Full transcript

  1. 0:47[Music]
  2. 0:52[Music]
  3. 0:55[Applause]
  4. 1:01will the commission come to order please
  5. 1:12today the commission will focus on the
  6. 1:15events leading to the decision to launch
  7. 1:18the Challenger
  8. 1:19commission has already reviewed a good
  9. 1:22deal of information about the seals and
  10. 1:24the O-rings on the solids rocket
  11. 1:26boosters should be noted however that it
  12. 1:29is not yet clear that the joint area was
  13. 1:31originating problem
  14. 1:33therefore it is important that all
  15. 1:35potential causes of the accident
  16. 1:38including the external tank be actively
  17. 1:40pursued
  18. 1:42in our sessions today and tomorrow we
  19. 1:45want to present in a thoughtful and
  20. 1:46orderly manner
  21. 1:48the facts relating to the decision to
  22. 1:51launch the Challenger
  23. 1:54because of a simple
  24. 1:56I will ask witnesses to identify the
  25. 1:58time and place of any event that they
  26. 2:00are addressing and the names and
  27. 2:02positions of persons who participated
  28. 2:07to be fair in the presentation of the
  29. 2:08facts
  30. 2:10because the subject matter may involve
  31. 2:12possible human error as distinguished
  32. 2:15from equipment failure the commission
  33. 2:17will attempt
  34. 2:19to give a right of reply as soon as
  35. 2:21possible to any person who believes he
  36. 2:24has been unfairly criticized or Whose
  37. 2:26actions may have been inaccurately
  38. 2:28portrayed
  39. 2:30during the last two weeks the commission
  40. 2:32has encouraged NASA
  41. 2:34to disclose a large number of facts and
  42. 2:36documents relating to the launch
  43. 2:38which has been done
  44. 2:40as a result we believe the public is
  45. 2:43better able to understand and assess
  46. 2:45many aspects of the accident
  47. 2:48we hope that this process will continue
  48. 2:49until all the facts are fully known and
  49. 2:52as much as possible fully understood
  50. 2:55while the commission has the
  51. 2:56responsibility
  52. 2:58on his mandate from the president to
  53. 3:00investigate the accident and report its
  54. 3:02findings
  55. 3:04the media plays a key role in the
  56. 3:06process by keeping the public informed
  57. 3:08we believe it has performed this role
  58. 3:11well and with our sense of
  59. 3:12responsibility
  60. 3:13if the commission effectively performs
  61. 3:15its duties and the media performs its
  62. 3:18role of accurately reporting the facts
  63. 3:19as they develop the public will be well
  64. 3:22served
  65. 3:23Witnesses who appear
  66. 3:25the day will be able to comment or to
  67. 3:27clarify their testimony as long as the
  68. 3:30substance common honor clarify the
  69. 3:32testimony as long as the substance is
  70. 3:34not altered
  71. 3:36of course any additional evidence or
  72. 3:38additional material that might assist
  73. 3:39the Commission in the performance of its
  74. 3:41studies and responsibilities will be
  75. 3:43welcome
  76. 3:45the first Witnesses this morning will be
  77. 3:47Alan
  78. 3:49um McDonald
  79. 3:50following Mr McDonald and at the request
  80. 3:53about inside call
  81. 3:55the commission will next year Jay Mason
  82. 3:57who's Executive Vice President of the
  83. 3:59fire call
  84. 4:01at first I would like now and now I
  85. 4:04would like to call about our executive
  86. 4:06director Dr Keel who will make a few
  87. 4:09comments before we hear Mr McDonald
  88. 4:12Mr chairman for the benefit of the
  89. 4:14commission we have put together a
  90. 4:15chronology of events
  91. 4:17relating to the period when the first
  92. 4:20temperature concerns were raised with
  93. 4:21respect to the Challenger indicating the
  94. 4:24activities
  95. 4:25and also the participants as the
  96. 4:27commission understands them based on
  97. 4:29testimony and documentation provided to
  98. 4:31the to the commission this chronology
  99. 4:33has been provided to all the witnesses
  100. 4:35Mr chairman so that they'll have an
  101. 4:36opportunity to understand our
  102. 4:39reconstruction of those events and to
  103. 4:41clarify them and also to it as
  104. 4:44appropriate to identify the nature of
  105. 4:47the discussions at each of these
  106. 4:48meetings and activities
  107. 4:49starting approximately from the scrub of
  108. 4:52the originally planned launch of
  109. 4:54Challenger for January 27th at 9 38 a.m
  110. 4:58ranging up to the launch of the
  111. 5:01Challenger on January 28th at 11 38 A.M
  112. 5:05there are Corrections that have to be
  113. 5:08made on this document we'll make them as
  114. 5:10we go along it's as accurate as we can
  115. 5:12make it at the present time
  116. 5:15now I like to call on Miss McDonald
  117. 5:16please
  118. 5:24McDonald I think you probably if you
  119. 5:26take the middle chair it might be the
  120. 5:29best
  121. 5:30I think in uh to be consistent uh let's
  122. 5:35swear all the witnesses in again
  123. 5:37some have been sworn and some have not
  124. 5:39so let's swear them all again please
  125. 5:46[Music]
  126. 5:51you're now employed by cycle important
  127. 5:53psychology that's correct and how long
  128. 5:56have you been employed by them I've been
  129. 5:58with Martin a little over 26 years
  130. 6:01and uh you're an engineer
  131. 6:04yes I have a bachelor's very in chemical
  132. 6:07engineering from Montana State
  133. 6:09University and a master's degree in
  134. 6:11engineering Administration from the
  135. 6:13University of Utah
  136. 6:15and uh
  137. 6:17can you give us some some history of
  138. 6:20your employment with cycle
  139. 6:24our lady director of the Space Shuttle
  140. 6:27side rocket motor project uh my
  141. 6:30responsibilities are for technical cost
  142. 6:33and schedule performance of the steel
  143. 6:36case Motors that are flown out of
  144. 6:38Kennedy and also the development
  145. 6:40qualification of the Summer Long case
  146. 6:41solid rocket motor
  147. 6:43be flown out of Vandenberg Air Force
  148. 6:45Base
  149. 6:46I've had this position for a little less
  150. 6:48than two years I started as a director
  151. 6:51in March of 1984 of the shuttle SRM
  152. 6:55project
  153. 6:56prior to that I was the manager of the
  154. 6:59project engineering division at Martin
  155. 7:01fire call which I was a technical
  156. 7:05responsibility from a project
  157. 7:07engineering standpoint for all of the
  158. 7:09programs in the plan for the exception
  159. 7:11of the Space Shuttle that included the
  160. 7:14Peacekeeper the MX sage1 Trident One C4
  161. 7:18production Trident II development
  162. 7:20the harm Mark 104 standard missile md2
  163. 7:25the improved performance space motor 2
  164. 7:28finished a contract on qualifications
  165. 7:30long life motor for Schram
  166. 7:32had all of the independent research and
  167. 7:34development advanced technology programs
  168. 7:37with the rocket propulsion Laboratory
  169. 7:39and also some work on airbag airfish and
  170. 7:43restraint systems
  171. 7:45I had that job I guess for about three
  172. 7:48four years prior to coming into the
  173. 7:50shuttle program and prior to that I was
  174. 7:52the
  175. 7:53manager of the profound Development
  176. 7:56Department for a few years
  177. 7:57and prior to that I was the
  178. 8:01manager of the project Engineering Group
  179. 8:04for advanced development development
  180. 8:06projects
  181. 8:07I started with fire call in 59
  182. 8:11after graduating from Montana State
  183. 8:13University and my first job was involved
  184. 8:17in designing the external insulation for
  185. 8:19the stage one of the Minutemen I did
  186. 8:22that design and I was then chosen as a
  187. 8:25group leader for flight test of the mid
  188. 8:28and was participated in the flight test
  189. 8:30about the first 20 flights the minute
  190. 8:32man out of the cape
  191. 8:33subsequent to that I spent considerable
  192. 8:36time working as a chief engineer on
  193. 8:40development of some controllable Solid
  194. 8:42Rock and motor concepts for several
  195. 8:44years
  196. 8:45I worked on a lot about the dance
  197. 8:46development programs before before I
  198. 8:48came involved in the Trident program in
  199. 8:52the early 70s
  200. 8:54so for the last three or four years
  201. 8:57where have you spent your time
  202. 8:59the last couple of years of course I
  203. 9:02spent my time as director of the solid
  204. 9:04rocket motor project which involves a
  205. 9:07considerable amount of coordination
  206. 9:10relative to production of the shuttle
  207. 9:13solid rocket Motors assessment of the
  208. 9:15flight Readiness reviews for the space
  209. 9:18shuttle side Rocket Motors I am the
  210. 9:21chairman of the senior material review
  211. 9:24board for the SRM
  212. 9:27that senior material review board that
  213. 9:30has to review all of the discrepancies
  214. 9:33on any of the hardware that's considered
  215. 9:35the criticality one or any that's
  216. 9:38outside the experience base of our
  217. 9:40previous experience
  218. 9:41as chairman at board there's members
  219. 9:45from our Quality Group our Engineering
  220. 9:47Group NASA Marshall Representatives but
  221. 9:50I have to sign every one of those that
  222. 9:52they're ready for flight I'm also a
  223. 9:54co-chairman of the problem review board
  224. 9:56with Marshall space flight center
  225. 9:58relative to any problems were identified
  226. 10:01from returned Hardware that come back to
  227. 10:03the tape and what actions are taken to
  228. 10:05uh to understand those problems and
  229. 10:07provide proper
  230. 10:09for those and prevent them from
  231. 10:10occurring
  232. 10:11my activities in the past year to a
  233. 10:16large extent have been involved with the
  234. 10:18design certification of the film along
  235. 10:21face solid rocket motor I'm also the
  236. 10:24co-chairman of the design certification
  237. 10:26team represented by Foxhall and Marshall
  238. 10:29at the SRM level
  239. 10:31before that and that has taken the
  240. 10:33conservative among my time this past
  241. 10:34summer in the series of reviews for
  242. 10:37certifying the graphite composite case
  243. 10:39for for Vandenberg
  244. 10:42yeah how much time did you spend in the
  245. 10:44performance of those duties that at
  246. 10:47Kennedy Space Center
  247. 10:49well I have been alternating with my
  248. 10:52supervisor the vice president of space
  249. 10:55militia programs Mr Joe kilminster on
  250. 10:57the Joe kilminster and what is this
  251. 11:00title uh he's the vice president of the
  252. 11:03space booster programs and he and I have
  253. 11:05been alternating uh going to the cape
  254. 11:08supporting the launches of the srms
  255. 11:13immediate supervisor yes and you
  256. 11:16alternated going to the cave yes the
  257. 11:18heart of that were under uh that works
  258. 11:22out very well we both of course have a
  259. 11:25fairly heavy Demand on our time with all
  260. 11:27the reviews uh initial process primarily
  261. 11:30with the trips to Huntsville and the
  262. 11:32Marshall space flight center
  263. 11:34I attended this course the sds-51l he
  264. 11:38was at the Fireflight and our charger is
  265. 11:42to attend the l-1 meeting
  266. 11:4551l is the Challenger launch that's
  267. 11:48correct and you were there at that time
  268. 11:51was he Mr the previous launch he was at
  269. 11:55the previous launch yeah what about the
  270. 11:56one before that one before that I was at
  271. 12:00he was one Hank for that we've been
  272. 12:02fairly well alternated
  273. 12:05what were your responsibilities when you
  274. 12:07were there
  275. 12:08at the cape at the time of the launch
  276. 12:11well at the time of the launch I was in
  277. 12:15the firing room too launch control
  278. 12:17center
  279. 12:19uh
  280. 12:20there's the seats there that for the
  281. 12:23monitors of many of the functions on the
  282. 12:26solid rocket boosters as well as the TV
  283. 12:28monitor
  284. 12:29on Marshall space flight center has a
  285. 12:31group
  286. 12:32at their console that involves the
  287. 12:36primary contractors for all of the
  288. 12:39subsystems the SRB has one monitored and
  289. 12:42they have people from usbi who provide
  290. 12:45part of the heart
  291. 12:47Hardware we also have a monitor from the
  292. 12:51uh our support to the Space Shuttle
  293. 12:55processing contractor that is right next
  294. 12:58to that monitor and Mr Carter Kennedy
  295. 13:02our vice president of our space
  296. 13:03operations at the cape was at that
  297. 13:06monitor it's right next to the Marshall
  298. 13:08Monitor and I was sitting with him at
  299. 13:09the time of the of the launch but I
  300. 13:11wasn't speaking so much about the
  301. 13:13Challenger launches I was generally
  302. 13:14speaking generally speaking when you or
  303. 13:16Mr skillmaster or Infinity you speak for
  304. 13:19the company is that it uh yes uh
  305. 13:22generally the process is the before a
  306. 13:26launch uh there's an L minus one meeting
  307. 13:29the day before the launch at which time
  308. 13:31all of the problems uh that were still
  309. 13:35open prior to the L minus one are
  310. 13:37reviewed was to Jess Moore on his board
  311. 13:40and uh assure that they're all closed
  312. 13:42out and we're ready for the launch
  313. 13:45uh subsequent to that meeting there's a
  314. 13:48poll that is taken he takes an all poll
  315. 13:50and everyone is involved in the launch
  316. 13:53including the as well as the propulsion
  317. 13:55systems with the payload and everyone
  318. 13:56else and every contractor that is
  319. 13:59involved in that has to answer to the
  320. 14:01polls whether they're ready to go and
  321. 14:02launch I attended that meeting as you
  322. 14:06know the
  323. 14:07L minus one meeting was conducted I
  324. 14:10believe on Saturday or something because
  325. 14:12I'd like to if you don't mind come to
  326. 14:14that and
  327. 14:15chronologically in just a moment but so
  328. 14:17at those meetings when you were there
  329. 14:19you spoke the thought of call yes I
  330. 14:21spoke for Thought
  331. 14:23um
  332. 14:24and how long has you been there prior to
  333. 14:27the launch of the Challenger physically
  334. 14:30located at Kennedy I was at Marshall
  335. 14:34space flight center earlier in the week
  336. 14:37on some negotiations for our subsequent
  337. 14:40contract and it had went down to uh
  338. 14:43Kennedy on the uh I believe it was the
  339. 14:47Thursday before the launch sure could
  340. 14:48you give some explanation of the
  341. 14:51relationship between yourself and
  342. 14:53Marshall before you went to Kennedy
  343. 14:56uh I'm not sure what you mean my
  344. 14:59relationship well what what function was
  345. 15:01Marshall performing at that time and
  346. 15:03what were you doing in representing
  347. 15:06Cyclone well Marshall has uh overall
  348. 15:09responsibility for all of the propulsion
  349. 15:11subsystems uh on the shuttle and we are
  350. 15:15part of the SRB team I work directly
  351. 15:19with Larry Ware who is the uh project
  352. 15:22manager for Marshall on solid rocket
  353. 15:24motor and he works for learning lawy he
  354. 15:27was the project manager on the SRB which
  355. 15:29includes the solid rocket motor in the
  356. 15:32outskirt TVA system in the parachute
  357. 15:35recovery system makes up the whole SRV
  358. 15:38and I always attend or joke illness
  359. 15:41attends the launches with Mr Malloy and
  360. 15:45yes the representatives also for the
  361. 15:47other subcontractors for for usbi
  362. 15:51in case there's any questions that come
  363. 15:53up that we can either resolve there or
  364. 15:55get resolution to uh prior to the launch
  365. 15:58just for the record where's Marshall
  366. 15:59located Marshall's located in Huntsville
  367. 16:01Alabama
  368. 16:02and when did you leave Wentzville
  369. 16:04Alabama to go to Cape Kennedy on this
  370. 16:06occasion well I think it was Windsor
  371. 16:09Thursday afternoon before the uh for the
  372. 16:12launch did you go by yourself it was
  373. 16:14some uh no I went by myself
  374. 16:16you know uh
  375. 16:18I want to give you a an opportunity to
  376. 16:22give a full description of the events
  377. 16:24the day before in the 27th and the day
  378. 16:27of the launch
  379. 16:29before I do that I I understand that you
  380. 16:32made some notes after the accident which
  381. 16:36put on papers or some of your
  382. 16:38Recollections of the United preceded the
  383. 16:40action is that correct that is correct
  384. 16:43and you have those notes now
  385. 16:45yes I have a I would like to explain to
  386. 16:49you that you had Liberty to refer to
  387. 16:51those notes
  388. 16:52in any way you want to and now beginning
  389. 16:57with the first recollection you have of
  390. 17:00the weather problem and how it came to
  391. 17:02your attention uh give us a full account
  392. 17:06of uh the events of that day and the
  393. 17:09following days 27th and 28th so we'll
  394. 17:12try not to interrupt you except possibly
  395. 17:14for clarification
  396. 17:15I want you to feel free to tell
  397. 17:17everything you recall about it and then
  398. 17:19after that we may ask some questions
  399. 17:21about to try to amplify any answers that
  400. 17:23you made yet
  401. 17:25well I first become aware of the concern
  402. 17:29of the low temperatures that were
  403. 17:30projected for the cape was late in the
  404. 17:33afternoon on the 27th
  405. 17:36I was at the farmer Kennedy's house he's
  406. 17:40the vice president of our as I mentioned
  407. 17:43the space operations center at the cape
  408. 17:45Corps the stacking of the of the srms
  409. 17:48and I had a call from Bob Edward he is
  410. 17:52the manager of our ignition system and
  411. 17:55final assembly works for me a program
  412. 17:57manager at the fire hall in Utah he
  413. 18:01called me and said that they had just
  414. 18:04received some word earlier that the
  415. 18:06weatherman was projecting temperatures
  416. 18:09as low as 18 degrees Fahrenheit
  417. 18:11sometime in the early morning hours of
  418. 18:14the 28th and that they had some meetings
  419. 18:17with some of the engineering people had
  420. 18:19some concerns about the O-rings getting
  421. 18:21to those kinds of temperatures and he
  422. 18:24wanted to make me aware of that and also
  423. 18:26wanted to get some more updated and
  424. 18:28better information on what the actual
  425. 18:30temperature history was going to be
  426. 18:31predicted so that they could make some
  427. 18:34calculations on what they expected real
  428. 18:36temperature the O-rings may see he was
  429. 18:38calling from Utah he was calling from
  430. 18:40Utah
  431. 18:41I told him that I would get that
  432. 18:43temperature data from for him and call
  433. 18:45him back cover Kennedy then when I hung
  434. 18:49up called the launch operations center
  435. 18:50to get the predicted temperatures from
  436. 18:52pad B
  437. 18:54as well as what the temperature history
  438. 18:56had been during the day up until that
  439. 18:58time and pepe was the area where the
  440. 19:01launch was I believe as he had that
  441. 19:03Challenger was fly off of this was the
  442. 19:05first time that would fly off of that
  443. 19:07pad
  444. 19:08he obtained those temperatures from the
  445. 19:11launch operations center and they
  446. 19:14basically said that they felt was going
  447. 19:17to get near freezing or freezing before
  448. 19:19midnight could be as low as 22 degrees
  449. 19:22as a minimum in the early morning hours
  450. 19:24probably around six o'clock
  451. 19:26and that they were predicting a
  452. 19:28temperature of about 26 degrees at the
  453. 19:31intended launch time about 9 38 the next
  454. 19:34morning
  455. 19:35I took that data and called back to the
  456. 19:37plant Senate to Bob Ebling and relay
  457. 19:41that to him and told him you had to use
  458. 19:43this temperature data for his
  459. 19:45predictions
  460. 19:46I thought this was very serious and make
  461. 19:49sure that he had the vice president
  462. 19:51engineering involved in this and all of
  463. 19:53his people
  464. 19:54that I wanted them to put together some
  465. 19:57calculations and a presentation material
  466. 20:00who's the vice president of offering Mr
  467. 20:02Bob Lund is our vice president of
  468. 20:04engineering at our Martin call facility
  469. 20:07in Utah to make sure that he was
  470. 20:09involved in this and that this decision
  471. 20:11should be an engineering decision not a
  472. 20:13program management decision
  473. 20:16and I told him that I would like him to
  474. 20:19make sure they prepared some charts and
  475. 20:20were in a position to recommend the
  476. 20:22launch temperature just don't recommend
  477. 20:24a launch but recommend a launch
  478. 20:25temperature and have the rationale
  479. 20:27for supporting that much temperature
  480. 20:30I then hung up and I called Mr Malloy he
  481. 20:35was staying at the Holiday Inn in
  482. 20:37Merritt Island and they couldn't reach
  483. 20:38him
  484. 20:39so I called Cecil Houston Cecil Houston
  485. 20:43is the resident manager for the Marshall
  486. 20:45space flight center office at KSC
  487. 20:49and told him about our concerns with the
  488. 20:51low temperatures and the potential
  489. 20:53problem of the O-rings
  490. 20:54and he said that he would set up a
  491. 20:57teleconference he had a four-wire system
  492. 20:59next to his office
  493. 21:01his office is right across from the VAB
  494. 21:03in the trailer complex C over there he
  495. 21:06was set up the four wire teleconference
  496. 21:09involving the engineering people at the
  497. 21:11Marshall space flight center at
  498. 21:12Huntsville our people back at Cyclone
  499. 21:15Utah and that I should come down to his
  500. 21:18office and participate at Kennedy from
  501. 21:20there
  502. 21:21and that he would get back with me and
  503. 21:22let me know when that time would be
  504. 21:26uh I waited for a short period of time I
  505. 21:29don't know exactly how long it wasn't
  506. 21:30very long who called back told me that
  507. 21:32he had contacted the parties and was all
  508. 21:34set up for 8 15 PM Eastern Time For That
  509. 21:37teleconference I really relayed that
  510. 21:40message on back to the plant told them
  511. 21:42that we have to have charts at that time
  512. 21:44faxed out
  513. 21:45to Kennedy as well as Marshall that we
  514. 21:47can discuss for that teleconference
  515. 21:50could you explain what charts mean well
  516. 21:53their charts any data that we had for uh
  517. 21:57showing why we had concerns on the
  518. 21:59O-rings of low temperatures what our
  519. 22:01history has been
  520. 22:03what any any calculations we might be
  521. 22:05able to make relative to their
  522. 22:07performance
  523. 22:09supporting it rationale for what
  524. 22:11accessible temperatures what might not
  525. 22:13be an acceptable temperature and review
  526. 22:15that and these would all Beyond charts
  527. 22:18that we would send by a fax machine so
  528. 22:20people could read those and we could
  529. 22:22discuss those as the rationale for
  530. 22:25either recommending a launch or not
  531. 22:28[Applause]
  532. 22:32that I arrived
  533. 22:35at the Kennedy Space Center
  534. 22:38at about 8 15 and
  535. 22:41the fly arrived there at that that's
  536. 22:44Kenny Space Center the other people had
  537. 22:46already had arrived were Larry Malloy
  538. 22:49was there he is the manager of the
  539. 22:53project manager for the SRB for Marshall
  540. 22:58was there and he is the manager of the
  541. 23:01shuttle project office he's flooring the
  542. 23:03white moth
  543. 23:04Cecil Houston was there the resident
  544. 23:06manager for Marshall and Jack Buchanan
  545. 23:09was there he happens the uh our manager
  546. 23:12in one back off manager of our launch
  547. 23:13Sports Services office at Kennedy
  548. 23:17the Silicon hadn't started yet it came
  549. 23:21on the network shortly after I got there
  550. 23:24but uh
  551. 23:25bestow to hold on because the charts
  552. 23:28have not been received either at
  553. 23:30Marshall or Kennedy at that time
  554. 23:32and we waited I guess for probably
  555. 23:34another half hour before those charts
  556. 23:37finally came through and we could
  557. 23:38reproduce them in fact they hadn't all
  558. 23:40even been received yet there were some
  559. 23:42conclusions recommendation charts didn't
  560. 23:45come for about half hour even later than
  561. 23:47that that was it essentially a telephone
  562. 23:48conference or was there actually a
  563. 23:50network with pictures it was a telephone
  564. 23:52conference just telling them you could
  565. 23:54have that you could hear the voices from
  566. 23:56the other two places as well as your own
  567. 23:58however
  568. 24:00the way those teleconferences work is
  569. 24:02buttons that you can push and we'll mute
  570. 24:05out to you speaking to someone else or
  571. 24:07speaking you can usually hear it better
  572. 24:08when you don't have your own mics open
  573. 24:11so there's a lot of conversations I'm
  574. 24:13sure at all habilities at one time which
  575. 24:15you can't hear but I'll relay on what I
  576. 24:18had heard on the conferences as best I
  577. 24:20can
  578. 24:23the teleconference started I guess uh
  579. 24:26close to nine o'clock
  580. 24:28and even though all the charts weren't
  581. 24:31weren't there we were told to begin and
  582. 24:33that Martin blackhaw should take a lead
  583. 24:35and filter the charts that they had
  584. 24:39sense of all centers
  585. 24:42the charts were presented by the
  586. 24:45engineering people from cycle in fact by
  587. 24:49the people that had made those
  588. 24:51particular charts some of them were
  589. 24:52typed some were handwritten
  590. 24:55and they discussed their concerns with
  591. 24:58the low temperatures relatively possible
  592. 25:01effects on the O-rings primarily the
  593. 25:03timing function the seal the feelings
  594. 25:06they presented the history of some of
  595. 25:10the data that we had accumulated both in
  596. 25:12in static tests and this white test
  597. 25:14relative to temperatures and the
  598. 25:16performance of the O-rings they reviewed
  599. 25:18the history of all of our erosion with
  600. 25:20any O-rings from the field joints any
  601. 25:23Blow by the primary o-ring was soot or
  602. 25:25products of combustion and decomposition
  603. 25:28that we had noted
  604. 25:29the performance of the secondary O-rings
  605. 25:32and there was an exchange amongst the
  606. 25:34technical people and on that data is
  607. 25:37what it meant in discussions
  608. 25:40but the real exchange never really came
  609. 25:43until the conclusions and
  610. 25:45recommendations came in
  611. 25:47uh at that point in time our vice
  612. 25:50president Mr Bob long presented those
  613. 25:53charts
  614. 25:55and he presented the charge from the
  615. 25:57conclusions and recommendations and the
  616. 25:59bottom line was is that the engineering
  617. 26:02people would not recommend the launch
  618. 26:04below 53 degrees Fahrenheit
  619. 26:06the basis for that recommendation was
  620. 26:08primarily our concern with the launch
  621. 26:11that had occurred about a year earlier
  622. 26:12in January of 85 I believe it was 51c it
  623. 26:17was our motor number srm15
  624. 26:20and that particular
  625. 26:23motor had a couple of field joints that
  626. 26:25not only had some erosion but they had
  627. 26:27some fairly severe Blow by the primary
  628. 26:30seals a fairly heavy soot over a fairly
  629. 26:32large Arc very deep and black
  630. 26:35and even though we could see no
  631. 26:39measurable erosion on the secondary
  632. 26:40o-ring there was a heat effect and by
  633. 26:43that because the machine was gone off of
  634. 26:44the O-ring seal it wasn't couldn't age
  635. 26:46anything but the sheen was gone
  636. 26:48and because of that we were concerned of
  637. 26:52launching beyond our experience base
  638. 26:54below that temperature
  639. 26:57for that temperature
  640. 26:59brought a lot of strong comments in
  641. 27:03reaction
  642. 27:04from several of the NASA officials
  643. 27:08uh I believe was Mr Malloy made some
  644. 27:11comments about when will ever fly if we
  645. 27:13have to live to that some sometime in
  646. 27:16the future
  647. 27:17and uh also commented that uh you know
  648. 27:20we are trying to establish new launch
  649. 27:22commit criteria we can't do that you
  650. 27:25don't do that the night before a launch
  651. 27:27that's a predetermined set of
  652. 27:29constraints
  653. 27:30and we can't do that and other comments
  654. 27:34were made about whether we could ever
  655. 27:36fly out of Vandenberg and 24 flights a
  656. 27:39year because it wasn't uncommon that 53
  657. 27:41degrees in the early morning hours or a
  658. 27:43lot of the launches occur
  659. 27:46one of the comments that came and this
  660. 27:49is by voice recognition I believe is
  661. 27:51some of Mr hardy
  662. 27:52Marshall space flight center was that he
  663. 27:55was appalled at that recommendation
  664. 27:58however he also said that he certainly
  665. 28:00wouldn't fly without uh not Floyd would
  666. 28:04not fly without fire costs concerns
  667. 28:06even though he was a fall with that
  668. 28:08recommendation
  669. 28:10I believe it was uh Stan reinhart's made
  670. 28:12a comment that he was under the
  671. 28:14impression that the sod rocker Motors
  672. 28:17were qualified from 40 to 90 degrees and
  673. 28:19that 53 degree recommendation sermon was
  674. 28:22inconsistent with that
  675. 28:24uh some place in the conversation about
  676. 28:28the impact of 53 degrees I believe Cecil
  677. 28:30Houston sometimes commented that you
  678. 28:33know uh wouldn't be till about Thursday
  679. 28:35that we would have uh morning
  680. 28:37temperatures probably in the 50s
  681. 28:39so he didn't seem to be as alarmed about
  682. 28:42when you know we could get to that
  683. 28:44temperature
  684. 28:46there were several challenges relative
  685. 28:49to this was felt uh how conclusive the
  686. 28:52effective temperature was on this whole
  687. 28:53problem of o-ring erosion of the farset
  688. 28:56blow by
  689. 28:57and the challenge came from working at
  690. 29:00the total beta because even though we
  691. 29:03were concerned about this flight which
  692. 29:06was the coldest ever and at that time
  693. 29:08from Florida a year earlier there was
  694. 29:10that flight uh back in the late fall of
  695. 29:1385 I think it was probably October 61a
  696. 29:16was our srm-22 set that had some Global
  697. 29:20idea O-rings no no erosion the primary
  698. 29:23O-rings in fact a couple of them I
  699. 29:24believe
  700. 29:25uh and that's happened to be a launch
  701. 29:28that had the highest temperature
  702. 29:30so there was some concern at the date it
  703. 29:33was inconclusive
  704. 29:35and also that we had some Motors that
  705. 29:39were static tested as low as 36 degrees
  706. 29:41Fahrenheit the M4 I believe and it
  707. 29:44showed not only no o-ring erosion but no
  708. 29:46blow-by well some of the comments that
  709. 29:48came back from that and I believe it was
  710. 29:49Roger bosia they commented this uh he
  711. 29:52felt that there was a significant
  712. 29:54difference in the observation of the
  713. 29:57actual soot that passed the primary
  714. 29:59o-ring on the SRM 15 sets it was a cold
  715. 30:03one versus the one that was worn that
  716. 30:06there was a much larger Arc between the
  717. 30:09two O-rings was affected the cert was
  718. 30:11much blacker it penetrated all the way
  719. 30:14up to the secondary o-ring and of course
  720. 30:16we had some heat effect there and he
  721. 30:17thought there was a significant
  722. 30:18difference and that well could be the
  723. 30:20difference just due to temperature
  724. 30:22uh I commented at that time about the
  725. 30:25static test history I told him I did not
  726. 30:27feel that that was a valid data
  727. 30:31for a couple of reasons one on the
  728. 30:33static test Motors the we keep the
  729. 30:35static test Motors in a environmental uh
  730. 30:38building essentially during the build up
  731. 30:41assembly and checkout of all
  732. 30:42instrumentation and that environmental
  733. 30:45building kept at 70 to 72 degrees that
  734. 30:48building then rolled back on a track
  735. 30:50about six hours before the static test
  736. 30:52so it wasn't exposed very long to the
  737. 30:55cold temperatures
  738. 30:56secondly in the static test Motors
  739. 30:59we went in and actually repaired and
  740. 31:02filled holes in the putty these holes
  741. 31:06are formed by the Assembly of the rocket
  742. 31:09motor as you form the tank clevis
  743. 31:11there's aircraft in there that Air's got
  744. 31:13to go someplace
  745. 31:15and sometimes that air will go up to the
  746. 31:17putty we had seen this and also when you
  747. 31:21run the leak check on the two seals if
  748. 31:23you get any Blow by doing a leak jacket
  749. 31:25made into propagate those and the static
  750. 31:29test Motors some of these are observed
  751. 31:31and they went in and filled those inside
  752. 31:33the motor
  753. 31:34a prior to static test so I told them I
  754. 31:36didn't feel that that data was
  755. 31:39conclusive and they shouldn't use that
  756. 31:40for deciding what the priority
  757. 31:43performance was
  758. 31:50other discussion on some of the charts
  759. 31:52that we had that was somewhat
  760. 31:55inconclusive we had a chart
  761. 31:57that had some subscale data where we had
  762. 32:00run some tests on Blow by with some
  763. 32:03subscale O-rings they actually had the
  764. 32:05full-scale diameter 280 thousands but
  765. 32:07they were smaller that was the cross
  766. 32:09section of the O-ring but they're
  767. 32:11smaller diameter Hardware
  768. 32:13and there were coal gas tests and uh
  769. 32:15we're tempting to try to measure what
  770. 32:17kind of blow-by one might get with a
  771. 32:19pressurization rates you see in the
  772. 32:21motor and we were using argon as the
  773. 32:24working fluid and also adding some Freon
  774. 32:27and we had run tested around the ambient
  775. 32:2930 degrees and those and did not see any
  776. 32:32difference so there was some conflicting
  777. 32:34data there it said it wouldn't make any
  778. 32:38difference but that I want to remind
  779. 32:39everyone it was a cold test
  780. 32:42that time I commented at the time that I
  781. 32:46felt the lower temperatures were in the
  782. 32:48direction of Badness for both O-rings
  783. 32:51because it slows down the timing
  784. 32:53function for both of those but the
  785. 32:55effect is much worse for the primary
  786. 32:57o-ring compared to the secondary o-ring
  787. 33:01because the leak check force is the
  788. 33:02primary o-ring in the wrong side of the
  789. 33:05O-ring Groove while it forces the
  790. 33:07primary o-ring in the proper direction
  791. 33:11this
  792. 33:12fraction the weighed and considered in
  793. 33:15making the valuation as to what the
  794. 33:19recommended temperature should be
  795. 33:22I was looking at a chart at that time
  796. 33:25that we had in fact as a chart that I
  797. 33:27had made with some help of our
  798. 33:29engineering people back last summer in a
  799. 33:31presentation I'd made here in Washington
  800. 33:33to the headquarters be from August 19th
  801. 33:37it was a chart that showed that there's
  802. 33:39really three phases or three regions of
  803. 33:42concern and during the ignition Transit
  804. 33:45relative to perform at the all right
  805. 33:47first phase of that is a condition for
  806. 33:50the O-ring the primary O-rings
  807. 33:52pressurized it starts as an energizing
  808. 33:55process and actually has to move from
  809. 33:58the forward face of the O-ring Groove
  810. 33:59because that's where it's at as a result
  811. 34:01of leak check and then has to move back
  812. 34:03and seal on the back face now this uh
  813. 34:07process we felt took uh took place in
  814. 34:10the early part of the ignition transient
  815. 34:12someplace before it got 200 PSI
  816. 34:15and in cold weather what's going to
  817. 34:18affect that is of course the the grease
  818. 34:20that's in that area also is very viscous
  819. 34:23instead the O-ring itself is stiff we
  820. 34:26knew that the cold temperature shrank
  821. 34:29the O-ring some and from our resiliency
  822. 34:31tests which are tests that basically
  823. 34:34show how the O-ring responds when you
  824. 34:37have it under some compression and
  825. 34:39release that load it shows as it gets
  826. 34:42cold and stiff it doesn't want to
  827. 34:43respond very well and I looked at it
  828. 34:45something like
  829. 34:47flat tire on the bottom of a I remember
  830. 34:49when I used to drive nylon tires when it
  831. 34:51was cold I get out and there's flat spot
  832. 34:53on them and
  833. 34:54that already being having to move that
  834. 34:58either has got to slide or Scott's role
  835. 35:00somewhat it's not a very big dimension
  836. 35:02of losing it's uh 20 30 000. but
  837. 35:06certainly it can't be as good as when
  838. 35:07you don't have that
  839. 35:09also being hard it then has to extrude
  840. 35:12into the gap between the two already
  841. 35:14seals
  842. 35:15and the harder it is I'm sure it's
  843. 35:18harder to extrude in that gap which
  844. 35:19means it may take a higher pressure to
  845. 35:22do that which also takes a lot of time
  846. 35:25I felt that based on what we had done in
  847. 35:28the past we had concluded that this
  848. 35:31blow-by phenomena had really occurred in
  849. 35:33this first part of the pressurization
  850. 35:35cycle
  851. 35:36and I think it was good evidence that it
  852. 35:38had because the threat that appeared
  853. 35:41between the two O-rings was uh exactly
  854. 35:44that it was soot we analyzed it but it
  855. 35:47didn't see any heat effect on the metal
  856. 35:49at all in some cases it discarded the
  857. 35:51grease it didn't really burn it so it
  858. 35:54was a product to the grease we could not
  859. 35:56see any real effect on the secondary
  860. 35:58o-ring so it couldn't have happened very
  861. 36:00long it couldn't happen then you were
  862. 36:02very severe conditions
  863. 36:04but at the same time the temperature
  864. 36:07effects are concerning that maybe we're
  865. 36:09going into another timing regime
  866. 36:12however if we felt that we had a good
  867. 36:15margin there then we felt that we do
  868. 36:18have a good secondary seal during this
  869. 36:20time and I think there's been some
  870. 36:22misconception about uh
  871. 36:24the redundancy the secondary seal
  872. 36:28uh the secondary seal is indeed
  873. 36:31redundant until the metal Parts between
  874. 36:35the time the credits actually rotate
  875. 36:37it's a full redundant seal and during
  876. 36:39this time period it is redundant and
  877. 36:42that's important but once those metal
  878. 36:44Parts rotate and you have a probability
  879. 36:48it may not be so that's why I was
  880. 36:51concerned about that area and but if we
  881. 36:53could convince ourselves the data set
  882. 36:55that wouldn't make that much different
  883. 36:57in that part of the phase then it would
  884. 36:58be a reasonable recommendation to say
  885. 37:00that we would expect much different
  886. 37:02performance
  887. 37:04the shortly thereafter
  888. 37:05that cycle was uh was asked about their
  889. 37:10recommendation and leave and Joe
  890. 37:12kilmister has asked himself what his
  891. 37:14recommendation would be since it was
  892. 37:16engineering that it recommended not
  893. 37:18flying at 53 and he said that he would
  894. 37:20not go against that recommendation he
  895. 37:22couldn't
  896. 37:23go against it
  897. 37:24So based on the controversy relative to
  898. 37:28how conclusive the effects of
  899. 37:29temperature actually were on this
  900. 37:31phenomena we were asked to reassess and
  901. 37:34reevaluate that data
  902. 37:36and uh we decided we would do that and
  903. 37:39the people at Utah said that well they
  904. 37:42would like to have a caucus for about
  905. 37:43five minutes and go off the line
  906. 37:46could I ask you this not to do this for
  907. 37:49moving in Quebec we come to the caucus
  908. 37:52in a minute but Quebec and and
  909. 37:57explained what was said to
  910. 38:02convey the decision of no launch
  911. 38:06I gather at that point the decisions I
  912. 38:09thought I call was to recommend against
  913. 38:10a launch uh that's correct that was at
  914. 38:14that point the recommendation was was
  915. 38:15not the launch of 53 degrees who did
  916. 38:18this talking on that subject was it uh
  917. 38:21that was uh Bob long the vice president
  918. 38:23engineering presented that position but
  919. 38:27uh did you were you able to ascertain
  920. 38:29from that conversation uh how the
  921. 38:32engineers as a group stood on that
  922. 38:35well the engineers as a group uh I you
  923. 38:38know I can't speak for the group I was
  924. 38:40not there but I did hear the engineers
  925. 38:42have presented the charts that they
  926. 38:44actually presented as part of that that
  927. 38:46supported the 53 degree recommendation I
  928. 38:49felt they're very strong in their
  929. 38:51conviction is why they felt
  930. 38:53uncomfortable to go outside that
  931. 38:55experience space
  932. 38:56that who were the Roger mojalay I think
  933. 39:00was one of the strongest ones and Arne
  934. 39:02Thompson that presented those positions
  935. 39:05and represented the charts that Mr
  936. 39:07learned himself at the time oh yes Mr
  937. 39:10Lund himself at the time uh didn't
  938. 39:13present the detailed technical charts
  939. 39:15but he did present the conclusions
  940. 39:17recommendations and that was his
  941. 39:18recommendation as vice presidential was
  942. 39:22anybody on the uh who was on a telecom
  943. 39:25from PI call side
  944. 39:27recommending launch
  945. 39:30at that time no there was no one that
  946. 39:33recommended launch and I don't recall
  947. 39:35there was anyone at either Marshall or
  948. 39:37or fire calls from NASA that didn't
  949. 39:40agree that you know Colt Hampshire is
  950. 39:42one in the wrong direction didn't help
  951. 39:43anything but no no one from Taco at that
  952. 39:46time recommended launch
  953. 39:48and what were the comments by uh NASA
  954. 39:53officials about that recommendation that
  955. 39:55you recall
  956. 39:57well as I recall there were some fairly
  957. 40:00strong comments about being appalled by
  958. 40:02recommendation about trying to Institute
  959. 40:05who launched commit criteria at the last
  960. 40:07minute uh about when we'll ever get this
  961. 40:10launch off
  962. 40:12I thought those were fairly strong
  963. 40:13comments and those were comments
  964. 40:15according to your recollection were made
  965. 40:16by whom
  966. 40:17well the comments relative to the launch
  967. 40:21commit criteria and when they'll ever
  968. 40:23get this office made by Mr Larry Molloy
  969. 40:25uh the comment about being appalled was
  970. 40:28George Hardy he was at Marshall I think
  971. 40:30I recognized his voice but that was my
  972. 40:32voice recognition
  973. 40:35so it was decided that that on any of
  974. 40:38any questions remember the commission
  975. 40:39have I said that Mr McDonald I have one
  976. 40:42question uh before you made uh went off
  977. 40:44the Met did you ask or make a comment
  978. 40:46about the secondary ovary ring Field
  979. 40:49seating that has been were they asked to
  980. 40:51make one no did you make it I did make a
  981. 40:53comment yes could you recall that
  982. 40:55comment please uh yes I think I read it
  983. 40:59to you and I'd be glad to do that again
  984. 41:01I made the comment that lower
  985. 41:03temperatures are in the direction of
  986. 41:04Badness for both O-rings because it
  987. 41:07slows down the timing function
  988. 41:09but the effect is much worse for the
  989. 41:11primary o-ring compared to the secondary
  990. 41:13o-ring because Elite check force is the
  991. 41:15primary o-ring into the wrong side of
  992. 41:17the groove while the secondary o-ring
  993. 41:19goes in the right direction and this
  994. 41:22condition should be evaluated making the
  995. 41:24final decision for recommending the
  996. 41:26lowest acceptable temperature for launch
  997. 41:28that was common I made that confused
  998. 41:30some people some of the witnesses I
  999. 41:32spoke to thought that that was a a
  1000. 41:34comment in support of the launch the
  1001. 41:36fact that this secondary o-ring seal
  1002. 41:37would seat
  1003. 41:39well that comment is a good news bad
  1004. 41:41news comment
  1005. 41:43uh there is good news and there's bad
  1006. 41:45news the good news is that the secondary
  1007. 41:47field is in the right position but
  1008. 41:49that's not unique to temperatures always
  1009. 41:51that way the bad news is is that the
  1010. 41:54primary seals the one we're depending on
  1011. 41:56for the full admission transient and
  1012. 41:58it's going to be a lot worse than it was
  1013. 41:59but even the secondary as I imagine
  1014. 42:01wouldn't be as good cold as it would be
  1015. 42:04normally but five has comment you are
  1016. 42:07not supporting the launch no not by that
  1017. 42:09comment I wasn't supporting the launch I
  1018. 42:10was just saying that's an important
  1019. 42:11consideration and I felt that if we
  1020. 42:14could run some calculations to show
  1021. 42:16that the temperature did not affect the
  1022. 42:20timing then that would be supportive of
  1023. 42:22the launch if it did it certainly and
  1024. 42:24that was a concern that if it pushed
  1025. 42:26that timing out long enough we had a
  1026. 42:28chart in there said that if that timing
  1027. 42:30goes beyond that 200 PSI regime while
  1028. 42:32you're still eroding the primary o-ring
  1029. 42:34that for whatever reason if you ever
  1030. 42:36bypass it at that time you can't depend
  1031. 42:38on the secondary and that's what's
  1032. 42:39important thank you
  1033. 42:42caucus then you
  1034. 42:45never favored launch now and you made it
  1035. 42:50clear that you were opposed to Lawrence
  1036. 42:51well I never said I was opposed to
  1037. 42:54launched I just made a few comments
  1038. 42:56about why I thought some of the data was
  1039. 42:58not appropriate like pathetic tests were
  1040. 43:01saying the O-rings were good to 36
  1041. 43:02degrees I made this comment about the uh
  1042. 43:06uh lower temperatures affecting both
  1043. 43:10O-rings but effects a little bit
  1044. 43:11differently because one of them it's a
  1045. 43:13dynamic ordering a moves one has a lot
  1046. 43:15more movement and effects on it than the
  1047. 43:17other one does because they have to move
  1048. 43:19across the group
  1049. 43:20I made those comments did you but you
  1050. 43:22accepted the recommendation except in
  1051. 43:24the recommendation yes I thought it was
  1052. 43:26appropriate recommendation in other
  1053. 43:27words you accept the recommendation of
  1054. 43:29no launch that was made by your company
  1055. 43:31that's correct
  1056. 43:32uh Mr Hanson would you would you be
  1057. 43:36surprised if uh your comments uh were
  1058. 43:41interpreted by uh both your own company
  1059. 43:43personnel and Marsh Personnel is being
  1060. 43:46supporting of the Marshall position
  1061. 43:49yeah I would be uh surprised uh at that
  1062. 43:52yes I think I wouldn't be surprised if
  1063. 43:54that would be uh evaluated as the effect
  1064. 43:58of that I'm surprised I was interpreted
  1065. 44:00and supportive yeah thank you
  1066. 44:02you mentioned the 40 to 90 degree uh
  1067. 44:07qualification limit was that referring
  1068. 44:09to ambient air temperatures
  1069. 44:13well I had a discussion about that later
  1070. 44:17it was my impression that the motor
  1071. 44:20itself was qualified from 40 to 90
  1072. 44:23degrees for operating
  1073. 44:25and uh
  1074. 44:26we got into a discussion in fact during
  1075. 44:29the the caucus That was supposed to last
  1076. 44:32for five minutes that lasted for about a
  1077. 44:33half hour on that very subject
  1078. 44:36I saw the people that were there from
  1079. 44:39that but I first of all didn't agree
  1080. 44:41that the motor was even qualified for 40
  1081. 44:44to 90 relative to all the tolerance and
  1082. 44:46subsystems I wasn't there in the
  1083. 44:48qualification the steel case motor that
  1084. 44:50I just recently went through that
  1085. 44:52process in the film along case SRM
  1086. 44:55and that I'm not aware of the testing or
  1087. 44:59analysis of the O-rings were good to
  1088. 45:01those temperatures
  1089. 45:03and that therefore it's part of the
  1090. 45:05elements and the way I interpret the
  1091. 45:07spec is that all of the components and
  1092. 45:10elements that make up the SRM should be
  1093. 45:12qualified as temperatures
  1094. 45:13Mr Larry Malloy at that time told me
  1095. 45:16well no the 40 degrees refers to a
  1096. 45:19propellant mean bulk temperature and the
  1097. 45:21propelled mean bulk temperature was
  1098. 45:23being predicted to be 55 degrees for
  1099. 45:25that launch
  1100. 45:26and that as long as Propel mean bulk
  1101. 45:29temperature wasn't below 40 degrees so
  1102. 45:31you could expose the other parts of the
  1103. 45:33motor the lower temperature as long as
  1104. 45:35you didn't drop the Propel mean low
  1105. 45:37temperature outside of the four degrees
  1106. 45:39I responded to the time I thought that
  1107. 45:41was absolutely ridiculous because you
  1108. 45:43could expose that motor to very severe
  1109. 45:45cold temperatures Sub-Zero temperatures
  1110. 45:47for a fairly long period of time and you
  1111. 45:49would change phylamine bump temperature
  1112. 45:51at all there's such a massive amount of
  1113. 45:54propel and insulator there that takes a
  1114. 45:55long time to do that and I'm sure that
  1115. 45:58this Factory didn't mean that that you
  1116. 46:00could do that so my interpretation is
  1117. 46:02certainly different than his
  1118. 46:04because they're in fact a minimum
  1119. 46:07temperature
  1120. 46:08established by a specification or by
  1121. 46:11rotor in some manner that related to the
  1122. 46:14O-rings or the joint well at that time
  1123. 46:18I wasn't aware of one for the O-rings I
  1124. 46:20found out later that there was a in our
  1125. 46:24specification it refers to a higher
  1126. 46:26level sophistication which is level two
  1127. 46:28at Johnson I think because I was 7 700
  1128. 46:31respect it says that the shuttle vehicle
  1129. 46:33has to be capable of launching in 31 to
  1130. 46:3799 degrees or something like that and
  1131. 46:39therefore since it's a higher level spec
  1132. 46:41that we should be able to comply with
  1133. 46:44that but I'm not aware that all of the
  1134. 46:46elements and subsystems were qualified
  1135. 46:48to that which doesn't mean by higher
  1136. 46:50level spec could you explain that
  1137. 46:52it's that's specification uh come down
  1138. 46:56from the uh Johnson Space Center who is
  1139. 46:59responsible for the overall operation of
  1140. 47:01the vehicle shuttle vehicle and what
  1141. 47:04it's capable of operating in
  1142. 47:06environments both pre-flight and flight
  1143. 47:08and
  1144. 47:10that investigation for the overall
  1145. 47:12vehicle gets incorporated as part of the
  1146. 47:15lower level specifications that go
  1147. 47:16through level three which is Marshall
  1148. 47:18space flight center to the various
  1149. 47:19elements and they refer to that
  1150. 47:22when they refer to that the way the
  1151. 47:24system's supposed to work is you're
  1152. 47:25supposed to comply with your own
  1153. 47:27specification plus any higher level
  1154. 47:29specifications that may involve the
  1155. 47:31entire shuttle system
  1156. 47:33and I was unaware of that frankly uh
  1157. 47:37that criteria was in there I'm still a
  1158. 47:40little bit puzzled about it because it
  1159. 47:41doesn't have any time limitation on it
  1160. 47:43either I was 31 degrees for five minutes
  1161. 47:46or 40 days well was there a fire call
  1162. 47:50Design
  1163. 47:51temperature limit at the time this motor
  1164. 47:54was designed with respect to low
  1165. 47:56temperatures I really can't answer that
  1166. 47:58because I wasn't involved in the
  1167. 48:00original design qualification
  1168. 48:02thank you
  1169. 48:04and come to some of these other
  1170. 48:05questions I'd like to continue the
  1171. 48:07chronology because we're going fine and
  1172. 48:10you stopped about the caucus Mr
  1173. 48:11Armstrong has a question
  1174. 48:15of your answer that you just gave uh had
  1175. 48:22had Morton thank all to your knowledge
  1176. 48:25ever informed NASA that the launch
  1177. 48:29commit criteria were inadequate or did
  1178. 48:31not in fact cover the kinds of
  1179. 48:34conditions that you were concerned about
  1180. 48:36I'm not aware they ever did not
  1181. 48:38knowledge and so we're really talking
  1182. 48:42about event that was within the launch
  1183. 48:43criteria launch commit criteria but
  1184. 48:46outside what your experience based with
  1185. 48:48well I I guess I don't even I'm not
  1186. 48:51convinced of that either I didn't learn
  1187. 48:53about the 31 degree thing until sometime
  1188. 48:56afterwards but we were told to make this
  1189. 48:59evaluation on the basis of launching at
  1190. 49:010938 in the morning or the predicted
  1191. 49:04temperature was 26 degrees Fahrenheit
  1192. 49:06that was predicted temperature and that
  1193. 49:08was the occasion that's made whether we
  1194. 49:09could launch at that time so I'm not
  1195. 49:12sure if that came from either
  1196. 49:14yeah just one follow-up to Neil's
  1197. 49:17question are you aware of NASA ever
  1198. 49:20asking fire call to qualify the SRM or
  1199. 49:23the SRB to 31 degrees
  1200. 49:26uh I'm not aware of it but again I
  1201. 49:28wasn't in that part of the program they
  1202. 49:30may have I I I can't say
  1203. 49:33if we may know let's go back you said
  1204. 49:36that a suggestion was made that uh
  1205. 49:41a recess for five minutes who made that
  1206. 49:44suggestion uh
  1207. 49:47that said yes it was made from someone
  1208. 49:50at fire hall I can't recall with that
  1209. 49:52was Joe I think it was probably Joe
  1210. 49:54filmmaster but I'm not sure
  1211. 49:56what happened uh you said that that
  1212. 49:59lasted almost a half an hour instead of
  1213. 50:03five minutes that's correct and during
  1214. 50:05that time what did you do and who are
  1215. 50:07you with well I was uh in the conference
  1216. 50:10room at Kennedy with Mr Reinhardt and Mr
  1217. 50:13Malloy Mr Houston and Jack Buchanan
  1218. 50:15still and I
  1219. 50:17gave you my conversation about
  1220. 50:19interpretation of the qualification
  1221. 50:20without share there I also commented
  1222. 50:24that time that uh
  1223. 50:26I suggested that maybe we consider a
  1224. 50:28late afternoon launch I didn't feel good
  1225. 50:31about the below temperature launch
  1226. 50:33because when I first come down to
  1227. 50:36Kennedy uh the original schedule was to
  1228. 50:38launch that in the late afternoon a
  1229. 50:40quarter to four or something like that
  1230. 50:42and based on the weather report I heard
  1231. 50:44the temperatures would be uh 48 50
  1232. 50:47degrees
  1233. 50:48in the late afternoon so I said why
  1234. 50:50don't we go to a late afternoon launch
  1235. 50:52and I was told that that was considered
  1236. 50:55but it was rejected because of some
  1237. 50:58problem either with visibility or
  1238. 51:00whether one of the transatlantic abort
  1239. 51:02sites I think was Dick Carr Captain
  1240. 51:04block one of those
  1241. 51:07uh I really expected in the reason it
  1242. 51:11was taking so long for this five minute
  1243. 51:13caucus was in that we were either trying
  1244. 51:15to find some more information support
  1245. 51:17our recommendation
  1246. 51:19or that we were trying to run some kind
  1247. 51:21of calculation to determine how far away
  1248. 51:24from that we could go because clearly 26
  1249. 51:27degrees is a long ways from 53.
