PMG Interview with Todd Selman — Transcript

by Christopher Glover · 4,529 words · 606 segments · language en · Watch on YouTube

Full transcript

  1. 0:01hello sundevils today we are privileged
  2. 0:04to interview Mr Todd Selman who is a uh
  3. 0:07project manager for the bricon
  4. 0:09corporation Todd thank you so much for
  5. 0:11joining us today thank you for having me
  6. 0:12I appreciate it so Todd tell us a little
  7. 0:14bit about your background well um I
  8. 0:17actually uh when I got out of high
  9. 0:19school I went into the Air Force and
  10. 0:20became a civil engineer so I started in
  11. 0:23uh in civil and worked in civil
  12. 0:25engineering
  13. 0:27until that was from '87 until about 95
  14. 0:31and then I got out of that and actually
  15. 0:33shockingly enough went into sales and
  16. 0:36and so I went into sales and really
  17. 0:38enjoyed sales but really missed um you
  18. 0:41architecture engineering and everything
  19. 0:43like that and so I went back into uh
  20. 0:45went to into Construction in 99 and back
  21. 0:48into construction and I have been in
  22. 0:50construction ever since so what are some
  23. 0:53qualities that every project manager
  24. 0:55should have according to you um
  25. 0:58according to me I mean the best thing
  26. 0:59you have to have to have is you have to
  27. 1:01be able to manage people you have to be
  28. 1:03able to manage your yourself more than
  29. 1:05anything because there are so many
  30. 1:07different things that you have to do at
  31. 1:08any given time um and the biggest thing
  32. 1:11is really to be personable so that you
  33. 1:14can actually pass on the information
  34. 1:16there's a lot of information that a
  35. 1:17project manager gets um and he has to be
  36. 1:20able to give that to everyone else and
  37. 1:22this person may accept it one way and
  38. 1:25this you say the exact same thing to
  39. 1:26another person they can't handle it or
  40. 1:28they don't understand it so you have
  41. 1:29have to be able to dissimilate that
  42. 1:31information to everybody so it's those
  43. 1:33are the probably the most important
  44. 1:35things so those soft skills those people
  45. 1:37skills are essential essential yeah
  46. 1:39essential so a lot of times you don't
  47. 1:42always get to choose who's on your team
  48. 1:44and some people are volunt told or
  49. 1:45assigned to a team but if you get to
  50. 1:47choose your team what type of team
  51. 1:50members would you like to have on your
  52. 1:52team um I'd like somebody that that
  53. 1:56actually has a can do attitude um I'm
  54. 1:58not looking for somebody that that that
  55. 2:00sits back and says oh let's identify the
  56. 2:02problems or anything like that um a lot
  57. 2:04of what I look for on a team is somebody
  58. 2:06that that okay we've identified a
  59. 2:08solution or a problem let's identify a
  60. 2:11solution and then move forward with that
  61. 2:13because what happens is a lot of people
  62. 2:15will get stuck on the problem and
  63. 2:18there's a problem and you you you you
  64. 2:20don't have time to deal with problems
  65. 2:22you have to move on from those problem
  66. 2:24so I look that's probably the first
  67. 2:25thing um the next thing is somebody that
  68. 2:28you know that you can honestly get along
  69. 2:30with you can have a conversation with um
  70. 2:32because you're going to be putting them
  71. 2:34in front of a client no matter what um
  72. 2:36as a project manager you're sitting
  73. 2:38there doing it and then I I want
  74. 2:40somebody that's technically um that
  75. 2:42technically can do the job that that
  76. 2:44that has the skills to do the job I'll
  77. 2:46take somebody that can read the plans
  78. 2:48and is nice over somebody that knows
  79. 2:50every technical spec in the book no I
  80. 2:53think that's completely understandable
  81. 2:55because again those people skills those
  82. 2:57soft skills are like they can be learned
  83. 3:00but it's very challenging to get people
  84. 3:03to to actually adopt those same
  85. 3:06practices and behaviors so that you
  86. 3:08don't have to worry if they're in front
  87. 3:09of a client and if they say the client's
  88. 3:11an idiot to their face so like you don't
  89. 3:13have to worry about losing that contract
  90. 3:15and and it's it's not and it's and
  91. 3:17that's the basis of it but it's not just
  92. 3:20that um if you have uh if you have an
  93. 3:23individual that has a tough time getting
  94. 3:25along with people um instead of 10
  95. 3:28inspections to get through a particular
