Resiliency in Construction: Better Materials & Methods for High Performance — Transcript
Full transcript
- 0:00All
- 0:05>> [music]
- 0:07>> right, my friends. Welcome back to
- 0:09another episode of the Build Show
- 0:13webinar. That's right. This is our time
- 0:15to get together and go deep on a
- 0:17particular topic. And we are talking
- 0:19today about resiliency. And I'm going to
- 0:22show you a wall concept that I bet
- 0:24you've never seen before. I met these
- 0:26guys at the International Builder Show
- 0:28and it was a display very similar to
- 0:31this that I kind of ran across and I met
- 0:34Todd, the founder and the COO of this
- 0:36company and Todd and I immediately hit
- 0:39it off. I fired off a hundred questions
- 0:41that he answered right away and I was
- 0:44like, man, this is really, really
- 0:46compelling, especially with this theme
- 0:48that we're talking about today, disaster
- 0:50resilience. So Todd Wright, founder and
- 0:52CEO. I've also got with me uh Kyle
- 0:56Hintan. Hintley.
- 0:57>> Yeah, you said it right. It's a tough
- 0:59one, but he's our sales guy. He's going
- 1:01to help you out in the future when
- 1:02you've got some sales uh that you want
- 1:04to talk to these guys about.
- 1:06>> But on this theme of resilience that
- 1:08we're talking about today, this is a
- 1:09really big deal nationally for us, Todd.
- 1:12And it's a big deal because of this
- 1:14slide right here. I mean, this stuff is
- 1:16happening and is in the news all over
- 1:18the place, isn't it?
- 1:19>> Yeah, it is. I mean from California to
- 1:21Florida, we've had Palisade fires, we
- 1:24have hurricanes constantly um in Florida
- 1:27and also here in Texas. So, you know,
- 1:30we're just plagued with uh all kinds of
- 1:32issues from mother nature all across the
- 1:35country, earthquakes, fires, hurricanes,
- 1:38etc.
- 1:39>> For sure. And if you look at this mockup
- 1:41wall that we put up here, that is what I
- 1:43would consider traditional framing. I
- 1:45mean, this is how we've been building in
- 1:46America for hundreds of years. is maybe
- 1:49not with 2x4s for hundreds of years, but
- 1:51with wood construction since our log
- 1:53cabin days.
- 1:54>> My [clears throat] cousin owns a 250y
- 1:56old log cabin. By the way,
- 1:57>> wow, that's But you know, we've been
- 1:59building with wood for a long time. And
- 2:01wood is great
- 2:02>> except for when it isn't. Except for
- 2:04when there's a fire or except for when
- 2:06you've got some mold issues or mold size
- 2:08of clients or except for when the
- 2:09termites come uh for that house. So,
- 2:13with that being said, Todd, uh let's
- 2:15actually show these guys, jump right
- 2:17into the mockup because what you guys
- 2:19have done is very different uh than what
- 2:24most people think of. And actually, I'm
- 2:25going to hang on one sec. One quick sec.
- 2:27Will you guys meet me over at the uh at
- 2:29the display here? Sure. Cuz I want to I
- 2:30want to start with this demo of how your
- 2:34system holds up against uh fire in
- 2:38particular. So, let's actually roll this
- 2:40video as we're coming out here.
- 2:41>> Yeah. So, what are we looking at on this
- 2:43video, Tob?
- 2:45>> So, this is a fire test that we did last
- 2:47week uh at our uh location in Florida.
- 2:51>> We essentially took a frame pretty close
- 2:53to this one right here. We wrapped it in
- 2:56MGO inside outside full credo system and
- 3:00then uh we put about 10 pallets inside
- 3:03and outside around the around the
- 3:05building
- 3:05>> and you could see the fire burning
- 3:07raging fire inside and outside on your
- 3:09wall assembly, isn't it? It was was
- 3:11actually pretty hot. We were a little
- 3:12over 100° that day and uh the fire uh
- 3:15got to about 1100°.
- 3:17>> Oh my gosh.
- 3:18>> And um we let it run for about an hour
- 3:20and and then we put it out. But uh
- 3:22>> and then part two of this video that
- 3:24we're playing now is after how long this
- 3:26video is playing?
- 3:27>> Uh this is about I think 48
- 3:32maybe 48 to 55 minutes or so.
- 3:34>> Okay. So about an hour later.
- 3:36>> Yeah.
- 3:36>> Yeah. We're ready to do some barbecue in
- 3:38there. Don't you think? It looks like
- 3:39you're ashed over, but it looks to me
- 3:41like your wall is also solid still. I'm
- 3:43just still standing.
- 3:44>> Yeah. Yeah, it is. Um, you see that back
- 3:47wall inside, you know, that was engulfed
- 3:49with flames.
- 3:50>> Mhm.
- 3:50>> And um unlike a typical fire, we've got
- 3:53flames on the inside and the outside of
- 3:55the building simultaneously. So, we
- 3:57really, you know, we're putting it to
- 3:58the test.
- 3:59>> Yeah, you were big time.
- 4:00>> Yeah. So, that particular uh
- 4:02configuration has a 12-in webbased floor
- 4:06system.
- 4:07>> Okay. made of cold form steel. It has an
- 4:09MGO uh subflooring. It has half inch MGO
- 4:13on the inside and then it has the MX7
- 4:16board on the outside of the building.
- 4:18>> Okay. So, now that you've seen that
- 4:20demo, let's show you a very similar
- 4:22mockup to exactly what you saw in that
- 4:24fire test a second ago. And and just for
- 4:27the uh the understanding of some of the
- 4:29logos and such, let me let me explain to
- 4:31you real quick. Uh their company is
- 4:33called Performance Building Solutions,
- 4:35right? So when you look at their
- 4:36website, performancebuilding solutions,
- 4:38but Kratos build and the Kratos wall is
- 4:41what exactly, Todd?
- 4:42>> Yeah. So it's really our building
- 4:44system. U we branded the product
- 4:47separate from the company, right? So
- 4:49>> um the Kratos wall is what we're looking
- 4:52at here, which is your exterior wall.
- 4:54>> So when I look at this, I think this
- 4:56looks like a lot like a commercial
- 4:58building to me, right? We
- 4:59[clears throat] we're building with
- 5:00platform uh concrete platforms and then
- 5:03we've got infill between the red iron.
- 5:05This is what I would see. Steel studs.
- 5:07>> Exactly.
- 5:08>> And something that's fireproof on the
- 5:09outside.
- 5:10>> Exactly. That's what we've done. We're
- 5:11essentially taking commercial grade
- 5:13construction, best of breed materials,
- 5:16and then bringing that to the
- 5:17residential market,
- 5:19>> but doing it in a way where we're doing
- 5:20it in a factory, right, which is
- 5:22industrialized construction.
- 5:23>> So, in other words, this is in effect a
- 5:26SIP panel. You know, when I think of
- 5:28SIPs, I think of the acronym structural
- 5:30insulated panel. And so, their company
- 5:33builds these panels in a factory. We're
- 5:35going to get into that in a minute.
- 5:37Ships them to the job site and you put
- 5:39them together. Uh, no organics. You're
- 5:42going to not see any wood in this system
- 5:44at all. And in fact, there's not even
- 5:46any paper facing as well cuz they've
- 5:48used this magnesium oxide board on the
- 5:50inside and the outside. But also what's
- 5:53different about this than a traditional
- 5:54SIP is your cavities are open like
- 5:57you're seeing on this back wall. Right.
- 5:59>> Right. Right. I mean that's if you've
- 6:01worked with SIPS, which I know you have
- 6:03in the past. Right. Couple of the few u
- 6:05couple of the issues that we run into
- 6:07with SIPS is that we get a lot of
- 6:09complaints from the trades, all the MEP
- 6:11trades, the inspectors can't see in the
- 6:13wall. Connections are an issue. So, um,
- 6:17we set out to try to achieve what was
- 6:21already achievable with the SIP panel by
- 6:24eliminating the thermal bridging, which
- 6:25I know we're going to talk about, but at
- 6:27the same time address the issues and
- 6:29challenges that we have with traditional
- 6:31SIP. Yeah.
- 6:31>> So, this is like a hybrid ZIP. We call
- 6:33it a CIS, which is a structural
- 6:35insulated system. Gotcha.
- 6:37>> Because we don't just sell wall panels,
- 6:39>> right? We're trying to um do a holistic
- 6:42design and engineering of the entire
- 6:43building.
- 6:44>> I like it. So the Kratos the Kratos wall
- 6:47is the exterior wall but the Kratos
- 6:49build is the entire structure. So that's
- 6:51your exterior walls, your interior
- 6:52walls, columns, beams, floor trusses,
- 6:54roof trusses, flashings, fasteners,
- 6:57sealants, the whole thing essentially as
- 7:00a kit, right, that you're going to tilt
- 7:02up wall in the in the field.
- 7:03>> Gotcha. Now steel framing obviously
- 7:06moldproof, obviously termite proof, very
- 7:09floody, right? And if I had a flood that
- 7:11occurred in this wall back here and you
- 7:14see I've got some closed cell foam, all
- 7:16I'd have to do is pull that cavity
- 7:17insulation out. And if this is a
- 7:20magnesium oxide board, will you hand me
- 7:21that board right behind me? By the way,
- 7:23uh this is also one of their products.
- 7:26This magnesium oxide board won't absorb
- 7:28water. Uh it's naturally mold resistant
- 7:30because there's no organics. I could
- 7:32actually remove that panel, dry out the
- 7:36cavity, and move on. Well, not only we
- 7:39were in the ninth ward of Louisiana, we
- 7:41could survive, right?
