- 0:21Welcome, welcome to banking and finance
- 0:25loss course. This is the third week.
- 0:28This week we are discussing different
- 0:30kinds of finance and this is the 15th
- 0:34session. In this session we will
- 0:37specifically discuss about project
- 0:39finance as part of different kinds of
- 0:43finance. In this week we have discussed
- 0:46debt length different kinds of debt
- 0:48finance compared it with equity finance.
- 0:51We have understood leverage buyout. We
- 0:54have discussed different finance
- 0:56structures and debt financing in the
- 0:59previous classes. So in this class we
- 1:02will discuss project finance.
- 1:05Project finance is usually used to
- 1:09finance large projects or where the
- 1:12volume of debt required is huge. This is
- 1:15one major component or generally where
- 1:18people companies are people establishing
- 1:21companies resort to project finance.
- 1:24And earlier in developed development
- 1:27financial institutions used to finance
- 1:30in this pattern. Now actually
- 1:32development financial institutions were
- 1:35specifically set up some of them to
- 1:37finance large projects and to finance
- 1:40long-term projects and to finance pay
- 1:44where repayment will be long-term and
- 1:47where the development is required. So
- 1:50those were some of the reasons for
- 1:51establishment of different different
- 1:53kinds of development financial
- 1:55institutions and they were giving
- 1:58finance in the project finance model.
- 2:01Banks were not providing project finance
- 2:04in those days. But with the size of the
- 2:07banks becoming bigger with merger of the
- 2:10banks and also the volume of deposits in
- 2:13the banks growing very high and with
- 2:16banks competing with global markets and
- 2:19banks being nationalized and uh
- 2:22attracted huge deposits. All of them
- 2:24became banks also became very bigger in
- 2:27size and also in terms of volume of
- 2:30money and also the kind of banking
- 2:32operations also has seen major changes.
- 2:36Banks have ventured into many many
- 2:38businesses and their potential to
- 2:40provide loans of large volume to big
- 2:43projects also has made a reason for
- 2:46banks also entering into project finance
- 2:49and providing finance to large projects
- 2:52in the project finance model. But
- 2:55usually financial institutions use it to
- 2:58provide and generally projects of
- 3:00national importance are also considered
- 3:03for project finance. Besides some
- 3:06corporates, private companies also
- 3:08taking project finance. Without public
- 3:11private partnership also this is
- 3:13possible. There are multiple models in
- 3:16which project finance is provided. There
- 3:19could be public private partnership
- 3:21where government and a private company
- 3:23come together and then partner and build
- 3:26a large project. Private company will
- 3:28build a large project, own it and then
- 3:30transfer it to the government as a
- 3:32national property. This is called build
- 3:35own transfer model B. Then there are
- 3:38other models like build, own, operate
- 3:41and transfer model which is called B.
- 3:45Build own operate model. So there are
- 3:47multiple models depending on the
- 3:50agreement and usually a special purpose
- 3:53vehicle is established to raise project
- 3:56finance. Let us understand how it works
- 3:59in more greater detail. Now in the fi
- 4:02financing of project finance, lender
- 4:05finances the project and once the
- 4:07project work is completed the cash flow
- 4:10from the project is used to repay the
- 4:13loan. This is one major uh concept of
- 4:16project finance where the lender has to
- 4:19look at the project so that this project
- 4:23will generate so much cash flow that it
- 4:25will be able to repay the loan that is
- 4:28given to this particular project. So the
- 4:31lender is financing the project not the
- 4:34person. Let us understand the
- 4:37distinctions between project finance and
- 4:40the regular finance. In regular finance,
- 4:44the creditworthiness of the borrower is
- 4:46very very important because if he is
- 4:49creditw worthy, he's giving collaterals
- 4:51and then he repays his credit history.
- 4:54All this becomes very very important.