  1250. 51:30I personally felt we certainly wouldn't
  1251. 51:31go above 40 because I thought my
  1252. 51:33interpretation of qualification was
  1253. 51:35correct and we wouldn't do that but that
  1254. 51:39reason it was taken as long as the
  1255. 51:42engineers were reassessing all the data
  1256. 51:44they had and finding any more that they
  1257. 51:46may have and trying to quantify more a
  1258. 51:49lot of that data was straight
  1259. 51:49qualitative
  1260. 51:55[Music]
  1261. 51:58hour and uh
  1262. 52:00I believe it was uh Joe filmster came on
  1263. 52:03the line and said that even though we
  1264. 52:06had some concerns about the lower
  1265. 52:08temperatures
  1266. 52:09that we would recommend that they
  1267. 52:12proceed in the launch
  1268. 52:14based on the fact that we felt the
  1269. 52:16temperature data that we had was not
  1270. 52:19totally conclusive
  1271. 52:20and he outlined several uh concerns
  1272. 52:24still that we had relatively effective
  1273. 52:26temperature but also some rationales why
  1274. 52:28we felt it was a safe to proceed can you
  1275. 52:31relate what he said
  1276. 52:33well it was the uh information basically
  1277. 52:37that ended up finally on the fact
  1278. 52:39statement uh relative to our concerns
  1279. 52:41the O-rings being colder and harder and
  1280. 52:45uh but that we also had some data that
  1281. 52:49was inconclusive relative temperature
  1282. 52:51and I'm sure it was the warmer
  1283. 52:53temperature launch where we had some
  1284. 52:55blow by
  1285. 52:56I didn't
  1286. 52:58see anything that I recognized there was
  1287. 53:00new information but maybe they had some
  1288. 53:02and I felt all the engineers were
  1289. 53:04certainly there that had generated the
  1290. 53:06original data evaluating it and maybe
  1291. 53:09they had
  1292. 53:11reconsidered or re-evaluated the data
  1293. 53:14they had and tried to quantify it or
  1294. 53:15felt it was probably okay
  1295. 53:20when he completed that uh
  1296. 53:22he was asked I believe it was by Mr
  1297. 53:25hardy you're not sure to you know put
  1298. 53:27that rationale in writing and
  1299. 53:30and to sign it
  1300. 53:33uh make sure to get it down to the cape
  1301. 53:35I think by morning early morning and uh
  1302. 53:39I was sitting across table from learning
  1303. 53:40Mallory at the time and I said well I
  1304. 53:42felt that I was one that's going to have
  1305. 53:44to sign it because I was at uh okay I
  1306. 53:46said I wouldn't sign that I couldn't
  1307. 53:48have to come from the plant
  1308. 53:52Minister said that you know he would
  1309. 53:54draft a a letter or a statement and send
  1310. 53:58it down and he would do it tonight
  1311. 54:00wouldn't wait until morning and
  1312. 54:03I was instructed to stay there until
  1313. 54:05that came came down and he would also
  1314. 54:07send it out to Marshall and it'd be a
  1315. 54:10few minutes uh before that would come
  1316. 54:12down
  1317. 54:15he went off the line at that time and I
  1318. 54:18asked Cecil Houston where the the facts
  1319. 54:20was and he told me that the other end of
  1320. 54:23the building
  1321. 54:24I had a conversation with uh
  1322. 54:27Staples back on this before they went
  1323. 54:29offline or they can send that
  1324. 54:31information in the Jackie Shannon's
  1325. 54:33office which is a fax machine right next
  1326. 54:34door to this conference we're head or
  1327. 54:37they can send it into the Marshall
  1328. 54:38office they had a fit and Bose machine
  1329. 54:41or something and they said well the
  1330. 54:42whole thing in the same one we send all
  1331. 54:44this other material because they have
  1332. 54:45the right number and all that happened
  1333. 54:46to be the Marshall one which was the
  1334. 54:47other end of the building
  1335. 54:49I said fine I would wait
  1336. 54:52again took some time for that facts to
  1337. 54:55get there so all the parties were in the
  1338. 54:57meeting were still sitting there
  1339. 54:59and uh
  1340. 55:01we started to talk about some things I
  1341. 55:04told them I didn't feel very good about
  1342. 55:05this recommendation and
  1343. 55:07I recognize it's a very difficult to
  1344. 55:10quite Quantified
  1345. 55:11at what temperature these seals may be
  1346. 55:13acceptable for they aren't acceptable
  1347. 55:15you know based on the data that
  1348. 55:17certainly was inconclusive there's no
  1349. 55:19doubt in my mind
  1350. 55:20uh not the difficult thing to quantify
  1351. 55:22but I even though I didn't agree with
  1352. 55:25the
  1353. 55:2640 degree
  1354. 55:28qualification of the motor
  1355. 55:30and all elements were qualified to that
  1356. 55:33it's my understanding that uh
  1357. 55:36there's a lot of people at most NASA and
  1358. 55:38fire call signed up to that so the
  1359. 55:42design certification process with a
  1360. 55:44critical design reviews
  1361. 55:46and I was absolutely surprised that NASA
  1362. 55:49would accept any recommendation below 40
  1363. 55:51degrees Fahrenheit especially when it
  1364. 55:52predicted temperature as low as 26
  1365. 55:55degrees Fahrenheit
  1366. 55:57so am I may be naive about what
  1367. 55:59generates a launch commit criteria
  1368. 56:02but I was under the impression that was
  1369. 56:04generated based on the qualification of
  1370. 56:07all elements or subsystems space shuttle
  1371. 56:09that anything that was outside that
  1372. 56:11qualification was a launch commit
  1373. 56:13criteria and we never went outside that
  1374. 56:15envelope
  1375. 56:16and I don't know why NASA would ever
  1376. 56:18launch below 40 degrees Fahrenheit if
  1377. 56:20that's what the SRM was qualified to
  1378. 56:25I made the direct statement that if
  1379. 56:27anything happened to this launch uh
  1380. 56:29until my show wouldn't want to be the
  1381. 56:31person that had to stand in front of a
  1382. 56:32board of inquiry
  1383. 56:34to explain why I launched this outside
  1384. 56:36of the
  1385. 56:37qualification of the solid rock motor or
  1386. 56:40any shuttle system
  1387. 56:42I made that statement No One commented
  1388. 56:44on that
  1389. 56:46was very still very upset
  1390. 56:49so I
  1391. 56:51I asked that they reconsider
  1392. 56:53this uh
  1393. 56:55decision for three reasons not one for
  1394. 56:58three
  1395. 56:59I said if I were the launch director I'd
  1396. 57:01cancel this launch for three reasons not
  1397. 57:04just one first one being the concern of
  1398. 57:06the cold o-ring so we just discussed but
  1399. 57:09there were two others
  1400. 57:11I just left Carver Kennedy's house with
  1401. 57:13Titusville Florida
  1402. 57:16and he's responsible not only for
  1403. 57:18stacking of the srms he's responsible
  1404. 57:20for the retrieval operations
  1405. 57:22and he had been in communication uh with
  1406. 57:24someone that was a hangar AF I believe
  1407. 57:27that contacts the booster recovery ship
  1408. 57:29to see
  1409. 57:32and they had told him that the booster
  1410. 57:34recovery ships were in a absolute
  1411. 57:37survival mode was how they put it that
  1412. 57:39they were in Seas or high of 30 feet
  1413. 57:42uh they were there was winds at 50 knots
  1414. 57:45sustained gusting to 70 knots
  1415. 57:48pitching the boat as much as 30 degrees
  1416. 57:51they even felt the rough Seas may have
  1417. 57:53damaged some of the retrieval equipment
  1418. 57:54on the back of the ship
  1419. 57:56they were steering directly into the
  1420. 57:58wind heading for sure at about three
  1421. 58:00knots and they've been doing that for
  1422. 58:01some time there's no way that they would
  1423. 58:04be able to support so early morning
  1424. 58:06launch if they wouldn't be in the
  1425. 58:08recovery area
  1426. 58:09[Music]
  1427. 58:10I then reminded everyone in the room
  1428. 58:13that you know there's some first on this
  1429. 58:14launch this is the first time that we're
  1430. 58:16going to use the new
  1431. 58:18electronic control system for separating
  1432. 58:21the nozzle extension cone on the srbs at
  1433. 58:24apogee rather than just before water
  1434. 58:26impact while it's under full main
  1435. 58:28parachute
  1436. 58:29and we're able to separate the
  1437. 58:31parachutes that water impact for the
  1438. 58:32very first time on this launch
  1439. 58:35and that based on the sea states that I
  1440. 58:38had just heard that appeared to me that
  1441. 58:40it was going to be nearly impossible to
  1442. 58:42be covered that Hardware either the
  1443. 58:45parachutes or the freshers
  1444. 58:48and also I felt that they were putting
  1445. 58:51the boosters at some risk as far as
  1446. 58:53recovery was concerned because the ships
  1447. 58:55were steering away
  1448. 58:59I also said that the third reason for
  1449. 59:01not launching is the formation of ice I
  1450. 59:04knew the sound suppression systems a
  1451. 59:07water system
  1452. 59:08and I felt there's probably a lot of ice
  1453. 59:09around there and I'm no expert in all
  1454. 59:12these matters but I do feel that there
  1455. 59:14may be a chance of that changing the
  1456. 59:16Acoustics may be a problem with debris
  1457. 59:18may have some effective structures I
  1458. 59:20didn't know
  1459. 59:21but I didn't think it was prudent to
  1460. 59:23Launch under that kind of a condition
  1461. 59:27I was told that you know these weren't
  1462. 59:29really my problems and I really
  1463. 59:30shouldn't concern myself with these uh
  1464. 59:33but I said you know all three of these
  1465. 59:36together
  1466. 59:37should be more than sufficient to cancel
  1467. 59:39the launch
  1468. 59:41from the one that we discussed earlier
  1469. 59:43what
  1470. 59:45and that's the people were there said
  1471. 59:47that well they would pass these on they
  1472. 59:49could tell I was I was Disturbed and
  1473. 59:50they passed those on and
  1474. 59:53as concerns and that they would do it in
  1475. 59:55advisory capacity
  1476. 59:58by Mr Malloy where the sign facts was
  1477. 1:00:01because some time had transpired since
  1478. 1:00:03the teleconference had ended and still
  1479. 1:00:05wasn't there so I said okay I'll go
  1480. 1:00:07check on that I went down to the other
  1481. 1:00:09end of the building
  1482. 1:00:10to this fax machine and there was
  1483. 1:00:13nothing there to come out yet and I
  1484. 1:00:15really wondered if it was working it was
  1485. 1:00:17getting kind of late
  1486. 1:00:18so I stayed down there I guess for about
  1487. 1:00:2110 minutes and finally came in
  1488. 1:00:23I brought the facts back it was a single
  1489. 1:00:26sheet of paper to Jack Buchanan's office
  1490. 1:00:29where we reproduced copies for everyone
  1491. 1:00:32I walked into uh I think it was Cecil
  1492. 1:00:35Houston's office there and there was a
  1493. 1:00:36telecon being conducted and I believe it
  1494. 1:00:38was the thorny Aldridge
  1495. 1:00:40and they're in the middle of this
  1496. 1:00:41telecon and they were discussing the
  1497. 1:00:43conditions of the booster recovery ships
  1498. 1:00:46and the high fee States and the fact
  1499. 1:00:49that they were in the survival mode
  1500. 1:00:51and I recall that Arnie Aldrich asked
  1501. 1:00:55Brian Malloy if he felt there was any uh
  1502. 1:00:58risk to recovering the boosters because
  1503. 1:01:00of this and he said no he didn't think
  1504. 1:01:02there was any you know significant risk
  1505. 1:01:04in carving boosters because they had
  1506. 1:01:07beacons and monitors and they're kind of
  1507. 1:01:09aircraft in the area also but that there
  1508. 1:01:12was a high probability that they would
  1509. 1:01:13not recover the parachutes or the
  1510. 1:01:16presidents
  1511. 1:01:18and the conclusion was that uh yet
  1512. 1:01:21they'd have to make a decision to launch
  1513. 1:01:23the basis that they would have the high
  1514. 1:01:25probability not recovering that Hardware
  1515. 1:01:27but they were compromising the recovery
  1516. 1:01:30of the booster significantly
  1517. 1:01:32and I remember Arnie asking uh
  1518. 1:01:36Larry you know the value of that
  1519. 1:01:38hardware and I think he gave some number
  1520. 1:01:40close to a million dollars and asked him
  1521. 1:01:42if he could you know afford the visits
  1522. 1:01:44and support the schedules and program
  1523. 1:01:46and he said that he had sufficient
  1524. 1:01:48inventory to do that
  1525. 1:01:50uh but Ernie also told him that in no
  1526. 1:01:53way have those ships attempt to turn
  1527. 1:01:56around in those kinds of conditions and
  1528. 1:01:58the safety shift is important to try to
  1529. 1:02:01support that launch and you turn around
  1530. 1:02:03too soon so to tell him to continue on
  1531. 1:02:05towards Shore until it was really safe
  1532. 1:02:07to turn around
  1533. 1:02:09they then briefly discussed the ice
  1534. 1:02:12issue about the ice and there was a
  1535. 1:02:15concern right there and Arnie I believe
  1536. 1:02:17that was Arnie responded that they had
  1537. 1:02:19discussed that issue earlier in the day
  1538. 1:02:21it was fairly brief conversation
  1539. 1:02:23alrighty is Mr Aldridge uh yes Mr
  1540. 1:02:26Aldrich
  1541. 1:02:27uh they also made it clear that they
  1542. 1:02:30were acting in advisory pasty only if
  1543. 1:02:33they weren't making some recommendations
  1544. 1:02:34or acting in visual capacity but wanted
  1545. 1:02:37to be aware of this information
  1546. 1:02:39I didn't hear anything discussed about
  1547. 1:02:41the O-ring steel problem I presume that
  1548. 1:02:43was done while I was down waiting for
  1549. 1:02:46that fax because that was the first
  1550. 1:02:48concern but you're not sure of that but
  1551. 1:02:50I'm not sure I presumed it was because I
  1552. 1:02:51got in the middle of the conversation on
  1553. 1:02:53the hosters and heard the ice I don't
  1554. 1:02:55know
  1555. 1:02:56and finally the conversation concluded
  1556. 1:03:00and the recommendation was to proceed on
  1557. 1:03:03with the uh it was launch uh I stayed
  1558. 1:03:07around a few more minutes and talked to
  1559. 1:03:08Jack McCannon for a few minutes and went
  1560. 1:03:11back to Carver's house in Titusville
  1561. 1:03:13where I stayed and got in there I guess
  1562. 1:03:14a little before one o'clock sometime
  1563. 1:03:20although I would say
  1564. 1:03:23a couple of questions one
  1565. 1:03:26when you first appeared before the
  1566. 1:03:29commission I remember you were
  1567. 1:03:32explaining the fact that your company
  1568. 1:03:35originally
  1569. 1:03:36had recommended against the launch
  1570. 1:03:40and then you
  1571. 1:03:41testify that after the caucus
  1572. 1:03:46they came back and changed their mind
  1573. 1:03:49said go ahead with the launch
  1574. 1:03:51and you said it was based on
  1575. 1:03:53inconclusive data
  1576. 1:03:56and I remember asking you how could they
  1577. 1:03:59have changed their mind based on
  1578. 1:04:01inconclusive data can you explain that
  1579. 1:04:04well I I can't explain that that was a
  1580. 1:04:08comment that was made that the data was
  1581. 1:04:10inconclusive relative to the effects of
  1582. 1:04:12the temperature
  1583. 1:04:13and I I prefer you ask those questions
  1584. 1:04:16to those that made that decision I don't
  1585. 1:04:18know I wasn't there I wasn't there but
  1586. 1:04:21all that data was
  1587. 1:04:23the reassess and evaluated and what
  1588. 1:04:25conclusions were gone one other question
  1589. 1:04:27Mr Dr Keel asked if the conclusion of
  1590. 1:04:31your testimony in the executive session
  1591. 1:04:32whether you felt that you were under
  1592. 1:04:35pressure or had been under pressure of
  1593. 1:04:37the companies and Under Pressure to
  1594. 1:04:40reverse its decision I think your answer
  1595. 1:04:41was yes do you remember that yes uh
  1596. 1:04:44definitely I there's no doubt in my mind
  1597. 1:04:47I felt some pressure I feel that I have
  1598. 1:04:50a responsible
  1599. 1:04:51management position in here and I felt
  1600. 1:04:53pressure
  1601. 1:04:55would you explain the reasons for the
  1602. 1:04:57for feeling pressure
  1603. 1:04:59well I've
  1604. 1:05:01I've been in many quite range of years
  1605. 1:05:03probably as many as as anyone in the
  1606. 1:05:05past year and a half that at that costs
  1607. 1:05:09and I've had to get up and stand before
  1608. 1:05:12I think a very critical audience at
  1609. 1:05:15Marshall and very good one
  1610. 1:05:17justifying why our Hardware was ready to
  1611. 1:05:20fly and I have to get up and explain
  1612. 1:05:23every major defect
  1613. 1:05:25is why we can fly with that defect
  1614. 1:05:29and for the most part they're very minor
  1615. 1:05:32very very minor and and I have been
  1616. 1:05:35hassled about how I'm sure that that's
  1617. 1:05:38okay to fly with
  1618. 1:05:39now such things as losing vacuum in a
  1619. 1:05:43carbon clock phenomic part in the nozzle
  1620. 1:05:45while the parts basically cured
  1621. 1:05:48now the Desiree effect of that it's a
  1622. 1:05:49critical process there's a lot of those
  1623. 1:05:51critical processes
  1624. 1:05:52and I have to address every one of those
  1625. 1:05:54the great detail is why I'm sure that
  1626. 1:05:57that part
  1627. 1:05:59has not been compromised
  1628. 1:06:01and it's been that way through all the
  1629. 1:06:03reviews I've ever had
  1630. 1:06:05and that's the way it should be
  1631. 1:06:08it's not pleasant but that's what it
  1632. 1:06:09should be and I was surprised here at
  1633. 1:06:12this particular meeting that the tone of
  1634. 1:06:15the meeting was was just opposite of
  1635. 1:06:17that I didn't have to prove
  1636. 1:06:19I was ready to fly in fact I think Mount
  1637. 1:06:21Griffin made the most accurate statement
  1638. 1:06:22I ever heard his conclusion that meeting
  1639. 1:06:25was is the philosophy scenes have
  1640. 1:06:27changed because you know he had the same
  1641. 1:06:29impression I did that the contractor
  1642. 1:06:31always had to get up and stand up and
  1643. 1:06:33prove that his Hardware was raised why
  1644. 1:06:35in this case we had to prove it wasn't
  1645. 1:06:37and that's a big difference and I felt
  1646. 1:06:39that was precious
  1647. 1:06:41and can you explain a little more what
  1648. 1:06:42source the pressure came from in your
  1649. 1:06:45mind well I think the strong statements
  1650. 1:06:48were made by Mr Malloy and even some of
  1651. 1:06:51those people at Marshall uh they're on
  1652. 1:06:53there Mr hardy where I think hardly
  1653. 1:06:55strong statement that I think has
  1654. 1:06:57pressure
  1655. 1:06:58about uh when will ever fly this thing
  1656. 1:07:02and launch commit criteria that we can't
  1657. 1:07:04generate at the last minute and uh
  1658. 1:07:07appalled by our recommendation the
  1659. 1:07:09supply temperatures high as 53 degrees
  1660. 1:07:13and and that to me that that was
  1661. 1:07:15pressured me and may not have been
  1662. 1:07:17interpreted by others that it was
  1663. 1:07:18pressure to me any other pressure that
  1664. 1:07:20you want to refer to at this time or at
  1665. 1:07:23any time
  1666. 1:07:25no no I I just felt that the way the
  1667. 1:07:29comments were made as strong as they
  1668. 1:07:31were made is the fact that the the
  1669. 1:07:33conditions were for justifying this
  1670. 1:07:35launch were so much different than
  1671. 1:07:37anything I had been involved with before
  1672. 1:07:39as far as the telephone is concerned
  1673. 1:07:41would you normally have signed that
  1674. 1:07:43telefox or was the was the procedure
  1675. 1:07:45that was followed the normal procedure
  1676. 1:07:48well I'm not sure I guess what the
  1677. 1:07:50normal procedure is I felt that since I
  1678. 1:07:53was uh
  1679. 1:07:54they are representing as a senior
  1680. 1:07:56official at the cape uh then I'm the one
  1681. 1:07:59that usually is responsible for that I
  1682. 1:08:01know at the L minus one and we have a
  1683. 1:08:04normal launch
  1684. 1:08:05there's a poll that's conducted by Jess
  1685. 1:08:08Moore of all the contractors where
  1686. 1:08:10they're ready to fly and I'm the guy
  1687. 1:08:12there that has to say yeah if that calls
  1688. 1:08:14Hardware is ready to fly
  1689. 1:08:15uh I felt that's my responsibility
  1690. 1:08:18that's why I'm there
  1691. 1:08:19I can't recall what we were asked to
  1692. 1:08:22sign anything like that before
  1693. 1:08:25we have a presentation that's given it
  1694. 1:08:28every quite Readiness review that signed
  1695. 1:08:30off by the principal party you know
  1696. 1:08:32filmmaster usually finds all those on
  1697. 1:08:34the formal review but if anything comes
  1698. 1:08:36up afterwards it's it's been done on an
  1699. 1:08:39oral basis but I don't know I've never
  1700. 1:08:41been put in that position I don't know
  1701. 1:08:43if Joe has I don't believe he has
  1702. 1:08:45so uh
  1703. 1:08:49the the fact that
  1704. 1:08:51I written a decision was requested as
  1705. 1:08:55far as you were concerned was not the
  1706. 1:08:57normal way to do it it was not the
  1707. 1:09:00normal as far as that's concerned and I
  1708. 1:09:02as I recall you a testimony you testify
  1709. 1:09:05that you made it clear that you would
  1710. 1:09:06not sign a written statement approved in
  1711. 1:09:08a large am I correct yeah that's correct
  1712. 1:09:11and I think that's been misinterpreted
  1713. 1:09:13at least by the Press they said that uh
  1714. 1:09:15I was overruled by my supervised that's
  1715. 1:09:18not true at all I chill is not to sign
  1716. 1:09:21that I did he didn't overrule me I felt
  1717. 1:09:23that that decision when I started was an
  1718. 1:09:26engineering decision by the people that
  1719. 1:09:29understood the problem the best that had
  1720. 1:09:30all of the date and facts and they're
  1721. 1:09:32the ones who should recommend it and
  1722. 1:09:33that's why I made that it wasn't I was
  1723. 1:09:35on the road
  1724. 1:09:36thank you very much I'm sure other
  1725. 1:09:38commission members are less than Mr
  1726. 1:09:39Thompson
  1727. 1:09:41yeah you were talking about the 40
  1728. 1:09:43degree uh qualified qualification of
  1729. 1:09:46various uh components of this electronic
  1730. 1:09:50experience and at one I was aware of the
  1731. 1:09:5340 degree limit on the on the green uh
  1732. 1:09:57bulk temperature but was there anything
  1733. 1:10:00else uh that the 40 degrees referred to
  1734. 1:10:03well in the stack uh going back after
  1735. 1:10:07sacral looking at it that's what it had
  1736. 1:10:09refers to as a profound mean buff
  1737. 1:10:10temperature
  1738. 1:10:12uh
  1739. 1:10:13I guess that's my thing is an oversight
  1740. 1:10:16may be inspect
  1741. 1:10:18or the
  1742. 1:10:20launch temperature 31 to 99 should be
  1743. 1:10:23stronger in there to apply to all
  1744. 1:10:26components and by qualification it
  1745. 1:10:28either has to be qualified by test or
  1746. 1:10:30some analysis and that means every
  1747. 1:10:31element
  1748. 1:10:32and I'm not aware that all those
  1749. 1:10:34elements were qualified with that
  1750. 1:10:37temperature I know we bought O-rings
  1751. 1:10:39that said they're good to minus 30 but I
  1752. 1:10:42never saw the analysis and the
  1753. 1:10:44application that we use them in that
  1754. 1:10:45says that they're they're good to that
  1755. 1:10:47that's the difference it's a material
  1756. 1:10:49problem versus a design problem I
  1757. 1:10:52understand that and I understand that
  1758. 1:10:54the 40 degrees was intended to protect
  1759. 1:10:56against grain cracking and the
  1760. 1:10:58consequences of that but uh What uh what
  1761. 1:11:03I didn't quite understand is why you
  1762. 1:11:06said you wouldn't recommend any time
  1763. 1:11:09launching below 40 degrees I'm trying to
  1764. 1:11:11get a well the reason I said that is I
  1765. 1:11:14felt that's what everybody had signed up
  1766. 1:11:16to is what this thing was really
  1767. 1:11:17qualified from an operating standpoint
  1768. 1:11:19now the motor does get exposed to much
  1769. 1:11:21lower temperatures we have a criteria in
  1770. 1:11:24our specification expose that to much
  1771. 1:11:26lower temperatures you know Sub-Zero
  1772. 1:11:28temperatures and 60 mile winds come
  1773. 1:11:30across Wyoming because we ship these
  1774. 1:11:32things from Utah down to the cape so in
  1775. 1:11:34a transportation mode they are subjected
  1776. 1:11:37to some very severe uh temperatures for
  1777. 1:11:39periods of time
  1778. 1:11:41and there has been analysis uh to show
  1779. 1:11:43that they will withstand those
  1780. 1:11:45temperatures as long as you don't
  1781. 1:11:46operate them
  1782. 1:11:47at those temperatures uh the 40 degrees
  1783. 1:11:49they won't crack there's no problem
  1784. 1:11:51there that's a uh primarily a
  1785. 1:11:53performance standpoint you lose total
  1786. 1:11:55impulse and performance the lower the
  1787. 1:11:57temperature you go you have a low 40 you
  1788. 1:11:59start listening to Performance out of
  1789. 1:12:01the shuttle and that's why that number
  1790. 1:12:02came about as far as the capability the
  1791. 1:12:05grain structural capability it can
  1792. 1:12:08withstand a lot colder temperatures than
  1793. 1:12:10that and then we have analysis for the
  1794. 1:12:12storage and transportation shows that
  1795. 1:12:14and it has a good margin to safety very
  1796. 1:12:16high margin to safety for exposure to
  1797. 1:12:19lower temperatures it's just the things
  1798. 1:12:21like the O-rings and some of these other
  1799. 1:12:23components I'm not aware that we have
  1800. 1:12:25really analyzed or tested those well
  1801. 1:12:27enough to understand how they would
  1802. 1:12:29operate in that kind of a temperature
  1803. 1:12:31there's a difference between exposing
  1804. 1:12:33them and storing them versus operating
  1805. 1:12:37thank you
  1806. 1:12:39I have a question just referring back to
  1807. 1:12:42the static test that you mentioned at 36
  1808. 1:12:44degrees which was used as a
  1809. 1:12:46justification was there an analysis to
  1810. 1:12:49indicate what the O-ring temperature
  1811. 1:12:50during that test was
  1812. 1:12:53well it was done after the fact and I
  1813. 1:12:56believe in the presentation that was
  1814. 1:12:57made
  1815. 1:12:58on the night before the launch it they
  1816. 1:13:02calculated like 47 degrees is what they
  1817. 1:13:04presented as what they expected the
  1818. 1:13:06O-ring temperature to really Bend when
  1819. 1:13:08that was static tested
  1820. 1:13:10I have a couple of other questions
  1821. 1:13:11regarding the uh the conference
  1822. 1:13:14was there a specific request by NASA to
  1823. 1:13:18reconsider or was the reconsideration as
  1824. 1:13:21a result of the implications of the
  1825. 1:13:23remarks made by the NASA people in the
  1826. 1:13:26conference
  1827. 1:13:27I mean the reconsideration of what of
  1828. 1:13:30the launched of the initial decision not
  1829. 1:13:32to launch that is the initial
  1830. 1:13:34recommendation of fire call was not to
  1831. 1:13:36launch and then that was reconsidered
  1832. 1:13:39did anyone from NASA explicitly asked
  1833. 1:13:42for reconsideration or would the
  1834. 1:13:44reconsideration occur because of the
  1835. 1:13:46negative remarks and comments on that
  1836. 1:13:49decision
  1837. 1:13:51well I think it was the the latter I
  1838. 1:13:54can't fully recall that they directed
  1839. 1:13:56this is that or not that we they had
  1840. 1:13:59concluded that the the temperature data
  1841. 1:14:01was inconclusive and I don't know
  1842. 1:14:03whether we volunteered to reassess it or
  1843. 1:14:04they said we need to I'm not fair to me
  1844. 1:14:07on that I'm not sure one further
  1845. 1:14:09question in regard to the signature on
  1846. 1:14:12the sheet which was faxed from Mr
  1847. 1:14:16killminster was there a specific request
  1848. 1:14:18for that to be signed and who made that
  1849. 1:14:21request
  1850. 1:14:22uh yeah there was a specific request for
  1851. 1:14:25that to be signed uh I believe it was uh
  1852. 1:14:30George Hardy and may have been learning
  1853. 1:14:32the lawyer that I think it was George
  1854. 1:14:33Hardy had requested that
  1855. 1:14:36[Music]
  1856. 1:14:38um Foundation
  1857. 1:14:45to the personal attention of Mr
  1858. 1:14:49or Mr Aldrich or Dr Lucas
  1859. 1:14:53well I'm uh
  1860. 1:14:56very familiar with the process by which
  1861. 1:14:59these things are reviewed and uh
  1862. 1:15:02I was absolutely positive and sure that
  1863. 1:15:05they would were brought to his their
  1864. 1:15:07attention because that's the way things
  1865. 1:15:09go I talked to the SRB project manager I
  1866. 1:15:12talked to his boss the shuttle project
  1867. 1:15:14manager the shuttle project office and I
  1868. 1:15:17was sure that those all went through
  1869. 1:15:18that review I had no doubt in my mind
  1870. 1:15:20that they had
  1871. 1:15:26NASA folk indicated that they would pass
  1872. 1:15:29your concerns along and I presume that
  1873. 1:15:32you
  1874. 1:15:33thought they would the three concerns
  1875. 1:15:36that you were talking about the O-rings
  1876. 1:15:37the ocean sea and the eye right but
  1877. 1:15:41could they have simply meant the last
  1878. 1:15:42two concerns the Sea and the ice that's
  1879. 1:15:45one question the other is which were who
  1880. 1:15:48were the NASA folk that promised to pass
  1881. 1:15:52your concerns along I I guess you could
  1882. 1:15:54interpret maybe if I thought it would be
  1883. 1:15:56all three but the people were Mr Malai
  1884. 1:15:59and uh
  1885. 1:16:00and Mr Reinhardt said that those pathos
  1886. 1:16:03on and I he said only passed them all on
  1887. 1:16:05I
  1888. 1:16:06didn't see a reason why they would
  1889. 1:16:11go
  1890. 1:16:12you mentioned earlier that you thought
  1891. 1:16:14this decision on launching should be an
  1892. 1:16:17engineering decision not a program
  1893. 1:16:19management decision
  1894. 1:16:21how would you characterize the final
  1895. 1:16:23decision to launch from thyakov was it
  1896. 1:16:26engineering or was it management
  1897. 1:16:29well I I guess I'd have to characterize
  1898. 1:16:31it as a management decision in the final
  1899. 1:16:33decision thank you
  1900. 1:16:37so got a couple questions on criticality
  1901. 1:16:40ones
  1902. 1:16:41um did I understand you to say that you
  1903. 1:16:43chair the board on on crit ones on the
  1904. 1:16:46SRM from uh yes on all defects that are
  1905. 1:16:49affected by that could you give us your
  1906. 1:16:52understanding of the meaning of
  1907. 1:16:54criticality one and just an estimate of
  1908. 1:16:57how many parts in the SRM system are
  1909. 1:17:00classified as grit one
  1910. 1:17:02well I don't have a good number for you
  1911. 1:17:05but there's a tremendous amount of crit
  1912. 1:17:07ones on the SRM
  1913. 1:17:09primarily because the uh
  1914. 1:17:12the motor doesn't have very many
  1915. 1:17:15redundant features solid rocker Motors
  1916. 1:17:17don't and uh of course bottom is
  1917. 1:17:20structure and structure is all becomes a
  1918. 1:17:23great one but fails uh could you define
  1919. 1:17:26a crit One Credit One is a single point
  1920. 1:17:29failure that if that element fails
  1921. 1:17:32there's there's no recovery you lose the
  1922. 1:17:35you lose the hardware and it's
  1923. 1:17:37catastrophic there's a lot of elements
  1924. 1:17:40in the SRM they're under that category
  1925. 1:17:42relative to the O-ring seals the
  1926. 1:17:45redundancy was built in because that was
  1927. 1:17:48a critical element
  1928. 1:17:49as a pressure CEO
  1929. 1:17:51in order to provide that redundancy I
  1930. 1:17:55think there is some confusion of the
  1931. 1:17:58blade as to what that crit 1 and 1R was
  1932. 1:18:02relative the seals and how it was
  1933. 1:18:04removed
  1934. 1:18:05uh I wasn't involved at the time that uh
  1935. 1:18:09it was found that because this joint
  1936. 1:18:11rotated
  1937. 1:18:12that if you took all of the worst
  1938. 1:18:15engineering tolerances and dimensions
  1939. 1:18:17are allowed by the prints and that means
  1940. 1:18:19the maximum clevis opening you could
  1941. 1:18:22have to start with the smallest and
  1942. 1:18:25thinest Tang that you could put into
  1943. 1:18:26that clevis opening the minimum o-ring
  1944. 1:18:29that you could put in there with a
  1945. 1:18:31maximum size of the grooves that you
  1946. 1:18:33could possibly put in there
  1947. 1:18:35that you put all those combinations
  1948. 1:18:37together you could show that you would
  1949. 1:18:39actually lose squeeze on the secondary
  1950. 1:18:41o-ring once you pressurized the system
  1951. 1:18:43and the joint rotated and therefore if
  1952. 1:18:46you ever had to call upon that O-ring as
  1953. 1:18:49a redundant system during that time
  1954. 1:18:51period you couldn't depend on it now
  1955. 1:18:55I can had an assessment made
  1956. 1:18:58of
  1957. 1:18:59have we flown any hardware in that
  1958. 1:19:01condition because I was a bit shocked
  1959. 1:19:03about that as much as anyone when I
  1960. 1:19:05first found that out which was by the
  1961. 1:19:07way last August and I made that
  1962. 1:19:09presentation here to not the
  1963. 1:19:12headquarters I did I wasn't aware of it
  1964. 1:19:14myself that we had such condition and we
  1965. 1:19:17were flying with a crit one on on that
  1966. 1:19:19part of the hardware
  1967. 1:19:20uh
  1968. 1:19:22based on the information that I have
  1969. 1:19:25received on all of the joints ever flown
  1970. 1:19:28on the shuttle
  1971. 1:19:30there was only one time where we had a
  1972. 1:19:33tolerance backup
  1973. 1:19:35of a joint that would have fallen from a
  1974. 1:19:38criticality one R to one and that was on
  1975. 1:19:40sps4
  1976. 1:19:42they have never had one since we didn't
  1977. 1:19:44have one for that we always had adequate
  1978. 1:19:47squeeze from the hardware when it
  1979. 1:19:51rotates to maintain it as a criticality
  1980. 1:19:531R now I'm not quite sure I understand
  1981. 1:19:55it because I thought that the the piece
  1982. 1:19:58of paper in the critical items list
  1983. 1:19:59specifically lists the primary o-ring as
  1984. 1:20:03a criticality one yes it does and the
  1985. 1:20:05reason it does that is because the draw
  1986. 1:20:07drawing tolerances allow you to install
  1987. 1:20:10uh Hardware to that may come together on
  1988. 1:20:13a worst case basis that cannot guarantee
  1989. 1:20:16a secondary seal and therefore it's
  1990. 1:20:17going to use all the hardware that's in
  1991. 1:20:18the inventory or you could possibly have
  1992. 1:20:20in the inventory Bill to acceptable
  1993. 1:20:23prints you could end up with a very
  1994. 1:20:25small fraction of it it's a very small
  1995. 1:20:27fraction that could go together that way
  1996. 1:20:28and therefore that document was written
  1997. 1:20:31to cover all that but in reality uh
  1998. 1:20:34other than that one case we've never
  1999. 1:20:36stumbled Hardware that way we've had we
  2000. 1:20:38haven't had the finished tanks with the
  2001. 1:20:40widest ultimate crevices was a minimum
  2002. 1:20:42over and put together
  2003. 1:20:44that's a concern in a sale is a very
  2004. 1:20:47serious concern in my opinion because
  2005. 1:20:49that decision was made at the time based
  2006. 1:20:52on what we knew about joint rotation
  2007. 1:20:55since that time we're getting this
  2008. 1:20:57information on resiliency and effects of
  2009. 1:20:59temperature which were never put into
  2010. 1:21:00that at that time that brings that
  2011. 1:21:03question back out in front yeah you know
  2012. 1:21:05I told you we didn't fly
  2013. 1:21:07from criticality one R1 lets true based
  2014. 1:21:10on the decisions and the information is
  2015. 1:21:13known that changed it from 1R to one
  2016. 1:21:14just on the tolerances and dimensions as
  2017. 1:21:17far as this resiliency thing I can't
  2018. 1:21:19assess that yet well enough to know but
  2019. 1:21:23I do know we never stacked Hardware
  2020. 1:21:24together that had tolerances so bad that
  2021. 1:21:27we didn't have the contact of the
  2022. 1:21:29secondary o-ring other than one joint
  2023. 1:21:31but just to be clear I guess that you
  2024. 1:21:33don't on a joint by joint basis go back
  2025. 1:21:35to the NASA board and kind of reclamor
  2026. 1:21:39the crit one and turn it back into a 1R
  2027. 1:21:42do you it's always classified as a
  2028. 1:21:44criticality one on the primary seal
  2029. 1:21:45that's absolutely right you're correct
  2030. 1:21:47now we do as part of our slight
  2031. 1:21:48Readiness if you do present those joints
  2032. 1:21:51that we're mating and what those o-ring
  2033. 1:21:53squeezes are and on every flight
  2034. 1:21:56did any discussion of the primary seal
  2035. 1:21:59of criticality one come up during the
  2036. 1:22:01the your meetings on on L minus one uh
  2037. 1:22:04no they did
  2038. 1:22:06okay thank you
  2039. 1:22:08that's the secondary CEO would not be
  2040. 1:22:10much affected by the temperature but now
  2041. 1:22:12you're telling us
  2042. 1:22:13because of those complete or nearly
  2043. 1:22:16complete loss of resilience that is the
  2044. 1:22:19tendency to spring back the secondary
  2045. 1:22:21seal would require very little rotation
  2046. 1:22:23to open do I understand correctly uh I
  2047. 1:22:27said it wouldn't be affected as much as
  2048. 1:22:29a primary field because it doesn't have
  2049. 1:22:33to move from one end of the slot to the
  2050. 1:22:35other as far as the effect of resilience
  2051. 1:22:37you're absolutely correct it still has
  2052. 1:22:38the same problems as far as extruding in
  2053. 1:22:40the Gap has still got the same problem
  2054. 1:22:43we were talking about somewhere there
  2055. 1:22:46was a discussion about the secondary
  2056. 1:22:47seal
  2057. 1:22:48being redundant until the metal Parts
  2058. 1:22:51rotate
  2059. 1:22:52when the pressure starts to build up it
  2060. 1:22:55can't move the primary seal until there
  2061. 1:22:57is some pressure and noon there's a very
  2062. 1:22:59small pressure perhaps
  2063. 1:23:01and the very small rotation isn't it
  2064. 1:23:03true isn't it true if the rotation is
  2065. 1:23:04more or less proportioned to the
  2066. 1:23:05pressure or is there some delay of some
  2067. 1:23:07sort there is no time delay between the
  2068. 1:23:10two there is some delay because the
  2069. 1:23:12joint's stiff enough that uh under
  2070. 1:23:14certain pressure heaters don't move it
  2071. 1:23:16at all so you have to build up some
  2072. 1:23:17pressure to make any rotation so there
  2073. 1:23:20is a delay in that time period but at
  2074. 1:23:22some point in time it becomes a direct
  2075. 1:23:24function of the pressure listen to laws
  2076. 1:23:26of elasticity such that everything is
  2077. 1:23:28proportional to the force and all the
  2078. 1:23:30displacements of proportionable force
  2079. 1:23:32then wouldn't it be true that at every
  2080. 1:23:34pressure there's some rotation and the
  2081. 1:23:36rotation is more or less proportional to
  2082. 1:23:37the pressure
  2083. 1:23:39well I I think that uh when you're down
  2084. 1:23:42to uh tpsi or 50 psi I don't think
  2085. 1:23:45you're rotating anything
  2086. 1:23:48if you're rotating at one tenth as much
  2087. 1:23:51as you rotated at 500 PSI is that right
  2088. 1:23:53well the structure is so stiff that I
  2089. 1:23:56can't believe you're rotating at all
  2090. 1:23:59at 50 psi
  2091. 1:24:03you are moving the O-ring seal back into
  2092. 1:24:05the grill power the
  2093. 1:24:09just go back to this criticality one so
  2094. 1:24:12that uh
  2095. 1:24:15I can understand it a little about it
  2096. 1:24:17it in nineteen
  2097. 1:24:20what 1985 change was made
  2098. 1:24:2483 83 I guess 82 or 83. at that point it
  2099. 1:24:31was listed as criticality one with an R
  2100. 1:24:35is that right that's correct not does
  2101. 1:24:39that mean that it was decided that if it
  2102. 1:24:43was a failure and that seam ordering
  2103. 1:24:47that the mission in the crew would be
  2104. 1:24:50destroyed the whole thing would be a
  2105. 1:24:52catastrophe but at that point the r
  2106. 1:24:54meant that there was there was a
  2107. 1:24:57redundancy there that you had two rings
  2108. 1:25:00that each at that point was considered
  2109. 1:25:02to support the other or at least one was
  2110. 1:25:04a backup for the other that's what our
  2111. 1:25:06meant that's correct it's redundant it
  2112. 1:25:08means redundant that's why the r is
  2113. 1:25:10there that's right now at that time the
  2114. 1:25:13experience fairly demonstrated that the
  2115. 1:25:17the uh analysis that you've been using
  2116. 1:25:21up to that point may not have been
  2117. 1:25:22correct so that instead of having
  2118. 1:25:25uh both the primary and the secondary
  2119. 1:25:28seal which provided redundancy it came
  2120. 1:25:31to the conclusion you didn't have the
  2121. 1:25:32redundancy
  2122. 1:25:34therefore it would change to criticality
  2123. 1:25:36one the eye was removed is that correct
  2124. 1:25:39that's correct and so from that point on
  2125. 1:25:43I believe it was in
  2126. 1:25:44what's the date
  2127. 1:25:47December 82
  2128. 1:25:51those shuttles have been flown
  2129. 1:25:54on the basis of criticality one so there
  2130. 1:25:56was a failure of that seal a catastrophe
  2131. 1:25:59would result because there was no
  2132. 1:26:01redundancy is that correct
  2133. 1:26:03well I guess that's the interpretation
  2134. 1:26:05of that but recognizing the actual
  2135. 1:26:07Hardware that was put together uh and
  2136. 1:26:10what we knew at that time I don't
  2137. 1:26:11believe that was that was true and what
  2138. 1:26:14was true was that the drawings as I
  2139. 1:26:16mentioned allowed a condition where that
  2140. 1:26:19could you could fly that Hardware in
  2141. 1:26:20that condition but but just to be just
  2142. 1:26:24what Brazil says is that the primary
  2143. 1:26:27O-rings is a criticality one and you're
  2144. 1:26:29not allowed to consider the secondary
  2145. 1:26:31o-ring as a backup to that that's true
  2146. 1:26:33sorry that's absolutely correct that's
  2147. 1:26:35what it meant
  2148. 1:26:38and that was known I assumed by everyone
  2149. 1:26:42that was working on the program where
  2150. 1:26:44most of the top people working on the
  2151. 1:26:45program is that would that be true
  2152. 1:26:47well I I kind of thought I was one of
  2153. 1:26:50the top people working the program and I
  2154. 1:26:51didn't know that until uh August of 1985
  2155. 1:26:54when I put that presentation together I
  2156. 1:26:56I presume it was I did find out there
  2157. 1:27:00was some
  2158. 1:27:01disagreement between uh both fire call
  2159. 1:27:04and Marshall and interpreting that
  2160. 1:27:06relative to the Joint rotation The Joint
  2161. 1:27:11rotation that was used for concluding
  2162. 1:27:13that was obtained from two different
  2163. 1:27:15sources
  2164. 1:27:16one of those sources was from the
  2165. 1:27:19structural test article one first
  2166. 1:27:21structural test article and this was
  2167. 1:27:22waiting for my time but
  2168. 1:27:25where this test article was taken to
  2169. 1:27:29Marshall and that's basically a forward
  2170. 1:27:31segment unloaded now and an app segment
  2171. 1:27:35you know where they input the uh both
  2172. 1:27:38the pre-launch loads and they put flight
  2173. 1:27:40loads and all that business into the
  2174. 1:27:42test article
  2175. 1:27:45and this test is run horizontally
  2176. 1:27:48he owns horizontal and they measured
  2177. 1:27:51through the elite Jack board I
  2178. 1:27:53understand there's some places the
  2179. 1:27:54actual rotation of the parks
  2180. 1:27:57and that's a fairly High numbers up
  2181. 1:28:00around 50 000 I believe is what they
  2182. 1:28:02said it rotated
  2183. 1:28:04we had run some tests ourselves in a
  2184. 1:28:07vertical assembly during a hybrid test
  2185. 1:28:11and measured some of the rotations and
  2186. 1:28:14got numbers like 30 to 40 thousands
  2187. 1:28:17so there was some disagreement as to
  2188. 1:28:20which numbers were correct some of our
  2189. 1:28:22people felt that the horizontal assembly
  2190. 1:28:24may have made the the structural test
  2191. 1:28:27article numbers uh not representative
  2192. 1:28:30the vertical assembly is better
  2193. 1:28:32and in fact because of that disagreement
  2194. 1:28:35uh we're in the process and started uh
  2195. 1:28:39early last summer at the direction of
  2196. 1:28:41Marshall to come up with what's called a
  2197. 1:28:43referee test
  2198. 1:28:45uh to do some very careful
  2199. 1:28:47instrumentation in a vertical assembly
  2200. 1:28:49to get a better handle on the exact
  2201. 1:28:51amount
  2202. 1:28:53of joint rotation
  2203. 1:28:55those joint rotations that are used or
  2204. 1:28:57those that are predicted for the maximum
  2205. 1:28:59expected operating pressure which by the
  2206. 1:29:02way we have never obtained unfortunately
  2207. 1:29:05hope we never knew but that's a three
  2208. 1:29:07sigma out there someplace
  2209. 1:29:10but that still is a point of controversy
  2210. 1:29:13as to what that number really is because
  2211. 1:29:15the still I believe the critical items
  2212. 1:29:18will have to change that from one
  2213. 1:29:19redundancy to one
  2214. 1:29:21not only assume the meop but I believe
  2215. 1:29:24it is filmed the larger rotation which
  2216. 1:29:27is about 50 percent more than some of
  2217. 1:29:30the data that we got from vertical so I
  2218. 1:29:31don't I still don't fully understand
  2219. 1:29:34that what I do understand is that it was
  2220. 1:29:37made at the time when temperature
  2221. 1:29:39effects were not known and the
  2222. 1:29:42resiliency problem is Dr Fineman brought
  2223. 1:29:44up I think the more serious one do it
  2224. 1:29:49coming back though beginning in 1985
  2225. 1:29:53when you've realized that the
  2226. 1:29:55criticality one was the who was on the
  2227. 1:29:58critical items list
  2228. 1:30:00uh you knew from that point on that a
  2229. 1:30:04single failure uh with the uh
  2230. 1:30:07catastrophe as far as the mission is
  2231. 1:30:09concerned
  2232. 1:30:10well uh as I mentioned earlier that uh
  2233. 1:30:15you have to postulate what your failure
  2234. 1:30:18mechanism is and uh
  2235. 1:30:21I felt very strongly that
  2236. 1:30:25the blow by that we had observed indeed
  2237. 1:30:28was on the early part of the ignition
  2238. 1:30:30Transit I think we all felt that way
  2239. 1:30:32we've modeled that by the way I think
  2240. 1:30:34fairly reasonably on the erosion
  2241. 1:30:36uh and that at that point in time when
  2242. 1:30:40the hardware really hasn't had a chance
  2243. 1:30:41to rotate taking the temperature effects
  2244. 1:30:43out now
  2245. 1:30:44that we do indeed have a good redundant
  2246. 1:30:46seal because if we lose the primary
  2247. 1:30:49o-ring at that time that secondary seal
  2248. 1:30:51is in a better shape than the primary
  2249. 1:30:53you really see them it hasn't come off
  2250. 1:30:55its land at all if you ignore the
  2251. 1:30:59resiliency problem
  2252. 1:31:01in a different scenario
  2253. 1:31:04suppose that there was the pressure is
  2254. 1:31:06increasing for some reason the primaries
  2255. 1:31:09just to understand what the situation is
  2256. 1:31:11the primary seal begins to erode
  2257. 1:31:14and by the time the pressure gets to
  2258. 1:31:16something like 600 or 700 PSI which is I
  2259. 1:31:19think just below the maximum operating
  2260. 1:31:20pressure it finally erodes all the way
  2261. 1:31:23through so that the gas can pass through
  2262. 1:31:26the primary seal
  2263. 1:31:27would you think there was a reasonable
  2264. 1:31:29probability that the whole thing would
  2265. 1:31:30fail because the rotation by that time
  2266. 1:31:33is enough that the secondary seal can't
  2267. 1:31:34hold it yes I think there was and that
  2268. 1:31:37was our assessment now that there was a
  2269. 1:31:39reasonable problem though okay that you
  2270. 1:31:40first knew or thought of in August 1985.