- 7:42>> Exactly. We actually had that happen to
- 7:44a house there, but uh
- 7:46>> uh the other important aspect of that is
- 7:49you can actually put the same board back
- 7:51on.
- 7:51>> Oh, how about that? Yeah,
- 7:52>> that's awesome.
- 7:53>> Yeah. Yeah. So, you're not sending all
- 7:54that, you know, like you would typically
- 7:56gut the entire thing and send that
- 7:58chipboard to the landfill, right?
- 7:59>> So, it's a very lose it structural
- 8:02abilities by getting soaked or
- 8:03underwater for a day or two.
- 8:04>> No, it's not. We've had these panels
- 8:06outside for over a year at our factory
- 8:08just sitting outside being rained on
- 8:12constantly. So, we should send you a
- 8:13couple of those samples so you can look
- 8:15at it. Yeah.
- 8:15>> Now, here's the downside of steel in my
- 8:17mind, though. I'm worried that if I get
- 8:19air leakage in here, especially if I'm
- 8:21building a house in the south. You know,
- 8:23you guys are based in Florida. I'm based
- 8:25here in Texas. If I'm building a Florida
- 8:27coastal house with this, it's often hot
- 8:29and humid out. I'm worried if I get any
- 8:31air leakage in this cavity, this steel
- 8:33is going to be the same temperature as
- 8:35my air conditioner. Uh, and I'm going to
- 8:37have some condensation issues. But
- 8:39you've addressed that. How, Todd?
- 8:41>> Well, the first thing that we have to
- 8:43address is the thermal bridging, right?
- 8:45You I mean, you flew all the way to
- 8:47Australia, right?
- 8:48>> Saw steel framing steel framing and I
- 8:50was sure worried about it.
- 8:51>> Exactly. No, it was a great point. Uh,
- 8:53so I I I love that uh that episode. So
- 8:57one of the one of the first things that
- 8:58we need to do is we need to eliminate
- 9:00the thermal bridging right so that's
- 9:02going to eliminate that cond you know
- 9:04that temperature variation and the and
- 9:07the uh uh the condensation to form
- 9:10>> and there's you know for a long time
- 9:12there's been a lot of conversation about
- 9:14breathable walls right hey those walls
- 9:16need to breathe we see those comments
- 9:18all the time
- 9:19>> but in reality the walls need don't need
- 9:21to breathe people need to breathe right
- 9:23so what we need to do is we need to make
- 9:26that there is a way for that wall to um
- 9:29exchange humidity, right? And that's
- 9:32inside. So by, you know, there's a
- 9:35saying, right? Build tight, ventilate,
- 9:37right?
- 9:37>> That's right.
- 9:38>> Right. So that's what we're trying to
- 9:39do. So we want to stop that air
- 9:41infiltration or leakage on the outside
- 9:44and let the wall breathe inside with the
- 9:47controlled humidity
- 9:48>> and air conditioning inside the house.
- 9:50And the other thing you've done with
- 9:51this assembly is this magnesium oxide
- 9:54board that's bonded to insulation is
- 9:57their product. They call this the MX7
- 10:00panel. So this sheathing that's on the
- 10:02outside is mag oxide. And that sheathing
- 10:05is bonded to, in this case a half inch,
- 10:07but it could be greater if you wanted
- 10:09to. Uh EPS foam. So now when you look at
- 10:12this sandwich, actually Kyle, will you
- 10:13help me rotate the wall here a little
- 10:15bit?
- 10:15>> Absolutely. You're going to notice that
- 10:18that sandwich is actually glued on to
- 10:21the assembly. Okay, that's probably good
- 10:24for now because I want to be able to
- 10:24share this side. So, this sandwich is
- 10:27actually glued on. And you can see a
- 10:28little bit of that glue right there.
- 10:31It's probably, I would guess, a
- 10:32polyurethane glue. They have a patent on
- 10:34this, so we probably can't tell you all
- 10:35the secret sauce. Uh, but that assembly
- 10:38is glued on. And then if you look in the
- 10:40back here, then at the factory, they've
- 10:44sprayed in a couple of inches of closed
- 10:47cell foam on top of that. So that whole
- 10:50assembly is a structural panel. It's
- 10:53been insulated and it's got a thermal
- 10:55break at all these steel studs. But the
- 10:58cool part about that is I've got an open
- 11:00stud bay that I can bring the
- 11:02electrician in. I can bring the plumber
- 11:04in and run all those services inside of
- 11:06that service bay. And then if I want to
- 11:08add additional insulation, you see he's
- 11:10got some rockwool bats in here, let's
- 11:12say, or that could be fiberglass. That
- 11:14could be whatever you could add more
- 11:15spray foam if you want. Then I could add
- 11:17additional cavity insulation. But what's
- 11:20cool about this now? Let's complete the
- 11:22rotation cuz I want to show them this.
- 11:24>> They can actually go right over top of
- 11:26this mag oxide board with what, Todd?
- 11:30What are we looking at here? This green
- 11:31face.
- 11:32>> Uh, this is a synthetic elastoic struck
- 11:36uh stucco. Mhm.
- 11:37>> Um it's what we call direct apply. We're
- 11:39all familiar with the EF system.
- 11:41>> Uh so this is called the DEF system,
- 11:44direct apply finish system, DFS.
- 11:46>> And um with the MGO board like
- 11:49cementitious type board, we're able to
- 11:51go directly to that substrate.
- 11:54>> Uh the in this particular case,
- 11:56>> so in other words, this isn't
- 11:57traditional L and plaster stucco. This
- 12:00is basically something that's adhering
- 12:02right to that cementitiousbased board.
- 12:05>> That's right. And it becomes the air
- 12:06barrier to the water barrier and you've
- 12:09got a sanded kind of coat with an
- 12:11elasame paint in the front. That's
- 12:12right.
- 12:13>> So that's your finish as well.
- 12:14>> Right. In fact, it comes in color.
- 12:16>> So with this this particular
- 12:18application, your Let's talk about the
- 12:20layers, right? So your first layer of
- 12:22course is the boards already part of the
- 12:24panel. When you tilt that wall up,
- 12:26you've already solved seven issues or
- 12:28seven trades.
- 12:29>> Okay. What are those?
- 12:30>> That's that's why you have the seven,
- 12:32right? So, you have your there's
- 12:33actually a few more, but essentially
- 12:35you've got your structural frame,
- 12:37>> you have your insulation, you have all
- 12:39your hold downs, okay? You have your
- 12:41exterior um continuous insulation, your
- 12:45CI,
- 12:46>> you've also got your exterior sheathing.
- 12:48>> You've got your fire rating.
- 12:50>> Okay. And
- 12:51>> what is the fire rating on this?
- 12:52>> So, this particular uh panel is the 1 in
- 12:56MX7.
- 12:57>> We rotate.
- 12:58>> So, it's 1 hour.
- 13:00>> It's a 1 hour. 1 hour. Yeah, the 1/2 in
- 13:02MGO is a 1 hour.
- 13:04>> So, you know, I actually have a big
- 13:06lighter over here and I was thinking
- 13:08about uh you know, putting this big
- 13:10lighter. I don't know if this is legal
- 13:11at the
- 13:12>> Oh, no. No. To see if this would
- 13:15actually catch fire.
- 13:16>> No, no, we don't want that. We want
- 13:17this.
- 13:18>> Oh, what do we got?
- 13:20>> Come on.
- 13:21>> All right. So,
- 13:22>> let's crank it up. So, we got the MX
- 13:25panel
- 13:26>> and we've applied it to wood framing
- 13:30instead of uh steel studs.
- 13:34>> Yeah.
- 13:36>> Check that out. That's pretty legit.
- 13:40>> It's up full blast.
- 13:43>> So, we're I don't know 1,000° or so on
- 13:46that magnesium oxide board. But you
- 13:49notice this is this is being applied to
- 13:51standard wood framing which they'll sell
- 13:53you just the magnesium oxide board.
- 13:55>> Wood's not going anywhere right in the
- 13:57Northeast everybody's using wood frame.
- 14:00>> Very little light gauge steel going on.
- 14:02Um
- 14:03it's it's coming down the pike but it's
- 14:05not there yet. So this is a great option
- 14:07here. You have your continuous
- 14:08insulation MGO panel. So you have your
- 14:10fire rated panel. You have it's water
- 14:13resistant. It's uh pest resistant. It's
- 14:15mold and mildew resistant. So, allin-one
- 14:18and your continuous insulation.
- 14:19>> It's pretty compelling.
- 14:21>> And Todd, when I met you at the
- 14:22International Builder Show, you had a
- 14:24sample uh of this MX7 board going with a
- 14:28torch that it looked like it had been
- 14:29sitting there for a while. This wasn't a
- 14:31two-minute demo like this.
- 14:33>> Yeah. In fact, we brought it with us.
- 14:35So, this ran about 3 hours. Uh what's
- 14:38impressive about this is that um it's
- 14:41only the half inch version. So, it's
- 14:43only rated to an hour. So you started
- 14:44this at 1, you know, 130, let's say, ran
- 14:47it for 3 hours, and that's how much
- 14:49damage was done to the face. It does not
- 14:51look like this has been structurally
- 14:53damaged.
- 14:54>> A little charring. You can
- 14:56>> And this is um
- 14:58>> Yeah. So this is
- 14:59>> technically this is only a 1hour fire
- 15:01rated wall, though.
- 15:02>> Right. Right. Technically,
- 15:03>> and part of that is because a little bit
- 15:04of the heat transferred through, right?
- 15:07>> And the EPS foam a little bit on the
- 15:09back melted. Now, not very much,
- 15:11frankly, and not a lot of damage.
- 15:14But that's not bad for three times what
- 15:16it's rated life at.
