  552. 18:35>> uh called Q Rock. And essentially what
  553. 18:36we're doing is we're marrying the
  554. 18:39acoustic mat to the underneath of the
  555. 18:42MGO board.
  556. 18:43>> Got it. So it's a little hard to tell,
  557. 18:44but this is actually an acoustic
  558. 18:47>> mat right in here. That's that comes
  559. 18:50already pre-applied to the
  560. 18:52>> already pre-applied
  561. 18:52>> and is gonna separate thermally and more
  562. 18:56more importantly acoustically. That's
  563. 18:58right.
  564. 18:58>> From this subfloor. So impact noises and
  565. 19:01other sound is not going to vibrate this
  566. 19:03like it would if it was mechanically
  567. 19:05attached MGO to steel.
  568. 19:07>> Y that's really smart.
  569. 19:08>> Yeah. And the other nice part about this
  570. 19:10is that you see it's underneath the
  571. 19:11subflooring where traditionally they'll
  572. 19:13install it as a separate process or a
  573. 19:15separate step with another crew when
  574. 19:18they install the final flooring.
  575. 19:19>> So here we're protecting that mat in a
  576. 19:21single install.
  577. 19:22>> That's pretty cool.
  578. 19:23>> Same concept as this MX7 board, right?
  579. 19:25We marry two products that are already
  580. 19:27going to go together
  581. 19:28>> together and we reduce our labor and our
  582. 19:31waste.
  583. 19:32>> I'm noticing that I've actually got a
  584. 19:34hold down in that cavity. Did that come
  585. 19:36from from your factory as well?
  586. 19:38>> Yeah. What we will typically do is is we
  587. 19:40will pre-install all the hold downs,
  588. 19:42clips, and connectors that go in the
  589. 19:45exterior wall in the factory. So that
  590. 19:48way we make sure that one they don't
  591. 19:50miss it. You know, a lot of times in the
  592. 19:51field
  593. 19:52>> there'll be an installation and they'll
  594. 19:53miss a hold down or a clip or some sort
  595. 19:55of connector
  596. 19:56>> and then of course the inspectors come
  597. 19:58and it's not there. So, um, we will, as
  598. 20:01a standard practice, pre-install all of
  599. 20:04the hold downs in those walls and even
  600. 20:07the X-racing as well.
  601. 20:09>> That's pretty awesome.
  602. 20:09>> Yeah.
  603. 20:10>> Now, isn't it a pain though for trades,
  604. 20:12Todd, cuz I got to drill this stud, then
  605. 20:15I got to find this plastic connector and
  606. 20:17I got to figure out where all my wiring
  607. 20:19and my electrical goes. Talk to me about
  608. 20:22transferring from a wood-based
  609. 20:24construction process to a steel-based.
  610. 20:26How hard is it?
  611. 20:27>> [snorts]
  612. 20:27>> Well, actually what we're what we're
  613. 20:30able to do is reduce about 50% of the
  614. 20:32labor
  615. 20:33uh with the MEP trades, especially the
  616. 20:36plumbing and the electrical by pre-
  617. 20:39punching all the service holes in the
  618. 20:40factory.
  619. 20:41>> Ah, so this actually comes from the
  620. 20:42factory.
  621. 20:43>> That's right. That's right. So unlike,
  622. 20:45you know, going to some sort of source
  623. 20:48for generic stud and track material
  624. 20:51that's generic, you have the same issue
  625. 20:53that you would if you're working with
  626. 20:55wood studs, right? you're having to pull
  627. 20:56through that, you're having to cut it,
  628. 20:58>> and you're having to drill all those
  629. 20:59holes. So, uh, one of the nice things
  630. 21:02that we can do to help the builder is do
  631. 21:06what we call value engineering. So,
  632. 21:09you'll see here these noggin
  633. 21:12uh here and here as an example. You'll
  634. 21:13see the noggin.
  635. 21:14>> So, the horizontal cross bracing is
  636. 21:16called a noggin.
  637. 21:17>> Yeah, it's called a noggin. So,
  638. 21:19>> so in other words, this noggin that I'm
  639. 21:20seeing here was pre-applied at the
  640. 21:22factory. That's right. Right. So, the
  641. 21:23electrician only had to just drop his
  642. 21:25box in there and screw it down. It's
  643. 21:26done.
  644. 21:27>> Yeah. Or if we know precisely where the
  645. 21:30boxes go, we can pre-install those as
  646. 21:31well.
  647. 21:31>> Is that right? Okay.
  648. 21:32>> Yeah. Wow.
  649. 21:33>> We usually like to stay inside the
  650. 21:34cavity.
  651. 21:35>> Very cool.
  652. 21:36>> Um but at least we resolve one of the
  653. 21:38dimensions.
  654. 21:39>> Yeah.
  655. 21:40>> Right. So, you're cutting the
  656. 21:41dimensioning by 50%. All they got to
  657. 21:42figure out is one, they got to know
  658. 21:44where that box goes
  659. 21:45>> and then they just need to figure out
  660. 21:47the horizontal dimension.
  661. 21:48>> Makes a lot of sense. But uh you know
  662. 21:50you get into production builds where
  663. 21:51you're building the same house or models
  664. 21:54over and over again hundreds or
  665. 21:55thousands of times. It would make sense
  666. 21:57to go through the value engineering
  667. 21:58process, determine where every box goes,
  668. 22:01every switch, every outlet,
  669. 22:03>> every cold and hot water routing, and
  670. 22:06pre- punch all of those.
  671. 22:08>> When I was a production builder back in
  672. 22:10the old days, uh there was a couple
  673. 22:12models that were real popular uh in the
  674. 22:14community that I was building. I was
  675. 22:16building for one of the top 10 national
  676. 22:17builders. I remember, for instance, the
  677. 22:19Chesterfield model. I could just about
  678. 22:22build that house in my sleep. I could
  679. 22:23walk into any room blindfolded and I
  680. 22:26could tell you where all the outlets
  681. 22:27were going,
  682. 22:28>> uh, exactly what that room looked like
  683. 22:29cuz we built that house
  684. 22:31>> uh, probably hundreds of times over the
  685. 22:33course of a couple of years.
  686. 22:35>> Sure.
  687. 22:35>> And so it really think I think to
  688. 22:38myself, hey, if you're watching this and
  689. 22:40you're a custom builder like me, you
  690. 22:42should get your production builders to
  691. 22:43watch this. I would think that you guys
  692. 22:45would be an absolutely bomber perfect
  693. 22:49fit for any production builder that's
  694. 22:51building anything uh on a repetitive
  695. 22:53basis or a large basis and certainly
  696. 22:57custom builders that are in any zone
  697. 23:00that's a disasterprone zone. I mean,
  698. 23:02when I look at the bones of this
  699. 23:04structure and I think about flooding and
  700. 23:07I think about tornado alley and I think
  701. 23:09about coastal builds that have
  702. 23:10hurricanes, this is pretty bomber. This
  703. 23:13is pretty impressive.
  704. 23:15>> Yeah. I mean, you think about what the
  705. 23:16cost just at the national level is,
  706. 23:19right? For us to build to code.
  707. 23:21>> Yep.
  708. 23:22>> All right. And not to build performance.
  709. 23:24I mean, you're looking at somewhere
  710. 23:25anywhere from 130 to$ 160 billion
  711. 23:27dollars
  712. 23:28>> a year is our cost at the national
  713. 23:31level. Wow.
  714. 23:32>> For, you know,
  715. 23:34>> all the rebuilding for disasters, fire,
  716. 23:36termite, mold, etc.
  717. 23:38>> Let's actually go back to that slide
  718. 23:39while we're talking about it.