- 4:57But in project finance, you should look
- 4:59at the project's creditworthiness
- 5:02because the cash flow of the project is
- 5:05supposed to repay the project finance
- 5:08and not the cash flow that is there to
- 5:10that person or to that company. So in a
- 5:13way the creditworthiness of the project
- 5:16is more importantly to be weighed as
- 5:19opposed to the creditworthiness of the
- 5:21project proponent
- 5:23because if the project fails repayment
- 5:26will not be recovered. You cannot
- 5:28recover the loan that is given repayment
- 5:31will be lost or in a way the borrower
- 5:34will not be able to repay. The risks
- 5:36have to be assessed more carefully. Why?
- 5:39Because it is done through the SPV. When
- 5:42we say what is the distinction between
- 5:44this SPV and the creditworthiness let me
- 5:47give you an example. Suppose there are
- 5:49big companies like say Tatas, Vipro,
- 5:52Bajage, Infosys or any of the major
- 5:56company that you know which is operating
- 5:58in India. Suppose they are operating and
- 6:01their business is in thousands of crores
- 6:03and if they approach a bank for 100
- 6:05crore loan, it may not look very high
- 6:08amount for their company's business and
- 6:11they will be easily able to repay given
- 6:13their profits as a company's whole
- 6:15profile. But in project finance that is
- 6:18not how they start a business. Suppose
- 6:21Tata Bajage or this Infosys or VRO they
- 6:24are taking project finance for a
- 6:26particular project or L&T or any other
- 6:29company they will establish an SPV that
- 6:32is another subsidiary company where they
- 6:35will invest the sponsor company or the
- 6:38sponsoring person will invest some
- 6:40amount of equity in that SPV. Suppose
- 6:43that SPV that is let us call it the
- 6:45project company. The project company is
- 6:48taking 100 cr loan. They may invest only
- 6:50five cr equity. So the entire 100 cr is
- 6:54financed by the banks or the financial
- 6:57institutions whichever is financing the
- 6:59project. Now this 105 cr will be used to
- 7:02build that project and once the project
- 7:05is completed the cash flow from the
- 7:08project will be used to repay the
- 7:10project. Usually until the project is
- 7:12completed also repayment won't start. So
- 7:15there is also a period where the
- 7:17interest also get accumulated and
- 7:19compounded to the principal and will be
- 7:22recovered later even that is possible.
- 7:24So it depends on what kind of project,
- 7:26how many years it will take to complete,
- 7:29what is the cash flow risks, what is the
- 7:31risks of completing the project, what is
- 7:33the creditworthiness of the project.
- 7:36Because if you look at the company which
- 7:38is sponsoring the SPV and give the loan,
- 7:41if the project fails, there is no need
- 7:43for that SPV to repay because the
- 7:46original sponsor's liability is limited
- 7:49to that 5 crore equity they have
- 7:51invested in that SPV and not to the
- 7:54complete loan that is given to that
- 7:58company. That means the company's
- 8:00sponsor's liability is limited only to
- 8:03the investment they made in the SPV and
- 8:06they are not liable for the repayment of
- 8:09the project finance. This is one major
- 8:12difference between project finance and
- 8:15regular finance.
- 8:17And why then people take these projects?
- 8:20Because for large projects, huge money
- 8:22will be available will be required to do
- 8:26the project up work that is construction
- 8:30work or manufacturing work or whatever
- 8:32is the project. So for laying the road
- 8:35or something like that, it requires huge
- 8:37money and it takes time to do that. And
- 8:40after that is done the asset will start
- 8:42recovering some cash. So till that time
- 8:45the financer has to wait. So this model
- 8:48of financing is called project
- 8:50financing. And if the project fails
- 8:53obviously the recovery will fail and
- 8:55there could be some very unforeseen
- 8:58difficulties in a project construction
- 9:00or uptaking which requires a realistic
- 9:03estimate. Now let us understand what
- 9:06kind of risks can be there. Suppose
- 9:09there is a highway road laying project.