  2271. 1:31:43that's correct not before that's correct
  2272. 1:31:45now follow me up on that would you
  2273. 1:31:48assume that other people have been
  2274. 1:31:49working on the program and working on
  2275. 1:31:51the sale and the O-rings would
  2276. 1:31:52understand that too
  2277. 1:31:54uh yes I think uh there's another
  2278. 1:31:57important piece of information uh
  2279. 1:32:01back in the end of April
  2280. 1:32:0485
  2281. 1:32:06forgot the exact flight but it was the
  2282. 1:32:09last one in April
  2283. 1:32:12we had a problem with the orange field
  2284. 1:32:15nozzle uh that's light after it came
  2285. 1:32:20back the nozzle is still attached to the
  2286. 1:32:22app segment and we disassemble the
  2287. 1:32:26segments when they're brought back to
  2288. 1:32:27the court and then they're put on rail
  2289. 1:32:30cars to send back to Utah and we never
  2290. 1:32:31got the segment back and until I don't
  2291. 1:32:33know sometimes a lot of part of June or
  2292. 1:32:35something
  2293. 1:32:35but this light was very in April we
  2294. 1:32:38disassembled that nozzle we found that
  2295. 1:32:41we had violated the primary seal back in
  2296. 1:32:43three locations and burned completely
  2297. 1:32:45through it
  2298. 1:32:47uh the secondary seal also hey road is
  2299. 1:32:50like 32 thousands
  2300. 1:32:52uh it better health and it did its job
  2301. 1:32:56uh that was in a nozzle joint uh uh the
  2302. 1:33:00primary field and also joined as a board
  2303. 1:33:02so yield quite similar to the steel
  2304. 1:33:04joint tolerances are a little different
  2305. 1:33:06but the secondary seal is a face seal
  2306. 1:33:11it's uh
  2307. 1:33:12you know they're both somewhat Dynamic
  2308. 1:33:15Fields this more a static field and the
  2309. 1:33:16bar Seal face deals truck down of the
  2310. 1:33:19bolts and it obviously did its job and
  2311. 1:33:23our conclusion was in that particular
  2312. 1:33:25instance was that the
  2313. 1:33:28even though we passed Elite chest with
  2314. 1:33:30the vacuum party may have massive Lake
  2315. 1:33:32check we were using at that time a uh a
  2316. 1:33:36pressure uh stabilizing pressure to run
  2317. 1:33:39that meat check at 100 PSI
  2318. 1:33:41we had had some data earlier that showed
  2319. 1:33:45us that
  2320. 1:33:47the consistency that honey is quite
  2321. 1:33:50variable and you can actually uh the
  2322. 1:33:52putty will come a good sealant in many
  2323. 1:33:54cases and it can hold as much as 100 PSI
  2324. 1:33:58for a good period of time sometimes
  2325. 1:33:59they're well through sometimes it won't
  2326. 1:34:01so our concern was that maybe we're not
  2327. 1:34:03really checking the O-ring seals we're
  2328. 1:34:05checking the putty and we've got to make
  2329. 1:34:06sure we're checking the ordering seals
  2330. 1:34:08so he jacks the pressure up to 200 PSI
  2331. 1:34:11that was the last flight that we were
  2332. 1:34:13still under the 100 PSI which is the
  2333. 1:34:14previous requirement
  2334. 1:34:17to stabilize it at 100 and then once you
  2335. 1:34:20stabilize it for a period of time there
  2336. 1:34:22you drop the pressure completely again
  2337. 1:34:24you bring it up to 50 psi and that's
  2338. 1:34:27what you run the leak Jack at for about
  2339. 1:34:2910 minutes it only allow one PSI drop
  2340. 1:34:32on that particular set of Hardware since
  2341. 1:34:35it was the last one we ran with 100 PSI
  2342. 1:34:38because the change hadn't gotten through
  2343. 1:34:40with all the paperwork system on what we
  2344. 1:34:42understood about what honey behaves
  2345. 1:34:44Under Pressure because we went 200 PSI
  2346. 1:34:47to the field joints at that time this
  2347. 1:34:50hadn't gotten a nozzle
  2348. 1:34:51that we concluded that the party May
  2349. 1:34:53well have masked that late check as it
  2350. 1:34:55was at 100 and therefore we may have had
  2351. 1:34:57some defects in that seal
  2352. 1:34:59that we didn't detect
  2353. 1:35:01and as a result that seal leaked at
  2354. 1:35:05ignition from time to zero
  2355. 1:35:07and when that happens you get
  2356. 1:35:11severe erosion on your o-ring because
  2357. 1:35:12you get the jet impingement so we've
  2358. 1:35:14been calculating which is direct onto
  2359. 1:35:16the O-ring seal like a flat plate but
  2360. 1:35:19when you bypass the o-ring in a leak
  2361. 1:35:22like that it actually chokes at that
  2362. 1:35:24point so you're forming a throat and he
  2363. 1:35:26rose very rapidly from underneath as
  2364. 1:35:28well as jet impingement and you lose
  2365. 1:35:30quite a bit of seal we lost most of the
  2366. 1:35:32seal in fact
  2367. 1:35:33but the nozzle feels very good the
  2368. 1:35:36secondary steel because it's around the
  2369. 1:35:37corner expands excuse me it spans goes
  2370. 1:35:42down around the corner and eroded some
  2371. 1:35:45of the secondary seal
  2372. 1:35:47uh we ran a lot of analysis after that
  2373. 1:35:50because that was the first time that we
  2374. 1:35:52had observed erosion of a primary seal
  2375. 1:35:55we did developed our models to predict
  2376. 1:35:58the erosion what would happen in Blow by
  2377. 1:36:01erosion and it was because of that that
  2378. 1:36:04we found that hardware and it was late
  2379. 1:36:07in June it was into July that we got all
  2380. 1:36:10that data together we're down to
  2381. 1:36:11Marshall and had very detailed reviews
  2382. 1:36:13because that is a was a serious concern
  2383. 1:36:15to everyone
  2384. 1:36:17we had violated primary CEO was in the
  2385. 1:36:19nozzle joint
  2386. 1:36:20that we were asked to come to Washington
  2387. 1:36:23the headquarters and review that there's
  2388. 1:36:25a very serious concern
  2389. 1:36:27it was that time that I got with the
  2390. 1:36:30engineering people and said we need to
  2391. 1:36:32not only put that whole story together
  2392. 1:36:33we need to put the whole story together
  2393. 1:36:35on all the pressure seals
  2394. 1:36:37because I and several others still felt
  2395. 1:36:40that even though that problem happened
  2396. 1:36:41with the nozzle the field joint was a
  2397. 1:36:43more serious concern
  2398. 1:36:45because I felt very good about the
  2399. 1:36:47secondary seal of the nozzle I didn't or
  2400. 1:36:50the field joint and I put together a
  2401. 1:36:52presentation for August that I think
  2402. 1:36:54showed where our real concerns were and
  2403. 1:36:57why we felt the highest priority was a
  2404. 1:36:59fuel joint even though we just
  2405. 1:37:00experienced that problem with a nozzle
  2406. 1:37:03we felt we had corrected the problem
  2407. 1:37:05with the nozzles as we all subsequent
  2408. 1:37:07flights had the 200 PSI leak check so
  2409. 1:37:10that we could not uh miss a possible
  2410. 1:37:12defective seal or contamination may have
  2411. 1:37:15prevented that seal from saving in the
  2412. 1:37:17first place
  2413. 1:37:18so that was some of the background that
  2414. 1:37:20I think really turned up the game
  2415. 1:37:22on the whole SEAL issue
  2416. 1:37:25from about April really in June on prior
  2417. 1:37:29to that time we were doing a lot of work
  2418. 1:37:31to better understand this this rotation
  2419. 1:37:33business and all but we have done a
  2420. 1:37:36tremendous amount of work in fact you
  2421. 1:37:39may have read in in the press and it's
  2422. 1:37:41true that we actually had went to a Fae
  2423. 1:37:44conference last fall a couple of our top
  2424. 1:37:47Engineers went there to try to get help
  2425. 1:37:49from the wholesale industry in the SAE
  2426. 1:37:51about field joint
  2427. 1:37:54uh is there a better way to seal that
  2428. 1:37:56joint as soon as I say a society of
  2429. 1:37:59Automotive engineers
  2430. 1:38:00and uh we we did a lot of work to try to
  2431. 1:38:05get help from the outside as well as do
  2432. 1:38:08the work we had inside and
  2433. 1:38:10I think that's all relevant to the
  2434. 1:38:12discussion though were you surprised
  2435. 1:38:14that some of the top people in the
  2436. 1:38:16decision-making process didn't know
  2437. 1:38:18about this at all
  2438. 1:38:19didn't know about the Cil or the
  2439. 1:38:22criticality one or well the whole thing
  2440. 1:38:24the concern and your point on the part
  2441. 1:38:26of it Cycles Engineers it's the original
  2442. 1:38:29decision that had been not to Launch
  2443. 1:38:31so that oh that oh I'm very surprised at
  2444. 1:38:34that I hardly believe that I the issue
  2445. 1:38:37is so controversial I thought that I'm
  2446. 1:38:39sure that they were aware that I I have
  2447. 1:38:42a hard time believing they didn't
  2448. 1:38:45ask one question uh in talking about
  2449. 1:38:49criticality one going to 1R
  2450. 1:38:52I think you made the comment that you'd
  2451. 1:38:55have to have all the tolerances going in
  2452. 1:38:56the wrong direction to meet that
  2453. 1:38:58condition but you did say that one unit
  2454. 1:39:00did meet that condition yes the best of
  2455. 1:39:03my knowledge and I had some record
  2456. 1:39:06search done that I was told that there
  2457. 1:39:08was a condition in the uh I think it was
  2458. 1:39:11a forward field joint of the fps4
  2459. 1:39:14someplace that uh was in that condition
  2460. 1:39:17but what if that launch had been done at
  2461. 1:39:19a cold temperature wouldn't it may have
  2462. 1:39:21you taken it over the edge
  2463. 1:39:24I don't know
  2464. 1:39:25[Music]
  2465. 1:39:26it's possible I certainly don't feel
  2466. 1:39:29good about that but the the reason I
  2467. 1:39:32asked the question it's it seemed to me
  2468. 1:39:33that if it was a criticality one item
  2469. 1:39:36then everybody should treat it as
  2470. 1:39:38criticality one
  2471. 1:39:39and not rationalize that that may not
  2472. 1:39:42ever happen well I agree with that I am
  2473. 1:39:45do you think everybody else agrees with
  2474. 1:39:47that
  2475. 1:39:47so I think he has to our engineering
  2476. 1:39:49people agree to that and that's why the
  2477. 1:39:51recommendation we had made originally
  2478. 1:39:53was it was the basis for that
  2479. 1:39:55recommendation
  2480. 1:39:56we felt that we
  2481. 1:39:59had observed the condition a year
  2482. 1:40:01earlier that we did feel was uh
  2483. 1:40:03attributed to temperature in some way or
  2484. 1:40:05another and it was not a good condition
  2485. 1:40:07and we didn't want to go much beyond
  2486. 1:40:09that because uh even though that one was
  2487. 1:40:12successful it certainly wasn't a good
  2488. 1:40:14condition
  2489. 1:40:16was it at NASA's uh was it NASA or
  2490. 1:40:20thiacoal that originally initiated the
  2491. 1:40:23change from criticality 1R to
  2492. 1:40:26criticality one for the primary o-ring
  2493. 1:40:30oh I have to tell you based on what I
  2494. 1:40:33was told because I wasn't involved in
  2495. 1:40:35that change but I was told that that was
  2496. 1:40:38a NASA initiated what experience led to
  2497. 1:40:42that change do you know
  2498. 1:40:45I'm not sure if I experience led to the
  2499. 1:40:48change I presume it was the
  2500. 1:40:50understanding from The Joint rotation
  2501. 1:40:52data and the growing tolerances of all
  2502. 1:40:57these parts that that condition could
  2503. 1:40:59exist someplace in the hardware and
  2504. 1:41:02therefore if we were going to fly the
  2505. 1:41:04hardware as it was designed that either
  2506. 1:41:07through refurbishment or new hardware
  2507. 1:41:09that was within those torrances maybe
  2508. 1:41:10matched together sometime to give us a
  2509. 1:41:12condition like that but I I think you'd
  2510. 1:41:14have to ask the people that were
  2511. 1:41:15involved in the organization how do you
  2512. 1:41:18account for what appears to be the fact
  2513. 1:41:21that between December 82 and the middle
  2514. 1:41:25of 85 when fire call became concerned
  2515. 1:41:28about the erosion of the bovine
  2516. 1:41:31um that
  2517. 1:41:33flights did not occur seemingly during
  2518. 1:41:36that time it led to the same concern
  2519. 1:41:41you know I can't explain then I
  2520. 1:41:43certainly didn't know about it until
  2521. 1:41:45August 8th I don't know I I think that
  2522. 1:41:48everyone was concerned at least from the
  2523. 1:41:50standpoint that we always had to present
  2524. 1:41:53data on the joints that we were making
  2525. 1:41:55the show we had adequate squeeze now
  2526. 1:41:59you know that data was presented and I'm
  2527. 1:42:01sure people were concerned about that
  2528. 1:42:05thank you
  2529. 1:42:07the questions we'll have a 10-minute
  2530. 1:42:09recess
  2531. 1:42:14[Music]
  2532. 1:42:20to take the stand
  2533. 1:42:34s
  2534. 1:42:35[Music]
  2535. 1:42:48[Music]
  2536. 1:42:55[Music]
  2537. 1:42:56[Applause]
  2538. 1:43:02this place new requested if you appear
  2539. 1:43:06after mystery Donald and we were glad to
  2540. 1:43:09welcome you and go ahead and proceed any
  2541. 1:43:12way you'd like thank you Mr chairman
  2542. 1:43:15uh we've given you a handout there and I
  2543. 1:43:19wanted to start on page 18.
  2544. 1:43:21we had originally thought to provide
  2545. 1:43:24some technical background that that can
  2546. 1:43:26be covered later
  2547. 1:43:28peace
  2548. 1:43:30on page 18. that I said we have of
  2549. 1:43:34course have received quite a lot of this
  2550. 1:43:36information executive session and we
  2551. 1:43:38will certainly be pleased to look at the
  2552. 1:43:42information on this first 18 pages but
  2553. 1:43:45to proceed in any way you like okay
  2554. 1:43:47thank you
  2555. 1:43:49my intent here is to uh
  2556. 1:43:52explain the organization structure and
  2557. 1:43:55those people that participated in the
  2558. 1:43:57discussions and then go through the
  2559. 1:43:59chronology
  2560. 1:44:01of the occurrences at night on the 27th
  2561. 1:44:05of January
  2562. 1:44:06first off uh I'm the senior vice
  2563. 1:44:09president of Wasatch operations we have
  2564. 1:44:12on the chart you have there selected
  2565. 1:44:15only those people with participated in
  2566. 1:44:17the discussions
  2567. 1:44:19but I might point out that there are
  2568. 1:44:21three divisions reporting to me the
  2569. 1:44:24space division under Mr Wiggins who was
  2570. 1:44:27listed there and there is there are also
  2571. 1:44:30a tactical and strategic division
  2572. 1:44:33reporting to me
  2573. 1:44:35Mr Lund who shows there as vice
  2574. 1:44:37president of engineering provides
  2575. 1:44:39Engineering Services for all of our uh
  2576. 1:44:43all three divisions
  2577. 1:44:45we've covered
  2578. 1:44:46just the space division in detail
  2579. 1:44:50you'll see that Mr kilminster reports to
  2580. 1:44:54Mr Wiggins and he's the head of the he's
  2581. 1:44:56the vice president of space booster
  2582. 1:44:58programs and of course you've just heard
  2583. 1:45:01from Mr Mcdonald
  2584. 1:45:03and reporting to him are Mr Abilene and
  2585. 1:45:05Russell
  2586. 1:45:07and then from the KSC office is Jack
  2587. 1:45:10Buchanan also reporting to Mr kilminster
  2588. 1:45:14within the engineering organization
  2589. 1:45:16there's a space shuttle project
  2590. 1:45:18Engineering Group under Mr Brinton
  2591. 1:45:22and uh Mr Macbeth reports to him
  2592. 1:45:26then the other part of engineering is
  2593. 1:45:28engineering design organization you'll
  2594. 1:45:31see the people listed there I don't need
  2595. 1:45:33to read them but they were all
  2596. 1:45:34participants in the discussion
  2597. 1:45:38we added a couple of notes Here uh we
  2598. 1:45:41thought were curtain one is that we do
  2599. 1:45:44have a fight Readiness review add more
  2600. 1:45:47than five call before
  2601. 1:45:49Marshall has their fight Readiness
  2602. 1:45:52reviews and Mr Wiggins chairs that fight
  2603. 1:45:55right instant free review group
  2604. 1:45:57and uh the results of that flight
  2605. 1:46:01writing this review are signed off both
  2606. 1:46:03by Mr kilmister and Mr Brinton to
  2607. 1:46:06indicate that we're ready to fly
  2608. 1:46:09and then Mr kilminster then attends the
  2609. 1:46:12uh the fight Readiness reviews of NASA
  2610. 1:46:15one other point we made here which was
  2611. 1:46:18also discussed by Mr McDonald and that
  2612. 1:46:20is that he and Mr kilminster have been
  2613. 1:46:24alternating as the attendees at the
  2614. 1:46:27launches
  2615. 1:46:28now as I go through the chronology we'll
  2616. 1:46:32you'll see the names of various people
  2617. 1:46:34here and you'll find them all in this
  2618. 1:46:37chart but I will try to point out where
  2619. 1:46:40they fit as I go through the phenology
  2620. 1:46:43thank you
  2621. 1:46:45[Music]
  2622. 1:46:47uh
  2623. 1:46:48we have the times here listed both in
  2624. 1:46:51the Eastern Standard and Mountain
  2625. 1:46:52Standard Time
  2626. 1:46:54and uh
  2627. 1:46:56the significant occurrences as we move
  2628. 1:46:59through it at one o'clock Eastern time
  2629. 1:47:03Mr Macbeth and
  2630. 1:47:06Mr Tony Thompson and Charlie Sater home
  2631. 1:47:09all received calls from Boyd Britton who
  2632. 1:47:12was at marshall
  2633. 1:47:13that's something I ought to point out
  2634. 1:47:15that throughout this discussion Mr
  2635. 1:47:18Brinton Who is the
  2636. 1:47:21manager of space shuttle project
  2637. 1:47:23engineering was at Marshall space flight
  2638. 1:47:25center as where Mr Speed
  2639. 1:47:29and as you know Mr McDonald was at
  2640. 1:47:32Kennedy as was Mr Buchanan
  2641. 1:47:35the rest of the people that we have
  2642. 1:47:37listed here then were all at the Wasatch
  2643. 1:47:40in Utah
  2644. 1:47:44um as a result of the the call at one
  2645. 1:47:47o'clock Mr Evelyn and kantner were
  2646. 1:47:50notified and uh
  2647. 1:47:52the Sater home started a bulk
  2648. 1:47:54temperature analysis in the propellant
  2649. 1:47:56and Brian Russell arranged a meeting Mr
  2650. 1:47:59ebling's office
  2651. 1:48:01they convened that meeting in Mr
  2652. 1:48:03ebling's office and uh the attendees are
  2653. 1:48:07as listed there
  2654. 1:48:10during that meeting they discussed the
  2655. 1:48:14O-ring resiliency data at 50 75 and 100
  2656. 1:48:19degrees
  2657. 1:48:20they talked about the amount of
  2658. 1:48:23blow-by-in erosion that had been seen on
  2659. 1:48:25the 51c which was the previous coldest
  2660. 1:48:29launch were you at those meetings I was
  2661. 1:48:32not at that meeting no sir so this is
  2662. 1:48:34his as far as that's right I I do get to
  2663. 1:48:38where I enter the picture here in a
  2664. 1:48:41moment this was an effort to get a a gen
  2665. 1:48:45an overview of what happened and where
  2666. 1:48:47to try to make the rest of the testimony
  2667. 1:48:50flow a little better
  2668. 1:48:53um
  2669. 1:48:54they did look at the other launch in
  2670. 1:48:57static test temperatures and concluded
  2671. 1:49:00that they did have a concern
  2672. 1:49:03they broke that meeting up and started
  2673. 1:49:07to do some work uh Mr ma was to run the
  2674. 1:49:11calculation of what the O-ring
  2675. 1:49:13temperature would be if the ambient were
  2676. 1:49:1618 degrees
  2677. 1:49:17and Mr Evelyn notified Mr kilminster of
  2678. 1:49:21the concern that they had
  2679. 1:49:23and uh Mr kilmister asked Evelyn to get
  2680. 1:49:27the Engineering Management including Mr
  2681. 1:49:28Lund involved and notify both Mr
  2682. 1:49:32McDonald and Mr Brinton of the Marshall
  2683. 1:49:36concern are the concern I assume that
  2684. 1:49:39there was no recording made of these
  2685. 1:49:41meetings this was reconstructed from
  2686. 1:49:43conversations you've had with other
  2687. 1:49:44people that's correct
  2688. 1:49:50uh we did we did talk to all the people
  2689. 1:49:53involved so we felt we had a consensus
  2690. 1:49:55of of the sequence
  2691. 1:50:02then Mr Buchanan
  2692. 1:50:05called to give us a uh some temperature
  2693. 1:50:08predictions at that time they were
  2694. 1:50:11predicting uh 34 degrees at launch time
  2695. 1:50:14at 9 38.
  2696. 1:50:18then Mr Thompson briefed the Jack cap on
  2697. 1:50:22his concerns
  2698. 1:50:24and Mr McDonald called from Kennedy
  2699. 1:50:29to Hope hoping to have a telecon between
  2700. 1:50:32the Morton cycle and NASA on those
  2701. 1:50:34concerns there were people called to the
  2702. 1:50:37conference room to support the telecon
  2703. 1:50:39and that uh required interrupting the
  2704. 1:50:43meeting that was at that point underway
  2705. 1:50:45in Mr Lund's office
  2706. 1:50:48so just for semantics
  2707. 1:50:51you say people called to support
  2708. 1:50:53telegram you means to take part in the
  2709. 1:50:55silicone
  2710. 1:50:56correct the
  2711. 1:50:59the conference room we have there has uh
  2712. 1:51:02uh microphone so that you can be in the
  2713. 1:51:05conference room and anyone can talk and
  2714. 1:51:07be picked up uh their conversation my
  2715. 1:51:10question really is to do the word
  2716. 1:51:12support
  2717. 1:51:13where you say your confidence to support
  2718. 1:51:15Telecom and interrupted to support
  2719. 1:51:17Telecom you mean take part in Excel
  2720. 1:51:19accounts to take part that's correct
  2721. 1:51:21correct
  2722. 1:51:24the uh that that conference or telecon
  2723. 1:51:28then proceeded with the the people that
  2724. 1:51:31are listed there some 13
  2725. 1:51:33including uh the uh people at Marshall
  2726. 1:51:37and at Kennedy
  2727. 1:51:42uh at the time that started uh they
  2728. 1:51:45notified Mr kilminster that was starting
  2729. 1:51:48at the same time essentially he received
  2730. 1:51:52a call from that LSS means of onto
  2731. 1:51:55report Services that's the the uh people
  2732. 1:51:58that worked for Mr Buchanan down at the
  2733. 1:52:00Kennedy they called and gave him an
  2734. 1:52:03updated overnight temperature
  2735. 1:52:05predictions uh on a two-hour uh basis
  2736. 1:52:09every two hours they gave him what the
  2737. 1:52:11temperature was going to be
  2738. 1:52:13so with any notes or records kept with
  2739. 1:52:16this kind of is this all reconstructed
  2740. 1:52:19from memory
  2741. 1:52:20well
  2742. 1:52:22I don't know of any specific notes
  2743. 1:52:25although there may be
  2744. 1:52:28um
  2745. 1:52:30just have to answer it that way
  2746. 1:52:33we uh I I know the calculations that
  2747. 1:52:37were run we those calculations exist
  2748. 1:52:40because they took those on every two
  2749. 1:52:42hour basis and and had started using 18
  2750. 1:52:46degrees and then proceeded to use the
  2751. 1:52:48more update updated temperatures because
  2752. 1:52:50ultimately we if we were told it was
  2753. 1:52:53forecast to be a 29 degree o-ring
  2754. 1:52:55temperature
  2755. 1:52:57in any event
  2756. 1:52:59those those concerns uh that were
  2757. 1:53:03existed were discussed
  2758. 1:53:05and they amounted to the fact that the
  2759. 1:53:09cold previous coldest launched had given
  2760. 1:53:12us the greatest uh bull Buy
  2761. 1:53:15and uh that coupled with concern about
  2762. 1:53:19the safer o-ring
  2763. 1:53:21uh that would exist at a lower
  2764. 1:53:24temperature was the focus of the
  2765. 1:53:27discussion
  2766. 1:53:28uh it was just that a discussion and so
  2767. 1:53:32uh it was decided and NASA requested
  2768. 1:53:36that we put together an organized uh
  2769. 1:53:39analysis or and organize the data and
  2770. 1:53:43write down what our concerns were so
  2771. 1:53:45they could be reviewed in a more
  2772. 1:53:47careful fashion
  2773. 1:53:49so there was a telecon then scheduled
  2774. 1:53:52for uh 6 15. to do that
  2775. 1:53:56and uh
  2776. 1:53:58at that point Mr kilmister called uh Mr
  2777. 1:54:02Wiggins and me we were in a another
  2778. 1:54:05meeting in our Brigham City plant
  2779. 1:54:08and uh told us that there were concerns
  2780. 1:54:11and that the telecon was going to start
  2781. 1:54:13at 6 15.
  2782. 1:54:15so we hopped in the next great question
  2783. 1:54:18yes sir
  2784. 1:54:22you you had data
  2785. 1:54:25where you reached a conclusion what was
  2786. 1:54:29the purpose of NASA asking you to better
  2787. 1:54:31organize that data was that for them to
  2788. 1:54:34review it and reach some of their own
  2789. 1:54:35decisions or just to see if your
  2790. 1:54:38thinking was proper at this point we had
  2791. 1:54:40not reached a conclusion during the
  2792. 1:54:43parts that I'm covering here we'd had
  2793. 1:54:46the discussion I still don't understand
  2794. 1:54:48why they needed the data better
  2795. 1:54:50organized we were providing it verbally
  2796. 1:54:53over the telecon they didn't have it in
  2797. 1:54:55front of them
  2798. 1:54:56so we were talking about things like
  2799. 1:54:58curves and that sort of thing that they
  2800. 1:55:00didn't have the direct visibility of and
  2801. 1:55:03we had not yet reached any conclusion we
  2802. 1:55:06were just saying that we were concerned
  2803. 1:55:07because it was cold
  2804. 1:55:10so the request was to get that data and
  2805. 1:55:14fax it down so they could look at it at
  2806. 1:55:17the same time that we were looking at it
  2807. 1:55:19[Applause]
  2808. 1:55:20and then uh when Mr Wiggins and I were
  2809. 1:55:24notified they were in the process of
  2810. 1:55:26putting together what data the need was
  2811. 1:55:30needed for the discussion
  2812. 1:55:32and at the same time uh Mr Lund was uh
  2813. 1:55:36trying to prepare the uh some
  2814. 1:55:39conclusions and recommendations
  2815. 1:55:42uh so the church preparation and the
  2816. 1:55:45conclusion recommendations were going on
  2817. 1:55:47simultaneously
  2818. 1:55:49and uh Mr Lund or Mr Wiggins and I then
  2819. 1:55:53arrived as that was going on
  2820. 1:55:56and uh
  2821. 1:55:58as it turned out we were not able to get
  2822. 1:56:01all the charts together in time to start
  2823. 1:56:03the telecon and we got the first charts
  2824. 1:56:06faxed down there by 6 30.