- 15:17>> Yeah. Yeah. And what I thought was
- 15:18interesting was one, you know, the EPS
- 15:21has air bubbles in it, right? So there's
- 15:23no offging or anything like that, but I
- 15:26thought it was interesting that the size
- 15:29of this area pretty much matched.
- 15:31>> Yeah. This,
- 15:32>> you know, so we didn't have a lot of
- 15:33propagation
- 15:35>> of the heat beyond the the the initial
- 15:38or direct impact of the flame. I thought
- 15:40that was
- 15:40>> was kind of interesting. Now, that
- 15:42coupled with wood framing is going to
- 15:44meet your, let's say, 1 hour rating if
- 15:46you're in a WOOI zone. Um, but we can
- 15:49also meet two or three hour ratings by
- 15:51doing what, guys?
- 15:52>> Well, so you have different thicknesses
- 15:53of the boards, right? So, you can go
- 15:55from/ inch to 5/8, right? Uh, and then
- 15:58you can also get a higher R value if
- 16:01you're doing EPS foam on the back if
- 16:02you're using the MX7 board. And you can
- 16:05do/ inch, 5/8, all the way up to an
- 16:08inch,
- 16:09>> three up to 3/4 in ongo.
- 16:11>> And do you guys have Oh, okay. So So we
- 16:13could go even a 3/4 MGO board.
- 16:16>> And so you guys in other parts of the
- 16:17world, didn't I hear you have an islands
- 16:19project going that has a three-hour
- 16:21rated fire?
- 16:21>> Yeah, we do. Yeah, we have a we have a
- 16:23project right now in the Bahamas that
- 16:25requires a three-hour fire rating
- 16:27because of the proximity of the
- 16:28buildings, uh, according to the Bohemian
- 16:30building code.
- 16:30>> How about that? So they're limited in
- 16:34being able to build with wood maximum
- 16:37two stories. Gotcha.
- 16:38>> And then they were limited to building
- 16:39with the CMU block and cast in place
- 16:42because of the cost and the weight.
- 16:44>> And so the light gauge steel system fit
- 16:46perfectly because it's non-combustible.
- 16:48We could go up to four stories
- 16:50>> and um also provided three-hour
- 16:53firewall. So looking at all the
- 16:55different building technologies, we
- 16:57really fit, you know, perfecting
- 16:59>> for that particular build. Now, let's uh
- 17:02explain to these guys from the bottom to
- 17:03the top real quick.
- 17:05>> Sure.
- 17:05>> Uh what you've got going on. So, first
- 17:07off, this floor framing system is also
- 17:10[snorts] like gauge steel and comes out
- 17:12of your factory.
- 17:13>> And what are we seeing in here when we
- 17:15look in this cavity?
- 17:16>> Yeah, we wanted to leave it open so you
- 17:17could see one I mean whether you're
- 17:19using a mineral wool or a bad insulation
- 17:21really, you know, doesn't matter. But if
- 17:23you look back in there, you'll see a
- 17:24solid sea joist.
- 17:26>> Okay. So we have equipment that can take
- 17:28the coils of steel and uh either you
- 17:32know roll stud or truss profiles or deep
- 17:34sea joist
- 17:36>> um you know which are
- 17:38>> well right and the nice thing about it
- 17:39when you do the rim tracks with the sea
- 17:41joist
- 17:42>> you can typically span a little further.
- 17:44>> Yeah.
- 17:44>> Um you don't have the assembly aspect in
- 17:47the factory so they're a little less
- 17:48expensive.
- 17:50>> Uh but on the other hand they're
- 17:51restrictive in that we really can only
- 17:53go 14 in. So 14, 12, or 10.
- 17:56>> Okay.
- 17:57>> So when we're looking at maybe a floor
- 17:59system that needs to be 24 in or even
- 18:02greater depending on the span, we'll
- 18:04need to uh resort to the web based
- 18:07>> trusses. Trusses.
- 18:08>> Yeah. Gotcha. And then what is this
- 18:09subfloor that's on top of this?
- 18:11>> This is a 3/4 in uh tongue and groove
- 18:16uh MGO board.
- 18:17>> Ah, so we also have a fire rating with
- 18:19that as well.
- 18:20done in condos or
- 18:22>> multifamily or mixed use residential
- 18:25commercial. This would also help us with
- 18:27our fire.
- 18:28>> Right. Right. And the interesting thing
- 18:29about this, this is a a product also
- 18:32that we make with one of our partner
- 18:34companies
- 18:35>> uh called Q Rock. And essentially what
- 18:36we're doing is we're marrying the
- 18:39acoustic mat to the underneath of the
- 18:42MGO board.
- 18:43>> Got it. So it's a little hard to tell,
- 18:44but this is actually an acoustic
- 18:47>> mat right in here. That's that comes
- 18:50already pre-applied to the
- 18:52>> already pre-applied
- 18:52>> and is gonna separate thermally and more
- 18:56more importantly acoustically. That's
- 18:58right.
- 18:58>> From this subfloor. So impact noises and
- 19:01other sound is not going to vibrate this
- 19:03like it would if it was mechanically
- 19:05attached MGO to steel.
- 19:07>> Y that's really smart.
- 19:08>> Yeah. And the other nice part about this
- 19:10is that you see it's underneath the
- 19:11subflooring where traditionally they'll
- 19:13install it as a separate process or a
- 19:15separate step with another crew when
- 19:18they install the final flooring.
- 19:19>> So here we're protecting that mat in a
- 19:21single install.
- 19:22>> That's pretty cool.
- 19:23>> Same concept as this MX7 board, right?
- 19:25We marry two products that are already
- 19:27going to go together
- 19:28>> together and we reduce our labor and our
- 19:31waste.
- 19:32>> I'm noticing that I've actually got a
- 19:34hold down in that cavity. Did that come
- 19:36from from your factory as well?
- 19:38>> Yeah. What we will typically do is is we
- 19:40will pre-install all the hold downs,
- 19:42clips, and connectors that go in the
- 19:45exterior wall in the factory. So that
- 19:48way we make sure that one they don't
- 19:50miss it. You know, a lot of times in the
- 19:51field
- 19:52>> there'll be an installation and they'll
- 19:53miss a hold down or a clip or some sort
- 19:55of connector
- 19:56>> and then of course the inspectors come
- 19:58and it's not there. So, um, we will, as
- 20:01a standard practice, pre-install all of
- 20:04the hold downs in those walls and even
- 20:07the X-racing as well.
- 20:09>> That's pretty awesome.
- 20:09>> Yeah.
- 20:10>> Now, isn't it a pain though for trades,
- 20:12Todd, cuz I got to drill this stud, then
- 20:15I got to find this plastic connector and
- 20:17I got to figure out where all my wiring
- 20:19and my electrical goes. Talk to me about
- 20:22transferring from a wood-based
- 20:24construction process to a steel-based.
- 20:26How hard is it?
- 20:27>> [snorts]
- 20:27>> Well, actually what we're what we're
- 20:30able to do is reduce about 50% of the
- 20:32labor
- 20:33uh with the MEP trades, especially the
- 20:36plumbing and the electrical by pre-
- 20:39punching all the service holes in the
- 20:40factory.
- 20:41>> Ah, so this actually comes from the
- 20:42factory.
- 20:43>> That's right. That's right. So unlike,
- 20:45you know, going to some sort of source
- 20:48for generic stud and track material
- 20:51that's generic, you have the same issue
- 20:53that you would if you're working with
- 20:55wood studs, right? you're having to pull
- 20:56through that, you're having to cut it,
- 20:58>> and you're having to drill all those
- 20:59holes. So, uh, one of the nice things
- 21:02that we can do to help the builder is do
- 21:06what we call value engineering. So,
- 21:09you'll see here these noggin
- 21:12uh here and here as an example. You'll
- 21:13see the noggin.
- 21:14>> So, the horizontal cross bracing is
- 21:16called a noggin.
- 21:17>> Yeah, it's called a noggin. So,
- 21:19>> so in other words, this noggin that I'm
- 21:20seeing here was pre-applied at the
- 21:22factory. That's right. Right. So, the
- 21:23electrician only had to just drop his
- 21:25box in there and screw it down. It's
- 21:26done.
- 21:27>> Yeah. Or if we know precisely where the
- 21:30boxes go, we can pre-install those as
- 21:31well.
- 21:31>> Is that right? Okay.
- 21:32>> Yeah. Wow.
- 21:33>> We usually like to stay inside the
- 21:34cavity.
- 21:35>> Very cool.
- 21:36>> Um but at least we resolve one of the
- 21:38dimensions.
- 21:39>> Yeah.
- 21:40>> Right. So, you're cutting the
- 21:41dimensioning by 50%. All they got to
- 21:42figure out is one, they got to know
- 21:44where that box goes
- 21:45>> and then they just need to figure out
- 21:47the horizontal dimension.
- 21:48>> Makes a lot of sense. But uh you know
- 21:50you get into production builds where
- 21:51you're building the same house or models
- 21:54over and over again hundreds or
- 21:55thousands of times. It would make sense
- 21:57to go through the value engineering
- 21:58process, determine where every box goes,
- 22:01every switch, every outlet,
- 22:03>> every cold and hot water routing, and
- 22:06pre- punch all of those.
- 22:08>> When I was a production builder back in
- 22:10the old days, uh there was a couple
- 22:12models that were real popular uh in the
- 22:14community that I was building. I was
- 22:16building for one of the top 10 national
- 22:17builders. I remember, for instance, the
- 22:19Chesterfield model. I could just about
- 22:22build that house in my sleep. I could
- 22:23walk into any room blindfolded and I
- 22:26could tell you where all the outlets
- 22:27were going,
- 22:28>> uh, exactly what that room looked like
- 22:29cuz we built that house
- 22:31>> uh, probably hundreds of times over the
- 22:33course of a couple of years.