- 9:12Now this project will require uh laying
- 9:16for say five six years. It will take
- 9:19time to lay that project of say 30
- 9:21kilometer or 100 kilome stretch. Let us
- 9:24imagine a 100 kilometer road laying
- 9:27stretch is being given to a particular
- 9:30contractor. Now this particular
- 9:32contractor is going in the project
- 9:34finance model. Now he will set up a SPV
- 9:39a special purpose vehicle. Suppose this
- 9:41is a highway road is a government thing
- 9:43national highway authority will be
- 9:45dealing with that. So it can be done in
- 9:48public private partnership. So in the
- 9:50SPV the government may invest some 10 cr
- 9:53or so and the company which got the
- 9:55project on tender may also put another
- 9:5810 cr but this 20 cr won't be sufficient
- 10:00to lay the road. It may require another
- 10:03500 cr. This 500 cr the com no company
- 10:07may be willing to lay that because 500
- 10:10cr a company has to invest and then
- 10:12construct the road for five six years
- 10:15after that the recovery will start in
- 10:17the meantime the interest and the amount
- 10:19the money gets struck. So they may not
- 10:22be willing to do that. So the government
- 10:24may provide project finance or the
- 10:27government may support the private
- 10:29company to get that project financed. So
- 10:32when this project finance is given to
- 10:35that private company, they may invest 10
- 10:37cr or 20 cr in that SPV as equity and
- 10:41the government also may invest some
- 10:43minor amount but they may raise 5 600 cr
- 10:46from the banks or financial institution
- 10:49to lay the road and it may take another
- 10:51five years. And here how does they repay
- 10:54the loan? That will be repaid only by
- 10:57the toll fee that will be recovered
- 10:59after the completion of the road and
- 11:01after public start using that road. Now
- 11:05here what are the risks that the bankers
- 11:07have to see? Now while financing a
- 11:10highway road project there could be
- 11:12problems like land acquisition. Public
- 11:14may protest against giving their land or
- 11:17even if it is acquired because state
- 11:20governments and the central government
- 11:22government has the authority to take the
- 11:25land of any public under eminent domain
- 11:28concept and pay them compensation. But
- 11:31people may go to court challenging the
- 11:33government decision. They may change
- 11:36challenge the compensation awarded as
- 11:38inadequate
- 11:40or they may dispute that the land is
- 11:42does not belong to the person who from
- 11:44to whom the compensation is given. So
- 11:46there could be multiple cases like this.
- 11:49So these cases may delay the project and
- 11:52the project proponent and the contractor
- 11:54who is building the road will be put to
- 11:57great loss of uh money and also his
- 12:01investment
- 12:03and his time the project finance that he
- 12:05raised on that will get being
- 12:07accumulated
- 12:09on that and he will go into bankruptcy
- 12:12position. Then the national highway road
- 12:15project though it is given say by the
- 12:17central government if it is crossing
- 12:19multiple states each state has its own
- 12:22problems. Suppose there could be public
- 12:25protests over this particular road
- 12:27expansion stating
- 12:30that this road is not going through
- 12:31their village or this gold road is going
- 12:34through their village. Some villagers
- 12:36might protest that the road is going
- 12:38through their village because it might
- 12:40disrupt their peaceful living. Some
- 12:43people might say that their business
- 12:44opportunities is lost because the road
- 12:47route is not in conssonance with the
- 12:49previous road. So there could be protest
- 12:52for any reason there and this is just
- 12:54one example. And state governments also
- 12:57have a policies which they may change
- 12:59from time to time. And that could also
- 13:03affect say for example they may say the
- 13:05entire business of all commercial
- 13:09businesses of uh uh vegetable vendors
- 13:12and other vendors will be beside the
- 13:15highway or beside the highways. There
- 13:18should not be schools and colleges
- 13:20educational institutions. Now these kind
- 13:23of policies will be challenged by those
- 13:25people
- 13:27saying that the school is existing here
- 13:29and the highway is coming now so you
- 13:31better stall the highway now not the
- 13:33school. So these kind of any kind of
- 13:36policy decision changes could also
- 13:38affect the uh project and it could delay
- 13:41or it could stall the project midway. So
- 13:44this also could be some kind of problem.