  2825. 1:56:08and uh
  2826. 1:56:10the last charts didn't get down until 7
  2827. 1:56:1220. so we were working this in a
  2828. 1:56:15real-time basis
  2829. 1:56:18uh we did start the discussion again at
  2830. 1:56:21seven and uh the engineers that had
  2831. 1:56:26prepared some of the charts discussed
  2832. 1:56:28their charts and then ultimately Mr Lund
  2833. 1:56:31discovered or discussed the conclusion
  2834. 1:56:33and recommendations chart
  2835. 1:56:36uh the fundamental issue however was the
  2836. 1:56:41concern about the fare effective cold
  2837. 1:56:44would have
  2838. 1:56:46on getting the primary o-ring to move
  2839. 1:56:49into its ceiling position and seal
  2840. 1:56:52and uh if if it needs clarification
  2841. 1:56:56later Mr Lund has some charts to explain
  2842. 1:56:59that but
  2843. 1:57:00the uh when we run the leak test
  2844. 1:57:04hmm the primary o-ring is moved into
  2845. 1:57:09the furthest point away from its ceiling
  2846. 1:57:12position and that's maybe 20 thousandths
  2847. 1:57:15of an inch or so whereas the secondary
  2848. 1:57:18is moved towards its ceiling position
  2849. 1:57:22and uh the concern was whether the cold
  2850. 1:57:26the stiffness of the O-ring and the
  2851. 1:57:29grease
  2852. 1:57:30would delay the the movement of the the
  2853. 1:57:34primary O-rings so that it would not
  2854. 1:57:36seat properly and there would be Blow by
  2855. 1:57:39and uh
  2856. 1:57:40uh perhaps damage to the secondary
  2857. 1:57:43o-ring
  2858. 1:57:46we looked at the the erosion history
  2859. 1:57:50we'd had
  2860. 1:57:52to see what correlation there was with
  2861. 1:57:54temperature and there there really
  2862. 1:57:57wasn't any correlation uh
  2863. 1:58:00there were there was uh also a review of
  2864. 1:58:04the blow by history in which Mr
  2865. 1:58:06McDonald's covered very well
  2866. 1:58:08and uh the correlation that appeared
  2867. 1:58:11there was that that we had Blow by in
  2868. 1:58:14both 75 and 53 degrees but it was much
  2869. 1:58:17more severe at 53 degrees and so it was
  2870. 1:58:22thought that that was evidence that the
  2871. 1:58:23cold did in fact affect performance of
  2872. 1:58:26the O-ring
  2873. 1:58:32hardness of the O-ring
  2874. 1:58:35and uh as a as an indication of how
  2875. 1:58:38stiff and difficult it might be for the
  2876. 1:58:40O-ring to move
  2877. 1:58:41and uh we determined that from 50
  2878. 1:58:45degrees
  2879. 1:58:46to 30 degrees a 20 degree drop would
  2880. 1:58:50increase the hardness by about 10
  2881. 1:58:52percent
  2882. 1:58:53uh in fact that put it in the range of
  2883. 1:58:57when we we discussed this that night in
  2884. 1:59:01the early in the program we were
  2885. 1:59:02deciding what hardness we wanted and we
  2886. 1:59:04had used
  2887. 1:59:05some 90 eurometer O-rings in some of the
  2888. 1:59:10uh hydrostatic tests we ultimately ended
  2889. 1:59:14up with the 80 durometer o-ring
  2890. 1:59:19but that was pointed out that we'd had
  2891. 1:59:22some experience with that O-ring which
  2892. 1:59:24was harder
  2893. 1:59:26then uh what do you mean by hardnesses
  2894. 1:59:30push it into the tiny crack but that
  2895. 1:59:33it's supposed to go into
  2896. 1:59:35what is the feature that hardness it's
  2897. 1:59:37not resiliency it's the difficulty of
  2898. 1:59:40pushing it into a corner yeah well it
  2899. 1:59:42was it was thought that that stiffness
  2900. 1:59:44might make it move more slowly moving
  2901. 1:59:47across the Gap and then it would be
  2902. 1:59:50harder to extrude it in however once
  2903. 1:59:54it's sealed the being slower to extrude
  2904. 1:59:57per se wouldn't be a problem once it's
  2905. 1:59:59sealed
  2906. 2:00:03the the points we're talking about of
  2907. 2:00:06course were the points that were
  2908. 2:00:07discussed back and forth that night
  2909. 2:00:10um
  2910. 2:00:10we did look at the temperature history
  2911. 2:00:12on our previous tests and flights
  2912. 2:00:16and uh
  2913. 2:00:18we discussed the fact that we had to run
  2914. 2:00:21the subscale blowby test at 30 degrees
  2915. 2:00:23which had shown no Boulevard
  2916. 2:00:26uh that was only an indicator because
  2917. 2:00:30that was a cold test and it was with a
  2918. 2:00:33fixed uh joint Gap so it was just
  2919. 2:00:37another another point of data that we
  2920. 2:00:40had to put in the in our heads
  2921. 2:00:43this had a vertical or a horizontal test
  2922. 2:00:46rig that you ran the subscale testing
  2923. 2:00:51um I don't know
  2924. 2:00:52did you find out for us please yes sir
  2925. 2:00:55there's several fellas there no I'm sure
  2926. 2:01:01very cool
  2927. 2:01:07[Music]
  2928. 2:01:08uh out of that discussion uh we got to
  2929. 2:01:12the point where we just it was we
  2930. 2:01:15couldn't make a clear conclusion of the
  2931. 2:01:18effect of temperature on the O-ring
  2932. 2:01:19performance
  2933. 2:01:21and uh the uh a number of the engineers
  2934. 2:01:25felt that on that basis they ought to
  2935. 2:01:29stay where we were in our flight history
  2936. 2:01:32and uh
  2937. 2:01:34with the information we had at that
  2938. 2:01:36point and as far as we had proceeded in
  2939. 2:01:39our thought process
  2940. 2:01:41that appeared to be the right thing to
  2941. 2:01:44do so we proceeded to uh present that
  2942. 2:01:48information
  2943. 2:01:49isn't it fair to say though that all of
  2944. 2:01:52the engineers felt that way notice which
  2945. 2:01:55ones were which ones they were at that
  2946. 2:01:58point it was a it was not a
  2947. 2:02:03Pro con sort of discussion it was
  2948. 2:02:07where are we in our thought process and
  2949. 2:02:10where we were in our thought process was
  2950. 2:02:12that what we've discussed today says
  2951. 2:02:15let's stay with our experience
  2952. 2:02:18and what I mean is didn't all the
  2953. 2:02:20engineers agree with it
  2954. 2:02:25anymore
  2955. 2:02:29I would say that at that point we all
  2956. 2:02:33agreed with that that it wasn't uh
  2957. 2:02:36engineering or anyone else we just had
  2958. 2:02:38had looked at what we had and went
  2959. 2:02:41through our thought process and at that
  2960. 2:02:44point we felt that that's that was the
  2961. 2:02:46recommendation
  2962. 2:02:48though that you took unanimously was the
  2963. 2:02:51engineering position was the base
  2964. 2:02:53recommendation on previous flight
  2965. 2:02:55history and you say 51c which was the
  2966. 2:02:59coldest launch had been made and we had
  2967. 2:03:02the most trouble isn't that right
  2968. 2:03:04that's right
  2969. 2:03:10the uh the the next comments then were
  2970. 2:03:15as essentially as Mr McDonald said that
  2971. 2:03:18Malloy Mr Malloy uh said he disagreed
  2972. 2:03:21because he didn't feel that uh that we
  2973. 2:03:24had shown any correlation between
  2974. 2:03:26blow-bye and erosion with temperature
  2975. 2:03:28and that uh therefore
  2976. 2:03:31the rationale that had been used when we
  2977. 2:03:35decided to fly in the first place it was
  2978. 2:03:37still a vowel attraction now
  2979. 2:03:39and Mr hardy expressed surprised at the
  2980. 2:03:43recommendation because it was above the
  2981. 2:03:45qualification temperature however he
  2982. 2:03:47said he wouldn't recommend flying
  2983. 2:03:49against our recommendation
  2984. 2:03:51and then Mr McDonald came on and uh
  2985. 2:03:55said that he too had concern about the
  2986. 2:03:59cold so he pointed out that the
  2987. 2:04:02secondary o-ring was in the position to
  2988. 2:04:06seal where it didn't have to move as the
  2989. 2:04:08primary did
  2990. 2:04:09and at this point ought to be considered
  2991. 2:04:13uh with that with that discussion we
  2992. 2:04:17were
  2993. 2:04:20we were on let's say we felt that we
  2994. 2:04:24needed to have further discussions to
  2995. 2:04:27see if these comments uh would in fact
  2996. 2:04:32cause us to have any change of our
  2997. 2:04:35position
  2998. 2:04:36and uh so we decided to do that off the
  2999. 2:04:40uh off the net and we asked for a caucus
  3000. 2:04:44now in the caucus
  3001. 2:04:46we Revisited all of our previous
  3002. 2:04:49discussions
  3003. 2:04:52and the important things that came out
  3004. 2:04:56of that was that as we had recognized we
  3005. 2:05:01we were we did have the possibility that
  3006. 2:05:04the old the primary o-ring might be
  3007. 2:05:06slower to move in the ceiling position
  3008. 2:05:08and that was our concern and that's what
  3009. 2:05:10we had focused on originally
  3010. 2:05:13uh the fact that we couldn't uh show
  3011. 2:05:18direct correlation with the O-ring
  3012. 2:05:19temperature was discussed but we still
  3013. 2:05:22felt that there was some concern about
  3014. 2:05:24it being colder
  3015. 2:05:26within
  3016. 2:05:28recognized that
  3017. 2:05:31if the primary did move more slowly
  3018. 2:05:35that we could get some bovine erosion on
  3019. 2:05:38the primer
  3020. 2:05:40but we we had pointed out to us in that
  3021. 2:05:43caucus point that had not come across
  3022. 2:05:46clearly or in our earlier discussions
  3023. 2:05:48and that is that we had run tests
  3024. 2:05:52where we deliberately cut large pieces
  3025. 2:05:55out of the O-rings to see what the
  3026. 2:05:59threshold of ceiling was
  3027. 2:06:01and we found uh that we could go to 125
  3028. 2:06:05thousandths of a cut out of the O-ring
  3029. 2:06:08and it would still seal
  3030. 2:06:11information is that a static test for a
  3031. 2:06:15dynamic test that's done by by blowing
  3032. 2:06:19the pressure against the O-ring and it
  3033. 2:06:21was done both cold and hot but not in a
  3034. 2:06:23moving joint not if that's correct right
  3035. 2:06:26and and I might follow that the
  3036. 2:06:31uh through the whole discussion
  3037. 2:06:34we were concerned about the or we
  3038. 2:06:38recognized that the O-ring either
  3039. 2:06:41primary primary or secondary would have
  3040. 2:06:44to seal before the joint at a time to
  3041. 2:06:48explain
  3042. 2:06:49now the the gas pressure
  3043. 2:06:53uh gets to the O-ring uh before
  3044. 2:06:58The Joint has the chance to expand
  3045. 2:07:02but the question was with the slower
  3046. 2:07:05movement of the O-ring would it still be
  3047. 2:07:08there in the seat before the joint
  3048. 2:07:11expanded
  3049. 2:07:12Mr Mason what kind of a time frame were
  3050. 2:07:15you talking about here in the time it
  3051. 2:07:16takes to get there well the the charts
  3052. 2:07:20that we had said that if you see in 160
  3053. 2:07:24milliseconds
  3054. 2:07:26that well let's see this goes back to
  3055. 2:07:28that one or one uh discussion that you
  3056. 2:07:32had and the the uh now what that boiled
  3057. 2:07:36down to was that
  3058. 2:07:38during the first 160 milliseconds the
  3059. 2:07:41joint is still closed enough that the
  3060. 2:07:43secondary o-ring actually provides
  3061. 2:07:45redundancy
  3062. 2:07:47up to 103 or up to 300 milliseconds
  3063. 2:07:50there's less certainty and above that
  3064. 2:07:52it's uh there's a serious question about
  3065. 2:07:55that now again that chart was based on
  3066. 2:07:59the worst conditions as far as joint
  3067. 2:08:02conditions were concerned as tolerances
  3068. 2:08:05and what we had here we knew was a
  3069. 2:08:07fairly nominal compression condition
  3070. 2:08:12160 milliseconds that joint is
  3071. 2:08:16officially classified as a criticality
  3072. 2:08:191R
  3073. 2:08:22it's not officially no man that's right
  3074. 2:08:25it's just a criticality one so even
  3075. 2:08:27during the first 160 milliseconds you
  3076. 2:08:29are not allowed to consider the
  3077. 2:08:31secondary seal a backup to the primary
  3078. 2:08:33seal
  3079. 2:08:34by the critic by the critical items list
  3080. 2:08:38well uh I I don't certainly want to
  3081. 2:08:41debate that point I what we did before
  3082. 2:08:43we considered uh we did consider that
  3083. 2:08:46that
  3084. 2:08:47when that when it was established that
  3085. 2:08:50it went from one R to one it was
  3086. 2:08:51identified that we were losing
  3087. 2:08:53redundancy after the ignition transient
  3088. 2:08:57and uh
  3089. 2:09:00we did consider and that is where I'm
  3090. 2:09:03headed that that there was some
  3091. 2:09:05protection during the ignition Transit
  3092. 2:09:08from the secondary o-ring
  3093. 2:09:12[Music]
  3094. 2:09:15Dr Wright's questions
  3095. 2:09:19well let me uh let me try again it
  3096. 2:09:22sounds it sounds to me yeah exercise
  3097. 2:09:25some kind of engineering judgment on
  3098. 2:09:27whether you can consider this a 1R or a
  3099. 2:09:30one
  3100. 2:09:31and I just don't think that the system
  3101. 2:09:34allows that I think that once something
  3102. 2:09:36is is classified as a criticality one
  3103. 2:09:39that sets a red flag in everyone's mind
  3104. 2:09:42that that's an extremely
  3105. 2:09:44dangerous situation and uh
  3106. 2:09:49I'm just not sure that you're allowed to
  3107. 2:09:52go back and rationalize it as uh well
  3108. 2:09:54during this hundred milliseconds we may
  3109. 2:09:56have a secondary seal we may be may be
  3110. 2:09:59allowed to consider it a redundant seal
  3111. 2:10:01we may have protection to a criticality
  3112. 2:10:04one system
  3113. 2:10:06well
  3114. 2:10:07um I can't I really can't address the
  3115. 2:10:11the propriety of it as far as as the
  3116. 2:10:13system is concerned I I'd have to State
  3117. 2:10:16what we did
  3118. 2:10:18and uh we we had recognized uh when we
  3119. 2:10:23when the criticality was changed from
  3120. 2:10:25one hour to one that it was done because
  3121. 2:10:28we didn't have a full-time redundant
  3122. 2:10:30seal and uh
  3123. 2:10:34at the at the time of this discussion
  3124. 2:10:37uh we were not addressing uh the thing
  3125. 2:10:41from a one or one Viewpoint we were
  3126. 2:10:43addressing it from what we knew of how
  3127. 2:10:45the joint performed
  3128. 2:10:47and what we knew was that early in the
  3129. 2:10:50ignition transient that the secondary in
  3130. 2:10:53fact did function until the uh until the
  3131. 2:10:56joint rotated
  3132. 2:10:58now but isn't that in fact changing the
  3133. 2:11:01critical items list
  3134. 2:11:06of the list shows that it there was no
  3135. 2:11:10redundancy and if I understand your
  3136. 2:11:11answer you're saying we as a management
  3137. 2:11:13team decided there was redundancy
  3138. 2:11:17we we did consider that as a factor in
  3139. 2:11:22our uh in our decision process and uh I
  3140. 2:11:27need to let me let me say first I I
  3141. 2:11:29didn't get to the thing in the in the
  3142. 2:11:32right sequence our our primary concern
  3143. 2:11:36and the thing we addressed in our in our
  3144. 2:11:39earlier conversation was getting making
  3145. 2:11:42sure the primary o-ring would seal
  3146. 2:11:45and uh
  3147. 2:11:48when we had this uh further discussion
  3148. 2:11:52it was pointed out that we had run the
  3149. 2:11:55test
  3150. 2:11:55which showed that we could tolerate
  3151. 2:11:59about three times as much erosion in the
  3152. 2:12:01primary o-ring as we had previously
  3153. 2:12:04experienced in fact in fact experienced
  3154. 2:12:07in the 51 C I should say in that in that
  3155. 2:12:11cold test
  3156. 2:12:12so we felt that we had a substantial
  3157. 2:12:17margin because we had the ability to
  3158. 2:12:20tolerate more much more erosionally than
  3159. 2:12:22we had
  3160. 2:12:23and that the erosion was driven by the
  3161. 2:12:28volume of gas that could be passed uh
  3162. 2:12:31past that O-ring and that that we felt
  3163. 2:12:35was limited so that it would very
  3164. 2:12:37unlikely that it could get beyond the
  3165. 2:12:39three-time erosion that we agree on the
  3166. 2:12:42uh three times the erosion we had seen
  3167. 2:12:44before can I ask some questions
  3168. 2:12:47isn't the erosion partly depend upon the
  3169. 2:12:50speed of the gas the size of the hole
  3170. 2:12:52through which it comes
  3171. 2:12:57do you have some kind of cow
  3172. 2:12:59Toes that you couldn't get more erosion
  3173. 2:13:02than the amount that you got in 51c
  3174. 2:13:12it tells us what that limit is or not
  3175. 2:13:16what made you think that 51c was the
  3176. 2:13:19maximum erosion that you could
  3177. 2:13:20reasonably expect
  3178. 2:13:25we did I we didn't say that we didn't
  3179. 2:13:28feel that that was the maximum we could
  3180. 2:13:30expect we said that if there was a a
  3181. 2:13:35temperature effect that made it move
  3182. 2:13:37slower we might get some more erosion
  3183. 2:13:40and we felt that the factor of three
  3184. 2:13:42times was was not likely to be exceeded
  3185. 2:13:46well let me explain I'm not interested
  3186. 2:13:48at the moment in the temperature I'm
  3187. 2:13:50going to criticize the original decision
  3188. 2:13:53that you could operate at 53 degrees
  3189. 2:13:54which is a different point of view
  3190. 2:13:57than what we're talking about based on
  3191. 2:13:59the idea that you've already seen that
  3192. 2:14:02you have one-third the amount of erosion
  3193. 2:14:04necessary to split the primary ring at a
  3194. 2:14:07time when the secondary has a high
  3195. 2:14:09probability of not being deceitable as
  3196. 2:14:12Mr McDonald said and I'd like to know
  3197. 2:14:15how you judge by having seen one-third
  3198. 2:14:19of an O-ring disintegrated in one flight
  3199. 2:14:23that is very unlikely
  3200. 2:14:26that you would get three times that
  3201. 2:14:27erosion on another flight
  3202. 2:14:29of this on the same circumstances
  3203. 2:14:35well uh
  3204. 2:14:37that that's the that's the Judgment
  3205. 2:14:40issue that we finally got down to I try
  3206. 2:14:42and understand in her judgment
  3207. 2:14:45when uh when we had the previous erosion
  3208. 2:14:49to get that we had to fill all the
  3209. 2:14:51cavity that was there Holly annular
  3210. 2:14:54cavity so there wasn't any way to get
  3211. 2:14:58any more substantially any more gas flow
  3212. 2:15:01doesn't it depend on the speed of the
  3213. 2:15:03gas and the temperature is it depend
  3214. 2:15:05maybe on the complexity
  3215. 2:15:08of the Blue Hole that goes through the
  3216. 2:15:11putty
  3217. 2:15:13so that it would be a matter of accident
  3218. 2:15:14how much you got
  3219. 2:15:16could it for example have been that you
  3220. 2:15:18got one-third the amount of erosion for
  3221. 2:15:21instance because the putty hole is
  3222. 2:15:23smaller and longer
  3223. 2:15:25with a reasonable probability well uh
  3224. 2:15:28the the engineers which are here have I
  3225. 2:15:33I don't have off the top of my head the
  3226. 2:15:35the numbers but we did run tests was
  3227. 2:15:38focused yet
  3228. 2:15:40and it was focused the most amount to
  3229. 2:15:43see how much erosion we would get and I
  3230. 2:15:46believe they can they can do a better
  3231. 2:15:47job of correlating that than I can I can
  3232. 2:15:51comment that my understanding of it was
  3233. 2:15:54that it would appear that because
  3234. 2:15:57there's a limited volume and we hadn't
  3235. 2:15:59looked at what a most highly focused yet
  3236. 2:16:02would erode the the combination of that
  3237. 2:16:05knowledge made us feel that probability
  3238. 2:16:08of getting three times the erosion was
  3239. 2:16:10very unlikely thank you
  3240. 2:16:13isn't isn't it true that the amount of
  3241. 2:16:15erosion you can tolerate actually
  3242. 2:16:17depends on the particular rocket motor
  3243. 2:16:19you're dealing with because the amount
  3244. 2:16:21of compression can vary on a particular
  3245. 2:16:24o-ring depending on where you are within
  3246. 2:16:27the tolerances of the two pieces which
  3247. 2:16:29make up that rocket motor as you analyze
  3248. 2:16:32a particular amount of compression on
  3249. 2:16:3451l these particular joints to see
  3250. 2:16:37whether or not that was the average
  3251. 2:16:39amount of compression and how much uh
  3252. 2:16:43erosion of the O-ring you could actually
  3253. 2:16:45tolerate we yes we did look at the
  3254. 2:16:49compression on that particular joint and
  3255. 2:16:51we compared it and matter of fact to the
  3256. 2:16:53compression that we'd had on the
  3257. 2:16:55previous cold launch
  3258. 2:16:58and the compression was essentially
  3259. 2:17:01nominal so I recall was around forty
  3260. 2:17:03thousands
  3261. 2:17:04so we did consider that
  3262. 2:17:09this for for just a second
  3263. 2:17:12um
  3264. 2:17:13we've got a criticality one system and
  3265. 2:17:16there's some question in in your minds
  3266. 2:17:18whether it'll perform at uh at the the
  3267. 2:17:22temperatures that are predicted at
  3268. 2:17:23launch around 29 or 30 degrees is what
  3269. 2:17:26you're
  3270. 2:17:27basing your your judgments on
  3271. 2:17:30what test data did you have to show that
  3272. 2:17:34or any test date at all on joint
  3273. 2:17:37rotation or the timing function or or
  3274. 2:17:41even seal erosion down at 30 degrees
  3275. 2:17:44that would allow you to make a
  3276. 2:17:47reasonable engineering judgment that
  3277. 2:17:49this critical one item criticality one
  3278. 2:17:51item was was safe to fly
  3279. 2:17:54well it was the various items that I
  3280. 2:17:57mentioned we had the durometer of the
  3281. 2:18:00O-ring down to uh
  3282. 2:18:03uh below 20 degrees I don't remember
  3283. 2:18:07exactly but it was it was down well
  3284. 2:18:09below the temperatures and we we could
  3285. 2:18:11see what the change in durometer was
  3286. 2:18:14with temperature
  3287. 2:18:15we did have the two tests we had run
  3288. 2:18:17with the fixed joint at 30 degrees to
  3289. 2:18:20indicate that the O-ring would would
  3290. 2:18:22seal if it moved in in the right timing
  3291. 2:18:25but she said that at the time you
  3292. 2:18:27weren't you weren't uh weren't uh
  3293. 2:18:30putting much emphasis on those tests
  3294. 2:18:33there were six plates in front of the
  3295. 2:18:36thing you're using the Argon gas not the
  3296. 2:18:37three ounce by that time we were trying
  3297. 2:18:40to avoid over emphasizing that test is
  3298. 2:18:43perhaps a better way to say it we wanted
  3299. 2:18:45to make sure we recognized that it
  3300. 2:18:47wasn't a totally representative test
  3301. 2:18:49because it didn't have the joint
  3302. 2:18:51rotation on the other hand we felt
  3303. 2:18:53because it was at the temperature and
  3304. 2:18:56did indicate that the O-ring would seal
  3305. 2:18:58if the timing was proper so that the
  3306. 2:19:01O-ring was in position before the joint
  3307. 2:19:03rotated we expected the seal fed did you
  3308. 2:19:06have data that would show you how the
  3309. 2:19:08joint would rotate at those temperatures
  3310. 2:19:11well we know how the joint rotation I
  3311. 2:19:14don't believe there's any real effect of
  3312. 2:19:16temperature on the joint rotation if
  3313. 2:19:19anything it would slow it down had that
  3314. 2:19:21analysis went down the joint rotation
  3315. 2:19:24analysis to see what the temperature
  3316. 2:19:26effect on on joint rotation is
  3317. 2:19:29I do not believe that's been done how
  3318. 2:19:32about the uh any tests or analysis to
  3319. 2:19:34determine what the timing function would
  3320. 2:19:36be at those temperatures had those been
  3321. 2:19:38done at the time well there had it not
  3322. 2:19:40have been done at the time we were in
  3323. 2:19:42the process of devising the test to try
  3324. 2:19:45to establish that
  3325. 2:19:47so those tests hadn't been done when you
  3326. 2:19:50made this decision they had not been
  3327. 2:19:52done well I I better not go beyond my
  3328. 2:19:55knowledge on the subject uh I don't know
  3329. 2:19:58personally what How Far We've progressed
  3330. 2:20:01in the in the timing test I can say this
  3331. 2:20:05we didn't have enough information that
  3332. 2:20:08we could quantify the the effect of the
  3333. 2:20:12cold okay you said that that your
  3334. 2:20:15previous uh you had a a factor of three
  3335. 2:20:18safety in in Seal erosion that sounds to
  3336. 2:20:22me like you were willing to accept
  3337. 2:20:23damage to a criticality one system
  3338. 2:20:26did you have any prediction of what the
  3339. 2:20:28seal erosion would be or any again test
  3340. 2:20:31or analysis on what seal erosion would
  3341. 2:20:33would be under these conditions or were
  3342. 2:20:36you extrapolating from the 53 degree
  3343. 2:20:38temperature and did you have a model to
  3344. 2:20:40do that extrapolation
  3345. 2:20:41[Applause]
  3346. 2:20:43well that's a lot of questions
  3347. 2:20:45um
  3348. 2:20:46we
  3349. 2:20:49we were we had done some modeling of the
  3350. 2:20:52uh of the flow in the in the Overflow
  3351. 2:20:58effect on the O-ring
  3352. 2:21:00and and I'm not qualified to really talk
  3353. 2:21:04about it and if that in detail but the
  3354. 2:21:06engineers when they get here can provide
  3355. 2:21:09more detail on that
  3356. 2:21:11um
  3357. 2:21:12I've lost track of the uh try to answer
  3358. 2:21:15all your questions and I have lost track
  3359. 2:21:18and could you ask me again okay the
  3360. 2:21:21first one I guess I was asking about was
  3361. 2:21:23the the seal erosion do you know that
  3362. 2:21:25whether you had any test date on the
  3363. 2:21:26seal erosion well I know we had a lot of
  3364. 2:21:29information as I said where we had had
  3365. 2:21:32focused deliberately focused uh hot
  3366. 2:21:36gases to see what how fast the water
  3367. 2:21:39Road what kind of gas flow rates were
  3368. 2:21:41necessary
  3369. 2:21:42and uh
  3370. 2:21:45that's on on erosion so let me ask a
  3371. 2:21:48different different sort of question
  3372. 2:21:51um were you willing to accept damage to
  3373. 2:21:55a criticality one system it sounds it
  3374. 2:21:58sounds as though
  3375. 2:21:59um you were willing to allow erosion on
  3376. 2:22:02the primary o-ring
  3377. 2:22:04the answer has to be yes now let me uh
  3378. 2:22:08explain that the position we were in is
  3379. 2:22:12that the first thing that has to happen
  3380. 2:22:14is you have to have the a below uh hole
  3381. 2:22:18through the putty
  3382. 2:22:20and uh our experience is that that
  3383. 2:22:23happens
  3384. 2:22:25like five percent of the time I don't
  3385. 2:22:28have that number exactly but if you look
  3386. 2:22:30at our our history in the flight Motors
  3387. 2:22:33that's like five percent of the time
  3388. 2:22:35when that happens you can either get no
  3389. 2:22:39effect just simply yes the hot gas
  3390. 2:22:42pressurizes the O-ring or you can get
  3391. 2:22:45blow-by and then the O-ring seats or you
  3392. 2:22:48can get erosion
  3393. 2:22:50and we had erosion if the memory serves
  3394. 2:22:53me four times
  3395. 2:22:54uh in the in the some 144 joints we'd
  3396. 2:23:00had
  3397. 2:23:00so we uh we we recognized that we might
  3398. 2:23:06get
  3399. 2:23:07some erosion
  3400. 2:23:09we also recognize that it was a low
  3401. 2:23:13frequency event
  3402. 2:23:15and that but that the possibility
  3403. 2:23:17existed and that if it did happen if we
  3404. 2:23:21had erosion that it would in our opinion
  3405. 2:23:24seal
  3406. 2:23:25because of the extra margin that we'd
  3407. 2:23:29identified by running the tests on the
  3408. 2:23:31amount of flow it would take to get
  3409. 2:23:34enough erosion to actually keep the
  3410. 2:23:36primary from seeding
  3411. 2:23:38[Music]
  3412. 2:23:40I guess what I'm what I'm really trying
  3413. 2:23:42to understand and
  3414. 2:23:44um is
  3415. 2:23:47whether you really had the engineering
  3416. 2:23:49data
  3417. 2:23:50or an engineering analysis
  3418. 2:23:52to back up the decision that this
  3419. 2:23:56criticality one system was safe to fly
  3420. 2:24:00at those temperatures you know what
  3421. 2:24:02we've seen in the chart so far is that
  3422. 2:24:03the data was inconclusive so you said go
  3423. 2:24:06ahead uh you know no yeah I'm sorry that
  3424. 2:24:09I would hope to convey that but
  3425. 2:24:12the the reason for the discussion was
  3426. 2:24:15the fact that we didn't have enough data
  3427. 2:24:19to quantify the effect of the cold
  3428. 2:24:22and that was that was the heart of our
  3429. 2:24:25discussion is how much effect is the
  3430. 2:24:28cold going to have on the performance
  3431. 2:24:31and the question
  3432. 2:24:34um
  3433. 2:24:35your engineers with the data they had
  3434. 2:24:38and with the concerted attemption did
  3435. 2:24:41reach a tentative conclusion at least
  3436. 2:24:43that's why not wait for at least the
  3437. 2:24:46temperature that had already been
  3438. 2:24:48flowing
  3439. 2:24:49um
  3440. 2:24:50yeah I guess you were responsible your
  3441. 2:24:54engineers were responsible for the
  3442. 2:24:56design
  3443. 2:24:56and the testing and qualification of
  3444. 2:24:59that design and I would assume the
  3445. 2:25:01interpretation of the data
  3446. 2:25:04and therefore I'm extremely puzzled why
  3447. 2:25:07um
  3448. 2:25:08uh a NASA person could disagree and ask
  3449. 2:25:12you to uh
  3450. 2:25:13review
  3451. 2:25:15the decision your engineers had reached
  3452. 2:25:17since it seemed to me theirs was the
  3453. 2:25:19responsibility for the design
  3454. 2:25:21well we let's say uh the the request to
  3455. 2:25:28reassess was
  3456. 2:25:29not a major factor in my view I the uh
  3457. 2:25:34the fact that we were
  3458. 2:25:37picking a temperature-based purely on
  3459. 2:25:40the one test or the one flight
  3460. 2:25:43and we've had uh we had
  3461. 2:25:47had static tests at other temperatures
  3462. 2:25:50and and Mr McDonald explained why we
  3463. 2:25:53didn't consider those conclusive but we
  3464. 2:25:56it was difficult to say that 53 degrees
  3465. 2:25:59was exactly the temperature that you
  3466. 2:26:02ought to fly at
  3467. 2:26:03and when Mr McDonald made the point
  3468. 2:26:06about the secondary o-ring being in a in
  3469. 2:26:10a favorable position
  3470. 2:26:12we felt it was appropriate to consider
  3471. 2:26:15that point and that's the reason that we
  3472. 2:26:18said well let's make sure that we've
  3473. 2:26:21considered everything
  3474. 2:26:23and the two things that came out of that
  3475. 2:26:25assessment were
  3476. 2:26:28that we did have we believed that we had
  3477. 2:26:32a margin a substantial margin of
  3478. 2:26:35allowable erosion and still have that
  3479. 2:26:38primary ring C concealed properly
  3480. 2:26:43we didn't know for sure that the what
  3481. 2:26:46the effect of that code was on the time
  3482. 2:26:49to move but we said if in fact it does
  3483. 2:26:53delay moving and it causes blow-by then
  3484. 2:26:57the secondary ring is already in
  3485. 2:27:00position the bobi who has to occur if it
  3486. 2:27:04occurs occurs immediately the Bovi
  3487. 2:27:07occurs on pressurization
  3488. 2:27:09and so under those conditions if you
  3489. 2:27:12were to have blow by you would be
  3490. 2:27:14seeding the the secondary now I
  3491. 2:27:16understand the the point about the the
  3492. 2:27:191R versus one I simply have to be honest
  3493. 2:27:22and say that we that's the way we were
  3494. 2:27:24looking at it then that that during the
  3495. 2:27:27ignition transient
  3496. 2:27:28that the the secondary really could
  3497. 2:27:32function and we had never said that it
  3498. 2:27:34couldn't function on the ignition trench
  3499. 2:27:38even when we wrote the Cil we'd
  3500. 2:27:40indicated that
  3501. 2:27:42um in any event we did expect the
  3502. 2:27:46primary deceit we expected to seat
  3503. 2:27:49because we had some Tolerance on the uh
  3504. 2:27:53on this ability to uh to erode and still
  3505. 2:27:57seats and seal
  3506. 2:27:59so those that was our that was our
  3507. 2:28:04thought process now the discussion was a
  3508. 2:28:07free open discussion with all the people
  3509. 2:28:10there and uh the I believe that it was
  3510. 2:28:16not a uh well I at that point it was
  3511. 2:28:19clear to me we were not going to get a
  3512. 2:28:20unanimous decision
  3513. 2:28:23um and so the question was
  3514. 2:28:27um did we have a reasonable uh position
  3515. 2:28:31to to go to 53 degrees or did we have
  3516. 2:28:34confidence that we could fly with a 29
  3517. 2:28:38degree o-ring
  3518. 2:28:39and uh the the people who were there had
  3519. 2:28:44heard all the discussion
  3520. 2:28:45so I concluded it was appropriate to
  3521. 2:28:48talk to to get a poll of the chief
  3522. 2:28:52engineer and the chief program manager
  3523. 2:28:54and Mr Wiggins who has a division
  3524. 2:28:57responsibility to see how they felt
  3525. 2:29:00whether they felt that we could safely
  3526. 2:29:03fly with all the information that had
  3527. 2:29:05been presented
  3528. 2:29:06and we did conduct that poll and then we
  3529. 2:29:11did conclude that it was it was safe to
  3530. 2:29:14Launch
  3531. 2:29:16could you tell us what the poll showed
  3532. 2:29:18you
  3533. 2:29:19you say that you and Mr kilmister and Mr
  3534. 2:29:22Wiggins
  3535. 2:29:23and Mr Lawrence were you unanimous how
  3536. 2:29:26about the others we will only hold the
  3537. 2:29:29management people because we had already
  3538. 2:29:31established that we were not going to be
  3539. 2:29:34unanimous and we'd already heard that
  3540. 2:29:37wasn't the question the question is what
  3541. 2:29:38about the others you testified before
  3542. 2:29:41that you thought probably all the
  3543. 2:29:44engineers
  3544. 2:29:45so were against the launch to all you
  3545. 2:29:47say you took a poll you only follow the
  3546. 2:29:50managers you didn't ask the engineers
  3547. 2:29:52how they felt after the review of the
  3548. 2:29:54data in that discussion I felt that
  3549. 2:29:57everyone had uh represented their
  3550. 2:30:00opinion and there are a number that I
  3551. 2:30:02felt indicated as we did that with the
  3552. 2:30:06consideration of the erosion margin
  3553. 2:30:09and well the very factors that I just
  3554. 2:30:11talked about they also considered that
  3555. 2:30:14to be a reasonable you know did they
  3556. 2:30:17express the change of mind did they say
  3557. 2:30:19well I've changed my mind
  3558. 2:30:21not per se
  3559. 2:30:23no uh okay excuse me I just feel that it
  3560. 2:30:28would it's the kind of discussion that
  3561. 2:30:30we we frequently have in which all of
  3562. 2:30:34the people Express their opinions and
  3563. 2:30:37they make them clear did you ever have
  3564. 2:30:39an experience where all the engineers
  3565. 2:30:40voted one way and management voted the
  3566. 2:30:42other
  3567. 2:30:45that wasn't the case here well what was
  3568. 2:30:47the case here looks that way it looks as
  3569. 2:30:49if you said the managers you pull be
  3570. 2:30:51unanimous and the engineers who were
  3571. 2:30:54opposed to launch were still apparently
  3572. 2:30:56opposed to it well there were some
  3573. 2:30:58Engineers which ones Mr Beaujolais and
  3574. 2:31:02Mr Thompson were the outspoken one no no
  3575. 2:31:05I'm asking which one has changed their
  3576. 2:31:07minds
  3577. 2:31:09before you testified that all the
  3578. 2:31:11engineers were opposed to Launch
  3579. 2:31:13now you went through this process you
  3580. 2:31:15just described at the commission my
  3581. 2:31:17question is did any of the engineers
  3582. 2:31:19change their minds and if so which ones
  3583. 2:31:23well let's say I
  3584. 2:31:27I would say then that uh
  3585. 2:31:31let's look at the list here it
  3586. 2:31:34I can
  3587. 2:31:36based on the conversations that we had
  3588. 2:31:39there
  3589. 2:31:43that uh
  3590. 2:31:45Mr Macbeth and cap
  3591. 2:31:48were supportive
  3592. 2:31:52and uh
  3593. 2:31:54Mr Brinton
  3594. 2:31:57who is at marshall
  3595. 2:31:59it's harder to judge because you didn't
  3596. 2:32:01he didn't have a lot to say the
  3597. 2:32:05what we were faced with is uh that there
  3598. 2:32:09was the outspoken individuals in the
  3599. 2:32:11rest uh participated to a lesser degree
  3600. 2:32:16but I believe that we are
  3601. 2:32:21familiar enough with the people in their
  3602. 2:32:23manner to be able to judge their their
  3603. 2:32:26feelings and we heard what they had to
  3604. 2:32:28say
  3605. 2:32:29facing earlier in testimony uh in
  3606. 2:32:33private session indicated that Mr
  3607. 2:32:34Beaujolais Mr Thompson were the most
  3608. 2:32:38knowledgeable on the seals is that
  3609. 2:32:39correct
  3610. 2:32:41yes then the two most knowledgeable
  3611. 2:32:44Engineers were still opposed and my
  3612. 2:32:47understanding if they were still
  3613. 2:32:48strongly opposed
  3614. 2:32:50uh why did you proceed in the light of
  3615. 2:32:53your two experts being very strongly
  3616. 2:32:56opposed well
  3617. 2:32:58um
  3618. 2:33:00the it's it's kind of a horse races to
  3619. 2:33:04who is the most expert on the subject
  3620. 2:33:06because they're different
  3621. 2:33:08areas of expertise some of the gas flow
  3622. 2:33:11some in the metal parts we identified
  3623. 2:33:14that Mr Beaujolais and Thompson were
  3624. 2:33:16both generally knowledgeable people on
  3625. 2:33:19those joints and they were they were
  3626. 2:33:21people that we whose opinion we regarded
  3627. 2:33:24however Mr cap
  3628. 2:33:26has uh the long history
  3629. 2:33:30on the joint and he's as knowledgeable
  3630. 2:33:32in my opinion as they are
  3631. 2:33:35and Mr Sayer uh to the lesser degree
  3632. 2:33:40so uh
  3633. 2:33:43I would say that we felt that uh
  3634. 2:33:47although they were outspoken
  3635. 2:33:50we listened to their reasons
  3636. 2:33:53uh more than the than the intensity
  3637. 2:33:57and the reasons boil down to the things
  3638. 2:33:59that I said the reason was the
  3639. 2:34:02uncertainty about the the rapidity with
  3640. 2:34:05which that primary would move
  3641. 2:34:08so
  3642. 2:34:09um did Mr Russell participate in the
  3643. 2:34:13conversation either on the telecon with
  3644. 2:34:16NASA or in the caucus
  3645. 2:34:19Ross line that followed
  3646. 2:34:22yes he he participated in the in the
  3647. 2:34:26both discussions my recollection what
  3648. 2:34:29were his views as far as you can
  3649. 2:34:31reconstruct them
  3650. 2:34:34I felt that uh
  3651. 2:34:36he
  3652. 2:34:38had the similar uh thoughts that we did
  3653. 2:34:43that he had the concern about the
  3654. 2:34:44uncertainty but beyond that uh
  3655. 2:34:50I would say that he was if anything
  3656. 2:34:52neutral that he was he was providing all
  3657. 2:34:56the information and was having some
  3658. 2:34:58difficulty as were the rest of us trying
  3659. 2:35:00to get to get a decision in which we had
  3660. 2:35:02confidence now during the telecon was
  3661. 2:35:06NASA
  3662. 2:35:07uh and during the private caucus offline
  3663. 2:35:12did anybody either at NASA or at
  3664. 2:35:15firecrawl
  3665. 2:35:18mentioned the change in the critical
  3666. 2:35:20items list to criticality one
  3667. 2:35:23no sir that was not discussed
  3668. 2:35:28but that was not an issue at that point
  3669. 2:35:34a question about the temperatures you
  3670. 2:35:38said that you decided that 29 degrees
  3671. 2:35:40was safe to launch the discussion result
  3672. 2:35:44in some lower temperature limits below
  3673. 2:35:46which you would have not have
  3674. 2:35:48recommended a launch
  3675. 2:35:52I'm sorry you're saying would we you're
  3676. 2:35:55you're ultimate recommendation to NASA
  3677. 2:35:58was that it was safe to launch and I
  3678. 2:36:00believe the predicted temperature of the
  3679. 2:36:02O-rings was 29 degrees that's correct
  3680. 2:36:04did your discussion uh result in the
  3681. 2:36:08establishment of a temperature below
  3682. 2:36:10which it would not have been safe to
  3683. 2:36:12Launch
  3684. 2:36:14no we didn't uh we didn't pursue it
  3685. 2:36:16below that I think that that the initial
  3686. 2:36:20concern when we had heard 18 degrees and
  3687. 2:36:22we were thinking that the O-ring might
  3688. 2:36:24be that cold
  3689. 2:36:26that's that's how all the discussion got
  3690. 2:36:29started and and there was a lot of
  3691. 2:36:31apprehension at 18 degrees
  3692. 2:36:33and then later found it was going to be
  3693. 2:36:35somewhat warmer than that but we didn't
  3694. 2:36:37uh pursue the idea of getting any colder
  3695. 2:36:41than 29 degrees
  3696. 2:36:43well you know how critical was this if
  3697. 2:36:45the temperature turned out to be 28
  3698. 2:36:47degrees would this have made a big
  3699. 2:36:48difference
  3700. 2:36:49the recommendation was based on a
  3701. 2:36:51prediction of course that was only
  3702. 2:36:53prediction at the time
  3703. 2:36:59and I would have thought that the
  3704. 2:37:01recommendation would have been more
  3705. 2:37:03specific so that uh depending on the
  3706. 2:37:06exact conditions which prevailed when
  3707. 2:37:08the launch occurred the recommendation
  3708. 2:37:10would have been one which could have
  3709. 2:37:11been used to make a decision
  3710. 2:37:14[Applause]
  3711. 2:37:15well I can't argue with that reasoning
  3712. 2:37:18we just simply didn't address we
  3713. 2:37:21we were addressing that the specific
  3714. 2:37:24condition and uh not looking for uh for
  3715. 2:37:27a threshold but usually engineering
  3716. 2:37:30decisions and calculations are pretty
  3717. 2:37:32exact calculations and you usually have
  3718. 2:37:35a very specific number that's why there
  3719. 2:37:37are launch criteria and those numbers
  3720. 2:37:39are specific numbers they're not ranges
  3721. 2:37:42and here evidently you had a range but
  3722. 2:37:45you didn't even specify what that range
  3723. 2:37:47was wasn't that rather unusual
  3724. 2:37:49[Applause]
  3725. 2:37:52yes I would say that was the fact that
  3726. 2:37:55we were focused on that at one point and
  3727. 2:37:58uh that's what we were addressing
  3728. 2:37:59normally
  3729. 2:38:02uh if you were earlier
  3730. 2:38:06preparing for another lunch or something
  3731. 2:38:08if the question came much up you would
  3732. 2:38:10in fact tend to bracket it we were we
  3733. 2:38:13were faced with this we felt a specific
  3734. 2:38:15condition here
  3735. 2:38:17and that's the reason we addressed it
  3736. 2:38:19that way so you didn't feel
  3737. 2:38:20uncomfortable with this position
  3738. 2:38:23I didn't I felt that after we had had
  3739. 2:38:27hashed it out and understood it that uh
  3740. 2:38:31we the uh inability to precisely
  3741. 2:38:35quantify the movement of that primary
  3742. 2:38:39o-ring was the concern that we had
  3743. 2:38:43but and and that's that's the additional
  3744. 2:38:46knowledge that I would like to have had
  3745. 2:38:49but I felt that with what the things
  3746. 2:38:52that I've already pointed out that we
  3747. 2:38:54were we had a reasonable basis for a
  3748. 2:38:58feeling it was a fight it's amazing you
  3749. 2:39:01you used the word uncertainty four or
  3750. 2:39:03five times now in the last five minutes
  3751. 2:39:05and now you just had the inability to
  3752. 2:39:07quantify this thing that was the best
  3753. 2:39:09thing you had going for you you know
  3754. 2:39:11every launch has a risk uh but you you
  3755. 2:39:13take that risk because something must be
  3756. 2:39:15achieved what was driving here what was
  3757. 2:39:18to be achieved that uh caused you to go
  3758. 2:39:22well uh why wouldn't you wait a day
  3759. 2:39:28well I it as far as waiting a day is
  3760. 2:39:31concerned we wouldn't have gained any
  3761. 2:39:33more information uh but you know to
  3762. 2:39:36gained temperature you had them true
  3763. 2:39:38that's true and uh
  3764. 2:39:41we we had to decide whether we felt that
  3765. 2:39:44it was safe to fly a 29 in order to
  3766. 2:39:47respond to the question should we fly
  3767. 2:39:51that's that was what we were that was a
  3768. 2:39:54question that we were trying to answer
  3769. 2:40:01in responding to the General's question
  3770. 2:40:04uh about the the use of the word
  3771. 2:40:07inconclusive and uncertainty in your
  3772. 2:40:09hope
  3773. 2:40:10a presentation here today uh you're
  3774. 2:40:13basing your decisions on inconclusive
  3775. 2:40:15and uncertain information yet my
  3776. 2:40:18understanding of NASA's flight
  3777. 2:40:19philosophy is that decisions to go or no
  3778. 2:40:23go are based on certainties and
  3779. 2:40:25conclusions
  3780. 2:40:26uh when did this change in philosophy uh
  3781. 2:40:30affect your operations
  3782. 2:40:34well I would I have to respond I think
  3783. 2:40:37it's the case of degree of uncertainty
  3784. 2:40:39either or
  3785. 2:40:40there's always any degree of uncertainty
  3786. 2:40:43before you launch
  3787. 2:40:51case in the design and
  3788. 2:40:54testing and so forth of the the whole
  3789. 2:40:57system there have to be some
  3790. 2:40:58uncertainties it's it's a question of
  3791. 2:41:01degree and uh
  3792. 2:41:04but it seems to me there was a high
  3793. 2:41:05degree of uncertainty in your
  3794. 2:41:07calculations here well there was
  3795. 2:41:11regarding to your own testimony well
  3796. 2:41:14that's that of course is the is the the
  3797. 2:41:17point that we were we were struggling
  3798. 2:41:19with that night was what degree of
  3799. 2:41:21uncertainty is there
  3800. 2:41:23and uh the area was uncertainty was the
  3801. 2:41:26moving of that primary o-ring well how
  3802. 2:41:29would you characterize it as a high
  3803. 2:41:31degree a low degree or a medium degree
  3804. 2:41:33of uncertainty
  3805. 2:41:36as far as the probability of of seeding
  3806. 2:41:40is concerned I thought there was a low
  3807. 2:41:42degree of uncertainty
  3808. 2:41:43[Music]
  3809. 2:41:47Mr kilmister when he wrote the cell
  3810. 2:41:49facts that capture data not conclusive
  3811. 2:41:52on predicting primary o-ring Blow by
  3812. 2:41:56isn't that a
  3813. 2:41:57not a very serious statement just saying
  3814. 2:42:01that it was not conclusive isn't that
  3815. 2:42:04another way saying that
  3816. 2:42:05there might be a conclusion that there
  3817. 2:42:07was going to be primary o-ring before
  3818. 2:42:09well we what we did was say since it
  3819. 2:42:13wasn't conclusive we were going to
  3820. 2:42:15assume that it would have a negative
  3821. 2:42:17effect that's the way we approached it
  3822. 2:42:19in other words this is a statement
  3823. 2:42:21saying we expect the primary holding
  3824. 2:42:23Blow by we said
  3825. 2:42:25we said we can't tell how much effect
  3826. 2:42:28the temperature is going to have so we
  3827. 2:42:31better look
  3828. 2:42:32at what can happen if in fact it does so
  3829. 2:42:37if that's the case then Dr Rice
  3830. 2:42:40question is most relevant because the
  3831. 2:42:42critical items listed that you cannot
  3832. 2:42:44rely on this redundancy if you're
  3833. 2:42:47predicting there's a possibility of
  3834. 2:42:49primary o-ring Blow by
  3835. 2:42:51you're violating the critical items to
  3836. 2:42:55list
  3837. 2:42:58well and we weren't predicting it but we
  3838. 2:43:01were saying because we weren't able to
  3839. 2:43:04be certain
  3840. 2:43:05that the situation we were faced with is
  3841. 2:43:07we have had
  3842. 2:43:09Obi on earlier flights
  3843. 2:43:12we had not had any uh reason to believe
  3844. 2:43:18that we couldn't experience it again
  3845. 2:43:21at any temperature
  3846. 2:43:24that's where we were right then
  3847. 2:43:28and so we we had to say that we can
  3848. 2:43:31experience Blow by because we had
  3849. 2:43:34experienced it and we had not yet been
  3850. 2:43:37able to figure out what to do to prevent
  3851. 2:43:40it
  3852. 2:43:41so we we knew that it could happen and
  3853. 2:43:45so we had to say
  3854. 2:43:46what's the probability but even given a
  3855. 2:43:50low probability we still had to think
  3856. 2:43:53what's it going to mean if it does
  3857. 2:43:56and that's what we we endeavored to do
  3858. 2:43:59is to think what does it mean if it does
  3859. 2:44:00even if it's a low probability but I
  3860. 2:44:03don't want to continue the argument
  3861. 2:44:05seems to me though that the critical
  3862. 2:44:06items list says if that's the case
  3863. 2:44:09is going to result in the catastrophe
  3864. 2:44:12because there is no redundancy that was
  3865. 2:44:14the finding as I understand it am I
  3866. 2:44:17correct that Christ
  3867. 2:44:21that just reading the critical items
  3868. 2:44:24list
  3869. 2:44:25um what it says is that it's the primary
  3870. 2:44:28o-ring
  3871. 2:44:29which is a criticality one
  3872. 2:44:31not a criticality one r
  3873. 2:44:33ather if you just read it in that that
  3874. 2:44:36sense yes but if you if you know how we
  3875. 2:44:40generated which was that it was not
  3876. 2:44:43redundant full-time that it was only
  3877. 2:44:46redundant during the ignition transient
  3878. 2:44:49and then it was non-redone once the
  3879. 2:44:51joint opened up and we knew that
  3880. 2:44:54we understood that and uh
  3881. 2:44:57that entered our that did enter our
  3882. 2:44:59thinking
  3883. 2:45:00in that
  3884. 2:45:02discussing this idea that the secondary
  3885. 2:45:05seal which will seat the principle is
  3886. 2:45:08that it's located in the correct place
  3887. 2:45:10because of it crusher put on during
  3888. 2:45:13making a check which is two days or so
  3889. 2:45:16before launch
  3890. 2:45:18after the check has been made in the VAB
  3891. 2:45:21building this
  3892. 2:45:22machine is put on a carrier and carried
  3893. 2:45:26and jiggled and so forth all the way out
  3894. 2:45:28to the site stands there for two days
  3895. 2:45:31and has rained upon and we have found in
  3896. 2:45:33other cases that water gets into the
  3897. 2:45:35seal
  3898. 2:45:36did you consider it any when you were
  3899. 2:45:39discussing these the probability or the
  3900. 2:45:41possibility that it all is jiggling and
  3901. 2:45:43then the water inside there freezing
  3902. 2:45:45making ice that it could have displaced
  3903. 2:45:47the secondary seal and that your
  3904. 2:45:50idea that the secondary steel isn't
  3905. 2:45:52exactly the right place and Will seat