- 22:35>> Sure.
- 22:35>> And so it really think I think to
- 22:38myself, hey, if you're watching this and
- 22:40you're a custom builder like me, you
- 22:42should get your production builders to
- 22:43watch this. I would think that you guys
- 22:45would be an absolutely bomber perfect
- 22:49fit for any production builder that's
- 22:51building anything uh on a repetitive
- 22:53basis or a large basis and certainly
- 22:57custom builders that are in any zone
- 23:00that's a disasterprone zone. I mean,
- 23:02when I look at the bones of this
- 23:04structure and I think about flooding and
- 23:07I think about tornado alley and I think
- 23:09about coastal builds that have
- 23:10hurricanes, this is pretty bomber. This
- 23:13is pretty impressive.
- 23:15>> Yeah. I mean, you think about what the
- 23:16cost just at the national level is,
- 23:19right? For us to build to code.
- 23:21>> Yep.
- 23:22>> All right. And not to build performance.
- 23:24I mean, you're looking at somewhere
- 23:25anywhere from 130 to$ 160 billion
- 23:27dollars
- 23:28>> a year is our cost at the national
- 23:31level. Wow.
- 23:32>> For, you know,
- 23:34>> all the rebuilding for disasters, fire,
- 23:36termite, mold, etc.
- 23:38>> Let's actually go back to that slide
- 23:39while we're talking about it.
- 23:41>> Yeah. I mean, it it's crazy how much
- 23:43time we spend on uh on rebuilding. And
- 23:46I'm going to back up to that slide just
- 23:47to uh show it right here. Um but this is
- 23:51the slide that we started out. And
- 23:52that's that's the number that Todd just
- 23:54referenced right there. 130 billion
- 23:57dollars annually and basically disaster
- 24:01rebuilds that [snorts] if we built with
- 24:03a system like yours, we wouldn't have
- 24:04to. Now, we might have to redo some
- 24:06finishes or some claddings on the
- 24:08outside, but the structure would be
- 24:10perfectly fine there.
- 24:11>> Yeah. I mean, and not only that, but
- 24:13just the long longevity, right? We're
- 24:15we're here today to talk about
- 24:16resiliency, and part of that really is
- 24:18the durability of that building to
- 24:20extend the life of it.
- 24:22>> So, you look at a traditional wood frame
- 24:25house today,
- 24:27>> um you know, you're looking maybe 60, 70
- 24:29years of a lifespan. Yeah.
- 24:31>> Based on the quality materials that
- 24:33we're using.
- 24:33>> Crazy. So we really need to look at um
- 24:37the building holistically as a system.
- 24:39>> Mhm.
- 24:40>> Uh from the HVAC to the exterior thermal
- 24:43bridging making that thing perform
- 24:45better. Um but also you know back to
- 24:48that slide we've seen the human cost of
- 24:50that as well. just in fires per year, we
- 24:53lose about 2,600 lives here in the
- 24:55United States. By essentially removing
- 24:58the organics out of the building and
- 25:01focusing on the bones of the structure,
- 25:04uh we can make a huge difference in the
- 25:06long-term value
- 25:08>> and performance of that structure. It's
- 25:11going to, you know, perform better and
- 25:14it's going to last two times minimum two
- 25:17times longer.
- 25:17>> And speaking of bones, check this out,
- 25:19guys. This is really compelling. This is
- 25:22a 3D model uh of all the structure that
- 25:26would come from their factory to your
- 25:29job site. They're able to model
- 25:31structurally the interior walls, the
- 25:33exterior walls, the rafters. You know,
- 25:35in this case here, like [clears throat]
- 25:36for instance, this X bracing went a
- 25:38little too fast flying through the
- 25:40building. That X bracing was there on
- 25:42purpose as additional shear value that
- 25:44the engineer put in. And if I zoom into
- 25:47this floor cavity, uh, let's see if I
- 25:50can do it well for us, Todd. We can see
- 25:53that these trusses have been lined up.
- 25:56And I could actually fly through that
- 25:58truss bay if I was good enough with my
- 25:59mouse to show you that it would
- 26:02[clears throat] be really easy, let's
- 26:03say, in this bay right here to route our
- 26:06uh HVAC system that we pre-planned to go
- 26:09into that system. So the uh the amount
- 26:12of forethought that's done uh with your
- 26:16system so that I can as a builder
- 26:18understand what I'm about to build is
- 26:20amazing. But that also yields some
- 26:22additional benefits which I think are on
- 26:24this slide right here. Let me go back to
- 26:26the slideshow presentation. U by the way
- 26:28I forgot to say this at the top of the
- 26:30hour. If you guys have questions and
- 26:32you're watching this live, I know a lot
- 26:34of you are going to watch this later.
- 26:35I'm sorry you missed the live version.
- 26:37Uh, but if you're watching this live,
- 26:39there's a Q&A tab. I'm looking at the
- 26:41Q&A's here. We're going to leave some
- 26:42time at the end uh to make sure we
- 26:44answer your Q&A time. So, throw your
- 26:46question there. And if you're not
- 26:48watching this live, be sure to ask uh
- 26:50for the link below for our newsletter
- 26:52that you can sign up. That's how you
- 26:54know when we've got these live webinars
- 26:55going on. But back to that, uh Todd,
- 26:58talk me through what we're seeing here
- 26:59in terms of the challenges that we face
- 27:00today and how you guys meet those
- 27:02challenges. I know that you probably
- 27:04know more about these challenges, you
- 27:06know, than than we do because you're on
- 27:08a daily basis. You're in the mix on a
- 27:09daily basis. But, uh,
- 27:11>> yeah, I mean, we've had a shrinking
- 27:13workforce. We've got a workforce that is
- 27:15not as as qualified, right? We in
- 27:18general, you know, when you look at the
- 27:20journeyman and the different trades,
- 27:22especially in the MEP trades,
- 27:24>> we're losing four to seven
- 27:28uh workers in those trades compared to
- 27:31one journeyman coming into the trade.
- 27:33So, all those trades are shrinking,
- 27:35right? So, we ought to do more with
- 27:37less. Y
- 27:38>> and part of the way that we can um
- 27:40address that particular challenge is by
- 27:42moving the fabrication of the shell to
- 27:45the factory where we can control
- 27:48>> u not only the products we can control
- 27:50waste we can work three shifts right
- 27:52under a roof
- 27:54>> uh we're not worried about the weather
- 27:56>> and so um we can minimize the amount of
- 28:00labor that's required in the field
- 28:02>> by up to around 50% as far as putting
- 28:04the shell up because as I mentioned
- 28:06earlier earlier when you tilt that wall
- 28:08up, you've you've already resolved many
- 28:11many um other uh aspects of that of that
- 28:15shell building. That's right.
- 28:16>> So,
- 28:17>> so then let's go to answering this
- 28:19question, which is really in general,
- 28:22why steel? And uh what's the difference
- 28:25on your system compared to let's say
- 28:27standard wood framing and the systems
- 28:29that we've been using for decades?
- 28:30[clears throat]
- 28:31>> Yeah, good question. Um, essentially
- 28:32what we're trying to do is we're trying
- 28:34to eliminate the organics out of the
- 28:36building, right? The organics really are
- 28:39the fuel and the food for all of the
- 28:41problems that we have. So if you were to
- 28:43try to do a, you know, a root cause
- 28:45analysis, right? What is the cause of
- 28:48all of the issues and challenges that we
- 28:49have today?
- 28:51>> So besides building in the field field,
- 28:54we have the materials that we're using.
- 28:55So it goes back to materials and methods
- 28:58and that's really our focus. Let's use
- 29:01best of breed materials. Let's use more
- 29:05um you know efficient methodologies
- 29:09and try to remove those things where we
- 29:11have a lot of waste in the field to the
- 29:13factory where we control them better. So
- 29:15that's really what we're trying to do in
- 29:17essence is remove the organics out of
- 29:19the building. And you start with the
- 29:21bones.
- 29:22>> Now cabinets, those can be swapped out.
- 29:25Flooring, you can swap those out. You
- 29:27can paint the walls. You can fix all of
- 29:28those things later. But to change the
- 29:31bones of the structure, it's not not
- 29:33going to happen after it's built, right?
- 29:34>> No, it's not going to happen.
- 29:35>> So,
- 29:36>> and this cutaway is kind of a compelling
- 29:38one with with your system.
- 29:40>> Uh really just reviewing what we talked
- 29:42about already with strength and
- 29:44performance and uh disaster mitigation.
- 29:47But let's let's actually talk about your
- 29:49value proposition and where you guys
- 29:52stack up uh in terms of uh building with
- 29:55you versus building with traditional
- 29:57materials. If you look at that slide,
- 29:59you'll see we have the same components,
- 30:01right? We still have operational cost,
- 30:03we have waste, we have labor, um, and we
- 30:05have the actual building materials. Uh,
- 30:07but again, by changing our focus to
- 30:11using highquality materials and
- 30:14industrialized construction, we're
- 30:16basically um, Robin Peter to pay Paul,
- 30:19right? We're pulling money out of the
- 30:21other line items in that construction
- 30:22budget and we're moving them to the
- 30:25material side because we're able to pay
- 30:28for them that way
- 30:29>> uh for the better quality of materials.
- 30:31>> Yeah. In effect, you're taking the best
- 30:33of the commercial construction world and
- 30:36bringing it to us in the residential
- 30:38world.
- 30:38>> And speaking of the residential world, I
- 30:40mean, this is a pretty typical Did you
- 30:42take that picture, by the way?
- 30:43>> Yeah, I took I took it last week.