- 13:46Then there are other problems like new
- 13:49technology may come for road laying
- 13:50which could become very very cheaper and
- 13:53the government would say now switch to
- 13:55that and this person may not have that
- 13:57knowledge or the technology to adopt and
- 13:59it could incur more costs and there
- 14:02could be some unforeseen calamities like
- 14:04COVID or manpower problems or earthquake
- 14:08or natural calamities floods anything
- 14:11like this. So these are multiple risks
- 14:13but when we compare these risks now
- 14:16these are not the regular risks banks or
- 14:19financial institutions were equipped to
- 14:21deal with. Banks and financial
- 14:24institutions are equipped to deal with
- 14:26risks like what is the collateral
- 14:28available? What kind of lean power they
- 14:31have over the assets? How to recover the
- 14:33news from these persons by filing cases
- 14:36or what are the kind of documents they
- 14:39must be asked to submit while taking
- 14:41finance. So verifying the documents
- 14:44authenticity these are the kind of risks
- 14:46they have earlier foreseen with regular
- 14:49finance and they are equipped with that.
- 14:52But these are the risks alien to a
- 14:54financial institutions regular finance
- 14:56business. So this challenges the uh
- 15:00bankers and financial institutions
- 15:03ability to foresee the difficulties and
- 15:06when we talk so besides all these risks
- 15:09if a bank or a financial institution is
- 15:11completely convinced that they are this
- 15:14project is worth to be given they will
- 15:16give the loan. So assessing the risks is
- 15:19one of the major component of a project
- 15:21finance. It might require banks or
- 15:24financial institutions to appoint some
- 15:26consultants who are experts in that
- 15:28field like engineers or structural
- 15:30engineers in a road laying project or a
- 15:33kind of sociologist. It could be anybody
- 15:35whom they think as appropriate and ask
- 15:38them to study the risks and suggest them
- 15:40whether it is a worthwhile project
- 15:42something like that. So they have to
- 15:44develop that requisite expertise
- 15:46depending on the project they are going
- 15:48to finance. And when we talk about
- 15:51repayment of a project finance, usually
- 15:55project finances are repaid from the
- 15:58cash flow of that particular project.
- 16:01Say in this example of we have taken of
- 16:03the highway road. It could be toll fee,
- 16:06it could be user fee
- 16:09that the contractor collects or the
- 16:12government collects and repays the
- 16:13contractor. It could be any model
- 16:16depending on the terms of the agreement
- 16:18between the government and contractor in
- 16:21the public private partnership agreement
- 16:23of project finance. So here they may
- 16:25agree that the contractor only will
- 16:27collect the toll fee until his loan is
- 16:30completely repaid and his fee is also
- 16:33collected and after that the road gets
- 16:35transferred to the government or it
- 16:37could be the other way the government
- 16:39keep collecting and keep paying the
- 16:41contractor or the government could pay
- 16:43half the cost while construction and
- 16:45half the cost could be collected through
- 16:47the project finance. So there are
- 16:49multiple ways in which it could be uh
- 16:52divided between how to repay the banker,
- 16:54whether government will collect and
- 16:56repay the banker or whether
- 16:59the contractor will collect and repay
- 17:02the banker. It depends on the terms of
- 17:04the agreement between government
- 17:05contractor and the financial institution
- 17:08which has lent the finance. And the
- 17:11lending could be in consortium model or
- 17:13syndicate lending model which we have
- 17:15seen in the previous class. And the debt
- 17:17agreement will determine the mode of
- 17:19repayment mostly. But one essential
- 17:22thing in project finance is the project
- 17:25sponsor is not going to repay the loan.
- 17:28But it is the project special purpose
- 17:30vacant. That is the project company
- 17:32which will promise to repay through the
- 17:34cash flow from the project. That is the
- 17:36essence of project finance as opposed to
- 17:39the regular finance.