  719. 23:41>> Yeah. I mean, it it's crazy how much
  720. 23:43time we spend on uh on rebuilding. And
  721. 23:46I'm going to back up to that slide just
  722. 23:47to uh show it right here. Um but this is
  723. 23:51the slide that we started out. And
  724. 23:52that's that's the number that Todd just
  725. 23:54referenced right there. 130 billion
  726. 23:57dollars annually and basically disaster
  727. 24:01rebuilds that [snorts] if we built with
  728. 24:03a system like yours, we wouldn't have
  729. 24:04to. Now, we might have to redo some
  730. 24:06finishes or some claddings on the
  731. 24:08outside, but the structure would be
  732. 24:10perfectly fine there.
  733. 24:11>> Yeah. I mean, and not only that, but
  734. 24:13just the long longevity, right? We're
  735. 24:15we're here today to talk about
  736. 24:16resiliency, and part of that really is
  737. 24:18the durability of that building to
  738. 24:20extend the life of it.
  739. 24:22>> So, you look at a traditional wood frame
  740. 24:25house today,
  741. 24:27>> um you know, you're looking maybe 60, 70
  742. 24:29years of a lifespan. Yeah.
  743. 24:31>> Based on the quality materials that
  744. 24:33we're using.
  745. 24:33>> Crazy. So we really need to look at um
  746. 24:37the building holistically as a system.
  747. 24:39>> Mhm.
  748. 24:40>> Uh from the HVAC to the exterior thermal
  749. 24:43bridging making that thing perform
  750. 24:45better. Um but also you know back to
  751. 24:48that slide we've seen the human cost of
  752. 24:50that as well. just in fires per year, we
  753. 24:53lose about 2,600 lives here in the
  754. 24:55United States. By essentially removing
  755. 24:58the organics out of the building and
  756. 25:01focusing on the bones of the structure,
  757. 25:04uh we can make a huge difference in the
  758. 25:06long-term value
  759. 25:08>> and performance of that structure. It's
  760. 25:11going to, you know, perform better and
  761. 25:14it's going to last two times minimum two
  762. 25:17times longer.
  763. 25:17>> And speaking of bones, check this out,
  764. 25:19guys. This is really compelling. This is
  765. 25:22a 3D model uh of all the structure that
  766. 25:26would come from their factory to your
  767. 25:29job site. They're able to model
  768. 25:31structurally the interior walls, the
  769. 25:33exterior walls, the rafters. You know,
  770. 25:35in this case here, like [clears throat]
  771. 25:36for instance, this X bracing went a
  772. 25:38little too fast flying through the
  773. 25:40building. That X bracing was there on
  774. 25:42purpose as additional shear value that
  775. 25:44the engineer put in. And if I zoom into
  776. 25:47this floor cavity, uh, let's see if I
  777. 25:50can do it well for us, Todd. We can see
  778. 25:53that these trusses have been lined up.
  779. 25:56And I could actually fly through that
  780. 25:58truss bay if I was good enough with my
  781. 25:59mouse to show you that it would
  782. 26:02[clears throat] be really easy, let's
  783. 26:03say, in this bay right here to route our
  784. 26:06uh HVAC system that we pre-planned to go
  785. 26:09into that system. So the uh the amount
  786. 26:12of forethought that's done uh with your
  787. 26:16system so that I can as a builder
  788. 26:18understand what I'm about to build is
  789. 26:20amazing. But that also yields some
  790. 26:22additional benefits which I think are on
  791. 26:24this slide right here. Let me go back to
  792. 26:26the slideshow presentation. U by the way
  793. 26:28I forgot to say this at the top of the
  794. 26:30hour. If you guys have questions and
  795. 26:32you're watching this live, I know a lot
  796. 26:34of you are going to watch this later.
  797. 26:35I'm sorry you missed the live version.
  798. 26:37Uh, but if you're watching this live,
  799. 26:39there's a Q&A tab. I'm looking at the
  800. 26:41Q&A's here. We're going to leave some
  801. 26:42time at the end uh to make sure we
  802. 26:44answer your Q&A time. So, throw your
  803. 26:46question there. And if you're not
  804. 26:48watching this live, be sure to ask uh
  805. 26:50for the link below for our newsletter
  806. 26:52that you can sign up. That's how you
  807. 26:54know when we've got these live webinars
  808. 26:55going on. But back to that, uh Todd,
  809. 26:58talk me through what we're seeing here
  810. 26:59in terms of the challenges that we face
  811. 27:00today and how you guys meet those
  812. 27:02challenges. I know that you probably
  813. 27:04know more about these challenges, you
  814. 27:06know, than than we do because you're on
  815. 27:08a daily basis. You're in the mix on a
  816. 27:09daily basis. But, uh,
  817. 27:11>> yeah, I mean, we've had a shrinking
  818. 27:13workforce. We've got a workforce that is
  819. 27:15not as as qualified, right? We in
  820. 27:18general, you know, when you look at the
  821. 27:20journeyman and the different trades,
  822. 27:22especially in the MEP trades,
  823. 27:24>> we're losing four to seven
  824. 27:28uh workers in those trades compared to
  825. 27:31one journeyman coming into the trade.
  826. 27:33So, all those trades are shrinking,
  827. 27:35right? So, we ought to do more with
  828. 27:37less. Y
  829. 27:38>> and part of the way that we can um
  830. 27:40address that particular challenge is by
  831. 27:42moving the fabrication of the shell to
  832. 27:45the factory where we can control
  833. 27:48>> u not only the products we can control
  834. 27:50waste we can work three shifts right
  835. 27:52under a roof
  836. 27:54>> uh we're not worried about the weather
  837. 27:56>> and so um we can minimize the amount of
  838. 28:00labor that's required in the field
  839. 28:02>> by up to around 50% as far as putting
  840. 28:04the shell up because as I mentioned
  841. 28:06earlier earlier when you tilt that wall
  842. 28:08up, you've you've already resolved many
  843. 28:11many um other uh aspects of that of that
  844. 28:15shell building. That's right.
  845. 28:16>> So,
  846. 28:17>> so then let's go to answering this
  847. 28:19question, which is really in general,
  848. 28:22why steel? And uh what's the difference
  849. 28:25on your system compared to let's say
  850. 28:27standard wood framing and the systems
  851. 28:29that we've been using for decades?
  852. 28:30[clears throat]
  853. 28:31>> Yeah, good question. Um, essentially
  854. 28:32what we're trying to do is we're trying
  855. 28:34to eliminate the organics out of the
  856. 28:36building, right? The organics really are
  857. 28:39the fuel and the food for all of the
  858. 28:41problems that we have. So if you were to
  859. 28:43try to do a, you know, a root cause
  860. 28:45analysis, right? What is the cause of
  861. 28:48all of the issues and challenges that we
  862. 28:49have today?
  863. 28:51>> So besides building in the field field,
  864. 28:54we have the materials that we're using.
  865. 28:55So it goes back to materials and methods
  866. 28:58and that's really our focus. Let's use
  867. 29:01best of breed materials. Let's use more
  868. 29:05um you know efficient methodologies
  869. 29:09and try to remove those things where we
  870. 29:11have a lot of waste in the field to the
  871. 29:13factory where we control them better. So
  872. 29:15that's really what we're trying to do in
  873. 29:17essence is remove the organics out of
  874. 29:19the building. And you start with the
  875. 29:21bones.
  876. 29:22>> Now cabinets, those can be swapped out.
  877. 29:25Flooring, you can swap those out. You
  878. 29:27can paint the walls. You can fix all of
  879. 29:28those things later. But to change the
  880. 29:31bones of the structure, it's not not
  881. 29:33going to happen after it's built, right?
  882. 29:34>> No, it's not going to happen.
  883. 29:35>> So,
  884. 29:36>> and this cutaway is kind of a compelling
  885. 29:38one with with your system.