- 30:45>> What do we see there? [laughter]
- 30:47It's it's you only see about half of it,
- 30:49but it's uh dumpsters and uh concrete
- 30:53materials and trusses and a whole lot of
- 30:57wood um strewn over the job site.
- 30:59>> All out on the weather too of the
- 31:01Florida coast where it's raining a lot
- 31:04and it's always wet during construction.
- 31:06>> Not treated, right?
- 31:07>> Yeah. Some of it is and some of it's
- 31:08not, but the trusses are not right. And
- 31:10so in Florida, we have this was just
- 31:12down the road from where I live in
- 31:13Orlando and and um you know, I'm
- 31:16visiting this job site on a on a daily
- 31:20week, you know, daily basis almost. And
- 31:22um I I took those I took that photo
- 31:25because, you know, here in a termite
- 31:28region, we have both, you know, the
- 31:30underground and also the hardwood,
- 31:32right? So,
- 31:33>> and a lot of people don't think about
- 31:34that.
- 31:34>> Exactly. From the ground and the air.
- 31:36>> Yeah. And they they lay their eggs
- 31:37there, right? And then you put the
- 31:38trusses in and now all of a sudden, you
- 31:40know, you've moved
- 31:42>> uh termite eggs into your building. So
- 31:44>> So give me the the direct comparison on
- 31:46this slide then. What what is it steel
- 31:48versus wood in terms of these direct
- 31:49comparisons?
- 31:50>> Well, what we're trying to do is really
- 31:52look at the key characteristics
- 31:55of the actual material, right? So wood,
- 31:58of course, it's organic, so it's subject
- 32:00to, you know, the mold, fire, rot,
- 32:04>> uh breaking, twisting. Um so that
- 32:08affects the dimensional stability that
- 32:09we were talking about in that particular
- 32:11slide. It also is heavier. So the
- 32:13strength to weight ratio of steel is
- 32:15much greater than wood.
- 32:17>> Yeah.
- 32:17>> Um it's always a balance um looking at
- 32:21the mass of the building uh as well
- 32:24because steel will outperform
- 32:26any other material in seismic activity,
- 32:29>> right? because it doesn't propagate the
- 32:31harmonic um waves
- 32:35>> of of seismic activity absorbs it.
- 32:37>> So it will it will sway a little bit and
- 32:40it will absorb that not propagate it
- 32:41through the building.
- 32:42>> Interesting.
- 32:43>> Uh so steel's really great in seismic
- 32:45but then again you look at the
- 32:46lightweight of steel. Well in hurricanes
- 32:49I need more mass right? So in some cases
- 32:52you need the mass in some cases you
- 32:54don't.
- 32:54>> Yeah. you know, so it's it's always a
- 32:56balance, but essentially, you know, the
- 32:58steel being inorganic material, we don't
- 33:01have any issues with moisture, mold,
- 33:03mildew, fire, any of that. So, you know,
- 33:05back to the bones again, right?
- 33:07>> Yep.
- 33:07>> Build build better with better
- 33:09materials.
- 33:10>> Now, I do think though with steel, I'm
- 33:12worried about that thermal bridging,
- 33:13right? I'm worried about that
- 33:14conductivity because it's way more
- 33:16conductive. I don't do frying pans out
- 33:19of wood. I don't do electrical wires out
- 33:21of wood for a reason because it's not
- 33:23very conductive.
- 33:24>> So, how do we get away from that
- 33:26downside of steel?
- 33:27>> Yeah, that's a great point. It's really
- 33:30uh the number one challenge with uh
- 33:32adoption of light gauge steel framing
- 33:35>> uh in in the industry
- 33:36>> and it's one that we, you know, focused
- 33:38on, right? Because that was back again
- 33:40to the root cause analysis why people
- 33:42aren't using like gauge steel framing.
- 33:45>> So, we have to create a thermal break. I
- 33:48think we all know that. We've been
- 33:49talking about it for a long time. And
- 33:52the interesting thing is is that we do
- 33:54have some thermal loss with wood, but
- 33:56not as much with steel. So that slide
- 33:59really was to show that if we're not
- 34:03applying a thermal brake, we can lose 60
- 34:05to 70% of our R value. M
- 34:07>> so you go put for example any type of
- 34:10wood or OSB type of material on a steel
- 34:14frame and you're not applying that CI on
- 34:16the outside
- 34:18>> you're you're that building although
- 34:20it's built in steel framing is not going
- 34:22to perform well
- 34:23>> right
- 34:23>> and so the energy bill is going to be
- 34:25high you have to have that
- 34:27>> right we got to look at the building
- 34:28holistically right as a system and we
- 34:30have to address all these issues
- 34:31>> and that's where your sheeting comes in
- 34:32which is something I'd never seen before
- 34:34that MGO board bonded to EPS PS foam
- 34:38that in your system is actually glued
- 34:40onto the wall. So there's no fasteners
- 34:42on that. So as we showed you that stucco
- 34:44wall, uh, you know, there's there's
- 34:46nothing in that wall, Kyle, in terms of
- 34:49fasteners, right?
- 34:50>> Yeah, that that's a pretty amazing part
- 34:52of the MGO panel and the Kratos system.
- 34:54Uh, you know, when we're at the IBS
- 34:57show, a lot of people are like, "How's
- 34:59it adhered? How does it work?" Um, and
- 35:01it's all from the the close cell spray
- 35:03foam, right? all adhering together
- 35:05>> uh and curing and and what what's the
- 35:07time? I think it's minimal time. I I
- 35:10don't know the number, but
- 35:11>> yeah, from the time that it's sprayed
- 35:13within a few minutes, you can move the
- 35:15walls. It's it's pretty pretty hard. But
- 35:18it does have a 24-hour
- 35:20>> curing and offging period. Yeah.
- 35:22>> Which happens in the factory and out in
- 35:23the yard before it gets to the job site.
- 35:25>> I mean, every builder is familiar with
- 35:26the uh with the Gorilla Glue analogy,
- 35:29right? You know, we all used tight bond
- 35:30for years, but then when we switched to
- 35:33Gorilla Glue, we're like, "Wow, this is
- 35:34so much stronger." And the same is true
- 35:37with for our wood-based framing, right?
- 35:38We've used polyurethane based glues
- 35:41forever now because it yields a
- 35:42squeak-free floor. So, when we use that
- 35:45polyurethane based spray foam and adhere
- 35:49that uh MX7 sheathing uh and then spray
- 35:53on the inside, we've got that structural
- 35:55benefit of that spray polyurethane foam
- 35:59uh to besides the Xracing that's already
- 36:02in there, really lock that building in
- 36:04place so that when it actually gets
- 36:06bolted onto that foundation, it is not
- 36:08moving.
- 36:08>> Yeah, that's a good that's that's a good
- 36:10point. We're using that foam really for
- 36:12for a variety of of of reasons, right?
- 36:15It serves a few purposes. So, you have
- 36:18the structural aspect of it.
- 36:20>> Um, you have the insulative aspect of it
- 36:22as well.
- 36:23>> But also past one and a half inches,
- 36:25it's impermeable.
- 36:26>> So, now people will ask a lot of times,
- 36:28hey, we got to wrap that building,
- 36:30right? With with [clears throat]
- 36:31building wrap. Well, when you look at
- 36:33the the composition of that composite
- 36:36wall,
- 36:36>> we're going through MGO, through EPS
- 36:38foam, and through one and a half to two
- 36:40inches of close vapor drive through
- 36:42there.
- 36:42>> Well, there's zero. Yeah. I mean, we've
- 36:43done all the testing in the lab, and
- 36:45there's absolutely zero perance. I mean,
- 36:47it's it's it's tight. The whole, you
- 36:49know, build tight, ventilate, right? We
- 36:51we got the build tight part down pat.
- 36:54So,
- 36:54>> and the beauty of that closed cell foam
- 36:55too is that it's it's correct vapor
- 36:58barriers on both sides
- 36:59>> because it's an impenetrable uh spray
- 37:02foam at an inch and a half thick. So,
- 37:04you've got it on both sides of the wall
- 37:05in the correct location.
- 37:07>> Right. And we're still allowing the wall
- 37:08to breathe but inside. Right. That's
- 37:10right. So, that's that's what you you
- 37:11want to try to achieve.
- 37:12>> Talk us through this case study.
- 37:13>> That was actually a house for my
- 37:15grandparents. We [laughter] fabricated
- 37:16that in uh in uh in Florida, put it in a
- 37:2053 ft drivein and shipped it to Kansas.
- 37:22How many trucks did it take to get that
- 37:23there?
- 37:24>> 2,000 ft. Was that four trucks?
- 37:26>> No, one 53 ft drive van.
- 37:27>> Oh my god.
- 37:28>> Placed very well. Wow.
- 37:30>> You know, in inside of it. So
- 37:31>> impressive.
- 37:32>> Yeah. So that uh it's about 2,000 square
- 37:35ft um 1600T under air.
- 37:39>> Okay. So a ranch style house 2,000 ft.
- 37:41And you actually put the timeline on
- 37:43what it took to build that thing.
- 37:45>> Yeah. Very seldom do we get the
- 37:47opportunity to really follow a build all
- 37:50the way through to the end because
- 37:51normally we're just focusing on the
- 37:52shell
- 37:53>> and then we don't get to come back.
- 37:54Right. So this particular build because
- 37:56it was one for our family. We tracked
- 37:58all of the cost from beginning to end.
- 38:01>> So that first photo there, yeah, we had
- 38:03uh was me, my dad, and four of our Amish
- 38:06friends come together for the first
- 38:08time. Never done it before. They'd never
- 38:10built in uh in steel frame before.
- 38:12Neither had my my father.