- 17:42And what are the risks associated other
- 17:45than the risks that could be foreseen
- 17:47there could be new road that may come up
- 17:49in the state state government also may
- 17:52lay some roads which may connect the uh
- 17:56two different places more in a very
- 17:59shorter distance than what this highway
- 18:01road is connecting. So your tollfree
- 18:03connectivity will be uh tollfree
- 18:06collection will be less because people
- 18:08will start commuting through the other
- 18:10routes because other forms of
- 18:11connectivity also may arise like a metro
- 18:14may be developed or a speed train like
- 18:17one BAT express may come or some other
- 18:20connectivity models might become more
- 18:22popular than the highway which the toll
- 18:25is expected to generate like say for
- 18:28example even flights say an airport may
- 18:30come up in between by people might
- 18:33travel through trains instead of flights
- 18:35instead of traveling through the road.
- 18:37So other forms of connectivity may pick
- 18:40up does the transport number of vehicles
- 18:43that will commute through that
- 18:45particular road might get lesser in
- 18:48number and less toll fee may be
- 18:50collected as opposed to what was
- 18:52estimated. Then there could be some
- 18:54fraud in computation like say the toll
- 18:57fee collecting cyber equipment may may
- 19:00be hacked or the toll fee calculation
- 19:04amount may be lost or some fraud may
- 19:06happen any embezzlement criminal
- 19:09misappropriation again they have to be
- 19:11dealt and government may change the
- 19:14criteria for collection. Say for example
- 19:16the government changed there are public
- 19:18protests against the toll fee which is
- 19:20abnormal or may say that the num amount
- 19:23of kilometer usage is less or annual fee
- 19:28payments should come something like that
- 19:30that may also reduce the amount of fee
- 19:32that you may collect and the sponsor
- 19:35company may go bankrupt and that is the
- 19:38SPV even the limit to which the SPV
- 19:41promise you to invest
- 19:44that also may cannot be recovered. This
- 19:46is generally a bankruptcy remote entity.
- 19:49Usually repayment is not very much
- 19:51dependent on sponsor but even the
- 19:54limited amount which the sponsor
- 19:55guaranteed that also may become a risky
- 19:58amount to recover. These are some of the
- 20:01problems that are the risks that are
- 20:03there with the project finance. And what
- 20:06are the strategies that the financial
- 20:08institutions have developed to address
- 20:11this risk? That is generally the debt
- 20:14agreement. They determine the terms of
- 20:16the contract. So these debt agreements
- 20:19have to bind the successive governments
- 20:21and any policy changes should not affect
- 20:24the existing debt agreement. So the
- 20:27terms of continuity of the contractual
- 20:29terms with any government change or
- 20:32policy changes should not be adversely
- 20:34affecting the project proponent and the
- 20:37contractor. So they have to understand
- 20:39then the co-obligation terms if it is a
- 20:42public private partnership or consortium
- 20:45lending or syndicate lending which
- 20:47financer will provide first who will
- 20:49provide how much when they will provide
- 20:52what are the terms to when at what
- 20:54intervals they will provide. These terms
- 20:57have to be very very carefully entered
- 20:59into otherwise suppose you got 100 cr at
- 21:03the very first installment and the care
- 21:05dispute is in litigation the money will
- 21:07be given to you and then it will get
- 21:10interesting charged but the work is not
- 21:12continuing or suppose the contractor has
- 21:15laid some road but the finance is not
- 21:17coming for another one year the road the
- 21:20road that was laid was kept pending and
- 21:23the your toll fee receivable also got
- 21:25delayed. So these kind of things will
- 21:27also affect. So the co-obligation terms.
- 21:30So the terms of the obligations of the
- 21:33contractor, government and the financers
- 21:35have to be very selectively and
- 21:37critically laid very carefully drafted
- 21:40in the very beginning itself and even
- 21:43the selection of the financers and also
- 21:46guaranteeing finance at the time
- 21:49required also is very important. Say the
- 21:51contractor may say sanction me 100 cr
- 21:54loan but I will take whenever I require.