  886. 29:40>> Uh really just reviewing what we talked
  887. 29:42about already with strength and
  888. 29:44performance and uh disaster mitigation.
  889. 29:47But let's let's actually talk about your
  890. 29:49value proposition and where you guys
  891. 29:52stack up uh in terms of uh building with
  892. 29:55you versus building with traditional
  893. 29:57materials. If you look at that slide,
  894. 29:59you'll see we have the same components,
  895. 30:01right? We still have operational cost,
  896. 30:03we have waste, we have labor, um, and we
  897. 30:05have the actual building materials. Uh,
  898. 30:07but again, by changing our focus to
  899. 30:11using highquality materials and
  900. 30:14industrialized construction, we're
  901. 30:16basically um, Robin Peter to pay Paul,
  902. 30:19right? We're pulling money out of the
  903. 30:21other line items in that construction
  904. 30:22budget and we're moving them to the
  905. 30:25material side because we're able to pay
  906. 30:28for them that way
  907. 30:29>> uh for the better quality of materials.
  908. 30:31>> Yeah. In effect, you're taking the best
  909. 30:33of the commercial construction world and
  910. 30:36bringing it to us in the residential
  911. 30:38world.
  912. 30:38>> And speaking of the residential world, I
  913. 30:40mean, this is a pretty typical Did you
  914. 30:42take that picture, by the way?
  915. 30:43>> Yeah, I took I took it last week.
  916. 30:45>> What do we see there? [laughter]
  917. 30:47It's it's you only see about half of it,
  918. 30:49but it's uh dumpsters and uh concrete
  919. 30:53materials and trusses and a whole lot of
  920. 30:57wood um strewn over the job site.
  921. 30:59>> All out on the weather too of the
  922. 31:01Florida coast where it's raining a lot
  923. 31:04and it's always wet during construction.
  924. 31:06>> Not treated, right?
  925. 31:07>> Yeah. Some of it is and some of it's
  926. 31:08not, but the trusses are not right. And
  927. 31:10so in Florida, we have this was just
  928. 31:12down the road from where I live in
  929. 31:13Orlando and and um you know, I'm
  930. 31:16visiting this job site on a on a daily
  931. 31:20week, you know, daily basis almost. And
  932. 31:22um I I took those I took that photo
  933. 31:25because, you know, here in a termite
  934. 31:28region, we have both, you know, the
  935. 31:30underground and also the hardwood,
  936. 31:32right? So,
  937. 31:33>> and a lot of people don't think about
  938. 31:34that.
  939. 31:34>> Exactly. From the ground and the air.
  940. 31:36>> Yeah. And they they lay their eggs
  941. 31:37there, right? And then you put the
  942. 31:38trusses in and now all of a sudden, you
  943. 31:40know, you've moved
  944. 31:42>> uh termite eggs into your building. So
  945. 31:44>> So give me the the direct comparison on
  946. 31:46this slide then. What what is it steel
  947. 31:48versus wood in terms of these direct
  948. 31:49comparisons?
  949. 31:50>> Well, what we're trying to do is really
  950. 31:52look at the key characteristics
  951. 31:55of the actual material, right? So wood,
  952. 31:58of course, it's organic, so it's subject
  953. 32:00to, you know, the mold, fire, rot,
  954. 32:04>> uh breaking, twisting. Um so that
  955. 32:08affects the dimensional stability that
  956. 32:09we were talking about in that particular
  957. 32:11slide. It also is heavier. So the
  958. 32:13strength to weight ratio of steel is
  959. 32:15much greater than wood.
  960. 32:17>> Yeah.
  961. 32:17>> Um it's always a balance um looking at
  962. 32:21the mass of the building uh as well
  963. 32:24because steel will outperform
  964. 32:26any other material in seismic activity,
  965. 32:29>> right? because it doesn't propagate the
  966. 32:31harmonic um waves
  967. 32:35>> of of seismic activity absorbs it.
  968. 32:37>> So it will it will sway a little bit and
  969. 32:40it will absorb that not propagate it
  970. 32:41through the building.
  971. 32:42>> Interesting.
  972. 32:43>> Uh so steel's really great in seismic
  973. 32:45but then again you look at the
  974. 32:46lightweight of steel. Well in hurricanes
  975. 32:49I need more mass right? So in some cases
  976. 32:52you need the mass in some cases you
  977. 32:54don't.
  978. 32:54>> Yeah. you know, so it's it's always a
  979. 32:56balance, but essentially, you know, the
  980. 32:58steel being inorganic material, we don't
  981. 33:01have any issues with moisture, mold,
  982. 33:03mildew, fire, any of that. So, you know,
  983. 33:05back to the bones again, right?
  984. 33:07>> Yep.
  985. 33:07>> Build build better with better
  986. 33:09materials.
  987. 33:10>> Now, I do think though with steel, I'm
  988. 33:12worried about that thermal bridging,
  989. 33:13right? I'm worried about that
  990. 33:14conductivity because it's way more
  991. 33:16conductive. I don't do frying pans out
  992. 33:19of wood. I don't do electrical wires out
  993. 33:21of wood for a reason because it's not
  994. 33:23very conductive.
  995. 33:24>> So, how do we get away from that
  996. 33:26downside of steel?
  997. 33:27>> Yeah, that's a great point. It's really
  998. 33:30uh the number one challenge with uh
  999. 33:32adoption of light gauge steel framing
  1000. 33:35>> uh in in the industry
  1001. 33:36>> and it's one that we, you know, focused
  1002. 33:38on, right? Because that was back again
  1003. 33:40to the root cause analysis why people
  1004. 33:42aren't using like gauge steel framing.
  1005. 33:45>> So, we have to create a thermal break. I
  1006. 33:48think we all know that. We've been
  1007. 33:49talking about it for a long time. And
  1008. 33:52the interesting thing is is that we do
  1009. 33:54have some thermal loss with wood, but
  1010. 33:56not as much with steel. So that slide
  1011. 33:59really was to show that if we're not
  1012. 34:03applying a thermal brake, we can lose 60
  1013. 34:05to 70% of our R value. M
  1014. 34:07>> so you go put for example any type of
  1015. 34:10wood or OSB type of material on a steel
  1016. 34:14frame and you're not applying that CI on
  1017. 34:16the outside
  1018. 34:18>> you're you're that building although
  1019. 34:20it's built in steel framing is not going
  1020. 34:22to perform well
  1021. 34:23>> right
  1022. 34:23>> and so the energy bill is going to be
  1023. 34:25high you have to have that
  1024. 34:27>> right we got to look at the building
  1025. 34:28holistically right as a system and we
  1026. 34:30have to address all these issues
  1027. 34:31>> and that's where your sheeting comes in
  1028. 34:32which is something I'd never seen before
  1029. 34:34that MGO board bonded to EPS PS foam
  1030. 34:38that in your system is actually glued
  1031. 34:40onto the wall. So there's no fasteners
  1032. 34:42on that. So as we showed you that stucco
  1033. 34:44wall, uh, you know, there's there's
  1034. 34:46nothing in that wall, Kyle, in terms of
  1035. 34:49fasteners, right?
  1036. 34:50>> Yeah, that that's a pretty amazing part
  1037. 34:52of the MGO panel and the Kratos system.
  1038. 34:54Uh, you know, when we're at the IBS
  1039. 34:57show, a lot of people are like, "How's
  1040. 34:59it adhered? How does it work?" Um, and
  1041. 35:01it's all from the the close cell spray
  1042. 35:03foam, right? all adhering together
  1043. 35:05>> uh and curing and and what what's the
  1044. 35:07time? I think it's minimal time. I I
  1045. 35:10don't know the number, but
  1046. 35:11>> yeah, from the time that it's sprayed
  1047. 35:13within a few minutes, you can move the
  1048. 35:15walls. It's it's pretty pretty hard. But
  1049. 35:18it does have a 24-hour
  1050. 35:20>> curing and offging period. Yeah.