- 38:14>> That's awesome. And uh we came together,
- 38:15flew there on a Monday and you see, you
- 38:19know, the first wall 3 hours later,
- 38:21walls up. We had the whole entire
- 38:23structure up uh day one. And then we had
- 38:26trusses uh on day two and day three we
- 38:30had um interior walls and the uh decking
- 38:33on the roof.
- 38:33>> That's fantastic.
- 38:34>> And day four uh peel and stick shingles
- 38:36started and all the doors and windows.
- 38:38And then Saturday morning, day five,
- 38:40took a photo and flew back to Florida.
- 38:42>> That's awesome. And then the other cool
- 38:43thing about that is you were actually
- 38:45able to see their energy bills after
- 38:46they moved in because you have a
- 38:48relationship with the owners.
- 38:49>> Yeah, exactly. Yeah. Tracked it for a
- 38:51full year.
- 38:52>> Yeah. The first one I think was uh was
- 38:54uh I think it was 42 $43 right around
- 38:57there.
- 38:57>> Oh my god.
- 38:58>> So yeah, we tracked all the energy
- 38:59bills, energy consumption cost, kilowatt
- 39:02hours.
- 39:02>> That's fantastic.
- 39:03>> We tracked all the costs as well. You
- 39:05know, our focus is really about the
- 39:06shell, right? Because that's what you
- 39:08know [clears throat] what we do.
- 39:09>> Yeah. But um so yeah we
- 39:12>> now Todd as we think about that that was
- 39:14one small single family. I think when
- 39:16you start looking at buildings like this
- 39:18though your system gets extremely
- 39:20compelling. Talk me through this
- 39:22workforce housing project.
- 39:24>> So this building actually was built into
- 39:26the Bahamas and on that um on that same
- 39:30lot set a very similar building actually
- 39:33made in sip panels.
- 39:34>> Oh really?
- 39:35>> Yeah. Blew blew away unfortunately. Oh,
- 39:37>> you know, but uh I mean the SIP panels
- 39:39are great, right? But the again the
- 39:41challenge is the connection.
- 39:42>> Mhm.
- 39:43>> Um so we actually worked with the
- 39:45structural engineer on this job to
- 39:49develop special holdowns that they
- 39:52wanted to see uh implemented into the
- 39:55building and um again fabricated in
- 39:58Florida. Nine containers shipped to the
- 40:01job site. They poured the slab and then
- 40:04uh flew there and uh worked with a crew
- 40:07of 10 who'd never built a house before.
- 40:09>> Oh wow.
- 40:09>> And the supervisor and um got that thing
- 40:12put up in How about that?
- 40:14>> And yeah, five five weeks.
- 40:15>> That's very cool.
- 40:16>> You know what the amazing part about
- 40:17that was? [clears throat] There was not
- 40:18one dumpster.
- 40:20>> They did not use one dumpster because
- 40:22there was no waste.
- 40:23>> No waste.
- 40:24>> That's really
- 40:24>> Yeah, the waste is usually unbelievable.
- 40:26>> Yeah, you're right. That's that's a
- 40:28that's a great point. You won't you
- 40:29won't see any or very few dumpsters at
- 40:32our at our job site.
- 40:33>> That's really cool. And here's the
- 40:34timeline on that same build. We don't
- 40:36want to belabor that because I want to
- 40:37make sure we get we get moving on.
- 40:39>> But you know, the numbers on this uh I
- 40:42think really tell a story uh about the
- 40:45speed, but also I want you to we haven't
- 40:47gotten to this yet and I'm seeing a
- 40:49bunch of great questions by the way.
- 40:50Good job gang. I think we got 30
- 40:52questions already come through. Tell me
- 40:54about cost compared to people that are
- 40:56used to building let's say with wood
- 40:57framing. How do you end up comparing on
- 41:00cost or or really we're on next slide uh
- 41:02address that?
- 41:04>> Yeah, the next slide will we will
- 41:05address it fairly well. Um
- 41:08>> so this is an even bigger project then.
- 41:10>> Yeah.
- 41:10>> 528 apartments uh 11 total buildings
- 41:14more than a half million square feet in
- 41:17Georgia. Uh and this was being evaluated
- 41:20with your system versus traditional
- 41:22state
- 41:22>> frame. Yeah, it was originally designed
- 41:24for wood um permitted in wood and we're
- 41:28going through the process right now with
- 41:30that developer to to build this actually
- 41:34in in our system. So what you see with
- 41:36this slide is the actual construction
- 41:38budget, the numbers that were provided
- 41:41by the builder,
- 41:42>> okay,
- 41:42>> for us and then we took and did our
- 41:45internal analysis with our proposal on
- 41:48our on our part and put them side by
- 41:51side. I mean, it looks to me like the
- 41:53budget numbers are darn similar. I mean,
- 41:55within a dollar a square foot to build
- 41:58traditionally versus to build Kratos.
- 42:00But what's really compelling about this,
- 42:02and it's a little hidden on this slide,
- 42:04if you look at that green column that
- 42:06says 24 months Kratos total versus 36
- 42:10months wood, I think this is really
- 42:12where the story gets compelling.
- 42:14>> Exactly. Exactly. Yeah. The the Paul
- 42:16Harvey rest of the story, right? So, um,
- 42:19but before we get to that, could you go
- 42:21back just
- 42:22>> I wanted to touch on something. So, a
- 42:24lot of times when, you know, Kyle, you
- 42:26know, he he gets, you know, beat up a
- 42:28lot, you know, because we'll we'll
- 42:30prepare the proposals. We'll send them
- 42:32out and they'll say, "Hey, you know,
- 42:33your steel shell package is way higher
- 42:35than that initial number, right?
- 42:37>> They're done, right? So, let's look at
- 42:38that here. So if you look at the metals
- 42:41in the woods, right, five and six,
- 42:43you're going to see that the wood model
- 42:44is about 24.7
- 42:47million,
- 42:48>> right?
- 42:50>> And you look at ours, we're 30 million.
- 42:53>> So if this client looked at the two and
- 42:57look, yeah, we're 6 million too high.
- 42:59Boop. Sorry. Done.
- 43:00>> Right.
- 43:01>> But if you go to the next line, go to
- 43:03the next screen.
- 43:04>> Okay. you'll see that not only were at
- 43:07the end of the construction budget, we
- 43:08were within a dollar per square foot,
- 43:10but you have to take into account the
- 43:12opportunity cost because we can close
- 43:15that project 12 months earlier.
- 43:18>> So when you look at the opportunity
- 43:21cost, this is a BTR, right? This is 528
- 43:24apartments.
- 43:25>> So now you look at the lost revenue for
- 43:2712 months, you look at the carrying
- 43:29cost,
- 43:30>> right, for that 12 months. I'd have to
- 43:32think there's a huge insurance
- 43:34difference, too. I mean, what insurance
- 43:35carrier would rather have that building,
- 43:39let's say, on the coast of Florida
- 43:40framed in wood compared to your system?
- 43:42They would be crazy to insure it for the
- 43:44same price.
- 43:44>> It's about 50 It's about 50% reduction.
- 43:47It's about 20
- 43:48>> 20 cents per hundred $100,
- 43:52>> okay?
- 43:52>> But versus about 40 cents on a on a wood
- 43:55frame. So, the builder's risk is is
- 43:57gigantic. Not only that, but the
- 43:59operational side after the thing is
- 44:01built just to ensure the the physical
- 44:04building, termite bonds and all those
- 44:06things. So when you look at at, you
- 44:08know, the rest of the story, you're
- 44:10looking at almost $12 million in
- 44:12additional savings.
- 44:13>> That's awesome.
- 44:13>> So now when you add not only is it a
- 44:16dollar less, but you add that savings of
- 44:18the opportunity cost in there, uh that's
- 44:20almost $20 a square foot less expensive
- 44:23for a better build.
- 44:25>> That's amazing
- 44:25>> than with with the wood product. So
- 44:27that's awesome.
- 44:28>> You know, I guess, you know, the the the
- 44:30essence of this story is you can't look
- 44:32at the line item, right? You got to go
- 44:34to the construction budget and you
- 44:35really need to look at the opportunity
- 44:36cost.
- 44:37>> Yeah, for sure. For sure.
- 44:39>> It's a long-term play, not a short-term
- 44:41play. You got to think about the
- 44:42holistic, not just the first check.
- 44:43You're right.
- 44:44>> Right.
- 44:44>> Yeah.
- 44:45>> Yeah.
- 44:45>> Um we'll be quick on this one, but I
- 44:48think there's a pretty interesting
- 44:48sustainability story with your product
- 44:50as well. Do you want to walk us through
- 44:51that?
- 44:53>> Yeah. So, we did a little bit of a study
- 44:54on um you know what the uh what the
- 44:57recycling is per year in the United
- 44:59States um if we were to try to fill that
- 45:04deficit for housing in the US between 3
- 45:07to 5 million homes and what's that look
- 45:09like on the macro scale. Right? So this
- 45:12is just a slide really to demonstrate
- 45:14that one we're taking we're taking um
- 45:17recycled steel from primarily
- 45:19automobiles and appliances which are the
- 45:21two major categories.
- 45:23We're converting those to coils of steel
- 45:26um and then we are converting that of
- 45:29course to um high durable resilient
- 45:33energy efficient buildings.
- 45:34>> It's awesome. And um so that that that
- 45:37number is actually pretty interesting,
- 45:38right? Because you look at just taking a
- 45:41standard 2,000 foot house, that's 6.5
- 45:44billion square feet,
- 45:46>> right, of space, the 3 to 5 million. And
- 45:50um that's 3.2 million houses. If we were
- 45:54to allocate the 19 million tons of steel
- 45:57that we recycle every year
- 45:59>> just from cars,
- 46:00>> just from cars, we could actually build
- 46:023.3 million homes with that. Gosh,
- 46:04that's wild.