  3906. 2:45:53immediately during that short Transit
  3907. 2:45:56might have even more uncertainty were
  3908. 2:45:58you considering that those possibilities
  3909. 2:46:00well we were not considering the
  3910. 2:46:02possibility of ice in the in the joint
  3911. 2:46:08um
  3912. 2:46:09they we did not discuss the the
  3913. 2:46:13potential for how much the O-ring might
  3914. 2:46:16move uh as a point of of rolling it out
  3915. 2:46:19although I think the feeling is that
  3916. 2:46:21that's pretty stiff going but doesn't
  3917. 2:46:23see any real movement but we did not
  3918. 2:46:25consider the possibility of ice in the
  3919. 2:46:27joint
  3920. 2:46:29interruption
  3921. 2:46:32approaches to Performance
  3922. 2:46:35expansions envelope expansions in case
  3923. 2:46:38of airplanes or component performance
  3924. 2:46:41envelope expansions normally take the
  3925. 2:46:45position well I flown in these places
  3926. 2:46:46and based on that and my analysis of
  3927. 2:46:50results of those flights I would be
  3928. 2:46:52willing to go this much farther for the
  3929. 2:46:55next case
  3930. 2:46:57but yet your your Engineering Group said
  3931. 2:47:00they wouldn't be willing to go outside
  3932. 2:47:02their existing experience race or
  3933. 2:47:05recommended that they not originally and
  3934. 2:47:07later you said well we'll go this much
  3935. 2:47:09more
  3936. 2:47:13was there a
  3937. 2:47:14before the fact
  3938. 2:47:16any evidence or any attempt let's say to
  3939. 2:47:21provide a level of expansion which the
  3940. 2:47:26company could stand behind
  3941. 2:47:28well there was work underway to get a
  3942. 2:47:31better understanding of all overall
  3943. 2:47:33performance to that joint defective
  3944. 2:47:35rotation and effects of cancer that that
  3945. 2:47:38was the program that was uh kicked off
  3946. 2:47:42after the August
  3947. 2:47:44meeting at headquarters where all of the
  3948. 2:47:47joint designs and performance was
  3949. 2:47:49reviewed
  3950. 2:47:51then there was a program plan put
  3951. 2:47:53together to look at ways to improve the
  3952. 2:47:57performance and to get a more Fuller
  3953. 2:48:01understanding that was underway but we
  3954. 2:48:05didn't have the data the reasons that
  3955. 2:48:07they didn't exist after you've flown as
  3956. 2:48:10you say 144 joints or whatever could you
  3957. 2:48:14attribute that to some uh some reason
  3958. 2:48:16was it
  3959. 2:48:18that you weren't interested or didn't
  3960. 2:48:20think it was important or that you
  3961. 2:48:23didn't have the resources or how would
  3962. 2:48:25you characterize the fact that you were
  3963. 2:48:26only as far as long as you were
  3964. 2:48:29well
  3965. 2:48:31it expanded along a fairly long period
  3966. 2:48:34of time but there had been
  3967. 2:48:36a fairly long period where we had made
  3968. 2:48:40some improvements
  3969. 2:48:41in the layup of the putty
  3970. 2:48:44we didn't put some controls on the time
  3971. 2:48:47it could be exposed and that sort of
  3972. 2:48:48thing we've tried to make some changes
  3973. 2:48:50that were not
  3974. 2:48:52a risk of uh of going the wrong
  3975. 2:48:56direction but we had high confidence
  3976. 2:48:59we're going in the right direction and
  3977. 2:49:01we had to have we're having a long
  3978. 2:49:03period of not having any any erosion or
  3979. 2:49:06Bovi
  3980. 2:49:08inside of that in the middle of that
  3981. 2:49:11period in the August
  3982. 2:49:14time period we still concluded that we
  3983. 2:49:17needed to proceed with an aggressive
  3984. 2:49:20effort
  3985. 2:49:21so there was a I say a little colon tug
  3986. 2:49:24there in that at that time the
  3987. 2:49:26performance was running pretty well but
  3988. 2:49:28at the same time they now said we needed
  3989. 2:49:30to get on with some improvements and we
  3990. 2:49:33were searching from improvements that we
  3991. 2:49:36could could prove out without running
  3992. 2:49:38any any risks on the flight
  3993. 2:49:42Mr McDonald
  3994. 2:49:45stated that he did feel some pressure in
  3995. 2:49:49this meeting and uh
  3996. 2:49:53would you characterize your own feelings
  3997. 2:49:56about pressure that may have influenced
  3998. 2:49:59the decision process in any way
  3999. 2:50:03I thought a lot about that and uh
  4000. 2:50:07and there was some pressure but I
  4001. 2:50:09believe it's in the in the range of what
  4002. 2:50:12we abnormally encounter there's a
  4003. 2:50:15whenever we're taking a position
  4004. 2:50:18of NASA tests us on that position
  4005. 2:50:22explain it justify it that sort of thing
  4006. 2:50:25and that's the way I perceived we were
  4007. 2:50:29being tested is how supportive uh how
  4008. 2:50:33well can we justify our position
  4009. 2:50:36and uh so we responded in that fashion
  4010. 2:50:40now
  4011. 2:50:43I can say I guess that I I get pressures
  4012. 2:50:48in a lot of cases for a lot of decisions
  4013. 2:50:50not just from NASA but from any people I
  4014. 2:50:54deal with my boss and so forth and I
  4015. 2:50:56think that I'm able to
  4016. 2:50:58treat that properly and make the Sound
  4017. 2:51:02Decision uh independent of that
  4018. 2:51:05well let me be more specific to follow
  4019. 2:51:07up
  4020. 2:51:10do you do you think uh schedule pressure
  4021. 2:51:14or cost pressure had significant
  4022. 2:51:16influences on in this instance
  4023. 2:51:19[Music]
  4024. 2:51:20cost pressure definitely was had no
  4025. 2:51:23bearing on it
  4026. 2:51:25from a schedule standpoint we we take a
  4027. 2:51:29lot of pride in the fact that we
  4028. 2:51:30supported all of the launches to date
  4029. 2:51:34and if there was any pressure we wanted
  4030. 2:51:37to we wanted to continue to do the job
  4031. 2:51:40we had been doing
  4032. 2:51:41and that that kind of situation exists
  4033. 2:51:45every time we happen to say are we ready
  4034. 2:51:49to fly or are we not and we want to be
  4035. 2:51:51ready to fly but we want to make sure
  4036. 2:51:52it's safe
  4037. 2:51:57anybody get in touch with you any calls
  4038. 2:51:59of any kind urging you to go ahead with
  4039. 2:52:01this launch
  4040. 2:52:02no sir as far as you know where any such
  4041. 2:52:05calls made to anybody in Cycles
  4042. 2:52:08that's my knowledge there were none the
  4043. 2:52:10only conversations we had were the ones
  4044. 2:52:13on the net that have already been
  4045. 2:52:14reported just one other question
  4046. 2:52:19did you realize in particularly a view
  4047. 2:52:21of Mr Hardy's point that they wouldn't
  4048. 2:52:23launch unless you agreed
  4049. 2:52:26you fully realize that in effect you
  4050. 2:52:29were making the decision to launch you
  4051. 2:52:31and your colleague
  4052. 2:52:33yes sir
  4053. 2:52:37I had 200 brief questions just like the
  4054. 2:52:41return to your analysis of the data
  4055. 2:52:43during your uh half an hour uh caucus uh
  4056. 2:52:48in regard to the uh imprecision or
  4057. 2:52:52uncertainty of the data is it not the
  4058. 2:52:54case that the largest amount of blow by
  4059. 2:52:57was associated with the coldest launch
  4060. 2:52:59and that point was made by some of the
  4061. 2:53:01engineers in the discussion why did you
  4062. 2:53:04not consider that conclusive well
  4063. 2:53:08we did consider but we we didn't
  4064. 2:53:10consider conclusive simply because we'd
  4065. 2:53:12had Bovi at the at the warmer
  4066. 2:53:14temperature and we have erosion at
  4067. 2:53:16varying temperatures but the largest
  4068. 2:53:18amount of blowby was at the lowest
  4069. 2:53:20temperature right right actually the
  4070. 2:53:22erosion is is more of a concern than the
  4071. 2:53:25Blow Bar in fact let's let's turn to the
  4072. 2:53:27erosion uh Mr McDonald just stated that
  4073. 2:53:30there was a case uh earlier in which uh
  4074. 2:53:35the primary o-ring on the motor seal was
  4075. 2:53:39on the
  4076. 2:53:41lowest seal was eroded and only the
  4077. 2:53:45secondary o-ring prevented a burn
  4078. 2:53:46through and since you could not really
  4079. 2:53:49rely on the secondary O-ring for the
  4080. 2:53:51other seals was that not also a very
  4081. 2:53:54significant parameter I noticed that is
  4082. 2:53:56not mentioned at all in your analysis of
  4083. 2:54:00your half an hour caucus
  4084. 2:54:04well first we were we were considering
  4085. 2:54:07the The Joint seal and uh as Mr McDonald
  4086. 2:54:11pointed out we had concluded that uh the
  4087. 2:54:16the most likely cause of the nozzle
  4088. 2:54:19problem nozzle joint problem was the
  4089. 2:54:21fact that we had tested in a low
  4090. 2:54:23pressure and probably had not had a seal
  4091. 2:54:26of the primary we had not confirmed that
  4092. 2:54:28seal and we'd subsequently gone to a
  4093. 2:54:32higher pressure the 200 PSI to be sure
  4094. 2:54:35that the seals were proper rather than
  4095. 2:54:39be matched by the putting what we found
  4096. 2:54:41was that at the lower pressures down to
  4097. 2:54:44100 PSI the putty could actually hold
  4098. 2:54:48the pressure and so you weren't certain
  4099. 2:54:50that the primary was seating
  4100. 2:54:53so we had to go to the higher pressure
  4101. 2:54:55which we knew the putty would not hold
  4102. 2:54:57and with that we could be sure the
  4103. 2:54:59O-ring was seating
  4104. 2:55:01so our feeling on the nozzle joint was
  4105. 2:55:04that that problem had been a product of
  4106. 2:55:06not having properly a proper ceiling
  4107. 2:55:09primary o-ring and it hadn't been tested
  4108. 2:55:12adequately because it was masked by the
  4109. 2:55:15putty but was that incident discussed
  4110. 2:55:17during this half an hour caucus it was
  4111. 2:55:19not discussed uh no sir we were we were
  4112. 2:55:22talking about the joint it was of course
  4113. 2:55:24known by everyone that that had occurred
  4114. 2:55:28information can you recall any previous
  4115. 2:55:31occasion when you're
  4116. 2:55:33uh
  4117. 2:55:35at least preliminary advice to NASA had
  4118. 2:55:38been not to launch and they wish to go
  4119. 2:55:41ahead of the launch
  4120. 2:55:43no sir I do not
  4121. 2:55:46was there any comment made during these
  4122. 2:55:48conversations that you've described with
  4123. 2:55:51NASA that this is a very unusual
  4124. 2:55:53situation
  4125. 2:55:56did anyone for example say that it's odd
  4126. 2:55:58that the shoe is on this foot
  4127. 2:56:02no not in that fashion no it was a
  4128. 2:56:07the situation
  4129. 2:56:09I felt sure future was clear because the
  4130. 2:56:13conversations that have gone on in the
  4131. 2:56:15discussions by all the people about how
  4132. 2:56:18they felt and the data they had was all
  4133. 2:56:21on the net so it was understood
  4134. 2:56:23where we were coming from
  4135. 2:56:28one question from
  4136. 2:56:29uh
  4137. 2:56:31in
  4138. 2:56:33the analysis to get ready for launch
  4139. 2:56:36there was this one statement that uh
  4140. 2:56:40temperature concerns were maybe fuzzy
  4141. 2:56:43because there was a blow-by or erosion
  4142. 2:56:46at a 53 degree launch but there is also
  4143. 2:56:49one at 75 degrees
  4144. 2:56:52I'm just
  4145. 2:56:54wondering whether getting a blow-by
  4146. 2:56:58erosion at a very good warm temperature
  4147. 2:57:00where everything could be working quite
  4148. 2:57:02well wouldn't that raise concerns that
  4149. 2:57:04maybe the system was running um
  4150. 2:57:07quite largely and then maybe temperature
  4151. 2:57:10would really put it in a submarginal
  4152. 2:57:12condition
  4153. 2:57:14that's one question the other one I have
  4154. 2:57:16is in this package you gave us it looks
  4155. 2:57:19as you proceed through the checks of the
  4156. 2:57:22um
  4157. 2:57:24Motors more erosion
  4158. 2:57:27and blow by
  4159. 2:57:29was occurring more recently than in
  4160. 2:57:31earlier times and the design changes
  4161. 2:57:34like the reduction of the structural
  4162. 2:57:37strength of the motors of the of the um
  4163. 2:57:40of the other cases the increase of the
  4164. 2:57:42thrust
  4165. 2:57:44was there a concern that I call that
  4166. 2:57:46perhaps as time was going on and the
  4167. 2:57:49system was asking to perform better that
  4168. 2:57:52perhaps the seal was getting in more
  4169. 2:57:54trouble I'm just trying to understand
  4170. 2:57:55was there that concern or uh were you
  4171. 2:57:58becoming more relaxed
  4172. 2:58:00[Music]
  4173. 2:58:01um
  4174. 2:58:02I I would say when we put it all
  4175. 2:58:05together in August
  4176. 2:58:08we
  4177. 2:58:09we indicated that we had a concern and
  4178. 2:58:13that we needed to work on an improvement
  4179. 2:58:16we also in that summary said that we
  4180. 2:58:20felt that it was safe to continue to fly
  4181. 2:58:23as long as we had proper conditions that
  4182. 2:58:26is the 200 PSI leak test of proper
  4183. 2:58:29assembly and that sort of thing so we
  4184. 2:58:32were we we endeavored to summarize where
  4185. 2:58:36we were
  4186. 2:58:37in that August meeting because we looked
  4187. 2:58:39at all three joints we looked at the
  4188. 2:58:41field joints looked at the nozzle joint
  4189. 2:58:44and we looked at the igniter joint we
  4190. 2:58:46looked at all our history
  4191. 2:58:47and quoting the history that you have
  4192. 2:58:50here
  4193. 2:58:51and uh made our assessment and
  4194. 2:58:54identified that we
  4195. 2:58:56ought to proceed in an orderly fashion
  4196. 2:58:58but aggressively to to make an
  4197. 2:59:01improvement in the joint well in in the
  4198. 2:59:03August meeting then were there some
  4199. 2:59:06ground rules
  4200. 2:59:07lay down
  4201. 2:59:09like like good inspections and the other
  4202. 2:59:13conditions to keep flying yes
  4203. 2:59:19what are do we have a record of what
  4204. 2:59:22those holidays it's in the august 19
  4205. 2:59:25briefing that we have provided copies to
  4206. 2:59:28the commission on
  4207. 2:59:29and it's it's uh maybe everything on
  4208. 2:59:32temperature
  4209. 2:59:34no uh in fact in the copies that we
  4210. 2:59:38provided we also put in a February 10th
  4211. 2:59:42set of pages
  4212. 2:59:44uh reflecting the uh things that had
  4213. 2:59:48happened since and in there we said that
  4214. 2:59:51that's the condition that we should have
  4215. 2:59:52as long as the blue pages are they not
  4216. 2:59:54correct right
  4217. 2:59:57that's cute
  4218. 3:00:00Mason in in testimony that the committee
  4219. 3:00:03has received an executive session and
  4220. 3:00:04also in personal notes made available
  4221. 3:00:07who characterizes telling
  4222. 3:00:10Mr Lund in this caucus to take off his
  4223. 3:00:12engineering had improvements management
  4224. 3:00:14hat as part of that final management
  4225. 3:00:16caucus
  4226. 3:00:18in fact in your notes here from your
  4227. 3:00:20your presentation from your charts
  4228. 3:00:23you indicate that you
  4229. 3:00:25have asked them to exercise best
  4230. 3:00:27judgment and make management
  4231. 3:00:28recommendation
  4232. 3:00:30now since Mr Lund was your vice
  4233. 3:00:32president of engineering
  4234. 3:00:34and since he presented the charts and
  4235. 3:00:36the recommendations not to launch
  4236. 3:00:38outside your ex experience today
  4237. 3:00:41that is below a temperature of 53
  4238. 3:00:43degrees for the O-rings
  4239. 3:00:44in the previous 845 Eastern Standard
  4240. 3:00:47Time teleconference what did you have in
  4241. 3:00:50mind when you asked him to take off his
  4242. 3:00:52engineering hat and put on his
  4243. 3:00:54management hat I had in mind the fact
  4244. 3:00:57that we had identified that we could not
  4245. 3:01:01quantify the movement of that Prime of
  4246. 3:01:06the time for movement of their primary
  4247. 3:01:07we couldn't we didn't have the data to
  4248. 3:01:10do that and therefore it was going to
  4249. 3:01:12take a judgment rather than a precise
  4250. 3:01:15engineering calculation in order to
  4251. 3:01:17conclude what we needed to conclude
  4252. 3:01:22what triggered the caucus that phone
  4253. 3:01:24call asked for according to testimony
  4254. 3:01:26was the fact that NASA had expressed
  4255. 3:01:28surprise concern about the impact of
  4256. 3:01:31such a recommendation of not launching
  4257. 3:01:33below a 53 degree Fahrenheit temperature
  4258. 3:01:35for the O-ring and particularly impact
  4259. 3:01:38on schedule
  4260. 3:01:39during the 30-minute caucus was there
  4261. 3:01:41any part of your discussion that
  4262. 3:01:43addressed that impact on schedule and
  4263. 3:01:46what that meant to Firefall any
  4264. 3:01:48management concern on that
  4265. 3:01:50well when you say what what triggers the
  4266. 3:01:53caucus uh was not this expression of
  4267. 3:01:57concern in fact there's a bit of irony
  4268. 3:02:00but they that from my viewpoint the
  4269. 3:02:02primary trigger was Mr McDonald's
  4270. 3:02:05comment about the fact that the
  4271. 3:02:06secondary was in the in a
  4272. 3:02:09preferred position and that's the point
  4273. 3:02:12that we had not actively considered in
  4274. 3:02:15our previous discussion
  4275. 3:02:18but what's the answer to the question
  4276. 3:02:19though I thought we had previous
  4277. 3:02:21testimonies that's what triggered it
  4278. 3:02:22regardless of what triggered it
  4279. 3:02:24considering those concerns were
  4280. 3:02:26expressed was there discussion and a
  4281. 3:02:28sign called caucus with respect to
  4282. 3:02:30schedule and the impact of sticking to a
  4283. 3:02:3253 degree Fahrenheit temperature is a
  4284. 3:02:34launch condition and what that meant no
  4285. 3:02:38there was not no discussion of
  4286. 3:02:39scheduling oh we simply addressed the
  4287. 3:02:41the issue of flight safety Mr Mason
  4288. 3:02:45Wendy to Lund
  4289. 3:02:47and
  4290. 3:02:49tell them in effect the takeoff is
  4291. 3:02:51engineering head and put on his
  4292. 3:02:53management hat
  4293. 3:02:55wasn't that pressure on your part to a
  4294. 3:02:59subordinate that he should change his
  4295. 3:03:01mind
  4296. 3:03:03well I hope not but it could be
  4297. 3:03:06interpreted that way
  4298. 3:03:08but so any other
  4299. 3:03:10uh that's the journey we reconvene at
  4300. 3:03:13one o'clock and three two o'clock excuse
  4301. 3:03:15me and uh we plan to have Mr Bush away
  4302. 3:03:20Mr Thompson Mr Lund after lunch
  4303. 3:03:27[Music]
  4304. 3:03:54[Music]
  4305. 3:04:15thank you
  4306. 3:04:18in that case
  4307. 3:04:22[Music]
  4308. 3:04:31virtually grab some ghettos just move a
  4309. 3:04:34mic over so you each have a microphone
  4310. 3:04:42[Music]
  4311. 3:04:47okay the commission come to order please
  4312. 3:04:52[Music]
  4313. 3:05:03[Music]
  4314. 3:05:12they're now present employed by Point
  4315. 3:05:15Cycles yes I am and how long have you
  4316. 3:05:18been employed by the approximately five
  4317. 3:05:19and a half years how many five and a
  4318. 3:05:22half years and what's your present
  4319. 3:05:23position
  4320. 3:05:25I'm a senior scientist it's my title I'm
  4321. 3:05:28basically a staff member to the manager
  4322. 3:05:30of Applied mechanics
  4323. 3:05:32and what kind of work have you been
  4324. 3:05:34doing for the last five years
  4325. 3:05:36I have been involved in the joints I
  4326. 3:05:39have gone down to the cape and taken a
  4327. 3:05:42significant amount of inspections of the
  4328. 3:05:44solid rocket boosters as they've come
  4329. 3:05:46back from flights
  4330. 3:05:48I reported on that information and that
  4331. 3:05:50information has been used in the
  4332. 3:05:51flavoring is reviews for the next flight
  4333. 3:05:54I've also participated in some of the
  4334. 3:05:56structural analysis
  4335. 3:05:59also was one of the primary directors of
  4336. 3:06:03the refurbishment specification on the
  4337. 3:06:05cases themselves particularly in the
  4338. 3:06:07area of the of the joints
  4339. 3:06:10I have given made a videotape and have
  4340. 3:06:13given a presentation
  4341. 3:06:15at our plant also at Vandenberg in a KSC
  4342. 3:06:19concerning the inspection
  4343. 3:06:20characteristics of the joint surfaces
  4344. 3:06:23themselves
  4345. 3:06:24I have been appointed as a member of the
  4346. 3:06:28special steel task force that was
  4347. 3:06:30initiated last August and I'm in that
  4348. 3:06:33position currently
  4349. 3:06:35you've been described
  4350. 3:06:37in previous testimony is
  4351. 3:06:40either the leading or a-leading
  4352. 3:06:44expert on the subject of seals and
  4353. 3:06:46joints and the booster rocket uh
  4354. 3:06:50have an idea that Mr Thompson works with
  4355. 3:06:54you in this connection uh Arnie used to
  4356. 3:06:57be my supervisor I used to work at the
  4357. 3:06:58end of approximately two years ago
  4358. 3:07:00and uh I went out of that capacity it's
  4359. 3:07:04like I said about two years ago Mr
  4360. 3:07:06Thompson you want to give a little
  4361. 3:07:08background of your own experience how
  4362. 3:07:10long have you been with cycle been a
  4363. 3:07:12cycle 21 years how many 31 21 years 21
  4364. 3:07:15years and during that time well what's
  4365. 3:07:18your present uh I'm supervisor for
  4366. 3:07:21structures design for rocket motor cases
  4367. 3:07:25metallic rocket motor cases
  4368. 3:07:28how many men work for you now about 25
  4369. 3:07:31people and are they mostly engineers
  4370. 3:07:35yes sir
  4371. 3:07:37[Music]
  4372. 3:07:40and have you had extensive experience in
  4373. 3:07:43the connection with the the
  4374. 3:07:45solid fuel booster rocket and the in the
  4375. 3:07:49O-rings and the seals that we've been
  4376. 3:07:51talking about
  4377. 3:07:52yes I would say so I've been involved
  4378. 3:07:55for about seven or eight years in the
  4379. 3:07:58case program I first came into it uh
  4380. 3:08:02right after the first hydroproof of the
  4381. 3:08:04cylindrical section
  4382. 3:08:09usually do you have Engineers working
  4383. 3:08:11for you or with you no I'm strictly in a
  4384. 3:08:14staff position at this present time
  4385. 3:08:19how do you want to go back a little bit
  4386. 3:08:21you've been doing some extra work in
  4387. 3:08:23connection with the uh with the sales
  4388. 3:08:26and the O-rings you want to describe
  4389. 3:08:29that as a result of my involvement in
  4390. 3:08:34Hardware inspections after the kit after
  4391. 3:08:36the vehicles had flown at Kennedy I got
  4392. 3:08:41involved
  4393. 3:08:42quite heavily in some of the flight
  4394. 3:08:44Readiness reviews that
  4395. 3:08:47presented problem areas with the seals
  4396. 3:08:49namely the erosion that was going on
  4397. 3:08:51we're going to move the microphone just
  4398. 3:08:53a little bit closer please good you know
  4399. 3:08:57I I was involved in going down to the
  4400. 3:08:59cape
  4401. 3:09:00and inspecting the hardware after it
  4402. 3:09:02flew and any of the hardware that
  4403. 3:09:06experience problems with the seals
  4404. 3:09:07namely erosion I was also involved in
  4405. 3:09:10the preparation sometimes the
  4406. 3:09:11presentations in Flight Readiness
  4407. 3:09:13reviews along with Al McDonald
  4408. 3:09:17so that you have have made some of the
  4409. 3:09:20actual inspections that we've been
  4410. 3:09:22talking about this morning in connection
  4411. 3:09:23with erosion and blow-wise and so forth
  4412. 3:09:25I was the person that was there when SRM
  4413. 3:09:2915 was disassembled I was the person
  4414. 3:09:32that inspected those joints and reported
  4415. 3:09:34on those joints took the samples of the
  4416. 3:09:37blackened grease characterized the
  4417. 3:09:39degrees of Arc that the black and Greece
  4418. 3:09:42existed directed The photographs taken
  4419. 3:09:44of the joint took the samples for
  4420. 3:09:47chemical analysis back to Morton's I
  4421. 3:09:49called for analysis of what the
  4422. 3:09:51blackened condition actually was and
  4423. 3:09:54then prepared the presentation to give
  4424. 3:09:56to Marshall on the condition of those
  4425. 3:09:59joints
  4426. 3:10:01so you've had as much first-hand
  4427. 3:10:03experience as probably anybody else in
  4428. 3:10:05the field that's correct
  4429. 3:10:12um
  4430. 3:10:13perhaps you could characterize for
  4431. 3:10:17the concern
  4432. 3:10:21and activities that went on with respect
  4433. 3:10:25to the joints starting back in the time
  4434. 3:10:28before the August of 85 times or
  4435. 3:10:31whatever before that work where you
  4436. 3:10:33should start
  4437. 3:10:35um yeah just
  4438. 3:10:37along about uh
  4439. 3:10:40srm8 thereabouts I could be off a
  4440. 3:10:43vehicle or two either way
  4441. 3:10:45uh we had previously to that experienced
  4442. 3:10:50putty going around the end of the
  4443. 3:10:53crevice
  4444. 3:10:54and up to the primary o-ring and
  4445. 3:10:57actually sometimes into the groove
  4446. 3:10:59and there was some concern expressed
  4447. 3:11:01about that situation because the putty
  4448. 3:11:04has a asbestos filler in it which is a
  4449. 3:11:07fiber store
  4450. 3:11:09concern was that the fibers might
  4451. 3:11:13interfere with the ceiling capability of
  4452. 3:11:16the O-ring
  4453. 3:11:17therefore a change was made
  4454. 3:11:20to lay up the putty in a little bit
  4455. 3:11:23different character on the end of the
  4456. 3:11:25clevis leg such that when you made it
  4457. 3:11:28you would not see that characteristic
  4458. 3:11:30amount of putty down there next to the
  4459. 3:11:32O-ring and by observation that intent
  4460. 3:11:35was successful because from that time on
  4461. 3:11:38I never saw putty past the chamber on
  4462. 3:11:41the end of the clevis leg and never
  4463. 3:11:43around the corner on the radio surface
  4464. 3:11:45and down towards the seal
  4465. 3:11:47then
  4466. 3:11:49we would report on the erosion
  4467. 3:11:52characteristics
  4468. 3:11:55on the fields as we observed them like I
  4469. 3:11:57said we photographed them
  4470. 3:11:59we documented the degree of our of any
  4471. 3:12:02of the damage both heat affected and
  4472. 3:12:04erosion the erosion generally is a very
  4473. 3:12:06localized
  4474. 3:12:09removal of the material in the O-rings
  4475. 3:12:11and it it goes some distance
  4476. 3:12:14longitudinally as the charge explained
  4477. 3:12:16that you have
  4478. 3:12:18and we would report on that and that
  4479. 3:12:20became a
  4480. 3:12:22focal point
  4481. 3:12:23for discussion as a problem area for the
  4482. 3:12:26next flight Readiness review
  4483. 3:12:27so basically that was my my task at that
  4484. 3:12:32time
  4485. 3:12:32who was there uh
  4486. 3:12:36an increase in concern in the mid 85 as
  4487. 3:12:41a result of the observations that you
  4488. 3:12:44and others have made yes if they're in
  4489. 3:12:4615 actually increase their concern
  4490. 3:12:48because that was the first time we had
  4491. 3:12:51actually penetrated a primary o-ring on
  4492. 3:12:53a field joint with heart gas and we had
  4493. 3:12:57a witness of that event because the
  4494. 3:12:59grease between the O-rings was blackened
  4495. 3:13:03just like coal for those Arc lengths
  4496. 3:13:05that were described in the charts and
  4497. 3:13:07that was so much more significant than
  4498. 3:13:09it had ever been seen before on any Blow
  4499. 3:13:12by on any joint when was that flight
  4500. 3:13:14that was a year ago last January and the
  4501. 3:13:18reason it was so vivid in my mind is
  4502. 3:13:19because I was at the cape prior to the
  4503. 3:13:22launch
  4504. 3:13:23giving the presentation to approximately
  4505. 3:13:25130 people at the launch facility on the
  4506. 3:13:29inspection techniques on the joint to be
  4507. 3:13:31used to ensure that any defects which
  4508. 3:13:34had been removed from the joint were
  4509. 3:13:36removed in a manner such that the
  4510. 3:13:38transition on the defect was very smooth
  4511. 3:13:41so that the elastomeric condition of the
  4512. 3:13:43O-ring could actually get into those
  4513. 3:13:45imperfections
  4514. 3:13:46because it had been smooth out and being
  4515. 3:13:49elastomer it would do just that
  4516. 3:13:51and uh I remember the watching the
  4517. 3:13:54launch in the launch I went out of the
  4518. 3:13:56VAB
  4519. 3:13:58and it was a afternoon launch my
  4520. 3:14:01recollection is sometime between one and
  4521. 3:14:02two o'clock in the afternoon I'm not
  4522. 3:14:04sure
  4523. 3:14:05but it was reasonably uh cool but yet I
  4524. 3:14:09went out without a suit Coke
  4525. 3:14:11uh during the presentation of that
  4526. 3:14:15vehicle after was inspected it was
  4527. 3:14:18calculated by the folks back at the
  4528. 3:14:21plant and he transferred folks that the
  4529. 3:14:24seal temperature
  4530. 3:14:25would have been approximately 53 degrees
  4531. 3:14:28for that launch and that was part of the
  4532. 3:14:30characterization of the presentation in
  4533. 3:14:33the flight rate industry View for the
  4534. 3:14:34next vehicle
  4535. 3:14:36now
  4536. 3:14:37that presentation
  4537. 3:14:40was a very
  4538. 3:14:41pointed discussion a very detailed
  4539. 3:14:44discussion
  4540. 3:14:46and quite frankly I commented to Elle
  4541. 3:14:48McDonald
  4542. 3:14:49once or twice that had I not been
  4543. 3:14:52personally there and been personally
  4544. 3:14:54witnessing what what I've seen in
  4545. 3:14:56presenting what I had physically seen I
  4546. 3:14:59don't think we could have been able to
  4547. 3:15:00convince NASA to continue to fly
  4548. 3:15:03uh I felt very strong about that fact
  4549. 3:15:06because I spoke from conviction and I
  4550. 3:15:09was challenged by just about everybody
  4551. 3:15:11in the room
  4552. 3:15:12about what I had reported and uh
  4553. 3:15:16I was very grateful that I was there and
  4554. 3:15:20was able to stick by my convictions
  4555. 3:15:22because I had seen
  4556. 3:15:23the condition of the joint Mr Rose lay
  4557. 3:15:26on 51c you saw a very blackened joint uh
  4558. 3:15:29two of them two of them however on 61a
  4559. 3:15:31the temperature was 75 degrees and that
  4560. 3:15:34has been used to uh minimize the effects
  4561. 3:15:36on on 51c saying that it occurs at the
  4562. 3:15:39warm temperature also would you explain
  4563. 3:15:41the difference that you saw or heard of
  4564. 3:15:42between the two joints yeah the
  4565. 3:15:44difference the srm-22 that was used as a
  4566. 3:15:48comparison basis was not one that I saw
  4567. 3:15:50personally but a junior engineer or a
  4568. 3:15:53younger I shouldn't say junior but a
  4569. 3:15:54younger engineer who works for Arne has
  4570. 3:15:57actually been at the cape and seen those
  4571. 3:15:59joints I questioned him
  4572. 3:16:02and ask him
  4573. 3:16:03to tell me in his words what he saw
  4574. 3:16:07what he told me was that he saw a light
  4575. 3:16:10grayish to dark grayish splotches that
  4576. 3:16:15occurred over an arc length of
  4577. 3:16:16approximately 40 degrees
  4578. 3:16:18then we discussed the photos he had a
  4579. 3:16:20photo of that joint and I had a photo
  4580. 3:16:23package of the srm15 and we put the
  4581. 3:16:26photos side by side and you could see
  4582. 3:16:30that the srm15 joint had coal black
  4583. 3:16:35color where we had photographed it and
  4584. 3:16:38the joint was as he described it was not
  4585. 3:16:40coal black it was significantly lighter
  4586. 3:16:43and a little bit splotchy the
  4587. 3:16:45splotchiness wasn't so definitive but
  4588. 3:16:47that's how we defined it to me now on
  4589. 3:16:49that basis
  4590. 3:16:51I concluded and so presented the night
  4591. 3:16:53before the launch that that was
  4592. 3:16:55extremely significant it was very
  4593. 3:16:58significant because it was telling us
  4594. 3:16:59that temperature was indeed a
  4595. 3:17:01discriminator and that although I
  4596. 3:17:03couldn't quantify
  4597. 3:17:05what that discriminator was
  4598. 3:17:07from a actual threshold standpoint in
  4599. 3:17:11other words I couldn't say you can Fly
  4600. 3:17:13Above This temperature you can fly you
  4601. 3:17:15can't fly below this temperature I
  4602. 3:17:16couldn't do that I didn't know of
  4603. 3:17:17anybody that could do that with the data
  4604. 3:17:19we had at the time but I was extremely
  4605. 3:17:21concerned and my concern ran deeper than
  4606. 3:17:24enter M15 it ran as a result of the SRM
  4607. 3:17:2816 nozzle
  4608. 3:17:30which the primary nozzle was compromised
  4609. 3:17:33and we presented that as having never
  4610. 3:17:36sealed and as having happened in the
  4611. 3:17:39ignition transient uh in in launching
  4612. 3:17:42that that vehicle now
  4613. 3:17:45that was characterized as a seal that
  4614. 3:17:48never sealed because it either was not
  4615. 3:17:50properly leak checked because of what
  4616. 3:17:52was explained before I shouldn't say not
  4617. 3:17:55properly checked but it was leak checked
  4618. 3:17:56at 100 PSI which we knew we had data
  4619. 3:17:59that said that putty could mask the leak
  4620. 3:18:01check at that level
  4621. 3:18:04we also postulated that maybe there was
  4622. 3:18:06nothing wrong with the leak check and
  4623. 3:18:07maybe in the transfer of the O-ring in
  4624. 3:18:09the groove it had simply ridden up on a
  4625. 3:18:12piece of contamination and never did
  4626. 3:18:13seal but the fact was that now you
  4627. 3:18:16introduced another phenomena you have
  4628. 3:18:18impingement erosion and bypass erosion
  4629. 3:18:21and the O-ring material gets removed
  4630. 3:18:25from the cross-section of the O-ring
  4631. 3:18:26much much faster when you have bypass
  4632. 3:18:28erosion or blow-bias people have been
  4633. 3:18:30terming it we usually use the
  4634. 3:18:32characteristic blowbyte and turn to
  4635. 3:18:35Define gas past it and we use
  4636. 3:18:39the other term to indicate that that
  4637. 3:18:42we're eroding at the same time so you
  4638. 3:18:45can have blow-by without erosion you can
  4639. 3:18:47have blow-by with erosion now I don't
  4640. 3:18:50remember the temperature of that
  4641. 3:18:51particular vehicle but that turned the
  4642. 3:18:54gain up very very high on the seal
  4643. 3:18:56problem extremely high in my mind we
  4644. 3:19:00were you know just playing with a
  4645. 3:19:02dangerous situation
  4646. 3:19:04so
  4647. 3:19:07if you've seen the packages that I've
  4648. 3:19:09turned in and you've probably read the
  4649. 3:19:12memo that I wrote and expressed the
  4650. 3:19:15concern I had to make absolutely sure in
  4651. 3:19:18in everybody's mind that management was
  4652. 3:19:21aware of my concerns saying that I was
  4653. 3:19:24one of the fellas that was most
  4654. 3:19:26involved with that particular situation
  4655. 3:19:30coming in
  4656. 3:19:33since you're on the task force uh yes
  4657. 3:19:36[Music]
  4658. 3:19:38tell us the history of the establishment
  4659. 3:19:40of that task force and what they were
  4660. 3:19:41charged to do we were charged
  4661. 3:19:44to look at alternate designs
  4662. 3:19:48in the joint
  4663. 3:19:51Upstream of the O-rings themselves and
  4664. 3:19:54to also look at the seal design as it
  4665. 3:19:57relates to the secondary seal
  4666. 3:20:00and that was to try to come up with
  4667. 3:20:03something that would replace the putty
  4668. 3:20:04would be of a vented design and assure
  4669. 3:20:07that we got gas pressurization to the
  4670. 3:20:10seal the primary seal also look at an
  4671. 3:20:13alternative secondary steel design which
  4672. 3:20:17would indeed follow the gap opening of
  4673. 3:20:20the metal Parts such that should a
  4674. 3:20:23primary o-ring be compromised in any
  4675. 3:20:25manner that the secondary seal would be
  4676. 3:20:28in a position because it was in contact
  4677. 3:20:30with both sides of the middle parts to
  4678. 3:20:32be pressurized pressure actuated and
  4679. 3:20:35cause the seal to to be affected and
  4680. 3:20:38that was the primary task of this team
  4681. 3:20:40to what extent were temperature
  4682. 3:20:42considerations involved in the work of
  4683. 3:20:44the to the extent that we had run tests
  4684. 3:20:47or Harney actually had them run at the
  4685. 3:20:49lab but I was aware of them we had run
  4686. 3:20:51tests on o-ring resiliency
  4687. 3:20:54you know and from the team standpoint we
  4688. 3:20:57cease to talk about an O-ring and
  4689. 3:20:59started to talk about seal because some
  4690. 3:21:02of the seals under investigation are not
  4691. 3:21:04O-rings they are cross-sections that
  4692. 3:21:06have metallic leaf springs in them such
  4693. 3:21:09that you will get a mechanical assist to
  4694. 3:21:12force the elastomer to remaining contact
  4695. 3:21:14such that if you did violate a primary
  4696. 3:21:17seal you would be capable of
  4697. 3:21:18pressurization
  4698. 3:21:20so with that information we were looking
  4699. 3:21:23at the whole regime we were trying to
  4700. 3:21:26get
  4701. 3:21:27resiliency data run at the plant since
  4702. 3:21:30last October which I mentioned in my
  4703. 3:21:32statement and also that night mentioned
  4704. 3:21:35over the over the phone and we had
  4705. 3:21:38trouble because we kept having machine
  4706. 3:21:39breakdowns we kept having priority
  4707. 3:21:42problems and here we were you know three
  4708. 3:21:44months later and we still didn't have
  4709. 3:21:45the data necessary to us to to pursue it
  4710. 3:21:50even further so that night we presented
  4711. 3:21:53the information on the basis of what we
  4712. 3:21:55knew and what we knew and I feel very
  4713. 3:21:58strong about it is that we had a problem
  4714. 3:22:01with temperature and it was away from
  4715. 3:22:03the direction of goodness and that's my
  4716. 3:22:04phrase because I can't quantify it but I
  4717. 3:22:07always use that it's away from the
  4718. 3:22:08direction of goodness and we had run
  4719. 3:22:11tests to show that the Seal never lifted
  4720. 3:22:13off
  4721. 3:22:14in a resiliency test at 100 degrees
  4722. 3:22:16Fahrenheit
  4723. 3:22:18we had a data point that night that
  4724. 3:22:20showed that the seal lifted off in the
  4725. 3:22:23in the ignition cycle for two and a half
  4726. 3:22:26seconds or 2.4 seconds at room
  4727. 3:22:28temperature 75 degrees we showed that it
  4728. 3:22:31lifted off and remained lifted off for
  4729. 3:22:35an excess of 10 minutes because we
  4730. 3:22:37stopped the test at 10 minutes at 50
  4731. 3:22:38degrees now with that testing that was
  4732. 3:22:41run initially I through my concern and
  4733. 3:22:45the joints that I had witnessed had
  4734. 3:22:48asked them to please run one more and
  4735. 3:22:50that was to back off
  4736. 3:22:53the instrument machine platens that had
  4737. 3:22:55compressed the seal ten thousandths of
  4738. 3:22:58an inch
  4739. 3:22:59and see what happens and they did that
  4740. 3:23:01and it remained seated that was my
  4741. 3:23:04comfort zone I am the one that made the
  4742. 3:23:06chart that Elle McDonald presented at
  4743. 3:23:09Washington in August which said that if
  4744. 3:23:12you go from zero to 170 milliseconds you
  4745. 3:23:15have a high probability of a good
  4746. 3:23:17secondary seal if you go from 170 to 330
  4747. 3:23:22milliseconds you have a reduced
  4748. 3:23:24probability of a secondary seal and if
  4749. 3:23:27you go beyond that point to full
  4750. 3:23:28pressurization you most assuredly might
  4751. 3:23:31not have a secondary seal now that was
  4752. 3:23:34based on the information that I had at
  4753. 3:23:36the time and I just went in and
  4754. 3:23:38estimated those from a pressure Trace
  4755. 3:23:40pressure time trace and made that
  4756. 3:23:42judgment and that was the basis of my
  4757. 3:23:46concern and that was also the basis of
  4758. 3:23:49continuing to fly because it happens
  4759. 3:23:51either it happens or it doesn't happen
  4760. 3:23:53right at the very first threshold of the
  4761. 3:23:56ignition Transit thank you Mr Thompson
  4762. 3:23:59uh you're uh in your group uh were any
  4763. 3:24:04of you or any of your people working
  4764. 3:24:06this problem as well or aware of this
  4765. 3:24:08yes sir we were right after the January
  4766. 3:24:12uh witness of SRM 15 and the disastrous
  4767. 3:24:17effects and my judgment on the ill ring
  4768. 3:24:18situation and seeing lots of soot in
  4769. 3:24:22both the primary O-rings of the field
  4770. 3:24:25joints and between primary in turkey and
  4771. 3:24:27the field joints and the nozzle it
  4772. 3:24:30appeared to me that some additional
  4773. 3:24:32tests need to be run and as Roger has
  4774. 3:24:35mentioned the resilience test was one of
  4775. 3:24:37the first because then if we're getting
  4776. 3:24:39so blow by by the primary o-ring we'd
  4777. 3:24:43better be checking and making sure that
  4778. 3:24:44our secondary is in in good good shape
  4779. 3:24:48so we devised the task to squeeze the
  4780. 3:24:50no-ring down a nominal amount and then
  4781. 3:24:52come up at about four inches per minute
  4782. 3:24:57in an instron machine and uh I'd like to
  4783. 3:25:00quantify that just a little bit
  4784. 3:25:03because if one looks at the rate at
  4785. 3:25:07which these surfaces separate it's a
  4786. 3:25:09non-linear function
  4787. 3:25:10it has kind of a toe line at first and
  4788. 3:25:13then has a fairly High rate over an
  4789. 3:25:15inflection point and then kind of comes
  4790. 3:25:17over the top
  4791. 3:25:18and uh the if one takes a secret from
  4792. 3:25:22Time Zero to the soft point which is
  4793. 3:25:25about uh oh forty forty two thousandths
  4794. 3:25:29at uh six tenths of a second that secant
  4795. 3:25:33was on the order of 3.2 inches per
  4796. 3:25:36minute
  4797. 3:25:37and the tests that we had run up to this
  4798. 3:25:40point including the night that we were
  4799. 3:25:41discussing this was two inches per
  4800. 3:25:43minute
  4801. 3:25:44and additionally the concern is if one
  4802. 3:25:47looks at the steeper slope after you
  4803. 3:25:49come off the toe through the inflection
  4804. 3:25:51point
  4805. 3:25:52that that slope is on the order of 10
  4806. 3:25:55inches per minute
  4807. 3:25:56so what it means to me and I hope to
  4808. 3:25:59others is that it's a very very high
  4809. 3:26:01rate shortly after that comes off on the
  4810. 3:26:05order of 100 to 200 milliseconds
  4811. 3:26:07so the message I believe and I tried to
  4812. 3:26:10convey
  4813. 3:26:11was that for 100 milliseconds to 200
  4814. 3:26:15milliseconds Rogers indicated 170. you
  4815. 3:26:19really probably do have a pretty good
  4816. 3:26:20chance for a seal thereafter you do not
  4817. 3:26:24and so to further answer the question
  4818. 3:26:26and hope I'm not too long is that blow
  4819. 3:26:29by of course was an issue and so uh I
  4820. 3:26:32set up a series of tests to try and
  4821. 3:26:35determine the factors that affect World
  4822. 3:26:38by such as squeeze such as temperature
  4823. 3:26:40and in fact trying to attempt to measure
  4824. 3:26:43the blow-by using argon at first and
  4825. 3:26:46then subsequently changed to Freon
  4826. 3:26:48because it's a better Witness
  4827. 3:26:51a question about the these tests
  4828. 3:26:55uh to measure the rate of a gap opening
  4829. 3:26:59if that's a proper term was this on a uh
  4830. 3:27:02an actual set of Hardware or was it a
  4831. 3:27:05test vehicle and how would tolerances
  4832. 3:27:08influence that could you get quite a
  4833. 3:27:10varied uh
  4834. 3:27:12answer depending on whether you had a
  4835. 3:27:14tight joint or whether you had a system
  4836. 3:27:17that was uh close to the other end of
  4837. 3:27:19the tolerance
  4838. 3:27:21yes sir what we did recognizing this is
  4839. 3:27:24first of all it was a bench test it was
  4840. 3:27:26a three inch piece of o-ring
  4841. 3:27:29in fact two inch two inch piece of
  4842. 3:27:31o-ring that was squeezed to about a
  4843. 3:27:34nominal squeeze which is like forty
  4844. 3:27:36thousands many of our joints have about
  4845. 3:27:39that squeeze the particular one in
  4846. 3:27:41question uh in the incident was thirty
  4847. 3:27:44five thousand thirty seven thousands
  4848. 3:27:46and so we just merely would give it the
  4849. 3:27:48squeeze and then back off at the
  4850. 3:27:50simulated rate
  4851. 3:27:52that uh we could do on the instron
  4852. 3:27:55machine
  4853. 3:27:57well the
  4854. 3:27:59um results an actual flight Hardware
  4855. 3:28:01then depending on uh the various
  4856. 3:28:04production runs on the cases yes sir we
  4857. 3:28:07do in fact if you have additional
  4858. 3:28:10squeeze you not only have the two
  4859. 3:28:13surfaces the one surface pushing off but
  4860. 3:28:16if it's a lot of squeeze in a small
  4861. 3:28:18o-ring Groove the side surface of the
  4862. 3:28:22O-ring probably can always help I can
  4863. 3:28:24also help and that gives you additional
  4864. 3:28:26energy to help it respond
  4865. 3:28:28well what about the other direction
  4866. 3:28:30where the tolerances are on the other
  4867. 3:28:32side
  4868. 3:28:33we investigated tolerances and gaps
  4869. 3:28:37and we have set up a matrix that to do
  4870. 3:28:40that very thing this was kind of a
  4871. 3:28:42preliminary test we had run
  4872. 3:28:44and as Roger mentioned we have refined
  4873. 3:28:47the test and not and have some results
  4874. 3:28:49now but after the fact
  4875. 3:28:51and the test included squeeze included
  4876. 3:28:55temperature and also the variable rate
  4877. 3:28:57that we think we really have in the
  4878. 3:28:59motor we have simulated that by input
  4879. 3:29:02using a function generator as an input
  4880. 3:29:04to the instron machine so that we could
  4881. 3:29:07generate the actual motion as we saw it
  4882. 3:29:10but with the fact that the testing is is
  4883. 3:29:13somewhat late
  4884. 3:29:14[Music]
  4885. 3:29:16and then that there's a lot of variables
  4886. 3:29:19and there's been a lot of commentary on
  4887. 3:29:22temperature
  4888. 3:29:23um
  4889. 3:29:24couldn't you uh come up with a situation
  4890. 3:29:26where temperature and tolerances uh
  4891. 3:29:29could develop a a sub marginal joint and
  4892. 3:29:33that of the 144 cases uh now that have
  4893. 3:29:37been fired you could run the gamut from
  4894. 3:29:39having very good ones the very bad ones
  4895. 3:29:42yes sir we could we ran as I say uh just
  4896. 3:29:45a preliminary run that showed the uh
  4897. 3:29:47that it was a problem but
  4898. 3:29:50would would all the parties be aware
  4899. 3:29:53that you could have wild variations and
  4900. 3:29:56then couldn't this develop quite a
  4901. 3:29:58concern on everybody's part that the
  4902. 3:30:00system was uh pretty tender
  4903. 3:30:03my feeling the system was tender and
  4904. 3:30:06this was the reason I objected the night
  4905. 3:30:07that was the point we tried to make that
  4906. 3:30:09night
  4907. 3:30:10is because we didn't have sufficient
  4908. 3:30:12data my question gets around to
  4909. 3:30:16why wouldn't everybody have that feeling
  4910. 3:30:18that uh the situation was uh very tender
  4911. 3:30:21and uh why wouldn't everybody develop a
  4912. 3:30:24feeling of great concern about them
  4913. 3:30:27by that means develop a very very
  4914. 3:30:29conservative attitude towards
  4915. 3:30:31approaching a launch
  4916. 3:30:33that's what we thought happened when the
  4917. 3:30:35original conclusions and recommendations
  4918. 3:30:37were made because they were quite
  4919. 3:30:39inconsistent quite consistent with what
  4920. 3:30:41we had presented prior to the meeting
  4921. 3:30:43and prior to making the charts
  4922. 3:30:47come to the the night of the launch and
  4923. 3:30:49the launch itself or the decisions a
  4924. 3:30:51little while but I'd like to go back
  4925. 3:30:52just a minute to some of the background
  4926. 3:30:54before we get to that point to show your
  4927. 3:30:57concern has expressed to management I
  4928. 3:31:01have here a letter which appears to be
  4929. 3:31:03one signed by you dated July 31st 1985
  4930. 3:31:08and I'll ask Dr Keel
  4931. 3:31:10to give it to you
  4932. 3:31:14[Applause]
  4933. 3:31:15uh and I gather from the files that we
  4934. 3:31:19received from you you wrote a series of
  4935. 3:31:22letters for memos to I guess memos is a
  4936. 3:31:25better way to describe it those are
  4937. 3:31:26activity reports yes
  4938. 3:31:28um expressing your concern about this
  4939. 3:31:31problem of the sales and the O-rings and
  4940. 3:31:34so forth I would ask you if you don't
  4941. 3:31:36mind to read that memorandum data July
  4942. 3:31:3831st which you wrote to doctor to RK
  4943. 3:31:42Lund who's vice president of engineering
  4944. 3:31:44yes would you mind yeah this letter is
  4945. 3:31:48written to ensure
  4946. 3:31:50that management is fully aware of the
  4947. 3:31:53seriousness of the current o-ring
  4948. 3:31:55erosion problem in the SRM joints from
  4949. 3:31:58an engineering standpoint
  4950. 3:32:00so mistakenly accepted position on the
  4951. 3:32:02joint problem was to fly without fear of
  4952. 3:32:05failure and to run a series of design
  4953. 3:32:07evaluations which would ultimately lead
  4954. 3:32:10to a solution or at least a significant
  4955. 3:32:13reduction of the erosion problem
  4956. 3:32:15this position is now drastically changed
  4957. 3:32:18as a result of the srm-16a nozzle joint
  4958. 3:32:22erosion which eroded a secondary o-ring
  4959. 3:32:25with a primary o-ring never ceiling
  4960. 3:32:28if the same scenario should occur in a
  4961. 3:32:30field joint parentheses and it could
  4962. 3:32:34then close parentheses then it is a jump
  4963. 3:32:37ball is the success or failure of the
  4964. 3:32:40joint because the secondary o-ring
  4965. 3:32:42cannot respond to the clevis opening
  4966. 3:32:44rate and may not be capable of
  4967. 3:32:46pressurization
  4968. 3:32:48the result would be a catastrophe of the
  4969. 3:32:51highest order Dash loss of human life
  4970. 3:32:55an unofficial team parentheses a memo
  4971. 3:32:59defining the team and its purpose was
  4972. 3:33:01never published close parentheses with
  4973. 3:33:04leader was formed on 19 July 1985.