  1051. 35:22>> Which happens in the factory and out in
  1052. 35:23the yard before it gets to the job site.
  1053. 35:25>> I mean, every builder is familiar with
  1054. 35:26the uh with the Gorilla Glue analogy,
  1055. 35:29right? You know, we all used tight bond
  1056. 35:30for years, but then when we switched to
  1057. 35:33Gorilla Glue, we're like, "Wow, this is
  1058. 35:34so much stronger." And the same is true
  1059. 35:37with for our wood-based framing, right?
  1060. 35:38We've used polyurethane based glues
  1061. 35:41forever now because it yields a
  1062. 35:42squeak-free floor. So, when we use that
  1063. 35:45polyurethane based spray foam and adhere
  1064. 35:49that uh MX7 sheathing uh and then spray
  1065. 35:53on the inside, we've got that structural
  1066. 35:55benefit of that spray polyurethane foam
  1067. 35:59uh to besides the Xracing that's already
  1068. 36:02in there, really lock that building in
  1069. 36:04place so that when it actually gets
  1070. 36:06bolted onto that foundation, it is not
  1071. 36:08moving.
  1072. 36:08>> Yeah, that's a good that's that's a good
  1073. 36:10point. We're using that foam really for
  1074. 36:12for a variety of of of reasons, right?
  1075. 36:15It serves a few purposes. So, you have
  1076. 36:18the structural aspect of it.
  1077. 36:20>> Um, you have the insulative aspect of it
  1078. 36:22as well.
  1079. 36:23>> But also past one and a half inches,
  1080. 36:25it's impermeable.
  1081. 36:26>> So, now people will ask a lot of times,
  1082. 36:28hey, we got to wrap that building,
  1083. 36:30right? With with [clears throat]
  1084. 36:31building wrap. Well, when you look at
  1085. 36:33the the composition of that composite
  1086. 36:36wall,
  1087. 36:36>> we're going through MGO, through EPS
  1088. 36:38foam, and through one and a half to two
  1089. 36:40inches of close vapor drive through
  1090. 36:42there.
  1091. 36:42>> Well, there's zero. Yeah. I mean, we've
  1092. 36:43done all the testing in the lab, and
  1093. 36:45there's absolutely zero perance. I mean,
  1094. 36:47it's it's it's tight. The whole, you
  1095. 36:49know, build tight, ventilate, right? We
  1096. 36:51we got the build tight part down pat.
  1097. 36:54So,
  1098. 36:54>> and the beauty of that closed cell foam
  1099. 36:55too is that it's it's correct vapor
  1100. 36:58barriers on both sides
  1101. 36:59>> because it's an impenetrable uh spray
  1102. 37:02foam at an inch and a half thick. So,
  1103. 37:04you've got it on both sides of the wall
  1104. 37:05in the correct location.
  1105. 37:07>> Right. And we're still allowing the wall
  1106. 37:08to breathe but inside. Right. That's
  1107. 37:10right. So, that's that's what you you
  1108. 37:11want to try to achieve.
  1109. 37:12>> Talk us through this case study.
  1110. 37:13>> That was actually a house for my
  1111. 37:15grandparents. We [laughter] fabricated
  1112. 37:16that in uh in uh in Florida, put it in a
  1113. 37:2053 ft drivein and shipped it to Kansas.
  1114. 37:22How many trucks did it take to get that
  1115. 37:23there?
  1116. 37:24>> 2,000 ft. Was that four trucks?
  1117. 37:26>> No, one 53 ft drive van.
  1118. 37:27>> Oh my god.
  1119. 37:28>> Placed very well. Wow.
  1120. 37:30>> You know, in inside of it. So
  1121. 37:31>> impressive.
  1122. 37:32>> Yeah. So that uh it's about 2,000 square
  1123. 37:35ft um 1600T under air.
  1124. 37:39>> Okay. So a ranch style house 2,000 ft.
  1125. 37:41And you actually put the timeline on
  1126. 37:43what it took to build that thing.
  1127. 37:45>> Yeah. Very seldom do we get the
  1128. 37:47opportunity to really follow a build all
  1129. 37:50the way through to the end because
  1130. 37:51normally we're just focusing on the
  1131. 37:52shell
  1132. 37:53>> and then we don't get to come back.
  1133. 37:54Right. So this particular build because
  1134. 37:56it was one for our family. We tracked
  1135. 37:58all of the cost from beginning to end.
  1136. 38:01>> So that first photo there, yeah, we had
  1137. 38:03uh was me, my dad, and four of our Amish
  1138. 38:06friends come together for the first
  1139. 38:08time. Never done it before. They'd never
  1140. 38:10built in uh in steel frame before.
  1141. 38:12Neither had my my father.
  1142. 38:14>> That's awesome. And uh we came together,
  1143. 38:15flew there on a Monday and you see, you
  1144. 38:19know, the first wall 3 hours later,
  1145. 38:21walls up. We had the whole entire
  1146. 38:23structure up uh day one. And then we had
  1147. 38:26trusses uh on day two and day three we
  1148. 38:30had um interior walls and the uh decking
  1149. 38:33on the roof.
  1150. 38:33>> That's fantastic.
  1151. 38:34>> And day four uh peel and stick shingles
  1152. 38:36started and all the doors and windows.
  1153. 38:38And then Saturday morning, day five,
  1154. 38:40took a photo and flew back to Florida.
  1155. 38:42>> That's awesome. And then the other cool
  1156. 38:43thing about that is you were actually
  1157. 38:45able to see their energy bills after
  1158. 38:46they moved in because you have a
  1159. 38:48relationship with the owners.
  1160. 38:49>> Yeah, exactly. Yeah. Tracked it for a
  1161. 38:51full year.
  1162. 38:52>> Yeah. The first one I think was uh was
  1163. 38:54uh I think it was 42 $43 right around
  1164. 38:57there.
  1165. 38:57>> Oh my god.
  1166. 38:58>> So yeah, we tracked all the energy
  1167. 38:59bills, energy consumption cost, kilowatt
  1168. 39:02hours.
  1169. 39:02>> That's fantastic.
  1170. 39:03>> We tracked all the costs as well. You
  1171. 39:05know, our focus is really about the
  1172. 39:06shell, right? Because that's what you
  1173. 39:08know [clears throat] what we do.
  1174. 39:09>> Yeah. But um so yeah we
  1175. 39:12>> now Todd as we think about that that was
  1176. 39:14one small single family. I think when
  1177. 39:16you start looking at buildings like this
  1178. 39:18though your system gets extremely
  1179. 39:20compelling. Talk me through this
  1180. 39:22workforce housing project.
  1181. 39:24>> So this building actually was built into
  1182. 39:26the Bahamas and on that um on that same
  1183. 39:30lot set a very similar building actually
  1184. 39:33made in sip panels.
  1185. 39:34>> Oh really?
  1186. 39:35>> Yeah. Blew blew away unfortunately. Oh,
  1187. 39:37>> you know, but uh I mean the SIP panels
  1188. 39:39are great, right? But the again the
  1189. 39:41challenge is the connection.
  1190. 39:42>> Mhm.
  1191. 39:43>> Um so we actually worked with the
  1192. 39:45structural engineer on this job to
  1193. 39:49develop special holdowns that they
  1194. 39:52wanted to see uh implemented into the
  1195. 39:55building and um again fabricated in
  1196. 39:58Florida. Nine containers shipped to the
  1197. 40:01job site. They poured the slab and then
  1198. 40:04uh flew there and uh worked with a crew
  1199. 40:07of 10 who'd never built a house before.
  1200. 40:09>> Oh wow.
  1201. 40:09>> And the supervisor and um got that thing
  1202. 40:12put up in How about that?