- 21:56So that kind of terms also should be
- 21:58negotiated
- 22:00very carefully and very well in advance
- 22:03otherwise the there will be huge risk
- 22:05for the project proponent and the
- 22:07project executing team. So the risk
- 22:10assessing team and their capabilities
- 22:11are very very important. You can't
- 22:13expect a financer to have all these
- 22:16assessing abilities. It is very
- 22:18important that they also take some
- 22:20consultants or take some people who can
- 22:23you know what you call assess the
- 22:26capabilities in a way they they must be
- 22:28able to foresee the difficulties or they
- 22:30had expertise in building that kind of
- 22:32thing. They may take another contractor
- 22:35who laid the another road into a
- 22:38financer can take a other contractor as
- 22:40a consultant to tell them about the
- 22:42risks or something like that. So there
- 22:45is nothing wrong in taking a risk
- 22:47assessing team which has the capacity to
- 22:49judge the risks and accordingly frame
- 22:53the terms and analyze the pros and cons
- 22:56and then provide project finance and
- 22:58more importantly proper documentation
- 23:01and even though it might cost legal
- 23:03charges huge but still it's very
- 23:05important to carefully drafted debt
- 23:08agreement and other co-obligation terms
- 23:11documents for the interest of all the
- 23:13parties and protect the interest in so
- 23:16that there is no future problem to the
- 23:20any party in the project finance that is
- 23:23either the SPV that is the sponsor and
- 23:25the uh financial institution or the
- 23:28institutions or if it is a government
- 23:30project the government and all the
- 23:32parties terms have to be carefully
- 23:33drafted. What are the major advantages
- 23:36of project finance? It definitely has
- 23:39helped in boosting infrastructure
- 23:41development. All the highways and the
- 23:44airports and the uh railways the big big
- 23:48major industries whatever we see
- 23:50majority of them had got their finance
- 23:52in the project finance model and they
- 23:55have definitely contributed to
- 23:57infrastructure development in India and
- 24:00big businesses cannot be done without
- 24:02huge finance. So the huge finance should
- 24:06not be a hindrance for national
- 24:08development and for contributing to the
- 24:11infrastructure or other development
- 24:13projects in India and anyway the project
- 24:16itself based the project there are many
- 24:18projects which takes years to even
- 24:20establish imagine an iron and steel
- 24:22factory even to establish a factory it
- 24:25takes years before it starts producing
- 24:27iron or something like that. So these
- 24:30projects require project finance and
- 24:33financially viable for all stakeholders
- 24:35because contractor is laying the road
- 24:38with the banker's money or the financial
- 24:41institutions money. Government is
- 24:43getting the road done through the
- 24:44contractor. So government is not
- 24:46investing for the banker. They are
- 24:49getting the interest that is repaid and
- 24:51for the public a road is coming. They
- 24:54can do the business. They can go and far
- 24:56away places, get some employment, their
- 24:59opportunities will grow and when they
- 25:01are commuting they pay dual fee. So for
- 25:04the public there is a facility that is
- 25:06coming. So in a way it contributes to
- 25:08the benefit of all the stakeholders and
- 25:11also contributes to the national
- 25:14development. So in a way project finance
- 25:16is very crucial for major infrastructure
- 25:18projects and other projects and it has
- 25:21immensely contributed to the uh
- 25:24development of the nation and not only
- 25:26the development financial institutions
- 25:29but bankers also have every major bank
- 25:32has project finance wing which they have
- 25:34been financing for many years now. So
- 25:37this has definitely helped specifically
- 25:40infrastructure projects major roads,
- 25:43airports and all of this we can see
- 25:45because of this even railway stations
- 25:47and all these developments majority of
- 25:50them were done through the project
- 25:52finance model and it is no longer
- 25:54limited to development financial
- 25:56institutions that is DFI alone bankers
- 25:59also are doing and in view of the large
- 26:01scale operations all our major banks are
- 26:04doing project finance these days. So
- 26:07with this we will conclude our
- 26:09discussion on different kinds of finance
- 26:12and we will go to discuss the powers and
- 26:15functions of the Reserve Bank of India
- 26:17and other banks the next week. Thank
- 26:21you.
About this transcript
This page contains the full transcript of Project Finance by NPTEL-NOC IITM, generated from the public captions YouTube serves with the video. The transcript has 3,929 words across 603 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.
What you can do with it
Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.
Free YouTube transcript tool
YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, translation to 100+ languages, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.