  96. 3:30phase you may have 20 inspections um and
  97. 3:33they'll nitpick every item that they
  98. 3:36possibly can but if you're personable if
  99. 3:38you can get along with people and
  100. 3:40everything else like
  101. 3:41that you you create those relationships
  102. 3:44you need to be create you need to be
  103. 3:46able to create those relationships
  104. 3:47quickly no absolutely so conflict is uh
  105. 3:51almost inevitable and it's going to
  106. 3:53happen and conflict can be a good thing
  107. 3:54it can be healthy for a team to go
  108. 3:56through um but what how do you handle
  109. 3:59conflict and conflict resolution in the
  110. 4:01teams that you've LED um I always try to
  111. 4:03look at it from their standpoint um you
  112. 4:05know there's what like they say there's
  113. 4:07always your side the other side and the
  114. 4:08actual truth um so I try to look at it
  115. 4:11from their side and identify exactly
  116. 4:13what is making them you know decide that
  117. 4:16that I'm wrong or or this is the wrong
  118. 4:18situation or something like that nine
  119. 4:20times out of 10 when you do that and you
  120. 4:21really take you take that Split Second
  121. 4:23to really think about where they're
  122. 4:24coming from you know maybe they've got
  123. 4:26pressure because you know the the
  124. 4:28budget's tighter or something something
  125. 4:29like that and you need to you need to
  126. 4:31attack it in a in a in a different way
  127. 4:34um you know example would be you know
  128. 4:36somebody says you you have a change
  129. 4:38order that you need to get done you have
  130. 4:40to get this work done but you know in
  131. 4:42your heart of hearts that the reality is
  132. 4:44if they don't do this they're going to
  133. 4:46spend twice as much money later well you
  134. 4:48go in and you say here's the change
  135. 4:50order and they blow up and they have
  136. 4:51conflict because they they say no we're
  137. 4:53not paying this and not paying this but
  138. 4:55if you to come in from the fact said
  139. 4:57listen here's a here's a potential
  140. 4:58problem that I'm seeing here's a
  141. 5:00potential issue that we may have but
  142. 5:02this change order will take care of that
  143. 5:03problem you will not have that problem
  144. 5:04in the future that would have been
  145. 5:06alleviated if you'd if you'd have taken
  146. 5:08that ta so getting to know the people
  147. 5:11understanding what makes them tick
  148. 5:12understanding what makes them think
  149. 5:14really helps you so when you're creating
  150. 5:17your team or you have your team how do
  151. 5:18you create a collaborative positive
  152. 5:20environment for uh success for the
  153. 5:23project um give everybody a stake in it
  154. 5:26um you know you you a lot of project man
  155. 5:29will go out there and they they want to
  156. 5:31be the end all be all they want to be
  157. 5:32they want to finish everything and do
  158. 5:34everything as quickly as possible but
  159. 5:35the simple fact is if if the if if your
  160. 5:38project engineer that's been on a job
  161. 5:40for six months doesn't feel that their
  162. 5:42job and what they're doing is is
  163. 5:43beneficial to the team then you're not
  164. 5:46going to get anywhere with that person
  165. 5:48and they're going to they're not going
  166. 5:49to want to want to work with you in the
  167. 5:51future so even if it's a small task if
  168. 5:54they complete the task correctly if they
  169. 5:55do it well you let them know you you
  170. 5:58constantly give that that feedback then
  171. 6:01if you've told them they've done a good
  172. 6:03job 10 times if you have to tell them
  173. 6:05that they they didn't do something or
  174. 6:06that you're going in a different
  175. 6:08direction they're not near as they're
  176. 6:10not near as hurt as as they would be no
  177. 6:12absolutely celebrating those small wins
  178. 6:14exactly that can like compile to the big
  179. 6:17wins I'm like everyone always celebrates
  180. 6:19those milestones and the deliverables
  181. 6:21and but it's celebrating those small
  182. 6:23wins that really help team morale and
  183. 6:26engagement as well it makes people feel
  184. 6:29appr appreciated um and I don't care
  185. 6:31what anybody says anytime you feel
  186. 6:33appreciated you want to go to work and
  187. 6:35you want to do well for that particular
  188. 6:37person or that particular client no
  189. 6:39absolutely so how do you measure pro uh
  190. 6:44success and team success Beyond just the
  191. 6:47metrics and the
  192. 6:48deliverables um one of the biggest