  1203. 40:14>> And yeah, five five weeks.
  1204. 40:15>> That's very cool.
  1205. 40:16>> You know what the amazing part about
  1206. 40:17that was? [clears throat] There was not
  1207. 40:18one dumpster.
  1208. 40:20>> They did not use one dumpster because
  1209. 40:22there was no waste.
  1210. 40:23>> No waste.
  1211. 40:24>> That's really
  1212. 40:24>> Yeah, the waste is usually unbelievable.
  1213. 40:26>> Yeah, you're right. That's that's a
  1214. 40:28that's a great point. You won't you
  1215. 40:29won't see any or very few dumpsters at
  1216. 40:32our at our job site.
  1217. 40:33>> That's really cool. And here's the
  1218. 40:34timeline on that same build. We don't
  1219. 40:36want to belabor that because I want to
  1220. 40:37make sure we get we get moving on.
  1221. 40:39>> But you know, the numbers on this uh I
  1222. 40:42think really tell a story uh about the
  1223. 40:45speed, but also I want you to we haven't
  1224. 40:47gotten to this yet and I'm seeing a
  1225. 40:49bunch of great questions by the way.
  1226. 40:50Good job gang. I think we got 30
  1227. 40:52questions already come through. Tell me
  1228. 40:54about cost compared to people that are
  1229. 40:56used to building let's say with wood
  1230. 40:57framing. How do you end up comparing on
  1231. 41:00cost or or really we're on next slide uh
  1232. 41:02address that?
  1233. 41:04>> Yeah, the next slide will we will
  1234. 41:05address it fairly well. Um
  1235. 41:08>> so this is an even bigger project then.
  1236. 41:10>> Yeah.
  1237. 41:10>> 528 apartments uh 11 total buildings
  1238. 41:14more than a half million square feet in
  1239. 41:17Georgia. Uh and this was being evaluated
  1240. 41:20with your system versus traditional
  1241. 41:22state
  1242. 41:22>> frame. Yeah, it was originally designed
  1243. 41:24for wood um permitted in wood and we're
  1244. 41:28going through the process right now with
  1245. 41:30that developer to to build this actually
  1246. 41:34in in our system. So what you see with
  1247. 41:36this slide is the actual construction
  1248. 41:38budget, the numbers that were provided
  1249. 41:41by the builder,
  1250. 41:42>> okay,
  1251. 41:42>> for us and then we took and did our
  1252. 41:45internal analysis with our proposal on
  1253. 41:48our on our part and put them side by
  1254. 41:51side. I mean, it looks to me like the
  1255. 41:53budget numbers are darn similar. I mean,
  1256. 41:55within a dollar a square foot to build
  1257. 41:58traditionally versus to build Kratos.
  1258. 42:00But what's really compelling about this,
  1259. 42:02and it's a little hidden on this slide,
  1260. 42:04if you look at that green column that
  1261. 42:06says 24 months Kratos total versus 36
  1262. 42:10months wood, I think this is really
  1263. 42:12where the story gets compelling.
  1264. 42:14>> Exactly. Exactly. Yeah. The the Paul
  1265. 42:16Harvey rest of the story, right? So, um,
  1266. 42:19but before we get to that, could you go
  1267. 42:21back just
  1268. 42:22>> I wanted to touch on something. So, a
  1269. 42:24lot of times when, you know, Kyle, you
  1270. 42:26know, he he gets, you know, beat up a
  1271. 42:28lot, you know, because we'll we'll
  1272. 42:30prepare the proposals. We'll send them
  1273. 42:32out and they'll say, "Hey, you know,
  1274. 42:33your steel shell package is way higher
  1275. 42:35than that initial number, right?
  1276. 42:37>> They're done, right? So, let's look at
  1277. 42:38that here. So if you look at the metals
  1278. 42:41in the woods, right, five and six,
  1279. 42:43you're going to see that the wood model
  1280. 42:44is about 24.7
  1281. 42:47million,
  1282. 42:48>> right?
  1283. 42:50>> And you look at ours, we're 30 million.
  1284. 42:53>> So if this client looked at the two and
  1285. 42:57look, yeah, we're 6 million too high.
  1286. 42:59Boop. Sorry. Done.
  1287. 43:00>> Right.
  1288. 43:01>> But if you go to the next line, go to
  1289. 43:03the next screen.
  1290. 43:04>> Okay. you'll see that not only were at
  1291. 43:07the end of the construction budget, we
  1292. 43:08were within a dollar per square foot,
  1293. 43:10but you have to take into account the
  1294. 43:12opportunity cost because we can close
  1295. 43:15that project 12 months earlier.
  1296. 43:18>> So when you look at the opportunity
  1297. 43:21cost, this is a BTR, right? This is 528
  1298. 43:24apartments.
  1299. 43:25>> So now you look at the lost revenue for
  1300. 43:2712 months, you look at the carrying
  1301. 43:29cost,
  1302. 43:30>> right, for that 12 months. I'd have to
  1303. 43:32think there's a huge insurance
  1304. 43:34difference, too. I mean, what insurance
  1305. 43:35carrier would rather have that building,
  1306. 43:39let's say, on the coast of Florida
  1307. 43:40framed in wood compared to your system?
  1308. 43:42They would be crazy to insure it for the
  1309. 43:44same price.
  1310. 43:44>> It's about 50 It's about 50% reduction.
  1311. 43:47It's about 20
  1312. 43:48>> 20 cents per hundred $100,
  1313. 43:52>> okay?
  1314. 43:52>> But versus about 40 cents on a on a wood
  1315. 43:55frame. So, the builder's risk is is
  1316. 43:57gigantic. Not only that, but the
  1317. 43:59operational side after the thing is
  1318. 44:01built just to ensure the the physical
  1319. 44:04building, termite bonds and all those
  1320. 44:06things. So when you look at at, you
  1321. 44:08know, the rest of the story, you're
  1322. 44:10looking at almost $12 million in
  1323. 44:12additional savings.
  1324. 44:13>> That's awesome.
  1325. 44:13>> So now when you add not only is it a
  1326. 44:16dollar less, but you add that savings of
  1327. 44:18the opportunity cost in there, uh that's
  1328. 44:20almost $20 a square foot less expensive
  1329. 44:23for a better build.
  1330. 44:25>> That's amazing
  1331. 44:25>> than with with the wood product. So
  1332. 44:27that's awesome.
  1333. 44:28>> You know, I guess, you know, the the the
  1334. 44:30essence of this story is you can't look
  1335. 44:32at the line item, right? You got to go
  1336. 44:34to the construction budget and you
  1337. 44:35really need to look at the opportunity
  1338. 44:36cost.
  1339. 44:37>> Yeah, for sure. For sure.
  1340. 44:39>> It's a long-term play, not a short-term
  1341. 44:41play. You got to think about the
  1342. 44:42holistic, not just the first check.
  1343. 44:43You're right.
  1344. 44:44>> Right.
  1345. 44:44>> Yeah.
  1346. 44:45>> Yeah.
  1347. 44:45>> Um we'll be quick on this one, but I
  1348. 44:48think there's a pretty interesting
  1349. 44:48sustainability story with your product
  1350. 44:50as well. Do you want to walk us through
  1351. 44:51that?
  1352. 44:53>> Yeah. So, we did a little bit of a study
  1353. 44:54on um you know what the uh what the
  1354. 44:57recycling is per year in the United
  1355. 44:59States um if we were to try to fill that
  1356. 45:04deficit for housing in the US between 3
  1357. 45:07to 5 million homes and what's that look
  1358. 45:09like on the macro scale. Right? So this
  1359. 45:12is just a slide really to demonstrate
  1360. 45:14that one we're taking we're taking um
  1361. 45:17recycled steel from primarily
  1362. 45:19automobiles and appliances which are the
  1363. 45:21two major categories.