  4974. 3:33:08and was tasked with solving the problem
  4975. 3:33:10for both the short and the long term
  4976. 3:33:13this unofficial team is essentially
  4977. 3:33:15non-existent at this time
  4978. 3:33:18in my opinion the fee must be officially
  4979. 3:33:21given the responsibility and the
  4980. 3:33:23authority to execute the work that needs
  4981. 3:33:26to be done on a non-interference basis
  4982. 3:33:29parentheses full-time assignment until
  4983. 3:33:31completed close parentheses
  4984. 3:33:34[Applause]
  4985. 3:33:37it is my honest and very real fear that
  4986. 3:33:41if we do not take immediate action to
  4987. 3:33:43dedicate a team to solve the problem
  4988. 3:33:46with the field joint having the number
  4989. 3:33:48one priority then we stand in Jeopardy
  4990. 3:33:51of losing a flight along with all the
  4991. 3:33:53launch pad facilities then I signed it
  4992. 3:33:56and the manager that I work for count
  4993. 3:33:58assigned it as concurred
  4994. 3:34:02thank you
  4995. 3:34:03I assume Mr Thompson you agree with the
  4996. 3:34:05contents of that memorandum absolutely
  4997. 3:34:07yes
  4998. 3:34:10um the left commission has any further
  4999. 3:34:12questions I'd like now to go to the uh
  5000. 3:34:16January 27th and January 28th to
  5001. 3:34:20ask you Mr fuchsia to uh describe in
  5002. 3:34:25your own words your first involvement in
  5003. 3:34:29those discussions and uh uh what was
  5004. 3:34:33said who took part in your position and
  5005. 3:34:36later on uh your position
  5006. 3:34:39okay
  5007. 3:34:40my foreign
  5008. 3:34:45you did make notes
  5009. 3:34:47on the 27th about the events of that
  5010. 3:34:51time yes I did I made a map of the
  5011. 3:34:54meeting you made the math but on the
  5012. 3:34:55same day yeah and then I made a few more
  5013. 3:34:57notes on the on the day of the launch
  5014. 3:35:00yeah prior to the launch and then I made
  5015. 3:35:02a short entry after the launch but the
  5016. 3:35:05the notes on the 27th and the 28th were
  5017. 3:35:08made on those days yes they were and the
  5018. 3:35:11other the the last one was made after
  5019. 3:35:13the accident that's correct uh in your
  5020. 3:35:16discussion you may refer to those notes
  5021. 3:35:18and we if you have no objection may make
  5022. 3:35:20them public I uh kind of just
  5023. 3:35:23paraphraged them and made them on three
  5024. 3:35:24by five cards but I think they
  5025. 3:35:26essentially have the content of what's
  5026. 3:35:28in those notes
  5027. 3:35:30uh my first knowledge about any consent
  5028. 3:35:33any temperature concern on the launch
  5029. 3:35:35was approximately 1 pm that on the 27th
  5030. 3:35:39of January
  5031. 3:35:41there was a preliminary meeting held to
  5032. 3:35:43discuss the concern at the low
  5033. 3:35:46temperature for resiliency
  5034. 3:35:48football by
  5035. 3:35:50previous launch and static test
  5036. 3:35:52temperatures
  5037. 3:35:54and there were several
  5038. 3:35:56well there were quite a few people in
  5039. 3:35:58that meeting most of whom were engineers
  5040. 3:36:00some were program management I don't
  5041. 3:36:01remember the names honestly
  5042. 3:36:03uh anyways that meeting concluded with
  5043. 3:36:07the
  5044. 3:36:08tempo that there was a valid concern for
  5045. 3:36:12temperature low temperature
  5046. 3:36:15also heard sometime afterwards that it
  5047. 3:36:18had been cold for several days
  5048. 3:36:21and what really impressed me about this
  5049. 3:36:23piece of information was that it was
  5050. 3:36:26opposite what srm15 has experienced
  5051. 3:36:30and that concerned me because when I got
  5052. 3:36:33off the plane a year ago last January
  5053. 3:36:36for the SRM 15 launch
  5054. 3:36:39it was very cold like 17 or 18 degrees
  5055. 3:36:42when I got off the airplane at Orlando
  5056. 3:36:44the next few days although it remained
  5057. 3:36:47cold it it got warmer and by launch time
  5058. 3:36:51like I said it was probably in the 60s
  5059. 3:36:53but it did get warmer now what was
  5060. 3:36:55concerning me about this piece of
  5061. 3:36:57information was it was the reverse it
  5062. 3:37:00had been cold for several days and it
  5063. 3:37:01was getting colder
  5064. 3:37:04and that's why I noted that because that
  5065. 3:37:07just turned the gain up on my concern
  5066. 3:37:09because it was away from goodness again
  5067. 3:37:12SRM 15 that I'm referring to was the
  5068. 3:37:14coldest launch up to that point in time
  5069. 3:37:17okay I felt we were very successful in
  5070. 3:37:19convincing Engineering Management of the
  5071. 3:37:21problem
  5072. 3:37:24by now we heard that the overnight low
  5073. 3:37:26was predicted to be 18 degrees
  5074. 3:37:28Fahrenheit
  5075. 3:37:31and again my concern deepen because what
  5076. 3:37:34I just spoke it was going in the wrong
  5077. 3:37:36direction from the past experience base
  5078. 3:37:39a telecon was set up with Marshall space
  5079. 3:37:42flight center and Kennedy Space Center
  5080. 3:37:45to present data over our concern about
  5081. 3:37:48the low temperature now there had been
  5082. 3:37:50some meetings in between and quite
  5083. 3:37:51frankly I'm almost a total blank because
  5084. 3:37:55I was down in my office I ran a
  5085. 3:37:57calculation that showed that the O-ring
  5086. 3:38:01shrinkage due to low temperature and
  5087. 3:38:03dropping from 75 degrees to 25 degrees
  5088. 3:38:06it was just a rough number was three
  5089. 3:38:09thousandths of an inch and that was due
  5090. 3:38:11to both the shrinkage on the diameter
  5091. 3:38:13and the effective temperature stretching
  5092. 3:38:16it around its circumference and thus
  5093. 3:38:18causing the diameter to shrink down
  5094. 3:38:19again there was roughly a 50 50 split in
  5095. 3:38:22those numbers but the bottom line was it
  5096. 3:38:24was about three thousandths of an inch
  5097. 3:38:26okay that shows me that squeeze wasn't
  5098. 3:38:30really in effect
  5099. 3:38:31squeeze was not an issue it never has
  5100. 3:38:33been an issue with me because if you
  5101. 3:38:35look at all the eroded O-rings they
  5102. 3:38:37don't correlate with squeeze the O-rings
  5103. 3:38:39that you would expect to be eroded are
  5104. 3:38:41those that have the lowest squeeze and
  5105. 3:38:42that's not the case so squeeze was never
  5106. 3:38:44an issue but I ran the number anyways to
  5107. 3:38:46assure myself that it was okay which it
  5108. 3:38:48was
  5109. 3:38:49okay the telecon data and I must
  5110. 3:38:51emphasize this we had very little time
  5111. 3:38:53to prepare data for that telecom when it
  5112. 3:38:57was decided in a group in our conference
  5113. 3:38:59room that we would take a systematic
  5114. 3:39:02approach and sign certain individuals
  5115. 3:39:04certain tasks to prepare we all Scurry
  5116. 3:39:07to our individual locations and prepared
  5117. 3:39:09that information on a timely manner
  5118. 3:39:11that's why the charts for the most part
  5119. 3:39:12are hand printed or handwritten because
  5120. 3:39:15we didn't have time to get them even
  5121. 3:39:16typed
  5122. 3:39:18uh each person during a telecon
  5123. 3:39:21presented their own charts
  5124. 3:39:24just for the record I presented charts
  5125. 3:39:262-1
  5126. 3:39:282-2
  5127. 3:39:29-3 and I also presented 3-1 which I did
  5128. 3:39:33not prepare but which was
  5129. 3:39:35sequence right after the one that I did
  5130. 3:39:37and I was asked just to present it which
  5131. 3:39:38I did I presented 4-1 and 5-1
  5132. 3:39:42[Applause]
  5133. 3:39:44I expressed deep concern about launching
  5134. 3:39:47at low temperature
  5135. 3:39:49I presented
  5136. 3:39:51chart 2-1 with emphasis now 2-1
  5137. 3:39:55if you want to see it I have it but
  5138. 3:39:57basically that was the chart that
  5139. 3:39:59summarized the primary concerns and that
  5140. 3:40:02was the chart that I pulled right out of
  5141. 3:40:04the Washington presentation without
  5142. 3:40:05changing one word of it because it was
  5143. 3:40:07still applicable
  5144. 3:40:08and IT addresses the highest concern of
  5145. 3:40:11the field joint in both the ignition
  5146. 3:40:13transient condition and the steady state
  5147. 3:40:16condition and it really sets down the
  5148. 3:40:19rationale for why we were continuing to
  5149. 3:40:21fly basically
  5150. 3:40:23if erosion penetrates the primary o-ring
  5151. 3:40:26seal
  5152. 3:40:27it's a high probability of no secondary
  5153. 3:40:29seal capability in a steady steady state
  5154. 3:40:31condition
  5155. 3:40:33and I had two sub bullets under that
  5156. 3:40:34which stated bench testing showed o-ring
  5157. 3:40:37not capable of maintaining contact with
  5158. 3:40:40metal Parts gap opening rate to maximum
  5159. 3:40:43operating pressure
  5160. 3:40:45and none about which stated bench
  5161. 3:40:48testing showed capability to maintain
  5162. 3:40:50o-ring contact during initial phase
  5163. 3:40:53parentheses 0 to 170 milliseconds of
  5164. 3:40:56transient that was my comfort basis of
  5165. 3:41:00continuing to fly into normal
  5166. 3:41:01circumstances normal being within the
  5167. 3:41:04database we had
  5168. 3:41:08[Music]
  5169. 3:41:11a shark
  5170. 3:41:12about the changing of the timing
  5171. 3:41:14function
  5172. 3:41:16of the O-ring as it attempted to seal
  5173. 3:41:19I was concerned that we may go from that
  5174. 3:41:22first beginning region into that
  5175. 3:41:24intermediate region from 0 to 170 being
  5176. 3:41:27the first region and 170 to 330 being
  5177. 3:41:30the intermediate region where we didn't
  5178. 3:41:32have a high probability of sealing or
  5179. 3:41:34seating
  5180. 3:41:36I didn't present it chart 2-2
  5181. 3:41:40with added concerns relating to the
  5182. 3:41:42timing function
  5183. 3:41:43and basically on that chart
  5184. 3:41:46I started off talking about lower
  5185. 3:41:49temperatures and current database
  5186. 3:41:50results in changing the primary o-ring
  5187. 3:41:52ceiling timing function
  5188. 3:41:54and I discussed the srm-15 observations
  5189. 3:41:57namely the 15a motor had 80 degrees Arc
  5190. 3:42:02of black grease between the O-rings and
  5191. 3:42:04make no mistake about it when I say
  5192. 3:42:06black I mean black just like coal it was
  5193. 3:42:09jet black
  5194. 3:42:10in SRM 15b at 110 degrees Arc of black
  5195. 3:42:15grease between the O-rings
  5196. 3:42:17we would have raw o-ring squeeze through
  5197. 3:42:20the low temperature which I calculated
  5198. 3:42:21earlier in the day
  5199. 3:42:23we would have higher o-ring Shore
  5200. 3:42:25hardness and that is the characteristics
  5201. 3:42:28similar to a hardness test that's done
  5202. 3:42:30on metal except it has a different Anvil
  5203. 3:42:33size and when you press against the
  5204. 3:42:35elastomeric material that is the measure
  5205. 3:42:37of how far a standard size Anvil will go
  5206. 3:42:40in to the particular what you asked them
  5207. 3:42:43right it gives you a measure of relative
  5208. 3:42:45hardness of the substance
  5209. 3:42:47now that would be harder and what that
  5210. 3:42:50really means basically is that the
  5211. 3:42:52harder the material is it would be
  5212. 3:42:54likened to trying to shove a brick into
  5213. 3:42:56a crack versus a sponge that's a good
  5214. 3:43:00analogy for purposes of this discussion
  5215. 3:43:03I also mentioned that thicker grease as
  5216. 3:43:06a result of lower temperatures would
  5217. 3:43:08have a higher viscosity it wouldn't be
  5218. 3:43:09as slick and slippery as it would be at
  5219. 3:43:11room temperature so it would be a little
  5220. 3:43:13bit more difficult to move across it
  5221. 3:43:16we would have higher o-ring pressure
  5222. 3:43:19actuation time in my opinion and that's
  5223. 3:43:21what I presented if action time and
  5224. 3:43:23these are the two these are the seven
  5225. 3:43:26substance of what I just presented if
  5226. 3:43:28action time increases
  5227. 3:43:30then the threshold of secondary steel
  5228. 3:43:32pressurization capability is approached
  5229. 3:43:35that was my fear
  5230. 3:43:37if the threshold is reached
  5231. 3:43:39then secondary seal may not be capable
  5232. 3:43:42of being pressurized and that was the
  5233. 3:43:44bottom line of everything that has been
  5234. 3:43:46presented up to that point
  5235. 3:43:50[Music]
  5236. 3:43:52issue with you
  5237. 3:43:54not well yeah I'm coming to that uh
  5238. 3:44:00I also showed a chart of the joint with
  5239. 3:44:02an exaggerated cross-section to show the
  5240. 3:44:05seal lifted off which has been shown to
  5241. 3:44:08everybody
  5242. 3:44:09uh I was at yeah at that point in time I
  5243. 3:44:12was asked to quantify my concerns
  5244. 3:44:16and I said I couldn't
  5245. 3:44:18I couldn't quantify it
  5246. 3:44:20I had no data to quantify it but I did
  5247. 3:44:23say I knew that it was away from
  5248. 3:44:25goodness in the current database
  5249. 3:44:28someone in the net commented that we had
  5250. 3:44:30football by
  5251. 3:44:32on answer M22 which was launched at 75
  5252. 3:44:35degrees I don't remember who made the
  5253. 3:44:36comment but that's where the first
  5254. 3:44:37comment came in about the disparity
  5255. 3:44:41between my conclusion and The observed
  5256. 3:44:44data because
  5257. 3:44:45srm-22 had Blow by at essentially a room
  5258. 3:44:49temperature launch
  5259. 3:44:50I then said that aftern-15 had much more
  5260. 3:44:53blow-by indication
  5261. 3:44:55and that it was indeed telling us that
  5262. 3:44:57lower temperature was a factor
  5263. 3:44:59this was supported by inspection of
  5264. 3:45:01flown Hardware by myself
  5265. 3:45:04I was asked again
  5266. 3:45:07for data to support my claim and I said
  5267. 3:45:09I have none
  5268. 3:45:10other than what is being presented but
  5269. 3:45:12and I had been trying to get resiliency
  5270. 3:45:15data Arnie and I both since last October
  5271. 3:45:18and that statement was mentioned on the
  5272. 3:45:20net
  5273. 3:45:22others in the room presented their
  5274. 3:45:24charts and the main Telecom session
  5275. 3:45:27concluded with Bob one who was our vice
  5276. 3:45:30president of engineering
  5277. 3:45:32presenting his conclusions and
  5278. 3:45:34recommendations tracks which were based
  5279. 3:45:36on our data input up to that point
  5280. 3:45:40this is on the telecon we're not pleased
  5281. 3:45:43with the conclusions and the
  5282. 3:45:45recommendations what was the conclusion
  5283. 3:45:47the conclusions were that we should not
  5284. 3:45:49fly outside of our database which was 53
  5285. 3:45:52degrees
  5286. 3:45:53those are the conclusions
  5287. 3:45:55and we were quite pleased because we
  5288. 3:45:58knew in advance having participated in
  5289. 3:45:59the preparation what the conclusions
  5290. 3:46:01were and we felt very comfortable with
  5291. 3:46:03that
  5292. 3:46:04instead of that conclusion uh Mr Bob
  5293. 3:46:07Lund right he he had prepared those
  5294. 3:46:09charts he had uh input from other people
  5295. 3:46:13but he had actually physically prepared
  5296. 3:46:14the charts and he prepared them
  5297. 3:46:17uh it was about that time
  5298. 3:46:20did Mr hardy from Marshall was asked
  5299. 3:46:24what he thought about the MTI
  5300. 3:46:26recommendation
  5301. 3:46:27and he said he was appalled at the MTI
  5302. 3:46:31decision
  5303. 3:46:33Mr hardy was also asked
  5304. 3:46:36about launching and he said no not at
  5305. 3:46:40the contractor recommended not launching
  5306. 3:46:42he would not go against the contractor
  5307. 3:46:43and launch
  5308. 3:46:45there was a short discussion that ensued
  5309. 3:46:47about temperature not being a
  5310. 3:46:49discriminator between SRM 15 and 22.
  5311. 3:46:53and shortly after I believe it was Mr
  5312. 3:46:55kilmensa asked
  5313. 3:46:58uh if he would excuse me I'm getting
  5314. 3:47:00confused here Mr kilman so was asked by
  5315. 3:47:04NASA if he would launch and he said no
  5316. 3:47:06because the engineering recommendation
  5317. 3:47:08was not to Launch
  5318. 3:47:11MTI management then asked for a
  5319. 3:47:14five-minute caucus I'm not sure exactly
  5320. 3:47:15who asked for that but it was asked in
  5321. 3:47:18such a manner that I remember it was
  5322. 3:47:19asked for a five-minute caucus which we
  5323. 3:47:21put on the line on mute and went offline
  5324. 3:47:24with the rest of the net
  5325. 3:47:26[Music]
  5326. 3:47:28at the time that you made the recommend
  5327. 3:47:30Eric YSI call major recommendation not
  5328. 3:47:32to launch was that unanimous
  5329. 3:47:34recommendation as far as you know yes
  5330. 3:47:37I've got to make something clear I have
  5331. 3:47:39been distressed by the things that have
  5332. 3:47:41been pairing in the paper
  5333. 3:47:43and things that have been said in
  5334. 3:47:44general and uh
  5335. 3:47:46there was never one positive pro-launch
  5336. 3:47:49statement ever made
  5337. 3:47:52by anybody
  5338. 3:47:56thank you
  5339. 3:47:58there have been some feelings since then
  5340. 3:48:00that folks have expressed that they
  5341. 3:48:03would support the decision but there was
  5342. 3:48:05not one positive statement for launch
  5343. 3:48:07ever made in that room
  5344. 3:48:13here
  5345. 3:48:16is that your recollection too
  5346. 3:48:19Mr Thompson yes yes particularly in the
  5347. 3:48:22caucus I think Roger and I were the only
  5348. 3:48:24one that only people that expressed our
  5349. 3:48:26views
  5350. 3:48:27but nope
  5351. 3:48:30you should proceed with a launch at that
  5352. 3:48:32time
  5353. 3:48:33not amongst the people that I was able
  5354. 3:48:35to hear
  5355. 3:48:37hey uh you said there was some confusion
  5356. 3:48:40in your mind as to Mr McDonald's
  5357. 3:48:42position at that time he came out with a
  5358. 3:48:44comment about the secondary ring ceiling
  5359. 3:48:46that you should consider that that's
  5360. 3:48:47correct when Alfred came on the line and
  5361. 3:48:50explained the situation about the
  5362. 3:48:52primary and secondary o-ring and how the
  5363. 3:48:53secondary o-ring was in position I had a
  5364. 3:48:56flash of confusion in my mind as to what
  5365. 3:49:00he was saying but I having worked on the
  5366. 3:49:03SRM 15 presentation in the SRM 16
  5367. 3:49:06presentation
  5368. 3:49:07realized exactly what he was trying to
  5369. 3:49:09say but I did have that tinge at the
  5370. 3:49:10beginning so there was definite
  5371. 3:49:13misunderstanding about Al's statement
  5372. 3:49:15there's no question in my mind because I
  5373. 3:49:16had it and I was probably close to that
  5374. 3:49:18joint than most anybody else and and I
  5375. 3:49:21had that change and I so stated that to
  5376. 3:49:23you
  5377. 3:49:26okay the uh
  5378. 3:49:29caucus was started by Mr Mason stating
  5379. 3:49:31that a management decision was necessary
  5380. 3:49:35those of us who opposed to the launch
  5381. 3:49:37continue to speak out and I'm
  5382. 3:49:39specifically speaking of Mr Thompson and
  5383. 3:49:41myself because in my recollection he and
  5384. 3:49:44I were the only ones that vigorously
  5385. 3:49:46continue to oppose the launch
  5386. 3:49:48and we were attempting to go back and
  5387. 3:49:51re-review
  5388. 3:49:52and try to make clear what we were
  5389. 3:49:54trying to get across and we couldn't
  5390. 3:49:56understand why it was going to be
  5391. 3:49:59reversed
  5392. 3:50:01so
  5393. 3:50:02we spoke out
  5394. 3:50:05and tried to explain once again the
  5395. 3:50:07effects and low temperature
  5396. 3:50:09Arnie actually got up from his position
  5397. 3:50:11which was down the table walked up the
  5398. 3:50:13table put a Quad Pad down in front of
  5399. 3:50:17the table in front of the management
  5400. 3:50:20folks and tried to sketch out once again
  5401. 3:50:23what his concern was with the joint
  5402. 3:50:26and when he realized he wasn't getting
  5403. 3:50:28through
  5404. 3:50:31he just stopped
  5405. 3:50:33I tried one more time with the photos I
  5406. 3:50:36grabbed the photos and I went up and
  5407. 3:50:38discussed the photos once again and
  5408. 3:50:40tried to make the point that it was my
  5409. 3:50:41opinion from actual observations that
  5410. 3:50:44temperature was indeed a discriminator
  5411. 3:50:46and we should not ignore the physical
  5412. 3:50:49evidence that we had observed
  5413. 3:50:54and again I brought to the point that
  5414. 3:50:57srm15 at 110 degree Arc of black grease
  5415. 3:51:00while srm-22 had a relatively different
  5416. 3:51:04amount which was less and wasn't quite
  5417. 3:51:06as black
  5418. 3:51:08I also stopped when it was a parent that
  5419. 3:51:10I couldn't get anybody to listen
  5420. 3:51:12at this point did anyone else speak up
  5421. 3:51:15in favor of the launch or no sir
  5422. 3:51:19no sir no one said anything to my
  5423. 3:51:21recollection nobody said word it was
  5424. 3:51:24then being discussed amongst the
  5425. 3:51:27management folks
  5426. 3:51:30after Arnie and I had our last day Mr
  5427. 3:51:33Mason said we have to make a management
  5428. 3:51:35decision
  5429. 3:51:36he turned to Bob one and asked him to
  5430. 3:51:38take off his engineering hat and put on
  5431. 3:51:41his management hat
  5432. 3:51:43from this point on management formulated
  5433. 3:51:45the points to base their decision on
  5434. 3:51:48there was never one comment in favor as
  5435. 3:51:50I've said uh of launching by any
  5436. 3:51:54engineer or other non-management person
  5437. 3:51:56in the room
  5438. 3:51:57before or after the caucus
  5439. 3:52:02I was not even asked to participate in
  5440. 3:52:05giving any input to the final decision
  5441. 3:52:07chart
  5442. 3:52:10so I'm back on the net
  5443. 3:52:12with the final chart or final chart
  5444. 3:52:15which was the rationale full launching
  5445. 3:52:18and that was presented by Mr kilminster
  5446. 3:52:21it was a handwritten on a notepad and he
  5447. 3:52:24read from that Notepad
  5448. 3:52:26I did not agree with some of the
  5449. 3:52:28statements that were being made to
  5450. 3:52:29support the decision
  5451. 3:52:31I was never asked
  5452. 3:52:33all pulled
  5453. 3:52:34and it was clearly a management decision
  5454. 3:52:37from that point
  5455. 3:52:39I must emphasize I had my say and I
  5456. 3:52:43never take
  5457. 3:52:44any management right
  5458. 3:52:46to take the input of an engineer and
  5459. 3:52:48then make a decision based on that input
  5460. 3:52:50and I truly believe that I've worked at
  5461. 3:52:52a lot of companies and that's been done
  5462. 3:52:55from time to time and I truly believe
  5463. 3:52:57that so
  5464. 3:52:58there was no point in me doing anything
  5465. 3:53:00any further and I had already attempted
  5466. 3:53:02to do
  5467. 3:53:04I did not see the final version of the
  5468. 3:53:06chart until the next day I just heard it
  5469. 3:53:09read
  5470. 3:53:10I left the room feeling badly defeated
  5471. 3:53:12but I felt I really did all I could to
  5472. 3:53:14stop the launch
  5473. 3:53:18I felt personally
  5474. 3:53:20the management was under a lot of
  5475. 3:53:21pressure to Launch
  5476. 3:53:23and they made a very tough decision but
  5477. 3:53:25I didn't agree with it
  5478. 3:53:29one of my colleagues that was in the
  5479. 3:53:31meeting
  5480. 3:53:32summed it up best
  5481. 3:53:35this was a meeting where the
  5482. 3:53:38determination was to Launch
  5483. 3:53:40and it was up to us to prove beyond a
  5484. 3:53:42shadow of a doubt that it was not safe
  5485. 3:53:45to do so
  5486. 3:53:47this is in total rebirth
  5487. 3:53:50to what the position usually is in a
  5488. 3:53:52pre-flight conversation or flight rate
  5489. 3:53:55in this review it's usually exactly
  5490. 3:53:56opposite then
  5491. 3:53:59do you know the source of the pressure
  5492. 3:54:00on management that you alluded to
  5493. 3:54:03well the the comments made over the net
  5494. 3:54:06uh is what I felt I can't speak for them
  5495. 3:54:09but I felt it I felt it I felt the tone
  5496. 3:54:12of the meeting exactly as I summed up
  5497. 3:54:14that we were having we were being put in
  5498. 3:54:16a position to prove that we should not
  5499. 3:54:19launch rather than be put in the
  5500. 3:54:21position and prove that we had enough
  5501. 3:54:23data to Launch and I felt that very real
  5502. 3:54:26these were the comments from the NASA if
  5503. 3:54:29people at Marshall and at KSC yes
  5504. 3:54:34you're trying to read
  5505. 3:54:37would fail
  5506. 3:54:38that's right and of course you couldn't
  5507. 3:54:40because as a matter of fact it didn't
  5508. 3:54:42that is five of them didn't and only one
  5509. 3:54:44of them did and therefore had you proven
  5510. 3:54:46that they were off that they were fair
  5511. 3:54:48you would have found yourself Incorrect
  5512. 3:54:49and on the criticism because five of
  5513. 3:54:52them didn't fail that's right I was very
  5514. 3:54:54very concerned that the cold
  5515. 3:54:56temperatures would change that timing
  5516. 3:54:57and put us in another regime and that
  5517. 3:55:00was the whole basis of my fighting that
  5518. 3:55:02night
  5519. 3:55:04that's right
  5520. 3:55:06to a point that they were intolerable
  5521. 3:55:07that's right
  5522. 3:55:09DeBarge away your correspondence in the
  5523. 3:55:12summer of 85
  5524. 3:55:13indicates that uh
  5525. 3:55:16the heightened sensitivity of the O-ring
  5526. 3:55:19problem at fire coil
  5527. 3:55:22was really initiated by heightened
  5528. 3:55:24sensitivity about it at NASA
  5529. 3:55:27and
  5530. 3:55:30for example references made to the the
  5531. 3:55:34problem that is escalated so badly in
  5532. 3:55:37the eyes of everyone especially our
  5533. 3:55:39customer NASA
  5534. 3:55:41well was any
  5535. 3:55:43mention made during the telecon net with
  5536. 3:55:48NASA the evening of January 27th of the
  5537. 3:55:52uh how the NASA View
  5538. 3:55:55had moved from this heightened
  5539. 3:55:57sensitivity to the O-ring problem to the
  5540. 3:56:00position that they were now putting
  5541. 3:56:02forward at the uh January 27th telecon
  5542. 3:56:06no that wasn't mentioned but in fact
  5543. 3:56:09they they were just as concerned as we
  5544. 3:56:11how counterparts that we worked with
  5545. 3:56:13that they were right on top of this
  5546. 3:56:16steel task force team with us and we had
  5547. 3:56:19status reviews
  5548. 3:56:21uh going on all the time in fact when
  5549. 3:56:24any time we'd hit a situation where they
  5550. 3:56:27felt we weren't going quick enough we
  5551. 3:56:30ended up having a visit and they would
  5552. 3:56:32just be there and watch over our
  5553. 3:56:34shoulders and make darn sure that we
  5554. 3:56:36were proceeding in a timely manner so
  5555. 3:56:38that to me told me that they were just
  5556. 3:56:40as concerned about it as we were
  5557. 3:56:43supposed
  5558. 3:56:46[Music]
  5559. 3:56:47team that was set up he alluded to it in
  5560. 3:56:51your letter of 31 July and you asked
  5561. 3:56:55that that team the uh reconstituted and
  5562. 3:56:58made more urgent did that happen
  5563. 3:57:00in a way I was on that team uh don
  5564. 3:57:04Kettner headed to team up
  5565. 3:57:06I was a member
  5566. 3:57:08Brian Russell was a member
  5567. 3:57:14of the master members
  5568. 3:57:16oh they had a counterpart team yes they
  5569. 3:57:19had a members of their team our main
  5570. 3:57:20interface was with a gentleman called
  5571. 3:57:22the Jerry peoples and Ron McIntosh but
  5572. 3:57:25they had their folks involved also you
  5573. 3:57:28had meetings uh with representatives
  5574. 3:57:31from both yes we did NASA and and fire
  5575. 3:57:33call yes we did when we outlined a plan
  5576. 3:57:35on how we were going to proceed to fix
  5577. 3:57:38this problem they were part and parcel
  5578. 3:57:40to that plan now this is the team that
  5579. 3:57:42involved a number of solutions uh to uh
  5580. 3:57:46this problem some of which have already
  5581. 3:57:48been publicized
  5582. 3:57:50that is correct and uh some of those
  5583. 3:57:53Solutions were short-term Solutions and
  5584. 3:57:55others were a long-term solution we
  5585. 3:57:57categorized them at least I did in in
  5586. 3:57:59all my notes as short-term Solutions
  5587. 3:58:01medium-term Solutions and long-term
  5588. 3:58:04Solutions and to give you a flavor for
  5589. 3:58:06what put what in what category was I
  5590. 3:58:09considered a short-term solution for
  5591. 3:58:12instance a 292 diameter o-ring which
  5592. 3:58:14would have afforded us twelve
  5593. 3:58:15thousandths more squeeze and still not
  5594. 3:58:18have an overfilled condition in the
  5595. 3:58:19groove with the elastomeric material
  5596. 3:58:21also couple that with Selective shimming
  5597. 3:58:24that would make the tang and clevis more
  5598. 3:58:27concentric to one another and take as
  5599. 3:58:29much of the free volume gap on the
  5600. 3:58:31outside away to make sure that we were
  5601. 3:58:34putting more and more squeeze on the
  5602. 3:58:35O-ring and less and less chance for The
  5603. 3:58:38Gap to open up to uh the rate that it's
  5604. 3:58:41opening did uh do you have some estimate
  5605. 3:58:44of how long the short-term solutions
  5606. 3:58:46would have taken yeah we had
  5607. 3:58:49tested assembly tested a 292 o-ring in a
  5608. 3:58:53qm in in some uh static motor joints uh
  5609. 3:58:57gives me some inert motor joints put
  5610. 3:59:00them together and found that we had a
  5611. 3:59:03good success with that they are
  5612. 3:59:05currently installed in the F2 field
  5613. 3:59:08joints of the qm5 test motor that was
  5614. 3:59:10ready to fly uh fire about uh two weeks
  5615. 3:59:13ago at our plant so we had made that
  5616. 3:59:17progress and we were well on our way to
  5617. 3:59:19showing that those seals will work in a
  5618. 3:59:22joint I must emphasize that the qm5
  5619. 3:59:26motor is a film along case motor and it
  5620. 3:59:28is a joint with a capture feature on it
  5621. 3:59:30that doesn't have the gap opening but
  5622. 3:59:31the major issue on a 295 on 292 o-ring
  5623. 3:59:36was the assembly characteristics of it
  5624. 3:59:38and we were getting like twelve
  5625. 3:59:40thousandths in each squeeze for free
  5626. 3:59:41basically that was a short-term issue
  5627. 3:59:43that we could Implement as quick as
  5628. 3:59:45possible was it did the team report on a
  5629. 3:59:48regular basis to vote NASA and fire coal
  5630. 3:59:50management we had status report with the
  5631. 3:59:54Marshall Folks at regular intervals and
  5632. 3:59:57we had a Friday teleconference at midday
  5633. 4:00:01and Status the proceedings of that
  5634. 4:00:04previous week with him
  5635. 4:00:06so everyone in the telecon on January
  5636. 4:00:0827th was aware of the work of this team
  5637. 4:00:10the solutions that it proposed I don't
  5638. 4:00:13know that everyone was but there were a
  5639. 4:00:16number of people that weren't yes I
  5640. 4:00:17don't know if I cannot make this
  5641. 4:00:18statement that everybody that was on a
  5642. 4:00:20telecom knew about that for instance I
  5643. 4:00:22had never
  5644. 4:00:23heard Cecil Houston's name before I
  5645. 4:00:25didn't know that he was a marshall type
  5646. 4:00:27until I heard on a telecon afterwards
  5647. 4:00:30that he was down at KFC I had not met
  5648. 4:00:32that gentleman so I don't know if he
  5649. 4:00:34knew it or not and I don't know if some
  5650. 4:00:36of the other folks knew but there were
  5651. 4:00:38enough folks on that telecon that knew
  5652. 4:00:40uh what the status was what about Mr
  5653. 4:00:42Mallory Mr hardy do you know if they
  5654. 4:00:44knew
  5655. 4:00:45I I don't have sure knowledge of that no
  5656. 4:00:47I don't know
  5657. 4:00:52that's your question which comes up
  5658. 4:00:55later and go back to the earlier time
  5659. 4:00:58when you're worrying about these things
  5660. 4:01:01and I would like to know
  5661. 4:01:02whether already you felt that there was
  5662. 4:01:05a serious problem in flying even at 53
  5663. 4:01:08degrees for the following logic is
  5664. 4:01:11possible perhaps and you'd correct me
  5665. 4:01:14if the
  5666. 4:01:16primary ring with the start to erode and
  5667. 4:01:20with the take enough time to erode that
  5668. 4:01:22it takes the pressure goes up to 600 PSI
  5669. 4:01:25or so
  5670. 4:01:26then if there's joint rotation from the
  5671. 4:01:29result of that the secondary seal May
  5672. 4:01:31Fail if the erosion would get all the
  5673. 4:01:33way through the primary
  5674. 4:01:36uh
  5675. 4:01:38seal the erosion got through a third of
  5676. 4:01:42the way of the primary seal in fact in
  5677. 4:01:4515c now I you feel that you understand
  5678. 4:01:48the process of erosion well enough to
  5679. 4:01:51know
  5680. 4:01:51that it was unlikely to go three times
  5681. 4:01:54as far yeah I think we need to clarify
  5682. 4:01:57one thing
  5683. 4:01:58one third of the seal was not eroded
  5684. 4:02:01one-third of the allowable erosion
  5685. 4:02:04number occurred and and you really have
  5686. 4:02:07to clarify that because we're talking
  5687. 4:02:08about a seal diameter that's 280 in
  5688. 4:02:10diameter okay and we really eroded about
  5689. 4:02:1532 thousandths of an inch on srm15 and
  5690. 4:02:18the factor of three is being used
  5691. 4:02:20against sub-scale data which show that
  5692. 4:02:22we were able to seal an eroded seal on a
  5693. 4:02:27subscale rig that had 10 inch diameter
  5694. 4:02:29seals
  5695. 4:02:30that up to an eighth of an inch then we
  5696. 4:02:34had a window where we failed the seal
  5697. 4:02:36and then we had another one up to I
  5698. 4:02:39believe it was 145 or 147 thousandths of
  5699. 4:02:42an inch that also sealed now the
  5700. 4:02:45analysis from the gas Dynamic standpoint
  5701. 4:02:48which is out of my area had been
  5702. 4:02:50conducted and they found an excellent
  5703. 4:02:52math model of that erosion process and
  5704. 4:02:56it correlated extremely well with this
  5705. 4:02:59subscale test data which had been run
  5706. 4:03:01about a year before and there were 27
  5707. 4:03:04tests that were characterized that
  5708. 4:03:06erosion they ran most of them at three
  5709. 4:03:10seconds and then they my recollection is
  5710. 4:03:12there was one or two five second tests
  5711. 4:03:14and one or two uh 20 some odd second
  5712. 4:03:17tests to show that it was indeed as
  5713. 4:03:20ignition transient and what was what
  5714. 4:03:22that test was all about
  5715. 4:03:24was they had a metal orifice with a
  5716. 4:03:27rectangular orifice that was 40 000 wide
  5717. 4:03:30and had different characteristic Heights
  5718. 4:03:33and they ran a parametric study using
  5719. 4:03:35those those tests that test rig and
  5720. 4:03:38determined what the erosion rate or not
  5721. 4:03:41the rate but the erosion depth was as a
  5722. 4:03:43function of the orifice size then the
  5723. 4:03:46math model was made and characterized
  5724. 4:03:49that and my recollection is they were
  5725. 4:03:50within 12 percent of all the test data
  5726. 4:03:53and they were very pleased that the
  5727. 4:03:56characterization analytically of what
  5728. 4:03:57was going on so from an erosion
  5729. 4:04:00standpoint I think it is fair to say
  5730. 4:04:02that
  5731. 4:04:04there was indeed sufficient margin but
  5732. 4:04:07that was not the issue erosion was not
  5733. 4:04:09the issue what was the issue is can you
  5734. 4:04:12stand a longer period of time in an
  5735. 4:04:15attempt to seal before the erosion each
  5736. 4:04:17you alive and you don't have a sale
  5737. 4:04:19period because once you get flow you
  5738. 4:04:22have two types of erosions you have blow
  5739. 4:04:24by erosion and impingement erosion the
  5740. 4:04:2727 test characterized impingement
  5741. 4:04:29erosion only there were no blowbys in
  5742. 4:04:32that end and I might say too we ran
  5743. 4:04:34tests on that same rig with out an
  5744. 4:04:37orifice
  5745. 4:04:38and pressurize it exactly the same way
  5746. 4:04:40on an unprotected o-ring and there was
  5747. 4:04:43not even a Sheen missing on the O-ring
  5748. 4:04:45so the analysis characterized that very
  5749. 4:04:49well and they understood it very well
  5750. 4:04:51what it is it's a volume feeling problem
  5751. 4:04:55as a function of time
  5752. 4:04:57the higher the volume the more the time
  5753. 4:04:59the hot gas flows if you have a Blow by
  5754. 4:05:02through the putty
  5755. 4:05:03that will enable you to get erosion and
  5756. 4:05:06and I I felt very confident they had a
  5757. 4:05:09good analytical handle on that
  5758. 4:05:11thank you I have another question on the
  5759. 4:05:14other side now
  5760. 4:05:15which is the Blow by early on that is in
  5761. 4:05:20the first whatever you call it 170
  5762. 4:05:22milliseconds yes
  5763. 4:05:24during which it was supposed
  5764. 4:05:27that the secondary ring would be close
  5765. 4:05:29enough to the right place to be sealed
  5766. 4:05:31if
  5767. 4:05:33but when now I'm going to talk about the
  5768. 4:05:36lower temperature
  5769. 4:05:37under those circumstances
  5770. 4:05:40where the thing is standing around and
  5771. 4:05:42has no resilience
  5772. 4:05:44and in fact when the engine goes off it
  5773. 4:05:48swings or it twines back and forth and
  5774. 4:05:51there are various stresses that have
  5775. 4:05:53been there since the time that the
  5776. 4:05:55ring has been pushed into place by the
  5777. 4:05:57test after which I now discover was 28
  5778. 4:06:00days earlier not just three days right
  5779. 4:06:03isn't it possible that the
  5780. 4:06:06that the secondary has gotten squozed or
  5781. 4:06:09squeezed to smaller size and it's
  5782. 4:06:12that it should be and then when it bends
  5783. 4:06:15back it leaves a hole that there's no
  5784. 4:06:17170 milliseconds at all
  5785. 4:06:21that it's already too small because it
  5786. 4:06:24has so zero so low and resilience time
  5787. 4:06:27it takes so long for it to respond after
  5788. 4:06:30it's been squeezed that is possible uh I
  5789. 4:06:33had done a series of tests relating
  5790. 4:06:36clevis opening problems back about three
  5791. 4:06:38years ago where we had experienced a
  5792. 4:06:41phenomena where the crevice was opening
  5793. 4:06:43up oh maybe three to five thousandths of
  5794. 4:06:46an inch over its original manufacture
  5795. 4:06:47dimensions
  5796. 4:06:49and we try to run that down and pin that
  5797. 4:06:52down as to where that came from
  5798. 4:06:54in the attempt to do that I ran a series
  5799. 4:06:58of tests which took an empty cylinder
  5800. 4:07:01segment and I actually
  5801. 4:07:04characterized when it was round what
  5802. 4:07:07happened to the clevis when I ovalized
  5803. 4:07:10the case what happened to the clevis
  5804. 4:07:12when I took the case and put shims
  5805. 4:07:15underneath the longitudinal Direction
  5806. 4:07:17what happened to the clevis and
  5807. 4:07:19characteristically with very large
  5808. 4:07:21numbers like when I ovalize it to a
  5809. 4:07:24value of approximately an inch I could
  5810. 4:07:26only affect the clevis gap opening say
  5811. 4:07:28several thousandths of an inch and and
  5812. 4:07:31so even though you get motion it was not
  5813. 4:07:35characterized as a major motion relative
  5814. 4:07:38to the squeeze that we had but in
  5815. 4:07:40reference the temperature which is what
  5816. 4:07:42you're talking about yes you could very
  5817. 4:07:43well have had that situation
  5818. 4:07:46unfortunately we've had some data on of
  5819. 4:07:50students we had some data you probably
  5820. 4:07:53know our experience with water
  5821. 4:07:56accumulating in the field joint while
  5822. 4:07:58it's standing out there on the stack
  5823. 4:08:01um
  5824. 4:08:01the uh as Dr Freeman pointed out uh 51
  5825. 4:08:06else stood out there for 28 days during
  5826. 4:08:08which there were some heavy uh rainstorm
  5827. 4:08:11wind driven rain what would the effect
  5828. 4:08:14and then we also had cold temperatures
  5829. 4:08:15the the night before and and a couple
  5830. 4:08:18nights earlier what would be the effect
  5831. 4:08:21if water accumulated in the field joint
  5832. 4:08:23and then froze during these hard freezes
  5833. 4:08:26well first of all I had no prior
  5834. 4:08:31pre-launch knowledge of that occurring
  5835. 4:08:35I had since found out that there was a
  5836. 4:08:38vehicle that they changed out one of the
  5837. 4:08:39segments and when they pulled the pin
  5838. 4:08:41water poured out of the joint uh did not
  5839. 4:08:44know that prior to the launch
  5840. 4:08:46we had been looking at that since the
  5841. 4:08:48incident and actually run a test in the
  5842. 4:08:51effect on on the actual opening of the
  5843. 4:08:54clevis the actually spreading of the of
  5844. 4:08:56the clevis itself was almost
  5845. 4:08:57unmeasurable and and we attribute that
  5846. 4:09:01I I guess to the fact that you cannot
  5847. 4:09:05fill the joint the fight by
  5848. 4:09:08configuration all the way up to the
  5849. 4:09:10secondary O-rings now if you postulate
  5850. 4:09:12that there was enough grease in there
  5851. 4:09:15and you actually moved the grease with
  5852. 4:09:18the ice then you could move the O-ring
  5853. 4:09:20but there has been that speculation at
  5854. 4:09:22this point it looks from the design
  5855. 4:09:25configuration of the joint that if you
  5856. 4:09:27fill the joint with water it still have
  5857. 4:09:28an air column that would probably be on
  5858. 4:09:31the order of 5 8 to 7 10 of an inch high
  5859. 4:09:33and you would simply compress the air
  5860. 4:09:35column and it appeared like you wouldn't
  5861. 4:09:37be able to generate enough pressure to
  5862. 4:09:39transfer the ring but in all thin it's
  5863. 4:09:41with running tests to find that out we
  5864. 4:09:43haven't completed them yet I should say
  5865. 4:09:45Marshall Mr Marshall yes
  5866. 4:09:48the U.S uh fire called the design of the
  5867. 4:09:53joint for these srms was developed no I
  5868. 4:09:57was not but you were there when srm8 was
  5869. 4:10:00fired were you not yes I was there when
  5870. 4:10:02srm1 was fired can you account for what
  5871. 4:10:06appears to be a concentration of of uh
  5872. 4:10:10erosion and blow-by cases in these
  5873. 4:10:13O-rings following srm8 as opposed to
  5874. 4:10:17prior to srna that had been a topic in
  5875. 4:10:20much discussion over the years and there
  5876. 4:10:22was a party change the original party
  5877. 4:10:24was a Randolph putty and then they
  5878. 4:10:27simply stopped making it uh no excuse me
  5879. 4:10:30not Randolph Phil O'Brien excuse me and
  5880. 4:10:33they simply stopped making it and then
  5881. 4:10:35we switched to a Randolph putty and that
  5882. 4:10:38is a simultaneous general area of time
  5883. 4:10:41sequence with the change in the layup of
  5884. 4:10:43the party to bring it back around from
  5885. 4:10:46the edge of the clevis so that we were
  5886. 4:10:49sure there wasn't anybody down by the
  5887. 4:10:50O-ring and but that hasn't fully tied
  5888. 4:10:54together either because the first
  5889. 4:10:55erosion that was ever indicated to my
  5890. 4:10:57knowledge was on srm2 or scs2 the second
  5891. 4:11:00flight in fact the second flight had the
  5892. 4:11:03most erosion yeah of any of the O-rings
  5893. 4:11:06on the field in the field Giant so we've
  5894. 4:11:09been struggling with that because the
  5895. 4:11:11data appears just totally random if you
  5896. 4:11:13look at the degree locations if you look
  5897. 4:11:15at the temperatures if you look at the
  5898. 4:11:18it's random in in regards to erosion per
  5899. 4:11:21se
  5900. 4:11:23call when the
  5901. 4:11:25critical items list was amended in
  5902. 4:11:28December 82 to make it a uh crit one
  5903. 4:11:32instead of the crit one R I was at that
  5904. 4:11:34call at that time but you know I don't
  5905. 4:11:36even know what a Cil is oh I see I I I'm
  5906. 4:11:39hearing all this for the first time I I
  5907. 4:11:42just don't know thank you
  5908. 4:11:47from your point of view uh in the
  5909. 4:11:49Engineering Group
  5910. 4:11:52did you feel that uh perhaps
  5911. 4:11:57[Music]
  5912. 4:11:58particular constraints needed to be
  5913. 4:12:00established on the operation of the the
  5914. 4:12:04motor in a case and its joints that
  5915. 4:12:07hadn't been and for example temperature
  5916. 4:12:10related or other uh other function
  5917. 4:12:12related and was that passed up the line
  5918. 4:12:16yes I did I feel impressed to
  5919. 4:12:20um back in the times of sts-1 which is
  5920. 4:12:23structural test article sta one
  5921. 4:12:25structural test article we discovered
  5922. 4:12:28that the joint was opening up rather
  5923. 4:12:30than closing as our original analysis
  5924. 4:12:31indicated
  5925. 4:12:33and its actors quite a bit is up to I
  5926. 4:12:35think fifty thousand fifty two thousands
  5927. 4:12:37at that time for the primary o-ring at
  5928. 4:12:39that point at that same meeting we went