- 46:04>> I mean, that's not going to happen,
- 46:05right? But if they took a third, you
- 46:07could build a million houses, million
- 46:08homes a year.
- 46:09>> We need that.
- 46:10>> And if we did that, we could save a
- 46:12little over 700 million trees.
- 46:14>> That's wild.
- 46:15>> Yeah.
- 46:15>> How cool.
- 46:16>> Yeah.
- 46:17>> Uh let's end with this slide because
- 46:19I've got a bunch of questions for you
- 46:21and I've got the audience that has a
- 46:22bunch of questions, too. So, we we need
- 46:24to keep moving. Um this is a current
- 46:27project in the Bahamas. Got you got
- 46:28going on?
- 46:29>> Yeah. Yeah, we're building multiples of
- 46:30this of this particular model. Yeah.
- 46:32>> Very cool. with your full system.
- 46:34>> Yeah. And this interesting because it
- 46:36shows the versatility of the system.
- 46:39We're sitting on a a CMU block, you
- 46:42know, uh first floor on that connecting
- 46:46then the second and third stories uh to
- 46:49that system.
- 46:49>> A bit of a hybrid system.
- 46:51>> Yep.
- 46:51>> Yeah.
- 46:51>> Yeah. And there's quite a bit of red
- 46:53iron. There's about 30,000 lbs of hot
- 46:55roll steel in that building.
- 46:57>> Wow.
- 46:57>> As well. So all galvanized. Um, spend a
- 47:00second talking about that because that's
- 47:02actually one of the questions someone
- 47:03asked in here was, you know, what about
- 47:05coastal builds? Shouldn't I be worried
- 47:06about rust? Tell us about that. What do
- 47:09we need?
- 47:09>> Yeah, I mean that's one of our common uh
- 47:11our common questions, right? So, uh, the
- 47:15answer to that is it really goes back to
- 47:17the hardness and the galvanization
- 47:20coating of the steel.
- 47:21>> On all of our coastal projects, we use
- 47:26G90 galvanized steel.
- 47:27>> Okay? So, a higher level than standard.
- 47:29>> That's right. That's right. The G a lot
- 47:31of the products that you'll find in the
- 47:33big box stores, the generic studs,
- 47:35they're a G40.
- 47:36>> Okay.
- 47:36>> Most of them and they'll rust out, you
- 47:38know, in no time.
- 47:40>> So, we're using um as a standard G60 and
- 47:44then on all coastal projects G90. Got
- 47:46>> all the hot roll steel is hot dipped
- 47:48galvanized. All of the hold downs are
- 47:51hot dipped galvanized or Zmax. All the
- 47:53screws are specially coated. So, we
- 47:56really go the distance to make sure that
- 47:57every fastener and
- 48:01hold down clip and the steel is going to
- 48:04be is coated. Yeah.
- 48:05>> Yeah. And speaking of which, we I think
- 48:06I missed this, but I do want to mention
- 48:08real fast. You know, if we're using your
- 48:10magnesium oxide board, there is a
- 48:13fastener story to talk about with this,
- 48:15right? We don't want to use standard
- 48:16fasteners on this. What do we need to
- 48:18know about that, Todd? Right.
- 48:19>> I forgot to mention this earlier.
- 48:21>> Yeah, that's a good point. So they're
- 48:22they're depending on the type of
- 48:24magnesium oxide board that's used there
- 48:26there's two basic categories either a
- 48:28chloride based or a sulfide based.
- 48:30>> Okay.
- 48:30>> Um and depending upon the chloride
- 48:32sulfide content you're going to have a
- 48:34certain level of corrosiveness. And so
- 48:36what we need to do is take precautions
- 48:38>> to make sure that uh one we're using a
- 48:40G90 grade coated steel and also we're
- 48:44using coated uh approved coated
- 48:46fasteners.
- 48:48uh could be a grabber guard, could be
- 48:50any type, could be a stainless steel,
- 48:53various suppliers that make these
- 48:55fasteners. And um of course you can go
- 48:58through this board with um
- 49:01>> uh with pins, nails, shooting them
- 49:04through, you can use but but primarily
- 49:05we use screws with it for the most part.
- 49:07>> Yeah, makes sense.
- 49:08>> On the roof decking, you're going to use
- 49:09>> We're going to upgrade to a stainless
- 49:10product typically when we're screwing
- 49:12into it, when we're nailing into it,
- 49:13that sort of thing.
- 49:14>> Right. Right. Yeah. You want to use a
- 49:16stainless steel connector. Gotcha.
- 49:18>> Yeah. So Todd, let me switch gears and
- 49:20go back to the beginning. Someone who's
- 49:22interested in using your system, they're
- 49:24they're uh they're thinking this is for
- 49:26them. What does the process look like?
- 49:29Who do they talk to? What does it look
- 49:31like? You know, let's say they've got an
- 49:32architect already. They've got a In
- 49:34fact, someone said, "I've got two
- 49:35projects in Miami Dade County right
- 49:37now." Uh you know, how do we how do they
- 49:40work with you?
- 49:40>> Yeah. You
- 49:41>> Yeah. No, so I mean I'm their their
- 49:43point of contact at that that case. Um,
- 49:45so they just reach out to me and I can
- 49:47uh get them all the information. I can
- 49:49gather their information, their
- 49:50architects, who they're working with and
- 49:52um start with the plans. If they have
- 49:54plans, they can send them to me. We can
- 49:55look at them together as a team uh and
- 49:57kind of go from there.
- 49:58>> Gotcha. And then typically you're going
- 50:00to have an engineer take the
- 50:01architecturals and turn it into your
- 50:03system structurally. Correct.
- 50:06>> Or they're going to have them.
- 50:07>> Yeah, you can go either way.
- 50:08>> Yeah, I could go either way. We a lot of
- 50:11a lot of customers uh do have their own
- 50:14architects and their engineers they work
- 50:15with. We have a library for our system
- 50:17that we can provide the architects and
- 50:19the engineers of details and connections
- 50:21and we'll provide those to them to help
- 50:22them through that process.
- 50:24>> Uh if they don't, it depends on where
- 50:26they are in the process. uh if they
- 50:28don't have an engineering firm that's
- 50:31already the
- 50:32>> EOh,
- 50:34>> we have variety of engineering firms
- 50:36that work with across the country and we
- 50:37can make recommendations for them to to
- 50:40find somebody.
- 50:40>> Okay, I like it. [clears throat] Uh
- 50:42local to Austin builder Sheay uh
- 50:45Milhauser says, "Does Kratos offer any
- 50:48MGO either wall or roof sheeting
- 50:51products that are rated for structural
- 50:53shear?"
- 50:55>> Yeah, we we do have that. We have two
- 50:57categories. We have a Mag Struct and a
- 50:59Mag Ultra. [clears throat] So, they're
- 51:01going to have different um physical
- 51:05structural properties. Got
- 51:06>> We also have a lightweight version,
- 51:08which is really more of a gypsson board
- 51:11um type alternative. You can score it,
- 51:13snap it, that sort of thing. It's
- 51:15lightweight. It's considered a
- 51:17nonstructural board. Okay.
- 51:18>> But there's no paper backing or anything
- 51:20like that. So, again, no organics in it.
- 51:22But yeah, we do have the structural
- 51:23versions of the boards and different
- 51:25sizes.
- 51:25>> Yeah. What are the sizes roughly, Cal?
- 51:27Someone else asked that question.
- 51:28>> Yeah. So, we have a 4x8, a 4x10, and a
- 51:314x12.
- 51:32>> Okay. So, all the normal like panel
- 51:34sizes that we're used to working with in
- 51:36wood. Yeah. Okay. Good.
- 51:38>> And also different edges, right? I think
- 51:40>> Yep.
- 51:42>> tapered edge, straight edge, tongue and
- 51:44groove, beveled, etc. So,
- 51:46>> gotcha. My architect buddy Armando,
- 51:49thank you Armando for all your support,
- 51:50says, "Can I specify the location of all
- 51:53the pre-punched service holes or can I
- 51:55add additional lines of holes?"
- 51:58>> Yes, please. [laughter]
- 52:00>> I I think the answer to your question
- 52:01is, Armando, they want you to integrate
- 52:03your MEPs as an AR Armono is a great
- 52:06architect in Dallas, by the way. uh they
- 52:08want you can integrate [clears throat]
- 52:09your MEPs to their software so that the
- 52:12MEP engineer can show all the runs for
- 52:14the duct work, can show all the plumbing
- 52:16runs, can show all the electrical runs.
- 52:18They can pre- punch everything. So the
- 52:20electrician doesn't have a hole hog on
- 52:22the on the job to drill anything. He's
- 52:25literally going to start running wire or
- 52:27running pipe right from the get- go. We
- 52:29need to figure all those things out
- 52:30ahead of time, which I think frankly is
- 52:32another big benefit of the system that
- 52:34you're you need to figure it out ahead
- 52:36of time. Yeah, it would certainly be
- 52:38beneficial. I mean, we've all been on
- 52:40job sites where, you know, you're trying
- 52:42to install a plenum or some sort of
- 52:44rigid duct work and all of a sudden
- 52:46there's a truss or some sort of a beam
- 52:49in the way, right? Or you go to put the
- 52:50toilet in and all of a sudden it's right
- 52:52over top of a truss. So, you know, clash
- 52:54detection is one
- 52:56>> uh important aspect of the process of
- 52:58our virtual design and construction. So
- 53:01we can build it virtually in the system,
- 53:03that model that you showed.