  1364. 45:23We're converting those to coils of steel
  1365. 45:26um and then we are converting that of
  1366. 45:29course to um high durable resilient
  1367. 45:33energy efficient buildings.
  1368. 45:34>> It's awesome. And um so that that that
  1369. 45:37number is actually pretty interesting,
  1370. 45:38right? Because you look at just taking a
  1371. 45:41standard 2,000 foot house, that's 6.5
  1372. 45:44billion square feet,
  1373. 45:46>> right, of space, the 3 to 5 million. And
  1374. 45:50um that's 3.2 million houses. If we were
  1375. 45:54to allocate the 19 million tons of steel
  1376. 45:57that we recycle every year
  1377. 45:59>> just from cars,
  1378. 46:00>> just from cars, we could actually build
  1379. 46:023.3 million homes with that. Gosh,
  1380. 46:04that's wild.
  1381. 46:04>> I mean, that's not going to happen,
  1382. 46:05right? But if they took a third, you
  1383. 46:07could build a million houses, million
  1384. 46:08homes a year.
  1385. 46:09>> We need that.
  1386. 46:10>> And if we did that, we could save a
  1387. 46:12little over 700 million trees.
  1388. 46:14>> That's wild.
  1389. 46:15>> Yeah.
  1390. 46:15>> How cool.
  1391. 46:16>> Yeah.
  1392. 46:17>> Uh let's end with this slide because
  1393. 46:19I've got a bunch of questions for you
  1394. 46:21and I've got the audience that has a
  1395. 46:22bunch of questions, too. So, we we need
  1396. 46:24to keep moving. Um this is a current
  1397. 46:27project in the Bahamas. Got you got
  1398. 46:28going on?
  1399. 46:29>> Yeah. Yeah, we're building multiples of
  1400. 46:30this of this particular model. Yeah.
  1401. 46:32>> Very cool. with your full system.
  1402. 46:34>> Yeah. And this interesting because it
  1403. 46:36shows the versatility of the system.
  1404. 46:39We're sitting on a a CMU block, you
  1405. 46:42know, uh first floor on that connecting
  1406. 46:46then the second and third stories uh to
  1407. 46:49that system.
  1408. 46:49>> A bit of a hybrid system.
  1409. 46:51>> Yep.
  1410. 46:51>> Yeah.
  1411. 46:51>> Yeah. And there's quite a bit of red
  1412. 46:53iron. There's about 30,000 lbs of hot
  1413. 46:55roll steel in that building.
  1414. 46:57>> Wow.
  1415. 46:57>> As well. So all galvanized. Um, spend a
  1416. 47:00second talking about that because that's
  1417. 47:02actually one of the questions someone
  1418. 47:03asked in here was, you know, what about
  1419. 47:05coastal builds? Shouldn't I be worried
  1420. 47:06about rust? Tell us about that. What do
  1421. 47:09we need?
  1422. 47:09>> Yeah, I mean that's one of our common uh
  1423. 47:11our common questions, right? So, uh, the
  1424. 47:15answer to that is it really goes back to
  1425. 47:17the hardness and the galvanization
  1426. 47:20coating of the steel.
  1427. 47:21>> On all of our coastal projects, we use
  1428. 47:26G90 galvanized steel.
  1429. 47:27>> Okay? So, a higher level than standard.
  1430. 47:29>> That's right. That's right. The G a lot
  1431. 47:31of the products that you'll find in the
  1432. 47:33big box stores, the generic studs,
  1433. 47:35they're a G40.
  1434. 47:36>> Okay.
  1435. 47:36>> Most of them and they'll rust out, you
  1436. 47:38know, in no time.
  1437. 47:40>> So, we're using um as a standard G60 and
  1438. 47:44then on all coastal projects G90. Got
  1439. 47:46>> all the hot roll steel is hot dipped
  1440. 47:48galvanized. All of the hold downs are
  1441. 47:51hot dipped galvanized or Zmax. All the
  1442. 47:53screws are specially coated. So, we
  1443. 47:56really go the distance to make sure that
  1444. 47:57every fastener and
  1445. 48:01hold down clip and the steel is going to
  1446. 48:04be is coated. Yeah.
  1447. 48:05>> Yeah. And speaking of which, we I think
  1448. 48:06I missed this, but I do want to mention
  1449. 48:08real fast. You know, if we're using your
  1450. 48:10magnesium oxide board, there is a
  1451. 48:13fastener story to talk about with this,
  1452. 48:15right? We don't want to use standard
  1453. 48:16fasteners on this. What do we need to
  1454. 48:18know about that, Todd? Right.
  1455. 48:19>> I forgot to mention this earlier.
  1456. 48:21>> Yeah, that's a good point. So they're
  1457. 48:22they're depending on the type of
  1458. 48:24magnesium oxide board that's used there
  1459. 48:26there's two basic categories either a
  1460. 48:28chloride based or a sulfide based.
  1461. 48:30>> Okay.
  1462. 48:30>> Um and depending upon the chloride
  1463. 48:32sulfide content you're going to have a
  1464. 48:34certain level of corrosiveness. And so
  1465. 48:36what we need to do is take precautions
  1466. 48:38>> to make sure that uh one we're using a
  1467. 48:40G90 grade coated steel and also we're
  1468. 48:44using coated uh approved coated
  1469. 48:46fasteners.
  1470. 48:48uh could be a grabber guard, could be
  1471. 48:50any type, could be a stainless steel,
  1472. 48:53various suppliers that make these
  1473. 48:55fasteners. And um of course you can go
  1474. 48:58through this board with um
  1475. 49:01>> uh with pins, nails, shooting them
  1476. 49:04through, you can use but but primarily
  1477. 49:05we use screws with it for the most part.
  1478. 49:07>> Yeah, makes sense.
  1479. 49:08>> On the roof decking, you're going to use
  1480. 49:09>> We're going to upgrade to a stainless
  1481. 49:10product typically when we're screwing
  1482. 49:12into it, when we're nailing into it,
  1483. 49:13that sort of thing.
  1484. 49:14>> Right. Right. Yeah. You want to use a
  1485. 49:16stainless steel connector. Gotcha.
  1486. 49:18>> Yeah. So Todd, let me switch gears and
  1487. 49:20go back to the beginning. Someone who's
  1488. 49:22interested in using your system, they're
  1489. 49:24they're uh they're thinking this is for
  1490. 49:26them. What does the process look like?
  1491. 49:29Who do they talk to? What does it look
  1492. 49:31like? You know, let's say they've got an
  1493. 49:32architect already. They've got a In
  1494. 49:34fact, someone said, "I've got two
  1495. 49:35projects in Miami Dade County right
  1496. 49:37now." Uh you know, how do we how do they
  1497. 49:40work with you?
  1498. 49:40>> Yeah. You
  1499. 49:41>> Yeah. No, so I mean I'm their their
  1500. 49:43point of contact at that that case. Um,
  1501. 49:45so they just reach out to me and I can
  1502. 49:47uh get them all the information. I can
  1503. 49:49gather their information, their
  1504. 49:50architects, who they're working with and
  1505. 49:52um start with the plans. If they have
  1506. 49:54plans, they can send them to me. We can
  1507. 49:55look at them together as a team uh and
  1508. 49:57kind of go from there.
  1509. 49:58>> Gotcha. And then typically you're going
  1510. 50:00to have an engineer take the
  1511. 50:01architecturals and turn it into your
  1512. 50:03system structurally. Correct.
  1513. 50:06>> Or they're going to have them.
  1514. 50:07>> Yeah, you can go either way.
  1515. 50:08>> Yeah, I could go either way. We a lot of
  1516. 50:11a lot of customers uh do have their own
  1517. 50:14architects and their engineers they work
  1518. 50:15with. We have a library for our system
  1519. 50:17that we can provide the architects and
  1520. 50:19the engineers of details and connections
  1521. 50:21and we'll provide those to them to help
  1522. 50:22them through that process.