  5929. 4:12:42to Marshall discussed the problem and we
  5930. 4:12:44also indicated in fact I think it was
  5931. 4:12:46made it indicated that the secondary
  5932. 4:12:48o-ring and certain uh worst on worse
  5933. 4:12:50conditions uh pressurized even without
  5934. 4:12:53uh resilience considered could be could
  5935. 4:12:57be open could be non-contact with the
  5936. 4:13:00adjoining surface
  5937. 4:13:02and so we have been working with these
  5938. 4:13:04problems uh for the last several years
  5939. 4:13:07and of course you can immediately see
  5940. 4:13:09are responsible throughout your end
  5941. 4:13:11myself
  5942. 4:13:12uh we know that we need elastomeric seal
  5943. 4:13:15very badly more so than in many
  5944. 4:13:18hydraulic applications because if you
  5945. 4:13:20look at a
  5946. 4:13:21uh the usual uh probably a dynamic seal
  5947. 4:13:25but nonetheless the requirements for a
  5948. 4:13:2870 dromeda Arena 1000 PSI people want to
  5949. 4:13:32talk about six or seven thousands and
  5950. 4:13:34now we're talking about that type of
  5951. 4:13:37clearance to start with but coupled with
  5952. 4:13:40another fifty thousands of motion and so
  5953. 4:13:43it's elastomeric uh problem of the the
  5954. 4:13:46first order in my judgment
  5955. 4:13:48and uh what's required is the
  5956. 4:13:50viscoelastic type of phenomena and we
  5957. 4:13:53all know that if any viscoelastic
  5958. 4:13:54material is very temperature sensitive
  5959. 4:13:58well did did you infect or do you know
  5960. 4:14:01of specific recommendations being made
  5961. 4:14:03with respect to establishing limitations
  5962. 4:14:06of any type on on yeah yes sir uh
  5963. 4:14:09several changes were made we looked at
  5964. 4:14:11the O-ring tolerances we looked at the
  5965. 4:14:14Orient Groove tolerances
  5966. 4:14:16we looked and we decreased and uh on the
  5967. 4:14:20side of goodness as Roger would say uh
  5968. 4:14:23all of those things in addition to that
  5969. 4:14:26the the shim we call it a centering
  5970. 4:14:28strip at that time was twenty thousands
  5971. 4:14:31we replaced that with a a a
  5972. 4:14:35m-type clip that goes over the pins in
  5973. 4:14:38that uh in that area and increase that
  5974. 4:14:40to 32 thousands
  5975. 4:14:43and these are some of the things we've
  5976. 4:14:45made an attempt to make the joint better
  5977. 4:14:49from where it was originally and it's
  5978. 4:14:51all the recommendations that you made to
  5979. 4:14:53your knowledge were accepted and
  5980. 4:14:55implemented uh no sir not all of them
  5981. 4:14:58were made uh recently and as late as
  5982. 4:15:02August of 82 I wrote a memo to my
  5983. 4:15:05management project engineering
  5984. 4:15:08indicated that we should stop Flying
  5985. 4:15:11until such Point as we could double The
  5986. 4:15:14Squeeze on the O-rings
  5987. 4:15:15what was the date of that about the 22nd
  5988. 4:15:18of August what is it 85 to 82 I think 85
  5989. 4:15:23yes 85 I'm sorry and my recommendation
  5990. 4:15:26there was to uh double the uh I went
  5991. 4:15:30through an example in the memo I think
  5992. 4:15:33it was srm20
  5993. 4:15:35where if we went to the shim that Mr
  5994. 4:15:38Beaujolais has indicated a full shim
  5995. 4:15:42which is about a 55 000 shim versus a uh
  5996. 4:15:4732 000 shim coupled with a
  5997. 4:15:51292 o-ring which is about the largest
  5998. 4:15:54o-ring we can get in there with
  5999. 4:15:55confidence that we're not going to Nick
  6000. 4:15:57it when we assemble that this would
  6001. 4:16:00about double The Squeeze on the O-ring
  6002. 4:16:02which we felt was an important thing to
  6003. 4:16:04do
  6004. 4:16:05and I realized at that point that the
  6005. 4:16:08O-ring committee that has been
  6006. 4:16:11dispatched to discover these things has
  6007. 4:16:14in fact discussed that but it was my
  6008. 4:16:17view that we needed to get it into the
  6009. 4:16:20flights right away for any
  6010. 4:16:22recommendation
  6011. 4:16:23respect to a temperature of the seal
  6012. 4:16:26area at lunch
  6013. 4:16:28to your knowledge not at that time but
  6014. 4:16:31uh the one that's one of the reasons is
  6015. 4:16:33if you get additional squeeze on it
  6016. 4:16:35particularly the secondary and the
  6017. 4:16:37primary the primary will have a better
  6018. 4:16:39chance of seating we think with
  6019. 4:16:41additional squeeze and the secondary
  6020. 4:16:43will get more help from the sidewalls of
  6021. 4:16:46the O-ring Groove and help its
  6022. 4:16:48resiliency problem
  6023. 4:16:49and we know that additional squeeze also
  6024. 4:16:52helps in extending the time that the
  6025. 4:16:55O-ring is in contact with the seal
  6026. 4:17:00all right and largely mentioned the
  6027. 4:17:02capture rangefield
  6028. 4:17:04as having been included excuse me in one
  6029. 4:17:07of the tests at what point if ever was a
  6030. 4:17:11capture ring uh seriously considered for
  6031. 4:17:14adoption as I understand it and
  6032. 4:17:17appreciate your comment on this the
  6033. 4:17:18capture ring is a flange which is
  6034. 4:17:22intended to arrest the opening up of the
  6035. 4:17:25two seal area the area of the two Fields
  6036. 4:17:30but when was that first seriously
  6037. 4:17:32considered or has it been seriously
  6038. 4:17:34concerned or for production when it was
  6039. 4:17:36first brought to my attention was in a
  6040. 4:17:39the design of the filament wow case I
  6041. 4:17:42believe someone from Marshall suggested
  6042. 4:17:45it in the adapters for the filament
  6043. 4:17:47wound case and roughly I think two and a
  6044. 4:17:49half or three years ago
  6045. 4:17:51and it seemed like a good idea because
  6046. 4:17:54what it does it holds that inside flange
  6047. 4:17:57in against the tang and our finite
  6048. 4:18:00element analysis indicate that instead
  6049. 4:18:03of opening on the order of 50 000 it
  6050. 4:18:06cuts it down to five or six thousands
  6051. 4:18:08which is in the direction that uh we
  6052. 4:18:10need to be going that is considered an
  6053. 4:18:13option uh
  6054. 4:18:15yes sir it particularly has come to
  6055. 4:18:18recent attention because of the heads up
  6056. 4:18:20program where we have discussed uh
  6057. 4:18:23higher pressure going up to 11 10
  6058. 4:18:25pressure
  6059. 4:18:27Mr Thompson could you uh tell us what
  6060. 4:18:29happened to those recommendations you
  6061. 4:18:31made in August of 1982
  6062. 4:18:3485 of any Apartments
  6063. 4:18:37were they ever implemented no sir they
  6064. 4:18:39were not
  6065. 4:18:41you don't have any idea why and why not
  6066. 4:18:44or did you ever receive a reply back
  6067. 4:18:47from management
  6068. 4:18:49to explain but the person that I wrote
  6069. 4:18:52it to directly involved in management
  6070. 4:18:54have since transferred down into my
  6071. 4:18:56group again
  6072. 4:18:58so that may have been part of the
  6073. 4:19:00problem but it uh management uh was
  6074. 4:19:03aware of it because of questions I and
  6075. 4:19:06feedback that I received from it but you
  6076. 4:19:08got no formal response for management
  6077. 4:19:09that is correct
  6078. 4:19:11on the uh capture flange I have a couple
  6079. 4:19:14more questions uh
  6080. 4:19:17[Applause]
  6081. 4:19:19sometime I take it the installation of
  6082. 4:19:22the flying is an integral part of the
  6083. 4:19:24case is that correct
  6084. 4:19:26yes sir it's part of the tang and as it
  6085. 4:19:29comes in engages first on a tapered
  6086. 4:19:32basis and then it comes into a
  6087. 4:19:34cylindrical basis
  6088. 4:19:36sorry please go ahead at first it was
  6089. 4:19:39attempted to have two tapers fit but the
  6090. 4:19:43tolerances became very unreasonable so
  6091. 4:19:45we would engage first on two tapered
  6092. 4:19:47surfaces and then come into cylindrical
  6093. 4:19:50engagement where we could maintain the
  6094. 4:19:52same type of tolerances that we have on
  6095. 4:19:54the ceiling joint and
  6096. 4:19:56does that involve or would that involve
  6097. 4:19:58a change in the forging process with
  6098. 4:20:01manufacturing process or the forging
  6099. 4:20:03Billet yes sir the inside bark on the
  6100. 4:20:05forging was not quite sufficient every
  6101. 4:20:09time assure that we'd be able to find a
  6102. 4:20:10fork I want to change that magnitude uh
  6103. 4:20:14been practical for your company to
  6104. 4:20:17undertake without the concurrence and
  6105. 4:20:19authorization from NASA
  6106. 4:20:22well I think that would take a high
  6107. 4:20:24cooperation between ourselves and NASA
  6108. 4:20:26it is quite a large undertaking of
  6109. 4:20:28course uh well could you clarify for me
  6110. 4:20:32uh if that in fact has been undertaken
  6111. 4:20:35and what the first implementation dates
  6112. 4:20:37were or might be obviously it wasn't on
  6113. 4:20:40the 51l
  6114. 4:20:42I think that it's indicated to me that
  6115. 4:20:45on a a general effort that it was on the
  6116. 4:20:48order of 18 months but on a on a basis
  6117. 4:20:51of an extremely uh large effort a
  6118. 4:20:56wartime effort I think was the word that
  6119. 4:20:57was used it could be made available in
  6120. 4:21:0012 to 13 months well are any under
  6121. 4:21:03process of being manufactured at the
  6122. 4:21:05present time with the yes I think
  6123. 4:21:08several four genes have been ordered and
  6124. 4:21:10I don't know if it's a full flight set
  6125. 4:21:12or not I'd have to some other people
  6126. 4:21:14would have to answer that I'd like to
  6127. 4:21:16address that on the seal term uh Team or
  6128. 4:21:19that was part of the long-term fix and
  6129. 4:21:22there had been some forgings ordered and
  6130. 4:21:24if the expected delivery was in a was in
  6131. 4:21:28February of 1987 and that was in the
  6132. 4:21:32works and that was part of the
  6133. 4:21:33peripheral action if you will on a
  6134. 4:21:35long-term basis of the seal tap team
  6135. 4:21:37have they been tested yet no sir they
  6136. 4:21:40haven't been one delivered but when is
  6137. 4:21:43the test schedule well the first
  6138. 4:21:45delivery was scheduled for February of
  6139. 4:21:4718 of 1987 so you wouldn't be able to
  6140. 4:21:49test until after the hardware was
  6141. 4:21:51received
  6142. 4:21:54so I'd like to ask a question about the
  6143. 4:21:56putty uh do you uh or does anyone know
  6144. 4:22:00what the impact of temperature is on the
  6145. 4:22:04putty and the formation of slow holes
  6146. 4:22:07we have a formation of bubbles
  6147. 4:22:10uh we have uh interpret the first part
  6148. 4:22:13before he said bubbles uh we have uh
  6149. 4:22:16since then during the investigation
  6150. 4:22:18which we of course didn't know at the
  6151. 4:22:20time we're making this decision uh uh
  6152. 4:22:23have tested buddy in a putty test
  6153. 4:22:26pictures somewhat similar to what the
  6154. 4:22:28motor is only instead of pressurizing
  6155. 4:22:30from the outside that we usually do in
  6156. 4:22:32running our
  6157. 4:22:34seal pressure test we pressurized from
  6158. 4:22:37the inside and in some cases on the
  6159. 4:22:40worst on worst uh small clearance bases
  6160. 4:22:42it held pressure for about 3 200 3200
  6161. 4:22:46seconds
  6162. 4:22:48I should amplify
  6163. 4:22:50the night of the launch the only data we
  6164. 4:22:53had in our possession on the putty was
  6165. 4:22:56that we had run temperature tests down
  6166. 4:22:58to 40 degrees and that was the
  6167. 4:23:01characterization that determined the
  6168. 4:23:03leak check pressure to ensure that the
  6169. 4:23:07leak check pressure was not mapped by
  6170. 4:23:09the putty and we have held up to 100 PSI
  6171. 4:23:14with the putty
  6172. 4:23:16pressurized through the leak check port
  6173. 4:23:19and so we had temperature data at 40
  6174. 4:23:21degrees on the putty at that particular
  6175. 4:23:23time and and we determined that 200 PSI
  6176. 4:23:27would be a conservative number it would
  6177. 4:23:29bracket all the testing that had been
  6178. 4:23:30done and we would have a leak check at
  6179. 4:23:33200 PSI for 15 minutes with an open
  6180. 4:23:36nitrogen gas fluids to ensure that the
  6181. 4:23:38putty was not masking the leak in the
  6182. 4:23:41O-ring and we dropped to zero
  6183. 4:23:44repressurized to 50 psi and run the
  6184. 4:23:47actual low pressure leak check on the
  6185. 4:23:49seal 50 psi is a very severe check on an
  6186. 4:23:52O-ring seal at low pressure so uh
  6187. 4:23:55holding that for 10 minutes and allowing
  6188. 4:23:57a one pound drop is a very very small
  6189. 4:24:00leak on the order of an atomic energy
  6190. 4:24:02type reactor leak there's one thing that
  6191. 4:24:05disturbs me somewhat about the
  6192. 4:24:07qualification test in regard to the
  6193. 4:24:09putty so I understand that during a
  6194. 4:24:11qualification test the putty was
  6195. 4:24:14actually uh
  6196. 4:24:16smoothed out or or
  6197. 4:24:19there were attempts made to eliminate
  6198. 4:24:23any imperfections in the putty but in
  6199. 4:24:25fact during an actual launch that is not
  6200. 4:24:28done so in that sense the qualification
  6201. 4:24:31test did not truly simulate large
  6202. 4:24:33conditions did that disturb anyone
  6203. 4:24:35yes sir that's true uh it to assemble
  6204. 4:24:38these motors under a horizontal
  6205. 4:24:40condition with which we would do for the
  6206. 4:24:42development Motors and the qualification
  6207. 4:24:45Motors the motors go uh out of round
  6208. 4:24:49probably more so than they do during a
  6209. 4:24:51normal stacking vertical operation and
  6210. 4:24:54so the putty has probably moved more
  6211. 4:24:56than it would be during normal stacking
  6212. 4:24:58so and probably more blow holes were
  6213. 4:25:01generated and you can see we sometimes
  6214. 4:25:03call them volcanoes in the putty
  6215. 4:25:06you say probably
  6216. 4:25:08you don't really have any any data does
  6217. 4:25:11anyone or has anyone actually photograph
  6218. 4:25:14the condition of the putty or examine
  6219. 4:25:17the putty uh when the vertical stacking
  6220. 4:25:20is done even early in the program
  6221. 4:25:22I had heard that someone was lowered in
  6222. 4:25:25the bolson's chair during the early
  6223. 4:25:28phases of the program to examine a putty
  6224. 4:25:32on a field joint that do you know
  6225. 4:25:33whether that has ever occurred I don't
  6226. 4:25:35have any detailed knowledge on that we
  6227. 4:25:37do know that as the Tang is inserted
  6228. 4:25:39into the uh clevis and the first then
  6229. 4:25:43once the O-ring covers up the uh on the
  6230. 4:25:47Tang the ceilings or the residual air is
  6231. 4:25:49compressed and we know for a fact that
  6232. 4:25:52sometimes that that air that's
  6233. 4:25:54compressed will cause a blow-by just on
  6234. 4:25:56Tang insertion
  6235. 4:25:58but I wonder if I could go back to the
  6236. 4:25:59broader broader question uh you talked
  6237. 4:26:02about data that you couldn't get uh
  6238. 4:26:04resources that you didn't have uh Mr
  6239. 4:26:07Thompson has mentioned a letter that he
  6240. 4:26:08put in August that he got no response to
  6241. 4:26:10you wrote an activity report on the 4th
  6242. 4:26:13of October uh the characterized some of
  6243. 4:26:15this could you summarize some of the
  6244. 4:26:17things you said in that that activity
  6245. 4:26:18before the key points please I just got
  6246. 4:26:21to check to make sure I know which one
  6247. 4:26:23you're speaking of
  6248. 4:26:26his title SRM seal problem task team
  6249. 4:26:28status
  6250. 4:26:30and it starts out with the team
  6251. 4:26:31generally has been experienced in
  6252. 4:26:33trouble
  6253. 4:26:39was written October the 4th
  6254. 4:26:41yes okay
  6255. 4:26:43you want me to read it well the
  6256. 4:26:44pertinent points I'd like you to make
  6257. 4:26:46those points if you would
  6258. 4:26:50uh
  6259. 4:26:51I felt
  6260. 4:26:53as I stated in my original memo before
  6261. 4:26:56the team was formed
  6262. 4:26:58that the only way that we could pull off
  6263. 4:27:01a timely resolution to this problem was
  6264. 4:27:05that people dedicated to this problem
  6265. 4:27:07full time with full cooperation
  6266. 4:27:10and I felt that wasn't coming
  6267. 4:27:13to pass I I felt very strongly that
  6268. 4:27:17we were working
  6269. 4:27:19towards a solution
  6270. 4:27:22in a timely manner but we were getting
  6271. 4:27:26um
  6272. 4:27:29okay Mr Dr kill will give it to you
  6273. 4:27:33[Music]
  6274. 4:27:38this is an activity report that I turned
  6275. 4:27:41in
  6276. 4:27:42it said SRM steel problem testing status
  6277. 4:27:46the team generally has been experiencing
  6278. 4:27:48trouble from the business as usual
  6279. 4:27:50attitude from supporting organizations
  6280. 4:27:53part of this is due to lack of
  6281. 4:27:55understanding of how important this task
  6282. 4:27:57team activity is and the rest is due to
  6283. 4:28:00Pure operating procedure inertia which
  6284. 4:28:02prevents timely results to a specific
  6285. 4:28:05request
  6286. 4:28:07the team met with Joe kilminster on 10
  6287. 4:28:10385 to discuss this problem
  6288. 4:28:14he wanted specific examples which he was
  6289. 4:28:18given and he simply concluded that it
  6290. 4:28:20was every team member's responsibility
  6291. 4:28:22to flag problems that occurred to
  6292. 4:28:25organizational supervision
  6293. 4:28:27and to work to remove the roadblock by
  6294. 4:28:30getting the required support to solve
  6295. 4:28:32the problem
  6296. 4:28:33the problem was further explained to
  6297. 4:28:36require almost full-time nursing of each
  6298. 4:28:39task to ensure that it is taken to
  6299. 4:28:41completion by a support group
  6300. 4:28:43Joe simply agreed and said we should
  6301. 4:28:46then nurse every task we have
  6302. 4:28:50he plain doesn't understand that there
  6303. 4:28:52are not enough people to do that kind of
  6304. 4:28:54nursing of each task but he doesn't seem
  6305. 4:28:56to mind directing that the task
  6306. 4:28:58nevertheless gets done
  6307. 4:29:00for example
  6308. 4:29:02the team just found out that when we
  6309. 4:29:04submit a request to purchase an item
  6310. 4:29:06that it goes to approximately six to
  6311. 4:29:09eight people
  6312. 4:29:10purchase order is written and the item
  6313. 4:29:13actually ordered
  6314. 4:29:15the vendors we are working with on seals
  6315. 4:29:18and spacer rings have responded to our
  6316. 4:29:19request in a timely manner yet we MTI do
  6317. 4:29:24not get a purchase order to them in a
  6318. 4:29:26timely manner
  6319. 4:29:28oh Ed has been waiting for a function
  6320. 4:29:30generator since 925.85
  6321. 4:29:34the paperwork authorizing the purchase
  6322. 4:29:36was finished by engineering on 924.85
  6323. 4:29:40and placed into the system we have yet
  6324. 4:29:43to receive the requested items
  6325. 4:29:45the reason I made an issue of that is
  6326. 4:29:48because we had heard it was on the Shelf
  6327. 4:29:51down in San Diego it's simply a matter
  6328. 4:29:52of
  6329. 4:29:53picking it up and using it
  6330. 4:29:56this type of
  6331. 4:29:59example is typical and results in Lost
  6332. 4:30:01resources that have been planned to do
  6333. 4:30:04the test work for us in a timely manner
  6334. 4:30:06I for one resent working at full
  6335. 4:30:09capacity all week long
  6336. 4:30:10and then being required to support
  6337. 4:30:12activity on the weekend that could have
  6338. 4:30:14been accomplished during the week
  6339. 4:30:16I might add that even NASA perceive that
  6340. 4:30:19the team is being blocked in its
  6341. 4:30:20engineering efforts to accomplish its
  6342. 4:30:22tasks NASA is sending an engineering
  6343. 4:30:25representative to stay with us starting
  6344. 4:30:27October 14th
  6345. 4:30:29we feel that this is the direct result
  6346. 4:30:32of their feeling that we MTI are not
  6347. 4:30:35responding quickly enough on the seal
  6348. 4:30:37problem
  6349. 4:30:38I should add that several of the team
  6350. 4:30:41members requested that we be giving a
  6351. 4:30:44specific manufacturing engineer a
  6352. 4:30:46quality engineer a safety engineer and
  6353. 4:30:50four to six technicians to allow us to
  6354. 4:30:52do our tests on a non-interference basis
  6355. 4:30:55with the rest of the system
  6356. 4:30:57this request was deemed not necessary
  6357. 4:30:59when Joe decided the nursing of the task
  6358. 4:31:01approach was directed
  6359. 4:31:04finally the basic problem boils down to
  6360. 4:31:07the fact
  6361. 4:31:08that all MTI problems have number one
  6362. 4:31:11priority and that upper management
  6363. 4:31:13apparently feels that the SRM program is
  6364. 4:31:16always for sure and a customer be damned
  6365. 4:31:19and I signed it October for 1984-85.
  6366. 4:31:25[Music]
  6367. 4:31:27both
  6368. 4:31:29I'm going to turn the
  6369. 4:31:31subject a little bit around now to
  6370. 4:31:33another aspect of it one of our
  6371. 4:31:35responsibilities is to attempt to
  6372. 4:31:37determine the cause or causes of the
  6373. 4:31:39accident
  6374. 4:31:40I guess both you gentlemen have
  6375. 4:31:42suggested in these memories that if
  6376. 4:31:45certain things were not done the
  6377. 4:31:46catastrophe might result
  6378. 4:31:48looking at the pictures that we now have
  6379. 4:31:51available to us which show a black puff
  6380. 4:31:55of black smoke
  6381. 4:31:57during the first lists and the first
  6382. 4:32:00second of the launch which was about 25
  6383. 4:32:02feet high
  6384. 4:32:04what is your opinion is that consistent
  6385. 4:32:07with the concern that you had of that a
  6386. 4:32:10catastrophe might occur in the in that
  6387. 4:32:12joint okay we should back up and give
  6388. 4:32:15you a little bit of background
  6389. 4:32:15information first
  6390. 4:32:17it was everybody's consented opinion
  6391. 4:32:19including mine and I'm not a solid
  6392. 4:32:21rocket mode of man I don't know anything
  6393. 4:32:23about the propellants or anything like
  6394. 4:32:25that
  6395. 4:32:26but it was everybody's considered
  6396. 4:32:27opinion that if we developed a problem
  6397. 4:32:29that we'd blow it up on the pad
  6398. 4:32:33and that we wouldn't have even lift off
  6399. 4:32:34the pads
  6400. 4:32:36uh
  6401. 4:32:38there's been a lot of speculation about
  6402. 4:32:40the puppet smoke it hasn't really been
  6403. 4:32:42determined what it came what it is where
  6404. 4:32:44it came from it for sure I mean there's
  6405. 4:32:46a lot of speculation but if that was a
  6406. 4:32:49joint
  6407. 4:32:50then that supports the seal
  6408. 4:32:53excuse me the leak seal leak Theory
  6409. 4:32:56which is to say that you had a puff of
  6410. 4:33:00smoke or a puff of products of
  6411. 4:33:02combustion past both seals at a very
  6412. 4:33:05early stage in the ignition transient
  6413. 4:33:08then you sealed with whatever remaining
  6414. 4:33:11material you had left in the seal and
  6415. 4:33:13you can postulate this visa to the
  6416. 4:33:14primary or the secondary it'll work both
  6417. 4:33:16ways and then at some time later due to
  6418. 4:33:19either going through a Max Q environment
  6419. 4:33:21or vectoring of the nozzle that you can
  6420. 4:33:25in vibration or aerodynamic forces
  6421. 4:33:27whatever you want to characterize that
  6422. 4:33:29there wasn't that much left and it
  6423. 4:33:31spitted out at that point in time and
  6424. 4:33:33started to leak again
  6425. 4:33:34that has not been really determined yeah
  6426. 4:33:38I was just really asking whether the
  6427. 4:33:42the first buffer black spoke which has
  6428. 4:33:45been described as about 25 feet high is
  6429. 4:33:48not inconsistent with the theory that
  6430. 4:33:51you've been concerned about that's right
  6431. 4:33:54uh Mr Marshall uh you uh Mr Marshall I
  6432. 4:33:57mean Mr Thompson do you agree with the
  6433. 4:34:00comments that Mr Moon Julie made earlier
  6434. 4:34:04about the discussions
  6435. 4:34:05uh in the Telecom and other discussions
  6436. 4:34:09that you engaged in
  6437. 4:34:11yes sir I think I prepared to talk about
  6438. 4:34:13these things but I think it's been
  6439. 4:34:15mentioned and most of the points that I
  6440. 4:34:17have have been brought out so why don't
  6441. 4:34:19you if you like to look over your notes
  6442. 4:34:21and see this anything you want to add is
  6443. 4:34:23we're perfectly glad to have you go
  6444. 4:34:24through the whole thing maybe you can
  6445. 4:34:26glance at them and see if you want to
  6446. 4:34:28add anything quickly summarize sure why
  6447. 4:34:31don't you do that
  6448. 4:34:32uh about 10 o'clock in the morning of
  6449. 4:34:34January 27th I received a phone call
  6450. 4:34:37from Mr Boyd Brenton he's project uh
  6451. 4:34:40program project manager project engineer
  6452. 4:34:43he called me from Marshall and told me
  6453. 4:34:45about the uh the 18 degree temperature
  6454. 4:34:48that was indicated that night and uh
  6455. 4:34:51this particular phone call was prompted
  6456. 4:34:53by Mr Larry Ware of msfc
  6457. 4:34:57program manager and indicating that they
  6458. 4:35:00were both both concerned about this and
  6459. 4:35:02they asked me what how I felt and what
  6460. 4:35:04my if I felt concerned and of course I
  6461. 4:35:06told him that I did
  6462. 4:35:07and it went through a series of meetings
  6463. 4:35:09up through engineering throughout today
  6464. 4:35:11uh ending up finally in Mr Lund's office
  6465. 4:35:15and we had concluded there that we would
  6466. 4:35:17not launch if the temperature were
  6467. 4:35:19anything lower than 53 degrees so at
  6468. 4:35:23this point I felt fairly content and we
  6469. 4:35:25met back over in the uh
  6470. 4:35:27engineering conference room
  6471. 4:35:29we call the Nick room and prepared to
  6472. 4:35:32make charts and you've heard much of
  6473. 4:35:34this conversation
  6474. 4:35:35and I guess the only thing I'd like to
  6475. 4:35:37add to it is I also heard that
  6476. 4:35:39Marshall's reaction is that they were
  6477. 4:35:40appalled at our recommendation and I was
  6478. 4:35:43very much surprised by this uh having
  6479. 4:35:46had the experiences over the years and
  6480. 4:35:48how careful and conservative these
  6481. 4:35:50people are and I really admire them so I
  6482. 4:35:53was extremely surprised and really not
  6483. 4:35:55ready for this type of a recommendation
  6484. 4:35:58and uh so I guess we had put together
  6485. 4:36:01some things probably we may have put
  6486. 4:36:03together some more if they had any
  6487. 4:36:05anticipation that this were not going to
  6488. 4:36:07be received I think we've pretty well
  6489. 4:36:09got everything out on the table that uh
  6490. 4:36:12that we had in mind
  6491. 4:36:15and uh they indicated that the seal was
  6492. 4:36:18not a function of temperature and being
  6493. 4:36:22a viscoelastic seal it had to be a
  6494. 4:36:24function temperature in my thinking and
  6495. 4:36:27although I was not unable to explain the
  6496. 4:36:29srm-22 where we've got some sit there
  6497. 4:36:32also and it's supposedly a warm motor
  6498. 4:36:35and during the caucus uh I've said Mr
  6499. 4:36:39bosio I have mentioned something that
  6500. 4:36:41I'm not used accustomed to doing and
  6501. 4:36:43sitting down between two managers and
  6502. 4:36:45trying one more time to explain and make
  6503. 4:36:49sure that I got my thoughts across to
  6504. 4:36:51them
  6505. 4:36:52and uh after not completing that
  6506. 4:36:55conversation but concluding that I
  6507. 4:36:57probably wasn't being I was
  6508. 4:37:00communicating and that may be my fault
  6509. 4:37:02I'm happy they're not happy but readily
  6510. 4:37:06admit that it may have been my type of
  6511. 4:37:08explanation I was wasn't being uh
  6512. 4:37:11getting through
  6513. 4:37:14um
  6514. 4:37:17I think that uh you know we had just one
  6515. 4:37:20last point I think that we had seen
  6516. 4:37:22erosion on srm15
  6517. 4:37:25erosion but more important we have seen
  6518. 4:37:27blow through
  6519. 4:37:29and it was very severe we had both
  6520. 4:37:31through on two field joints and in fact
  6521. 4:37:34two nozzle joints also we saw soot
  6522. 4:37:36between the O-rings in four places that
  6523. 4:37:38I recall and that was 53 degrees and it
  6524. 4:37:41was my judgment we had no
  6525. 4:37:45reason to take the risk of shooting at a
  6526. 4:37:49a o-ring temperature that was lower than
  6527. 4:37:52the 53 degrees
  6528. 4:37:54and my recommendation in some of the
  6529. 4:37:57former meetings was just merely to wait
  6530. 4:37:59a day
  6531. 4:38:00wait at least until the afternoon and
  6532. 4:38:02then depending on temperatures perhaps
  6533. 4:38:04waiting another day
  6534. 4:38:06and I think that concludes me can you
  6535. 4:38:08remember any time in your experience of
  6536. 4:38:10tackle when the Engineering Group has
  6537. 4:38:13been overruled and effect by management
  6538. 4:38:16nothing that comes immediately to my
  6539. 4:38:18mind sir
  6540. 4:38:19thank you
  6541. 4:38:22the activity report of October 4 85 to
  6542. 4:38:26whom was that directed
  6543. 4:38:28I turn that into my immediate
  6544. 4:38:30supervision for incorporation to go up
  6545. 4:38:33through the flatter as it reports on a
  6546. 4:38:36weekly basis
  6547. 4:38:38who did you give it to what individual
  6548. 4:38:40my supervisor is Jack kef I turn it into
  6549. 4:38:43his secretary
  6550. 4:38:45were you given an opportunity to discuss
  6551. 4:38:48it in any subsequent time with anybody
  6552. 4:38:50in management no sir
  6553. 4:38:53[Music]
  6554. 4:38:56thank you
  6555. 4:39:01just to be perfectly about this uh is it
  6556. 4:39:05fair to say that as Engineers you don't
  6557. 4:39:08believe that you had
  6558. 4:39:09data or analysis to characterize the
  6559. 4:39:12performance of The Joint at a 30 degree
  6560. 4:39:15temperature that's correct
  6561. 4:39:17[Music]
  6562. 4:39:20Julie yes yes sir
  6563. 4:39:23okay thank you very much
  6564. 4:39:28Well we'd ask Mr Lund Mr kiltminster and
  6565. 4:39:33Brian Russell
  6566. 4:39:35[Applause]
  6567. 4:40:02thank you
  6568. 4:40:06[Music]
  6569. 4:40:08again
  6570. 4:40:09[Music]
  6571. 4:40:12[Applause]
  6572. 4:40:19do you want to proceed and
  6573. 4:40:23and to make any
  6574. 4:40:27make any remarks or give any testimony
  6575. 4:40:29that you'd care to and stick their line
  6576. 4:40:32of the testimony we've had
  6577. 4:40:34this morning and this afternoon I'm not
  6578. 4:40:37sure there's anything we've been over so
  6579. 4:40:39many things
  6580. 4:40:42there are additional questions that
  6581. 4:40:43you're going to be able to
  6582. 4:40:47uh
  6583. 4:40:51all right how
  6584. 4:41:00I really explain the fact that you seem
  6585. 4:41:05to change your mind when you change your
  6586. 4:41:07hat
  6587. 4:41:12I guess we got to go back a little
  6588. 4:41:14further in the
  6589. 4:41:15conversations on that
  6590. 4:41:18we've dealt with Marshall for a long
  6591. 4:41:21time and I've always been in the
  6592. 4:41:22position of defending our position
  6593. 4:41:26to make sure that we're ready to fly
  6594. 4:41:30and I guess I didn't realize until after
  6595. 4:41:32that meeting and after several days that
  6596. 4:41:35we had absolutely changed in a
  6597. 4:41:38from what we had been before
  6598. 4:41:42that evening it was uh I guess I had
  6599. 4:41:45never had those kinds of things come
  6600. 4:41:47from the people at Marshall that we had
  6601. 4:41:49to prove to them that we weren't ready I
  6602. 4:41:52wouldn't move to a mic a little bit
  6603. 4:41:53closer please okay
  6604. 4:41:55so we got ourselves uh in the thought
  6605. 4:41:58process that we were trying to find some
  6606. 4:42:01way to prove to them that wouldn't work
  6607. 4:42:02and we were unable to do that
  6608. 4:42:04we couldn't prove absolutely that that
  6609. 4:42:06motor wouldn't work in other words you
  6610. 4:42:09had you honestly believe that you had a
  6611. 4:42:11duty to prove that it wasn't that's kind
  6612. 4:42:15of the mode we got ourselves into that
  6613. 4:42:16evening
  6614. 4:42:18is it seems like we've always been in
  6615. 4:42:19the opposite mode
  6616. 4:42:21I should have detected that but I did
  6617. 4:42:23not but the roles kind of Switched
  6618. 4:42:28so after
  6619. 4:42:29making a or listening to the verbal
  6620. 4:42:33presentation in the afternoon they asked
  6621. 4:42:35what fire calls positional it was and I
  6622. 4:42:37looked around the room and I was a
  6623. 4:42:38senior person and I I said I don't want
  6624. 4:42:40to fly looks to me the story says the 53
  6625. 4:42:42degrees is about it
  6626. 4:42:44and of course we requested that to go
  6627. 4:42:46back and do something more
  6628. 4:42:48and prepare detailed charts and to show
  6629. 4:42:51that in more detail
  6630. 4:42:53so we got busy then and I gave
  6631. 4:42:56assignments to a dozen or so people who
  6632. 4:42:58go out and generate data that would in a
  6633. 4:43:00Workman like manner
  6634. 4:43:02show the
  6635. 4:43:04rationale show the data that we had
  6636. 4:43:07so let everyone understand all the data
  6637. 4:43:10and where it came from
  6638. 4:43:12and we spent the next couple of hours
  6639. 4:43:13beating the bushes trying to put
  6640. 4:43:15together that data
  6641. 4:43:18so we did that and began transmitting
  6642. 4:43:21charts even late then and then went
  6643. 4:43:23through that rationale and all this time
  6644. 4:43:25we were preparing the day today it was
  6645. 4:43:27coming in I was trying to put together
  6646. 4:43:29what I was concluding out of all this
  6647. 4:43:30because there was some additional data
  6648. 4:43:32that was being generated
  6649. 4:43:34and uh
  6650. 4:43:35trying to understand and to absorb all
  6651. 4:43:38of the data that was there to again see
  6652. 4:43:40what my thought processes were and so we
  6653. 4:43:43stood at the white board there in the
  6654. 4:43:45management information center and the
  6655. 4:43:46data would come in we would try and say
  6656. 4:43:48now what does this tell us what does
  6657. 4:43:50this tell us and put together a
  6658. 4:43:51rationale for what we wanted to do
  6659. 4:43:55oh it was in a in a real-time mode and
  6660. 4:43:58we were trying to absorb the data and
  6661. 4:44:00put together the story
  6662. 4:44:02well as a result of that
  6663. 4:44:04Telecom
  6664. 4:44:06I gave the charts that made the
  6665. 4:44:07recommendation
  6666. 4:44:09that we wait until the motor got to 53
  6667. 4:44:12degrees
  6668. 4:44:14I didn't see anything different than I
  6669. 4:44:16hadn't seen before
  6670. 4:44:18and uh
  6671. 4:44:20of course you've heard the story of what
  6672. 4:44:21happened after that
  6673. 4:44:24now let me ask a question yes
  6674. 4:44:2653 degrees you've stated that you uh
  6675. 4:44:31it's been often stated that the
  6676. 4:44:33recommendation was just at this point in
  6677. 4:44:35time to stay within your experience
  6678. 4:44:36space and I find that to be a peculiar
  6679. 4:44:39recommendation in the operation of any
  6680. 4:44:42kind of system because normally you say
  6681. 4:44:44from our experience space
  6682. 4:44:47our data points our analysis and our
  6683. 4:44:49extrapolation
  6684. 4:44:51we're willing we would be willing at any
  6685. 4:44:54time to go beyond our experience point
  6686. 4:44:56out to this far as a Next Step
  6687. 4:45:00and the only reason you would say I'd
  6688. 4:45:02stay within my experience space is that
  6689. 4:45:04you had a problem at that point that
  6690. 4:45:07said you dare not go any farther because
  6691. 4:45:09so could you clarify
  6692. 4:45:11that it wasn't a question of uh of that
  6693. 4:45:14it was the very definite question of
  6694. 4:45:16conservatism
  6695. 4:45:17you know this program has people on it
  6696. 4:45:20so I'm very concerned about that and I
  6697. 4:45:22want to make sure that if there's any
  6698. 4:45:24hint of a problem that we're not
  6699. 4:45:25extending that
  6700. 4:45:27we didn't have any data at that point
  6701. 4:45:29that would indicate that we should go
  6702. 4:45:30beyond that
  6703. 4:45:31now is that an answer to the question or
  6704. 4:45:33do I try again
  6705. 4:45:35maybe a slightly different I'm asking
  6706. 4:45:39that is is
  6707. 4:45:41normally when when you're trying to
  6708. 4:45:44extrapolate Beyond maybe beyond your
  6709. 4:45:48flight experience you rely on your
  6710. 4:45:49qualification testing program and a
  6711. 4:45:52system or a subsystem is qualified to
  6712. 4:45:56fly within a certain regime or a certain
  6713. 4:45:59envelope that would include
  6714. 4:46:01environmental effects like like
  6715. 4:46:03temperature
  6716. 4:46:04um
  6717. 4:46:05did you have any sort of uh
  6718. 4:46:08qualification range on the temperature
  6719. 4:46:10of the of the SRM well yeah we had
  6720. 4:46:13development claw Motors that were down
  6721. 4:46:15in the 40s uh as has been pointed out
  6722. 4:46:18the data because of the horizontal
  6723. 4:46:21assembly problems what we were trying to
  6724. 4:46:22do is put them back to a condition that
  6725. 4:46:25would resemble that that we would have
  6726. 4:46:27in a vertical installation
  6727. 4:46:29and so we'd gone in and repaired the
  6728. 4:46:30putty because when you put those
  6729. 4:46:31together horizontally you can't do it
  6730. 4:46:34the same thing
  6731. 4:46:35you can't do it the same way so although
  6732. 4:46:38the intent was to put them back to the
  6733. 4:46:40vertical there's some doubt that you can
  6734. 4:46:42really do that adequately
  6735. 4:46:45so there's always the question well this
  6736. 4:46:48wasn't perfect and the answer was it was
  6737. 4:46:49not
  6738. 4:46:50and so my belief is that those 40 degree
  6739. 4:46:55Motors you're probably valid and
  6740. 4:46:56adequate
  6741. 4:46:58but there's the doubt
  6742. 4:47:01[Music]
  6743. 4:47:03um
  6744. 4:47:04or 40 degrees
  6745. 4:47:06you could consider it an extraction
  6746. 4:47:09taking it Taking it below what the uh
  6747. 4:47:11what the motor has been qualified to I
  6748. 4:47:14think one thing that we need to make
  6749. 4:47:15very clear is we've talked about SRM 15
  6750. 4:47:18and srm-22 being the two Motors that
  6751. 4:47:20were the blow by Motors and that we
  6752. 4:47:22couldn't tell because of those but we've
  6753. 4:47:24got to keep in mind there were 10 Motors
  6754. 4:47:26between those
  6755. 4:47:27uh 30 joints between those two
  6756. 4:47:30temperatures it had no Bubble at all
  6757. 4:47:33so I think that as Marshall pointed out
  6758. 4:47:37I think Mr boy pointed out he said you
  6759. 4:47:39know the date is just not conclusive at
  6760. 4:47:42all and it wasn't because we had a low
  6761. 4:47:44temperature motor and a high temperature
  6762. 4:47:45motor we had 10 Motors in between that
  6763. 4:47:47showed nothing could I ask you a
  6764. 4:47:49question on that
  6765. 4:47:50in looking at uh
  6766. 4:47:52the earlier data it appears there is a
  6767. 4:47:56erosion and blow-by occurring more
  6768. 4:47:58frequently later than sooner and Mr
  6769. 4:48:01Borgia pointed out that uh during the
  6770. 4:48:06year 1985 because of what he learned in
  6771. 4:48:09looking at inspecting uh uh the one
  6772. 4:48:12motor that he looked at he developed
  6773. 4:48:15greater concern and in uh in line with
  6774. 4:48:18Neil's question
  6775. 4:48:21um did you want to stay with 53 rather
  6776. 4:48:24than say exploring something slightly uh
  6777. 4:48:26beyond that because there was a greater
  6778. 4:48:28concern developing and uh this was his
  6779. 4:48:32concern uh uh did you share Mr borgele's
  6780. 4:48:35concern uh or just just why did you stay
  6781. 4:48:39with 53 again and not say explore a
  6782. 4:48:41little further
  6783. 4:48:42well again the conservative aspect of
  6784. 4:48:45looking at what our experience has been
  6785. 4:48:47and that was the rationale that we
  6786. 4:48:48presented to Marshall is stay within the
  6787. 4:48:50experience band but I don't understand
  6788. 4:48:52how did you view uh you mentioned 10
  6789. 4:48:55Motors without uh Blow by and looking at
  6790. 4:48:57the data that uh was handed out this
  6791. 4:49:00morning uh there are several cases of uh
  6792. 4:49:02of problems with various uh parts of the
  6793. 4:49:05motors and it seemed to be more of it
  6794. 4:49:07later than earlier
  6795. 4:49:09we we haven't been able to identify
  6796. 4:49:12those parameters that are causing that
  6797. 4:49:15more
  6798. 4:49:16uh pronounced effect but you look at
  6799. 4:49:19that develop since you had a problem
  6800. 4:49:21that was developing to a greater extent
  6801. 4:49:24and you it was an unknown reason is why
  6802. 4:49:26this problem would happen I can't
  6803. 4:49:28understand why there wasn't a greater
  6804. 4:49:30area of concern developing well there
  6805. 4:49:32was and that's why we initiated all of
  6806. 4:49:34this uh what are we going to do with the
  6807. 4:49:36joint how are we going to investigate it
  6808. 4:49:37set up a special task team I took one of
  6809. 4:49:40my best supervisors gave him the task of
  6810. 4:49:42doing that we signed Mr Beaujolais to
  6811. 4:49:44the task team we put one of our best
  6812. 4:49:45project Engineers on it
  6813. 4:49:46[Applause]
  6814. 4:49:48and uh
  6815. 4:49:51program manager was assigned we
  6816. 4:49:53implemented a full-time activity to to
  6817. 4:49:55evaluate do that one more question since
  6818. 4:49:59you
  6819. 4:50:00your people were responsible for the
  6820. 4:50:02design
  6821. 4:50:03were responsible for the testing were
  6822. 4:50:06responsible for the qualification when
  6823. 4:50:08it came up to the point where there was
  6824. 4:50:11a question of whether a lot should be
  6825. 4:50:13made shouldn't um
  6826. 4:50:16uh you you alone or your organization
  6827. 4:50:20alone be the one that says yes or not
  6828. 4:50:22and uh why would there be a question
  6829. 4:50:26coming uh from NASA because of not
  6830. 4:50:30having data
  6831. 4:50:32as well presented whether he wanted why
  6832. 4:50:35would they raise questions on your data
  6833. 4:50:37and why would you respond to that
  6834. 4:50:39question why didn't you just tell them
  6835. 4:50:41it's our decision and this is it and not
  6836. 4:50:43respond to the pressure
  6837. 4:50:50as a quarterback on Monday morning
  6838. 4:50:52that's probably what I should have done
  6839. 4:50:54but
  6840. 4:50:55you know you you work with people and
  6841. 4:50:58you develop some confidence and I have
  6842. 4:50:59some great confidence in those people in
  6843. 4:51:01NASA we've worked with we worked with
  6844. 4:51:03for a long long time in in what I think
  6845. 4:51:06I've heard is that uh
  6846. 4:51:09your experts who are developing a
  6847. 4:51:11greater and greater concern including
  6848. 4:51:14writing a rather powerfully stated memos
  6849. 4:51:17and uh it's hard to understand why they
  6850. 4:51:20didn't get more attention
  6851. 4:51:24[Music]
  6852. 4:51:30response the earlier answer about the 10
  6853. 4:51:32Motors between the 53 degrees and the 75
  6854. 4:51:35degrees
  6855. 4:51:37well one conclusion might be from that
  6856. 4:51:41database is that you shouldn't
  6857. 4:51:44operate at 75 degrees or 53 degrees but
  6858. 4:51:47you ought to stay within the temperature
  6859. 4:51:49range of those motors which exhibited no
  6860. 4:51:52erosion or Flow by uh so again I'm going
  6861. 4:51:58to ask you the same question I asked
  6862. 4:52:00before uh what
  6863. 4:52:05what was conservative about saying 53 or
  6864. 4:52:09instead of a number other than that
  6865. 4:52:11which might be higher or might be lower
  6866. 4:52:13depending on how you approach the
  6867. 4:52:14problem trying to understand your
  6868. 4:52:16thought process I guess all of the
  6869. 4:52:18engineering rationale says that coal was
  6870. 4:52:21probably worse the warm was probably
  6871. 4:52:22better in all the physics of the
  6872. 4:52:24situation as we best understood them
  6873. 4:52:27so we felt that you know the
  6874. 4:52:30conservative thing to do would be to
  6875. 4:52:31stay warmer yeah but did you like 53
  6876. 4:52:33degrees did you like the results on the
  6877. 4:52:3553 degree flight
  6878. 4:52:38I would rather have a motor that has no
  6879. 4:52:40erosion no blow by and looks perfect at
  6880. 4:52:42the end of the motor fire then then
  6881. 4:52:43might not you not have taken the
  6882. 4:52:45position that 57 would have been a
  6883. 4:52:47better number 62 or some other room we
  6884. 4:52:49have had you know Motors down in the low
  6885. 4:52:5160s and I guess there's some just
  6886. 4:52:54looking at my chart
  6887. 4:52:57uh in the low 60s at least that were
  6888. 4:53:00perfect
  6889. 4:53:02it has some had some in the the lower
  6890. 4:53:0550s that were not anywhere near as bad
  6891. 4:53:07as the 15.