  193. 6:50things is if if you have people that you
  194. 6:53know whether they be at the low level of
  195. 6:54the team or the high level of the team
  196. 6:56they're comfortable being able to bring
  197. 6:58an issue to the table
  198. 7:00without feeling that they're going to
  199. 7:01get some sort of Retribution um so if
  200. 7:03there's a problem they bring it to the
  201. 7:05Forefront they you you get you get to
  202. 7:07attack that problem directly and move on
  203. 7:10um so I look at it kind of like okay
  204. 7:12I've got a good team they're fine coming
  205. 7:14to me and say hey you said this in this
  206. 7:17meeting but in this meeting you said the
  207. 7:20opposite thing which one is it you know
  208. 7:22i' I'd much rather be able to to to tell
  209. 7:25them yeah I want you to bring come to me
  210. 7:28with that with that criticism as well so
  211. 7:31so uh what are some of the tools that
  212. 7:34you use for your job as a project
  213. 7:36manager um mean you talking software you
  214. 7:39talk anything and everything you go from
  215. 7:40software to even your phone or a
  216. 7:42calendar um it's very funny because when
  217. 7:45I when I first started back in
  218. 7:46construction I used to tell everybody
  219. 7:48you could give me a telephone and a
  220. 7:50screwdriver and I can I can get you
  221. 7:52anything you want built um and nowadays
  222. 7:54it's a little bit more challing a little
  223. 7:57more challenging um but I mean more than
  224. 8:00anything I'm on you know I'm using um
  225. 8:03you know Microsoft Office and any sort
  226. 8:06of and that that entire suite and then
  227. 8:08you have to basically work with Google
  228. 8:09Docs you have to be familiar with all
  229. 8:11that stuff um the tool I use more than
  230. 8:14anything right now is probably email um
  231. 8:17and texting um because a lot of a lot of
  232. 8:20times when you have conversations with
  233. 8:22somebody that that conversation gets uh
  234. 8:25misconstrued after um other things
  235. 8:28happen and so always it's always very
  236. 8:30very important to have that data to back
  237. 8:33up um so I use that and then um we use
  238. 8:38in the company I'm with now we use
  239. 8:40Autodesk which is a basically a suite
  240. 8:43that handles all of your documentation
  241. 8:45and everything else like that so it's a
  242. 8:48phenomenal it's just a phenomenal
  243. 8:49software program it's come a long way
  244. 8:51since Lotus Notes believe me so um so
  245. 8:54what I use those and then uh and then
  246. 8:56frankly you can't go wrong with a good
  247. 8:59spreadsheet you know you really can't no
  248. 9:03absolutely they can become very
  249. 9:04essential and help you in the long run
  250. 9:07yes they can that's for sure so so how
  251. 9:09do you as a project manager prioritize
  252. 9:11any tasks that you have to complete um I
  253. 9:15start the day before um so my my when
  254. 9:19I'm leaving work the first thing I do is
  255. 9:21say okay I'm leaving work what are the
  256. 9:23tasks that I need need to accomplish now
  257. 9:25and identify those tasks and in the
  258. 9:28order that they need to be done and so
  259. 9:29that in the in the morning I can get
  260. 9:31those tasks done right away if there's a
  261. 9:33task that I need to get done that needs
  262. 9:35to be done immediately then I'll you
  263. 9:37know if I'm driving home I'll make that
  264. 9:38call make that text do whatever I need
  265. 9:40to do but I always start the day before
  266. 9:43um when you're when you're when you're
  267. 9:45working from that day and you're working
  268. 9:47from emergencies you're never going to
  269. 9:49succeed um you're you're you're just
  270. 9:51never you're just never going to succeed
  271. 9:52and so what my brain does and the way
  272. 9:55I've kind of taught everybody that I've
  273. 9:57ever taught that is that I've ever
  274. 9:59trained is if you're thinking about what
  275. 10:01ha what's going to happen tomorrow
  276. 10:03you're already a little bit too late you
  277. 10:05need to look out you know depending on
  278. 10:07the job it's a multi-million dollar job
  279. 10:09you may look out a month if it's a if
  280. 10:12it's a you know a smaller job you may
  281. 10:14look out something else if you're if
  282. 10:15you're looking at a task specific issue
  283. 10:18maybe you're looking out a week but if
  284. 10:19you're not looking out at those
  285. 10:21intervals you're going to be in trouble
  286. 10:23and so I always kind of end my day with