  1523. 50:24>> Uh if they don't, it depends on where
  1524. 50:26they are in the process. uh if they
  1525. 50:28don't have an engineering firm that's
  1526. 50:31already the
  1527. 50:32>> EOh,
  1528. 50:34>> we have variety of engineering firms
  1529. 50:36that work with across the country and we
  1530. 50:37can make recommendations for them to to
  1531. 50:40find somebody.
  1532. 50:40>> Okay, I like it. [clears throat] Uh
  1533. 50:42local to Austin builder Sheay uh
  1534. 50:45Milhauser says, "Does Kratos offer any
  1535. 50:48MGO either wall or roof sheeting
  1536. 50:51products that are rated for structural
  1537. 50:53shear?"
  1538. 50:55>> Yeah, we we do have that. We have two
  1539. 50:57categories. We have a Mag Struct and a
  1540. 50:59Mag Ultra. [clears throat] So, they're
  1541. 51:01going to have different um physical
  1542. 51:05structural properties. Got
  1543. 51:06>> We also have a lightweight version,
  1544. 51:08which is really more of a gypsson board
  1545. 51:11um type alternative. You can score it,
  1546. 51:13snap it, that sort of thing. It's
  1547. 51:15lightweight. It's considered a
  1548. 51:17nonstructural board. Okay.
  1549. 51:18>> But there's no paper backing or anything
  1550. 51:20like that. So, again, no organics in it.
  1551. 51:22But yeah, we do have the structural
  1552. 51:23versions of the boards and different
  1553. 51:25sizes.
  1554. 51:25>> Yeah. What are the sizes roughly, Cal?
  1555. 51:27Someone else asked that question.
  1556. 51:28>> Yeah. So, we have a 4x8, a 4x10, and a
  1557. 51:314x12.
  1558. 51:32>> Okay. So, all the normal like panel
  1559. 51:34sizes that we're used to working with in
  1560. 51:36wood. Yeah. Okay. Good.
  1561. 51:38>> And also different edges, right? I think
  1562. 51:40>> Yep.
  1563. 51:42>> tapered edge, straight edge, tongue and
  1564. 51:44groove, beveled, etc. So,
  1565. 51:46>> gotcha. My architect buddy Armando,
  1566. 51:49thank you Armando for all your support,
  1567. 51:50says, "Can I specify the location of all
  1568. 51:53the pre-punched service holes or can I
  1569. 51:55add additional lines of holes?"
  1570. 51:58>> Yes, please. [laughter]
  1571. 52:00>> I I think the answer to your question
  1572. 52:01is, Armando, they want you to integrate
  1573. 52:03your MEPs as an AR Armono is a great
  1574. 52:06architect in Dallas, by the way. uh they
  1575. 52:08want you can integrate [clears throat]
  1576. 52:09your MEPs to their software so that the
  1577. 52:12MEP engineer can show all the runs for
  1578. 52:14the duct work, can show all the plumbing
  1579. 52:16runs, can show all the electrical runs.
  1580. 52:18They can pre- punch everything. So the
  1581. 52:20electrician doesn't have a hole hog on
  1582. 52:22the on the job to drill anything. He's
  1583. 52:25literally going to start running wire or
  1584. 52:27running pipe right from the get- go. We
  1585. 52:29need to figure all those things out
  1586. 52:30ahead of time, which I think frankly is
  1587. 52:32another big benefit of the system that
  1588. 52:34you're you need to figure it out ahead
  1589. 52:36of time. Yeah, it would certainly be
  1590. 52:38beneficial. I mean, we've all been on
  1591. 52:40job sites where, you know, you're trying
  1592. 52:42to install a plenum or some sort of
  1593. 52:44rigid duct work and all of a sudden
  1594. 52:46there's a truss or some sort of a beam
  1595. 52:49in the way, right? Or you go to put the
  1596. 52:50toilet in and all of a sudden it's right
  1597. 52:52over top of a truss. So, you know, clash
  1598. 52:54detection is one
  1599. 52:56>> uh important aspect of the process of
  1600. 52:58our virtual design and construction. So
  1601. 53:01we can build it virtually in the system,
  1602. 53:03that model that you showed.
  1603. 53:05>> And then ideally, not only are we
  1604. 53:07looking at the structural aspect of that
  1605. 53:09model, but we're bringing in the MEP, so
  1606. 53:12they're in the 3D BIM model as well, so
  1607. 53:14we can do clash detection. If you,
  1608. 53:16again, if you're going to do this one
  1609. 53:18time for a custom home, probably doesn't
  1610. 53:20make sense. Figure it out on the job
  1611. 53:22site. But if you're going to build that
  1612. 53:23house a thousand or 10,000 times
  1613. 53:25>> or even 10 times
  1614. 53:26>> or 10 times, it makes sense to figure it
  1615. 53:28out in advance. And you're going to save
  1616. 53:30many many hours in the job site as well.
  1617. 53:33>> Yeah.
  1618. 53:33>> Right.
  1619. 53:34>> Here's a Florida question for you. Have
  1620. 53:36you had any projects in Miami date or
  1621. 53:38Broward counties? And how do you work in
  1622. 53:40those uh HVHZ zones, especially with
  1623. 53:43building departments? Do I assume the
  1624. 53:45building departments probably love your
  1625. 53:47system?
  1626. 53:47>> Yeah, they do. We've built in Miami
  1627. 53:49Dade. Most of our work is in Florida and
  1628. 53:51also in the islands, which are all Miami
  1629. 53:53Dade compliant. So, uh, the the the the
  1630. 53:59caveat is is that the engineers are
  1631. 54:02typically doing component level
  1632. 54:04engineering, right? They're looking at
  1633. 54:06the steel frame, the X bracing, the
  1634. 54:08board,
  1635. 54:09>> and unfortunately, we've had a difficult
  1636. 54:11time getting the engineers to consider
  1637. 54:14the structural capacity of the foam
  1638. 54:16>> because we know that it has a big
  1639. 54:18impact. That's right. But they're like,
  1640. 54:19"Hey, you know, and unless we've got
  1641. 54:21some sort of document that shows that,
  1642. 54:23then of course they're not going to
  1643. 54:24consider it." But but yeah, we've done
  1644. 54:26we've done several projects
  1645. 54:28>> in Miami Dade, Broward, Monroe County
  1646. 54:30down in the Keys, which are all Miami
  1647. 54:32Dade.
  1648. 54:32>> Yeah.
  1649. 54:33>> Yeah.
  1650. 54:33>> If I think about your system, I'm I'm we
  1651. 54:35have time for one or two more questions,
  1652. 54:37but but this is just kind of the Matt
  1653. 54:38Risinger wrap up here. When I think
  1654. 54:40about building coastal, building in a
  1655. 54:43hurricane zone, building in a floodprone
  1656. 54:45zone, tornado alley, wooi zones, the
  1657. 54:49islands, anywhere where there's termites
  1658. 54:51or mold issues, this is a bomber system.
  1659. 54:55But what they don't sell you and that
  1660. 54:57you really also need to think about is
  1661. 54:59all of your windows and doors. Because
  1662. 55:01this incredible system right here, if
  1663. 55:03you put a vinyl window in and you're in
  1664. 55:05a woo zone, the window is going to fall
  1665. 55:07out and your house is going to be
  1666. 55:08breached, right? Yeah.