  6892. 4:53:09so there's no clear dividing line at
  6893. 4:53:11least there's a lot of other factors
  6894. 4:53:12other than the temperature that might be
  6895. 4:53:14involved is that correct that's correct
  6896. 4:53:15so we don't know how we don't know how
  6897. 4:53:17to know what the effect the temperature
  6898. 4:53:19was
  6899. 4:53:20you can ask one more question
  6900. 4:53:23um
  6901. 4:53:23uh you know I heard these comments that
  6902. 4:53:26uh some tests look pretty good at 75 and
  6903. 4:53:29others looked okay at 53
  6904. 4:53:33but was the qualification testing
  6905. 4:53:36thorough enough for any proper database
  6906. 4:53:39to be in hand to really know what the uh
  6907. 4:53:43critical variables are like the thrust
  6908. 4:53:46of the motor
  6909. 4:53:48the the tolerances of the metal joints
  6910. 4:53:52the tolerances of the O-rings or the
  6911. 4:53:54application of the putty or the
  6912. 4:53:56application of the seal isn't one of
  6913. 4:53:59your problems the fact that the
  6914. 4:54:00qualification testing was inadequate
  6915. 4:54:04it seems like the
  6916. 4:54:06size of the qualification program is
  6917. 4:54:10inversely proportional to the size of
  6918. 4:54:12the motor
  6919. 4:54:13which is called dollars and there's no
  6920. 4:54:15doubt about that with small typical
  6921. 4:54:17Motors It's Not Unusual to fire for many
  6922. 4:54:19many many and the larger the motor than
  6923. 4:54:21the smaller the qualification program
  6924. 4:54:23and to get a full statistical range of
  6925. 4:54:25every parameter in that motor
  6926. 4:54:28I don't think there's enough money in
  6927. 4:54:30the National treasury to do that
  6928. 4:54:32so there's a practical limit to what you
  6929. 4:54:35do go from the qualified motor and make
  6930. 4:54:38changes and uh and and go into another
  6931. 4:54:41area of further unknown exploration like
  6932. 4:54:44reducing the strength of the uh a motor
  6933. 4:54:46or increasing the thrust or changing the
  6934. 4:54:49putty
  6935. 4:54:51there were qualification Motors of
  6936. 4:54:53course to do the strength of or the
  6937. 4:54:56thickness of the case and the thrust
  6938. 4:54:57change
  6939. 4:54:59well worthy etiquette
  6940. 4:55:03engineering opinion yes
  6941. 4:55:06I have a question on
  6942. 4:55:08Mr McDonald testified that he had a
  6943. 4:55:11discussion I believe it was Mr Malloy
  6944. 4:55:13about the meaning of the temperature
  6945. 4:55:17range of 40 to 90 degrees rather reply
  6946. 4:55:21just to the bulk temperature of the
  6947. 4:55:22motor or whether it's applied to every
  6948. 4:55:25part of the shuttle what's your
  6949. 4:55:26understanding
  6950. 4:55:29you would have asked me uh
  6951. 4:55:31a month ago I told you the motor is 40
  6952. 4:55:34to 90.
  6953. 4:55:35so there's no qualification in your mind
  6954. 4:55:39on the O-ring temperature
  6955. 4:55:42for example the O-ring temperature could
  6956. 4:55:44have been quite cold because the O-ring
  6957. 4:55:46is certainly going to move in
  6958. 4:55:49temperature with metal case the metal
  6959. 4:55:51case could be quite a bit colder than
  6960. 4:55:54the bulk temperature of the propellant
  6961. 4:55:56if the weather had been cold there was
  6962. 4:55:59no full-scale Motors fire below 40.
  6963. 4:56:02but what I'm asking is
  6964. 4:56:04did you as the supplier of the system to
  6965. 4:56:09the government have a specification on
  6966. 4:56:12the O-ring temperature
  6967. 4:56:15or could the Oregon temperature have
  6968. 4:56:16been anything
  6969. 4:56:18I don't believe there is a specification
  6970. 4:56:20on the O-ring temperature other than the
  6971. 4:56:23material itself
  6972. 4:56:25and what is that specification well it's
  6973. 4:56:29a specification that says the material
  6974. 4:56:31can withstand these kinds of
  6975. 4:56:33environments
  6976. 4:56:34but it doesn't specify the operational
  6977. 4:56:37aspect
  6978. 4:56:39in fact the milsomatic says specifically
  6979. 4:56:42that the O-ring should be qualified for
  6980. 4:56:45whatever uses they're put to
  6981. 4:56:47so did you take any steps to do that is
  6982. 4:56:50qualified the range of temperatures over
  6983. 4:56:54which these O-rings were to be yes they
  6984. 4:56:57used the development Motors were fired
  6985. 4:56:59from 40 to 84 and the qualification
  6986. 4:57:02motors from 45 to 83. so then 40 degrees
  6987. 4:57:05was the temperature limit for the owner
  6988. 4:57:09in the full-scale call program that's
  6989. 4:57:11correct so when it was predicted that
  6990. 4:57:14the temperature of the O-ring had
  6991. 4:57:17launched 51l was going to be 29 degrees
  6992. 4:57:19the O-ring was outside of the
  6993. 4:57:22qualification temperatures by some 10
  6994. 4:57:24degrees that's correct then how could
  6995. 4:57:26you make a recommendation to launch if
  6996. 4:57:28you're 10 degrees outside of your
  6997. 4:57:30qualification
  6998. 4:57:31our original recommendation course was
  6999. 4:57:34not to launch well I understand that but
  7000. 4:57:36your final recommendation was to launch
  7001. 4:57:38okay what we need to do then is go
  7002. 4:57:40through that rash now
  7003. 4:57:45are you going to answer my question then
  7004. 4:57:46at the end of this discussion hopefully
  7005. 4:57:50well you want to go through now I'd be
  7006. 4:57:52glad to do that
  7007. 4:57:56I mean I think we've heard what
  7008. 4:57:59the explanation you've given I think the
  7009. 4:58:01problem we're having is
  7010. 4:58:03it doesn't it's not convincing
  7011. 4:58:05I mean let me if you don't mind actually
  7012. 4:58:08uh
  7013. 4:58:11you I assume you have great confidence
  7014. 4:58:14in your engineers and Thompson the
  7015. 4:58:16others
  7016. 4:58:18and they're probably as well qualified
  7017. 4:58:20as anybody in the country they're
  7018. 4:58:21dealing with these problems or rings and
  7019. 4:58:24seals and so forth
  7020. 4:58:25so
  7021. 4:58:27yeah
  7022. 4:58:29and uh
  7023. 4:58:31you had a long discussion in the Telecom
  7024. 4:58:34and you decided all of you I understand
  7025. 4:58:37all of you decided that for safety
  7026. 4:58:40reasons you would oppose the launch
  7027. 4:58:45[Music]
  7028. 4:58:47NASA in one way or another made it clear
  7029. 4:58:50that they who were displeased with that
  7030. 4:58:53recommendation
  7031. 4:58:55and I assume that you knew when you made
  7032. 4:58:58the recommendation that that your
  7033. 4:59:01recommendation in fact was going to
  7034. 4:59:03determine whether that shuttle would be
  7035. 4:59:05launched or not because
  7036. 4:59:07NASA had indicated to you they would not
  7037. 4:59:09fly unless they had a written report
  7038. 4:59:11from high call saying you approved the
  7039. 4:59:14launch
  7040. 4:59:15I don't I didn't know that NASA would
  7041. 4:59:17accept that you didn't know that well
  7042. 4:59:20you must have known your recommendation
  7043. 4:59:22was very important
  7044. 4:59:23you knew that if you voted against the
  7045. 4:59:26launch it would not have been launched
  7046. 4:59:27didn't you well we voted prior to it and
  7047. 4:59:30they didn't accept it so I I couldn't
  7048. 4:59:33forecast for NASA no but you knew that
  7049. 4:59:35that was the reason they asked you to
  7050. 4:59:37reconsider that's why you went had the
  7051. 4:59:39five-minute recess didn't you that's
  7052. 4:59:41fair statement yes now knowing that
  7053. 4:59:45and knowing that the the safety of the
  7054. 4:59:48crew is involved
  7055. 4:59:50and knowing your own people the
  7056. 4:59:53engineers that you respected were still
  7057. 4:59:55against the launch what was it that
  7058. 4:59:58occurred in your mind that satisfied you
  7059. 5:00:01to say okay let's take a chance
  7060. 5:00:04well I didn't say take a chance because
  7061. 5:00:06I I felt there was some rationale that
  7062. 5:00:09allowed us to to go ahead
  7063. 5:00:12well maybe that isn't fair then what was
  7064. 5:00:14it that occurred in your mind that
  7065. 5:00:16caused you to be willing to change your
  7066. 5:00:19mind
  7067. 5:00:20I guess one of the the big things was is
  7068. 5:00:23that we really didn't know whether
  7069. 5:00:24temperature was the driver or not we
  7070. 5:00:26couldn't tell
  7071. 5:00:28we had Hot Motors that blew by and coal
  7072. 5:00:30Motors that blew by and some very near
  7073. 5:00:32either end that did not the data was
  7074. 5:00:35inconclusive
  7075. 5:00:36so I had trouble justifying my online
  7076. 5:00:39temperature is a factor
  7077. 5:00:42second uh manner for just one moment uh
  7078. 5:00:46Mr Beaujolais has said that the thing
  7079. 5:00:48which was compelling to him was that the
  7080. 5:00:51blow by on the coldest motor was much
  7081. 5:00:55more severe he's emphasized how black
  7082. 5:00:57was the bulldeye how large an hangover
  7083. 5:00:59which occurred but three or four degrees
  7084. 5:01:01above that there was Zero
  7085. 5:01:03so his his discussion was not convincing
  7086. 5:01:07to you well it wasn't totally convincing
  7087. 5:01:09because you know at two or three degrees
  7088. 5:01:11it went from very very bad to
  7089. 5:01:14no problem
  7090. 5:01:16[Music]
  7091. 5:01:23so it's obviously a random effect it
  7092. 5:01:26depends upon whether or not you're going
  7093. 5:01:28to blowhole you don't get a blowhole so
  7094. 5:01:30there's a bit of particular flight it
  7095. 5:01:31happens at all six Fields don't get a
  7096. 5:01:34block or that's no information the fact
  7097. 5:01:37that as far as I can understand this it
  7098. 5:01:39doesn't mean you're suddenly good
  7099. 5:01:41because it worked and the next time when
  7100. 5:01:43one goes off you're suddenly bad well
  7101. 5:01:45it's just to me that it has to be
  7102. 5:01:47understood as a probabilistic and
  7103. 5:01:49confusing complicated situation that
  7104. 5:01:51we're never going to be able to decide
  7105. 5:01:53that they're all going to break or
  7106. 5:01:55they're all not going to break it's not
  7107. 5:01:56the wonderful one-horse shed and when
  7108. 5:01:58you look at it that way then it's a
  7109. 5:02:00question of increasing and decreasing
  7110. 5:02:02probabilities that we have to consider
  7111. 5:02:04rather than did it work with things that
  7112. 5:02:05work and I'd like to think explain it to
  7113. 5:02:08me from that point of view well the
  7114. 5:02:10question still is is temperature the
  7115. 5:02:12thing that caused the srn 15. you heard
  7116. 5:02:15your engineers argued that there was an
  7117. 5:02:17effect of temperature which looked like
  7118. 5:02:19it made things worse is it not
  7119. 5:02:21inconceivable that there's something
  7120. 5:02:23else that sometimes produces Blow by
  7121. 5:02:25that there's more than one effect and
  7122. 5:02:27that the temperature could still be an
  7123. 5:02:29important effect and increase the
  7124. 5:02:31probability of the fact that at a high
  7125. 5:02:33temperature it gets worse is there any
  7126. 5:02:35evidence
  7127. 5:02:36the temperature is not a important
  7128. 5:02:38matter just because at some high
  7129. 5:02:40temperature you have an accident well
  7130. 5:02:43there's as you point out there are many
  7131. 5:02:44variables in the thing and it wasn't
  7132. 5:02:46clear the temperature was the effect
  7133. 5:02:49it was logically from the point of view
  7134. 5:02:51of the engineers they were explaining
  7135. 5:02:53why the temperature would have an
  7136. 5:02:54Effectiveness in the in the when you
  7137. 5:02:56don't have any data you have to use
  7138. 5:02:58reason okay and they were giving reasons
  7139. 5:03:00that's right and that's what we did is
  7140. 5:03:03we included in our rationale the fact
  7141. 5:03:05that sure enough the temperature could
  7142. 5:03:07be in effect
  7143. 5:03:08okay it wasn't clear but we said we will
  7144. 5:03:10consider that to be so
  7145. 5:03:12I I have great difficulty with this
  7146. 5:03:16unusual practice when there's any uh a
  7147. 5:03:21real doubt about flight safety for this
  7148. 5:03:24aircraft or whatever you simply don't
  7149. 5:03:26and it seems to me this is a reverse and
  7150. 5:03:29I I just have great difficulty
  7151. 5:03:31understanding the question that's been
  7152. 5:03:34asked before that is understanding any
  7153. 5:03:36answer I just haven't heard it as to why
  7154. 5:03:38if there is doubt in your mind why you
  7155. 5:03:41went ahead why you change your mind I
  7156. 5:03:44just don't understand it I appreciate
  7157. 5:03:46very much if you could explain that
  7158. 5:03:50he signed the Halifax and we've we've
  7159. 5:03:54asked us to learn a lot of questions and
  7160. 5:03:56I think maybe a fairness to Mr one Mr
  7161. 5:03:58can you uh
  7162. 5:04:01uh
  7163. 5:04:03attempt to explain to the commission
  7164. 5:04:06so why
  7165. 5:04:08I guess you changed your mind too didn't
  7166. 5:04:11you yes sir based on the uh discussion
  7167. 5:04:14that we had in the rationale that was
  7168. 5:04:17developed so how can you say you changed
  7169. 5:04:19your mind when you say capture data not
  7170. 5:04:21conclusive on predicting primary o-ring
  7171. 5:04:24Boulevard
  7172. 5:04:26did you have a feeling you had to prove
  7173. 5:04:28that it was
  7174. 5:04:30uh the burden of proof was I knew to
  7175. 5:04:34show that it wasn't safe no I think we
  7176. 5:04:37were asked to re-look at the data which
  7177. 5:04:39we did but what could you tell me what
  7178. 5:04:41data was that you looked at that was
  7179. 5:04:43different from the data you looked at
  7180. 5:04:44first
  7181. 5:04:45there was one piece of data that we
  7182. 5:04:47looked at which has been discussed
  7183. 5:04:49before that was the erosion parameter
  7184. 5:04:52and the factor of three but my
  7185. 5:04:55evaluation was is that the only new
  7186. 5:04:58piece of data that's really the only new
  7187. 5:05:00piece of data that we had not previously
  7188. 5:05:02discussed on the telephone
  7189. 5:05:05but I think that the data that we did
  7190. 5:05:08show
  7191. 5:05:09the fact that we had subscale tests
  7192. 5:05:11uh at 30 degrees showing no blow by was
  7193. 5:05:15an indicator
  7194. 5:05:17we as Mr Lund pointed out had other
  7195. 5:05:20flight Motors at temperatures between
  7196. 5:05:22the two in question that is 75 degrees
  7197. 5:05:25and 53 degrees overring temperatures
  7198. 5:05:27that had shown no blow by
  7199. 5:05:30and we had static test Motors at
  7200. 5:05:33temperatures lower than 53 degrees that
  7201. 5:05:35had no bull buy now I'd like to discuss
  7202. 5:05:37that just a moment could you
  7203. 5:05:39particularly though point out the new
  7204. 5:05:41data because the purposes we understand
  7205. 5:05:44it for the recess was to it was to find
  7206. 5:05:48out if there was any new data
  7207. 5:05:50however you just have to change your
  7208. 5:05:53mind based on the data you had
  7209. 5:05:56one piece of data that was new in our
  7210. 5:05:59discussion
  7211. 5:06:00was that if we did have blow by past the
  7212. 5:06:04primary o-ring
  7213. 5:06:06as it was being positioned to seal and
  7214. 5:06:09recognizing the fact that the cold
  7215. 5:06:12temperatures could cause that timing
  7216. 5:06:13function to extend
  7217. 5:06:16then we had an opportunity perhaps of
  7218. 5:06:20having some erosion occur
  7219. 5:06:22we looked at the erosion that had
  7220. 5:06:24occurred on 51 Charlie
  7221. 5:06:27and compared that to the data that we
  7222. 5:06:29had developed both from cold
  7223. 5:06:32hydraulic oil testing and from hot
  7224. 5:06:36subscale testing that indicated we that
  7225. 5:06:39that very polite had a safety factor of
  7226. 5:06:42three
  7227. 5:06:43over what would have to have happened
  7228. 5:06:46in order to get to an area of
  7229. 5:06:49questionable ceiling capability
  7230. 5:06:52and with that information in mind then
  7231. 5:06:55and also the fact that we had had some
  7232. 5:06:59analytical work done earlier to develop
  7233. 5:07:02the limiting erosion parameters on
  7234. 5:07:06O-rings
  7235. 5:07:07uh led me to believe that we were ha we
  7236. 5:07:11were in the condition of having a safe
  7237. 5:07:13position for recommending a flight the
  7238. 5:07:15positive erosion excuse me how come that
  7239. 5:07:18data wasn't available the first time how
  7240. 5:07:20did it happen to show up at the recess
  7241. 5:07:22well it was just a matter of a
  7242. 5:07:25discussion that we had while we had the
  7243. 5:07:28recess
  7244. 5:07:29when we said that well if indeed the
  7245. 5:07:33temperature is going to cause a longer
  7246. 5:07:35time for the primary function primary
  7247. 5:07:37o-ring to function
  7248. 5:07:39and there is the possibility of
  7249. 5:07:40additional erosion
  7250. 5:07:43then where do we stand relative to 51c
  7251. 5:07:46and how much more margin did that
  7252. 5:07:49exhibit so you really had the data there
  7253. 5:07:51before yes you had to analyze it in
  7254. 5:07:53other words it was not new data just say
  7255. 5:07:56that you hadn't properly analyzed right
  7256. 5:07:58I was stated that we hadn't uh prepared
  7257. 5:08:00or discussed on the earlier telecon
  7258. 5:08:03earlier portion of the time that was
  7259. 5:08:04through an oversight
  7260. 5:08:07um well I don't know if there's an
  7261. 5:08:08oversight for uh just another piece of
  7262. 5:08:10data that we were searching for in order
  7263. 5:08:13to establish our positions
  7264. 5:08:17[Music]
  7265. 5:08:18of three over the 51c
  7266. 5:08:22erosion problem
  7267. 5:08:26how were you how were you attempting to
  7268. 5:08:29analyze how the timing function would
  7269. 5:08:31change
  7270. 5:08:34and how much erosion that could possibly
  7271. 5:08:36give you on on 51l only on a subjective
  7272. 5:08:40basis that
  7273. 5:08:42if as has been stated the timing
  7274. 5:08:45function under cold condition was to
  7275. 5:08:47extend and if what was observed under 51
  7276. 5:08:50C uh not only the blow by but the
  7277. 5:08:54erosion were combined then we developed
  7278. 5:08:58the rationale about that safety factor
  7279. 5:09:00of three
  7280. 5:09:01humans feeling of pressure being put on
  7281. 5:09:04You by NASA or you just calmly uh
  7282. 5:09:08reassessing
  7283. 5:09:10uh and I felt that the pressure that was
  7284. 5:09:12put on us was to go back and look at the
  7285. 5:09:15data look at the detailed information
  7286. 5:09:17that had been presented to see if there
  7287. 5:09:20was something that we were seeing that
  7288. 5:09:23we were not representing on the phone
  7289. 5:09:25you didn't feel that they were trying to
  7290. 5:09:27get you to change your mind I did not
  7291. 5:09:29feel a significant amount of pressure in
  7292. 5:09:32that regard
  7293. 5:09:34Spencer
  7294. 5:09:36have you had an opportunity to look at
  7295. 5:09:38the
  7296. 5:09:39correspondence of Mr Beaujolais written
  7297. 5:09:42in the Summer and Autumn of 85
  7298. 5:09:45no I have none
  7299. 5:09:53they're both nice
  7300. 5:09:54to you
  7301. 5:09:5531 August 31 July rather you receive
  7302. 5:09:59that in in Reddit I presume yes we took
  7303. 5:10:02immediate action on that and we
  7304. 5:10:03established the O-ring task team within
  7305. 5:10:05a week or so of that memo did you pass
  7306. 5:10:08along Mr Beaujolais concerns to uh
  7307. 5:10:11anyone at NASA
  7308. 5:10:13thank you
  7309. 5:10:15the normal process of that sort of
  7310. 5:10:17information is through the project
  7311. 5:10:18office and Mr McDonald and so on were on
  7312. 5:10:22that that would be their task well then
  7313. 5:10:25you're saying that it would have been Mr
  7314. 5:10:27McDonald's responsibility to alert NASA
  7315. 5:10:30that the key engineer on a catastrophe
  7316. 5:10:33was possible I think NASA understood
  7317. 5:10:35that clearly and we have been working
  7318. 5:10:37with him since that time on this whole
  7319. 5:10:39problem I'm not asking that I'm asking
  7320. 5:10:41whether as a result of Mr bolsheva's
  7321. 5:10:44memo to you
  7322. 5:10:45you or Mr McDonald or anyone else at
  7323. 5:10:48Firefall alerted NASA to the concerns of
  7324. 5:10:52this key engineer
  7325. 5:10:55I did not call anyone at Nasa
  7326. 5:10:57specifically but I saw that they were
  7327. 5:10:58alerted because of their immediate
  7328. 5:11:00response in working with us
  7329. 5:11:02are you aware of their having heard that
  7330. 5:11:06a potential catastrophe was possible
  7331. 5:11:17I like that a couple of questions about
  7332. 5:11:21the temperature if I may a sequence of
  7333. 5:11:24questions
  7334. 5:11:25uh you say that on this 40 to 90 degree
  7335. 5:11:29launch or certification criteria is this
  7336. 5:11:32a cold soap as far as this uh some other
  7337. 5:11:36kind of a temperature and the 40 to 90
  7338. 5:11:40degrees is a mean bulk temperature of
  7339. 5:11:42the propellant which means to me that we
  7340. 5:11:45could have a motor that where the
  7341. 5:11:47propellant grain was soaked out to 40
  7342. 5:11:50degrees or conversely propellant grain
  7343. 5:11:53was soaked out to 90 degrees what's the
  7344. 5:11:55time constant on this case plus the
  7345. 5:11:58insulator and so forth and to get to a
  7346. 5:12:01equilibrium bulk temperature
  7347. 5:12:04uh and we ran some calculations based on
  7348. 5:12:07equilibrium at the cape and I believe
  7349. 5:12:10it's about 30 days so that it's possible
  7350. 5:12:13to be exposed to a cold temperature and
  7351. 5:12:16have sharp temperature gradients within
  7352. 5:12:18the propellant or the insulator and and
  7353. 5:12:22so part of it would be at a temperature
  7354. 5:12:24for outside of what you think would be
  7355. 5:12:27appropriate and the rest of them will
  7356. 5:12:30still be warmer shall we say yes but I
  7357. 5:12:33think that is limited by the other
  7358. 5:12:35requirements which uh was spelled out in
  7359. 5:12:38a level two document that said 31
  7360. 5:12:40degrees to 99 degrees
  7361. 5:12:43is it possible that some of it could be
  7362. 5:12:45at 26 degrees and other at 55 degrees
  7363. 5:12:50uh considering again it's 21 to 30-day
  7364. 5:12:54transient to get to the ball temperature
  7365. 5:12:56that's not the way I would read the the
  7366. 5:12:59combined two specifications or two
  7367. 5:13:02requirements is it possible that there
  7368. 5:13:05is a difference between the behavior of
  7369. 5:13:07the subscale motors at some temperature
  7370. 5:13:09and the behavior of the large Motors at
  7371. 5:13:12the same temperature if one was in
  7372. 5:13:14thermal equilibrium and the other was in
  7373. 5:13:16some sort of a non-uniform temperature
  7374. 5:13:18distribution yes I would expect there
  7375. 5:13:20could be some differences so there may
  7376. 5:13:22be some doubt in your mind about how
  7377. 5:13:24exactly to apply the subscale motor data
  7378. 5:13:27and within the framework of a
  7379. 5:13:29large-scale motor if you will offer the
  7380. 5:13:31temperature temperature transient yes
  7381. 5:13:33sir all right thank you Russell
  7382. 5:13:38[Music]
  7383. 5:13:40when I was talking with you a few days
  7384. 5:13:42ago at your plant I think I'm correct in
  7385. 5:13:45recalling that one of you told me that
  7386. 5:13:47if the temperature at the cape on the
  7387. 5:13:52day of launch have been in the 9 to 10
  7388. 5:13:55degrees above zero
  7389. 5:13:57Fahrenheit range there would be no
  7390. 5:14:00question but that you would have stuck
  7391. 5:14:02to a no launch position am I right in
  7392. 5:14:04that recollection that's right there's
  7393. 5:14:06many many things in the motor head that
  7394. 5:14:08would be concerned so so you did
  7395. 5:14:09recognize that temperature was a
  7396. 5:14:12discriminator yes in an absolute sense
  7397. 5:14:14the only question was what the margin
  7398. 5:14:16was below 53 degrees that's correct
  7399. 5:14:21um
  7400. 5:14:22were you
  7401. 5:14:24acquainted at all with this
  7402. 5:14:26correspondence which I assume you have a
  7403. 5:14:28chance to read if Mr Beaujolais written
  7404. 5:14:31in the
  7405. 5:14:32Summer and Autumn of 85
  7406. 5:14:34it seems to say that
  7407. 5:14:37management does not have an adequately
  7408. 5:14:40heightened
  7409. 5:14:41sense of the urgency of the work to be
  7410. 5:14:44done on the O-ring problem
  7411. 5:14:46the seal problem
  7412. 5:14:48I my question is were you aware of that
  7413. 5:14:52feeling on his part at the time
  7414. 5:14:55and did it cause you concern and what if
  7415. 5:14:58anything
  7416. 5:14:59did you do about it we had I didn't meet
  7417. 5:15:02with Mr Bosley I met with Don Kettner
  7418. 5:15:04who is the task team leader he made
  7419. 5:15:07recommendations to us and I think we
  7420. 5:15:09followed those recommendations and did
  7421. 5:15:11everything we could to help them with
  7422. 5:15:12them now they're undoubtedly are things
  7423. 5:15:14that were bugging them that they didn't
  7424. 5:15:16bring to my attention that I didn't do
  7425. 5:15:17anything about because they didn't know
  7426. 5:15:18about them
  7427. 5:15:19but when they came and Don Kenner
  7428. 5:15:23particularly we worked very hard with
  7429. 5:15:24him to try and establish and take
  7430. 5:15:26corrective action as needed thank you
  7431. 5:15:31[Music]
  7432. 5:15:32I'm sure that all of you and everybody
  7433. 5:15:35associated with shuttle knew that it was
  7434. 5:15:38NASA's intention to fly
  7435. 5:15:40on a very rapid time schedule throughout
  7436. 5:15:43the year or build up to the point of the
  7437. 5:15:45and that they would have to launch on
  7438. 5:15:47winter mornings and other time did in
  7439. 5:15:51the process of eval evaluating the the
  7440. 5:15:54information brought to you did you at
  7441. 5:15:56any time suggest to NASA that the launch
  7442. 5:16:00it launch commit criteria the lcc's or
  7443. 5:16:04other rules may be uh
  7444. 5:16:08insufficiently constraining and if you
  7445. 5:16:10ought to establish rules with respect to
  7446. 5:16:12the SRM that kept you one either within
  7447. 5:16:16your experience base your qual test or
  7448. 5:16:18your extrapolations we did not uh Mr
  7449. 5:16:22McDonald evidently had some discussions
  7450. 5:16:24with him on that line
  7451. 5:16:27thank you sir
  7452. 5:16:30thanks for Mr Russell
  7453. 5:16:33[Applause]
  7454. 5:16:33um
  7455. 5:16:34perhaps you would give us your
  7456. 5:16:37recollection of the thought process
  7457. 5:16:39followed in your mind
  7458. 5:16:41uh in the change of position between the
  7459. 5:16:47view presented in the Telecom that fire
  7460. 5:16:50coil was opposed to a launch and the
  7461. 5:16:53subsequent conclusion of the caucus
  7462. 5:16:55within the company
  7463. 5:16:58I uh
  7464. 5:17:00I was part of the overall days efforts
  7465. 5:17:03that started off pretty early as has
  7466. 5:17:05been mentioned and and as the day
  7467. 5:17:09developed uh pretty much agreed with the
  7468. 5:17:11recommendations and as ours our
  7469. 5:17:13presentation was made on the charts the
  7470. 5:17:16subsequent answers that came back you've
  7471. 5:17:19asked others if if they felt pressure
  7472. 5:17:22and undue pressure and and
  7473. 5:17:25I felt some pressure with some of the
  7474. 5:17:27comments I thought our rationale was was
  7475. 5:17:30reasonable I've seen many instances in
  7476. 5:17:33the past where we have used previous
  7477. 5:17:37limits for data on on putty that I'm
  7478. 5:17:40familiar with and other raw materials
  7479. 5:17:42for example that we do not exceed are
  7480. 5:17:44experience based in the usage of these
  7481. 5:17:46materials and so I felt that this was
  7482. 5:17:49the proper thing to do albeit our 53
  7483. 5:17:51degree experience that has been
  7484. 5:17:53mentioned uh wasn't desirable but we had
  7485. 5:17:57deemed it acceptable at that time and
  7486. 5:18:01the statements that seem to me to
  7487. 5:18:05to uh
  7488. 5:18:07to put pressure or at least to to make
  7489. 5:18:10me feel the pressure were the uh the
  7490. 5:18:14responses of of being appalled at our
  7491. 5:18:16recommendations
  7492. 5:18:17uh the responses of when we should
  7493. 5:18:21launch how long do we have to wait April
  7494. 5:18:23and and also there was an argument about
  7495. 5:18:26what sort of rationale we could have for
  7496. 5:18:2853 degrees and Mr Armstrong made the
  7497. 5:18:30point that that what temperature could
  7498. 5:18:32we make a a strong statement on and the
  7499. 5:18:35data was uh couldn't tell us which
  7500. 5:18:39temperature other than 53 degrees which
  7501. 5:18:41had been our previously
  7502. 5:18:43uh most successful low temperature and
  7503. 5:18:47so I I felt some pressure based on those
  7504. 5:18:49comments I'd like to add that my feeling
  7505. 5:18:51is as uh I believe it was Mr Malloy and
  7506. 5:18:55this is Again by voice recognition but
  7507. 5:18:57after we had made our recommendation
  7508. 5:18:58initially
  7509. 5:19:00he
  7510. 5:19:01he
  7511. 5:19:03for about five minutes and explained in
  7512. 5:19:05his mind uh why the data really didn't
  7513. 5:19:08add up to the conclusions that we had
  7514. 5:19:10made and I'll have to admit at that time
  7515. 5:19:13that it was a very logical presentation
  7516. 5:19:16uh that he had made and then there was
  7517. 5:19:18talk back and forth as to what the data
  7518. 5:19:20really meant and this has been mentioned
  7519. 5:19:22here there in the caucus they're they're
  7520. 5:19:26weren't any new data uh brought up that
  7521. 5:19:29I recognized we pretty much talked over
  7522. 5:19:32the same types of of things and and my
  7523. 5:19:35feeling of it was is
  7524. 5:19:37what uh some of us were understanding
  7525. 5:19:39and what others were understanding and
  7526. 5:19:41feeling important didn't really agree I
  7527. 5:19:44didn't make I think I can only recall
  7528. 5:19:47making one comment in the caucus uh I
  7529. 5:19:50can't even remember what that was and it
  7530. 5:19:52was very brief and I I don't think made
  7531. 5:19:54a big impact at all and the reason that
  7532. 5:19:57I didn't make so many comments despite
  7533. 5:19:58what I I felt was that Roger and Arnie
  7534. 5:20:03were were making the points to the best
  7535. 5:20:05that they could and I couldn't see a way
  7536. 5:20:06of making them any better
  7537. 5:20:08so
  7538. 5:20:10um
  7539. 5:20:11we got to a point in the caucus where Mr
  7540. 5:20:15Mason said and rightfully so we're we're
  7541. 5:20:17covering the same information we're not
  7542. 5:20:19talking about anything new here and it's
  7543. 5:20:21time for a decision
  7544. 5:20:23and uh
  7545. 5:20:25I
  7546. 5:20:26I may depend in my position to to feel
  7547. 5:20:29pressure more so I know these other
  7548. 5:20:31gentlemen have many pressures from all
  7549. 5:20:34sides and so I can't really speak to
  7550. 5:20:36them but I felt pressure that we were
  7551. 5:20:40and I don't know if if Roger was
  7552. 5:20:42referring to me in his testimony but he
  7553. 5:20:44could have been because I had the
  7554. 5:20:46feeling that we were in it or it was a
  7555. 5:20:48distinct feeling that we were in the
  7556. 5:20:50position of having to prove it was
  7557. 5:20:52unsafe instead of the other way around
  7558. 5:20:53which uh was a totally new experience
  7559. 5:20:57and I believe I made that statement
  7560. 5:20:59afterward I know I did when I went home
  7561. 5:21:01and talked about it with my wife
  7562. 5:21:04but here again I
  7563. 5:21:09it's I think it's impossible for me to
  7564. 5:21:11say what might have swung the decision
  7565. 5:21:13but I I felt in my mind that that once
  7566. 5:21:16we had done our very best to explain why
  7567. 5:21:17we were concerned and we meaning those
  7568. 5:21:20in the camp who who really felt strongly
  7569. 5:21:23about the recommendation of 53 degrees
  7570. 5:21:26uh uh the decision was was to be made
  7571. 5:21:30and and a poll was was then taken and I
  7572. 5:21:34remember distinctly at the time whether
  7573. 5:21:36I would have the the courage if I asked
  7574. 5:21:38and I thought I might be
  7575. 5:21:40um
  7576. 5:21:41what I would do and whether I would be
  7577. 5:21:43alone I didn't think I'd be alone but I
  7578. 5:21:45was wondering if I'd have the courage I
  7579. 5:21:47remember that distinctly to stand up and
  7580. 5:21:49say no uh however uh
  7581. 5:21:52we were not asked as uh as the
  7582. 5:21:55engineering people it was a a management
  7583. 5:21:59decision that the vice president's level
  7584. 5:22:01and they had heard all that that they
  7585. 5:22:03could hear and
  7586. 5:22:05and uh I I felt there was nothing more
  7587. 5:22:08to say uh that we could change anything
  7588. 5:22:11and also felt in my mind that I didn't
  7589. 5:22:14see and I I believe I mentioned this to
  7590. 5:22:16you last week that I I didn't see a
  7591. 5:22:18dangerous concern I knew we were
  7592. 5:22:21entering into increased risk
  7593. 5:22:24and I
  7594. 5:22:26I didn't feel comfortable doing that I
  7595. 5:22:28was nervous you asked how I slept that
  7596. 5:22:30night and I I said I thought I slept
  7597. 5:22:32okay my wife differed with that as I
  7598. 5:22:34talked with her after that but uh there
  7599. 5:22:37there wasn't nervousness there that we
  7600. 5:22:39were increasing the risk and I believe
  7601. 5:22:40all of us knew that uh
  7602. 5:22:43that if
  7603. 5:22:45if it were increased to the level of an
  7604. 5:22:48O-ring burn through what the
  7605. 5:22:49consequences would be and I don't think
  7606. 5:22:51there's any question anyone's mind about
  7607. 5:22:53that uh I I don't know if I've answered
  7608. 5:22:57the question I guess your original
  7609. 5:22:57question was what I thought was in the
  7610. 5:22:59thought process but that was what was in
  7611. 5:23:02my thoughts
  7612. 5:23:03thank you very much
  7613. 5:23:06I think we'd like to adjourn for today
  7614. 5:23:08do either of you a gentleman School Mr
  7615. 5:23:11Mr Lund have any pressures outside
  7616. 5:23:14pressures anybody call you anybody
  7617. 5:23:16suggest you
  7618. 5:23:17should vote to launch anything of that
  7619. 5:23:20kind at all the commission should know
  7620. 5:23:21about either one of us no sir
  7621. 5:23:24okay thanks very much we'll address
  7622. 5:23:26today
  7623. 5:23:33friends
  7624. 5:23:37[Applause]
  7625. 5:24:15[Applause]

About this transcript

This page contains the full transcript of Presidential Commission on the Space Shuttle Challenger Accident Hearing, February 25, 1986 by Cape Canaveral Space Force Museum, generated from the public captions YouTube serves with the video. The transcript has 48,105 words across 7,625 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.