- 53:05>> And then ideally, not only are we
- 53:07looking at the structural aspect of that
- 53:09model, but we're bringing in the MEP, so
- 53:12they're in the 3D BIM model as well, so
- 53:14we can do clash detection. If you,
- 53:16again, if you're going to do this one
- 53:18time for a custom home, probably doesn't
- 53:20make sense. Figure it out on the job
- 53:22site. But if you're going to build that
- 53:23house a thousand or 10,000 times
- 53:25>> or even 10 times
- 53:26>> or 10 times, it makes sense to figure it
- 53:28out in advance. And you're going to save
- 53:30many many hours in the job site as well.
- 53:33>> Yeah.
- 53:33>> Right.
- 53:34>> Here's a Florida question for you. Have
- 53:36you had any projects in Miami date or
- 53:38Broward counties? And how do you work in
- 53:40those uh HVHZ zones, especially with
- 53:43building departments? Do I assume the
- 53:45building departments probably love your
- 53:47system?
- 53:47>> Yeah, they do. We've built in Miami
- 53:49Dade. Most of our work is in Florida and
- 53:51also in the islands, which are all Miami
- 53:53Dade compliant. So, uh, the the the the
- 53:59caveat is is that the engineers are
- 54:02typically doing component level
- 54:04engineering, right? They're looking at
- 54:06the steel frame, the X bracing, the
- 54:08board,
- 54:09>> and unfortunately, we've had a difficult
- 54:11time getting the engineers to consider
- 54:14the structural capacity of the foam
- 54:16>> because we know that it has a big
- 54:18impact. That's right. But they're like,
- 54:19"Hey, you know, and unless we've got
- 54:21some sort of document that shows that,
- 54:23then of course they're not going to
- 54:24consider it." But but yeah, we've done
- 54:26we've done several projects
- 54:28>> in Miami Dade, Broward, Monroe County
- 54:30down in the Keys, which are all Miami
- 54:32Dade.
- 54:32>> Yeah.
- 54:33>> Yeah.
- 54:33>> If I think about your system, I'm I'm we
- 54:35have time for one or two more questions,
- 54:37but but this is just kind of the Matt
- 54:38Risinger wrap up here. When I think
- 54:40about building coastal, building in a
- 54:43hurricane zone, building in a floodprone
- 54:45zone, tornado alley, wooi zones, the
- 54:49islands, anywhere where there's termites
- 54:51or mold issues, this is a bomber system.
- 54:55But what they don't sell you and that
- 54:57you really also need to think about is
- 54:59all of your windows and doors. Because
- 55:01this incredible system right here, if
- 55:03you put a vinyl window in and you're in
- 55:05a woo zone, the window is going to fall
- 55:07out and your house is going to be
- 55:08breached, right? Yeah.
- 55:09>> So, you know, I would tell you that the
- 55:11weak point of this system is whatever
- 55:14you as the homeowner, the builder, the
- 55:16architect specify for the windows and
- 55:18doors. So, you know, don't do this
- 55:20system and then cheap out by not putting
- 55:23Miami date hurricane rated products in,
- 55:25right? We probably want to do a
- 55:27structural aluminum. We want tempered
- 55:29glass. We want laminated glass. We want
- 55:32to think about all those things that are
- 55:33going to resist the winds from
- 55:35breaching. We need to think about our
- 55:36garage door. uh you know, our garage
- 55:39door needs to be wind load rated as
- 55:41well. Uh it's really important to think
- 55:43of this as a full system, but man, if
- 55:45you're in any of those zones, you should
- 55:47be talking to these guys. This is an
- 55:48incredible system.
- 55:50>> And if you're a wood builder like me
- 55:52who's only built with wood, these guys
- 55:54will talk you through it. I think that
- 55:56you could do one of these incredibly
- 55:58successfully for your very first build
- 56:00out there, having never worked in their
- 56:02system before.
- 56:03>> Yeah. Yeah. And that's a good point. I
- 56:05think you touched on it earlier, right?
- 56:06I mean, when you think about the
- 56:08non-combust
- 56:11steel framing, that's fantastic.
- 56:14>> But the the MX7 board really provides a
- 56:17tremendous, I think, advantage to the
- 56:19wood frame because we're going to wrap
- 56:21that wood that vulnerable wood frame in
- 56:24MGO inside and out. We're to protect it,
- 56:26you know. So,
- 56:27>> uh, there's like five questions about
- 56:29cost that I'm going to summarize and
- 56:31we'll kind of end here. Uh, I think if I
- 56:34could summarize on cost, if you're just
- 56:36simply comparing this to a stick frame
- 56:38build, it's going to be a percentage
- 56:40more on the actual uh, just steel cost
- 56:44or Kratos cost compared to your 2x4
- 56:47cost. I think the big advantage here is
- 56:49speed, is durability, is resilience, is
- 56:53actually meeting those one, two, or
- 56:55threehour fire codes with a product
- 56:57that's naturally fire resistant,
- 56:59naturally termite resistant. It's a
- 57:02really impressive system. So, will this
- 57:04look on a line item to line item car
- 57:06comparison more? Probably. But go back
- 57:09to those slides that we talked about
- 57:10earlier. I think if you look at this
- 57:11holistically from a project view and not
- 57:14just a single line item view, you're
- 57:16going to find this is a very compelling
- 57:17system that that could actually end up
- 57:19being less expensive, not more
- 57:22expensive.
- 57:22>> Yeah.
- 57:23>> How did I summarize it?
- 57:24>> Yeah, you said that's perfect the way
- 57:25you just said it.
- 57:26>> Yeah, it's it's it's a great point. And
- 57:29and again, back to value ad, I think
- 57:31that, you know, there's there's been for
- 57:34a long time this conflict between the
- 57:37builder's goals and objectives and the
- 57:39owner operator, right? We want to get
- 57:41in, build it, get out, you know,
- 57:43maximize our profits and get out the
- 57:44door. Where the owner operator, they
- 57:46want maximum value. They want
- 57:48performance. They want low energy bills.
- 57:49They want longevity, low maintenance.
- 57:51So, there's this constant conflict. And
- 57:53I think with our system, it really
- 57:55provides the foundation for us to really
- 57:57achieve a win-win situation for
- 57:59everybody,
- 58:00>> you know, and and not that
- 58:04>> the builder cannot, you know, has to
- 58:07sell their house or their services for
- 58:10the same price either because we're
- 58:11bringing value at.
- 58:12>> That's right.
- 58:13>> Right. So, not only if the cost goes
- 58:15maybe goes up a little bit, then you can
- 58:17also sell it for a little bit more, you
- 58:19know, if the customer is willing to pay
- 58:20that. So,
- 58:20>> that's right. Any final thoughts, guys,
- 58:22before we wrap it up?
- 58:23>> No, I I mean, I think we touched on
- 58:25everything. I thought that was great. I
- 58:27appreciate everything you've done for
- 58:28us, Matt. So,
- 58:29>> for sure. How How can people get a hold
- 58:31of you?
- 58:31>> Uh, they can email me. Uh, they can go
- 58:33to the website, performancebuilding
- 58:35solutions.
- 58:35>> Performancebuildings.com.
- 58:37>> Yep. That's it.
- 58:39>> Guys, really appreciate your time.
- 58:40Thanks for coming all the way to Texas.
- 58:42>> Thanks for taking the time with me.
- 58:44>> Appreciate it.
- 58:44>> Thank you, man. We appreciate it.
- 58:45>> Appreciate you for your support. Uh,
- 58:47this obviously was a live webinar, but
- 58:50you're probably watching this later. The
- 58:52way that you can get notified about our
- 58:54new webinars is by signing up for our
- 58:57newsletter. We send three emails a week
- 58:59because we end up having about 20 new
- 59:01videos a week. If you're watching this
- 59:03live, this will be sent out as a
- 59:05recorded version as well. So, if you
- 59:07want to send this to your production
- 59:08builder buddy, to your buddy who builds
- 59:10apartments, you your friend who's
- 59:11building a house in the Bahamas and
- 59:13should know about this system, there
- 59:15will be a link coming out soon if you're
- 59:17watching this live. But I appreciate
- 59:18your support, guys. Uh, lastly, these
- 59:21guys are going to be at Build Show Live,
- 59:23correct?
- 59:23>> Yep, we'll be there.
- 59:24>> So, if you're coming to Build Show Live
- 59:26in September, you should come talk to
- 59:27these guys. Todd's a celebrity now.
- 59:29Everybody knows him. [laughter] And
- 59:30Kyle, you've gotten to know him the last
- 59:32hour. So, make sure you tell them that
- 59:33you saw the webinar and you want to ask
- 59:36those specific nerdy questions that
- 59:38maybe I didn't get to today. They're
- 59:39going to answer those live. Build Show
- 59:41Live is in San Antonio September 10th
- 59:43through 12th. Build Show Live for
- 59:45tickets. And you can see a lot of
- 59:47incredible companies like the guys, like
- 59:49these guys, as well as all 20 of our
- 59:51contributors teaching you how to build a
- 59:54better, more resilient, more durable,
- 59:57more healthy house, cuz that's what
- 59:58we're all about here. That being said,
- 1:00:00guys, follow us on Instagram, follow us
- 1:00:02on Facebook or Instagram. Otherwise,
- 1:00:04we'll see you next time on the Build
- 1:00:06Show webinar.
- 1:00:13>> [music]
About this transcript
This page contains the full transcript of Resiliency in Construction: Better Materials & Methods for High Performance by Matt Risinger, generated from the public captions YouTube serves with the video. The transcript has 11,935 words across 1,824 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.
What you can do with it
Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.
Free YouTube transcript tool
YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, translation to 100+ languages, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.