  1667. 55:09>> So, you know, I would tell you that the
  1668. 55:11weak point of this system is whatever
  1669. 55:14you as the homeowner, the builder, the
  1670. 55:16architect specify for the windows and
  1671. 55:18doors. So, you know, don't do this
  1672. 55:20system and then cheap out by not putting
  1673. 55:23Miami date hurricane rated products in,
  1674. 55:25right? We probably want to do a
  1675. 55:27structural aluminum. We want tempered
  1676. 55:29glass. We want laminated glass. We want
  1677. 55:32to think about all those things that are
  1678. 55:33going to resist the winds from
  1679. 55:35breaching. We need to think about our
  1680. 55:36garage door. uh you know, our garage
  1681. 55:39door needs to be wind load rated as
  1682. 55:41well. Uh it's really important to think
  1683. 55:43of this as a full system, but man, if
  1684. 55:45you're in any of those zones, you should
  1685. 55:47be talking to these guys. This is an
  1686. 55:48incredible system.
  1687. 55:50>> And if you're a wood builder like me
  1688. 55:52who's only built with wood, these guys
  1689. 55:54will talk you through it. I think that
  1690. 55:56you could do one of these incredibly
  1691. 55:58successfully for your very first build
  1692. 56:00out there, having never worked in their
  1693. 56:02system before.
  1694. 56:03>> Yeah. Yeah. And that's a good point. I
  1695. 56:05think you touched on it earlier, right?
  1696. 56:06I mean, when you think about the
  1697. 56:08non-combust
  1698. 56:11steel framing, that's fantastic.
  1699. 56:14>> But the the MX7 board really provides a
  1700. 56:17tremendous, I think, advantage to the
  1701. 56:19wood frame because we're going to wrap
  1702. 56:21that wood that vulnerable wood frame in
  1703. 56:24MGO inside and out. We're to protect it,
  1704. 56:26you know. So,
  1705. 56:27>> uh, there's like five questions about
  1706. 56:29cost that I'm going to summarize and
  1707. 56:31we'll kind of end here. Uh, I think if I
  1708. 56:34could summarize on cost, if you're just
  1709. 56:36simply comparing this to a stick frame
  1710. 56:38build, it's going to be a percentage
  1711. 56:40more on the actual uh, just steel cost
  1712. 56:44or Kratos cost compared to your 2x4
  1713. 56:47cost. I think the big advantage here is
  1714. 56:49speed, is durability, is resilience, is
  1715. 56:53actually meeting those one, two, or
  1716. 56:55threehour fire codes with a product
  1717. 56:57that's naturally fire resistant,
  1718. 56:59naturally termite resistant. It's a
  1719. 57:02really impressive system. So, will this
  1720. 57:04look on a line item to line item car
  1721. 57:06comparison more? Probably. But go back
  1722. 57:09to those slides that we talked about
  1723. 57:10earlier. I think if you look at this
  1724. 57:11holistically from a project view and not
  1725. 57:14just a single line item view, you're
  1726. 57:16going to find this is a very compelling
  1727. 57:17system that that could actually end up
  1728. 57:19being less expensive, not more
  1729. 57:22expensive.
  1730. 57:22>> Yeah.
  1731. 57:23>> How did I summarize it?
  1732. 57:24>> Yeah, you said that's perfect the way
  1733. 57:25you just said it.
  1734. 57:26>> Yeah, it's it's it's a great point. And
  1735. 57:29and again, back to value ad, I think
  1736. 57:31that, you know, there's there's been for
  1737. 57:34a long time this conflict between the
  1738. 57:37builder's goals and objectives and the
  1739. 57:39owner operator, right? We want to get
  1740. 57:41in, build it, get out, you know,
  1741. 57:43maximize our profits and get out the
  1742. 57:44door. Where the owner operator, they
  1743. 57:46want maximum value. They want
  1744. 57:48performance. They want low energy bills.
  1745. 57:49They want longevity, low maintenance.
  1746. 57:51So, there's this constant conflict. And
  1747. 57:53I think with our system, it really
  1748. 57:55provides the foundation for us to really
  1749. 57:57achieve a win-win situation for
  1750. 57:59everybody,
  1751. 58:00>> you know, and and not that
  1752. 58:04>> the builder cannot, you know, has to
  1753. 58:07sell their house or their services for
  1754. 58:10the same price either because we're
  1755. 58:11bringing value at.
  1756. 58:12>> That's right.
  1757. 58:13>> Right. So, not only if the cost goes
  1758. 58:15maybe goes up a little bit, then you can
  1759. 58:17also sell it for a little bit more, you
  1760. 58:19know, if the customer is willing to pay
  1761. 58:20that. So,
  1762. 58:20>> that's right. Any final thoughts, guys,
  1763. 58:22before we wrap it up?
  1764. 58:23>> No, I I mean, I think we touched on
  1765. 58:25everything. I thought that was great. I
  1766. 58:27appreciate everything you've done for
  1767. 58:28us, Matt. So,
  1768. 58:29>> for sure. How How can people get a hold
  1769. 58:31of you?
  1770. 58:31>> Uh, they can email me. Uh, they can go
  1771. 58:33to the website, performancebuilding
  1772. 58:35solutions.
  1773. 58:35>> Performancebuildings.com.
  1774. 58:37>> Yep. That's it.
  1775. 58:39>> Guys, really appreciate your time.
  1776. 58:40Thanks for coming all the way to Texas.
  1777. 58:42>> Thanks for taking the time with me.
  1778. 58:44>> Appreciate it.
  1779. 58:44>> Thank you, man. We appreciate it.
  1780. 58:45>> Appreciate you for your support. Uh,
  1781. 58:47this obviously was a live webinar, but
  1782. 58:50you're probably watching this later. The
  1783. 58:52way that you can get notified about our
  1784. 58:54new webinars is by signing up for our
  1785. 58:57newsletter. We send three emails a week
  1786. 58:59because we end up having about 20 new
  1787. 59:01videos a week. If you're watching this
  1788. 59:03live, this will be sent out as a
  1789. 59:05recorded version as well. So, if you
  1790. 59:07want to send this to your production
  1791. 59:08builder buddy, to your buddy who builds
  1792. 59:10apartments, you your friend who's
  1793. 59:11building a house in the Bahamas and
  1794. 59:13should know about this system, there
  1795. 59:15will be a link coming out soon if you're
  1796. 59:17watching this live. But I appreciate
  1797. 59:18your support, guys. Uh, lastly, these
  1798. 59:21guys are going to be at Build Show Live,
  1799. 59:23correct?
  1800. 59:23>> Yep, we'll be there.
  1801. 59:24>> So, if you're coming to Build Show Live
  1802. 59:26in September, you should come talk to
  1803. 59:27these guys. Todd's a celebrity now.
  1804. 59:29Everybody knows him. [laughter] And
  1805. 59:30Kyle, you've gotten to know him the last
  1806. 59:32hour. So, make sure you tell them that
  1807. 59:33you saw the webinar and you want to ask
  1808. 59:36those specific nerdy questions that
  1809. 59:38maybe I didn't get to today. They're
  1810. 59:39going to answer those live. Build Show
  1811. 59:41Live is in San Antonio September 10th
  1812. 59:43through 12th. Build Show Live for
  1813. 59:45tickets. And you can see a lot of
  1814. 59:47incredible companies like the guys, like
  1815. 59:49these guys, as well as all 20 of our
  1816. 59:51contributors teaching you how to build a
  1817. 59:54better, more resilient, more durable,
  1818. 59:57more healthy house, cuz that's what
  1819. 59:58we're all about here. That being said,
  1820. 1:00:00guys, follow us on Instagram, follow us
  1821. 1:00:02on Facebook or Instagram. Otherwise,
  1822. 1:00:04we'll see you next time on the Build
  1823. 1:00:06Show webinar.
  1824. 1:00:13>> [music]

About this transcript

This page contains the full transcript of Resiliency in Construction: Better Materials & Methods for High Performance by Matt Risinger, generated from the public captions YouTube serves with the video. The transcript has 11,935 words across 1,824 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.