  287. 10:27okay this is what needs to happen
  288. 10:28tomorrow so that two weeks I can have
  289. 10:30this done and in a week I can have this
  290. 10:31done and everything like that and then
  291. 10:33in the morning I have a task list of
  292. 10:35items that I need to take care of and it
  293. 10:37may be two tasks and it and that I need
  294. 10:40to that I need to tackle to make sure
  295. 10:42that work is done but I make sure that
  296. 10:44those tasks are done in the
  297. 10:45morning so if a team member comes to you
  298. 10:48and requires more time to complete what
  299. 10:50they've been assigned how do you handle
  300. 10:51that situation um you identify why um
  301. 10:55because maybe there's something maybe
  302. 10:56they didn't understand the task maybe
  303. 10:59the um maybe the task was too much for
  304. 11:01them maybe they didn't have the skills
  305. 11:02maybe you didn't give them the skills
  306. 11:04and and teach them the skills they
  307. 11:05needed to complete that task um I always
  308. 11:08I try to identify why the task didn't
  309. 11:11get done and then once you identify why
  310. 11:13the task didn't get done help them with
  311. 11:16the task make sure that task gets taken
  312. 11:18care of and then walk them through How
  313. 11:20To Succeed so that the next time that
  314. 11:22task comes up or the next time that
  315. 11:23issue comes up they can they can do it
  316. 11:26typically it's because you didn't show
  317. 11:27them something most the time yeah
  318. 11:30usually if you can help educate them or
  319. 11:32at least find out what's wrong then you
  320. 11:34can solve that problem you're a good
  321. 11:36project manager is only as good as the
  322. 11:38people that they the people that they
  323. 11:39work with that's all there is to it so
  324. 11:42so like we discussed earlier rarely does
  325. 11:44any project go off without a hitch and
  326. 11:46usually challenges come up or something
  327. 11:48might happen can you share a time or
  328. 11:50experience where you were working a
  329. 11:52project and something unforeseen
  330. 11:54happened and how did you handle it and
  331. 11:56what did you learn from it well um I
  332. 11:58mean I can give you an example from
  333. 12:00today um we have a a particular Chiller
  334. 12:03system that that we're working on a huge
  335. 12:05vapco system and the pump on the motor
  336. 12:10um was out it's not part of my it's not
  337. 12:12part of my purviews so I don't I don't
  338. 12:13have I don't have hands on it I don't
  339. 12:15have contract for it I don't have
  340. 12:17anything but the the the step I need to
  341. 12:20accomplish is is is is and come that one
  342. 12:24actually work basically by this and so
  343. 12:26you know the first thing you do is
  344. 12:27identify okay what's the problem what
  345. 12:29can we do about the problem is it a
  346. 12:30problem that's going to stop any other
  347. 12:32function and then um you know so I
  348. 12:35basically called up today and I said Hey
  349. 12:37listen I need this motor because I have
  350. 12:39to have this piece piece of equipment
  351. 12:41functioning to perform my next step and
  352. 12:44my next step is coming up on Tuesday and
  353. 12:46so you know I really need to get this
  354. 12:49motor I talked to the owner explained to
  355. 12:51him exactly what I needed what what I
  356. 12:53needed to get done um and I said you can
  357. 12:56either have me do it and I will gladly
  358. 12:58do it I have no problem but we need to
  359. 13:00add that as a change order and
  360. 13:01everything else or you can handle it
  361. 13:04with your in-house people and basically
  362. 13:06tell me that it's going to be done on
  363. 13:07Monday um he said I don't really know if
  364. 13:10my in-house people can do it and so we
  365. 13:12basically collaborated together we
  366. 13:13identified exactly what needed to be
  367. 13:15done we went up we got the got all the
  368. 13:17motor specs and everything like that
  369. 13:19gave that gave that information to him
  370. 13:20he identified the motor the motor's
  371. 13:22coming uh on tomorrow it'll be installed
  372. 13:25on Monday and so therefore we can move
  373. 13:28on with our with our task but as long as
  374. 13:31you're looking ahead and managing ahead
  375. 13:35if an emergency happens you have the
  376. 13:37ability to do that if you're working for
  377. 13:39next tomorrow's work you don't have that
  378. 13:42that fries everything so you know I was
  379. 13:44I had the ability to look and and be
  380. 13:47able to help him because we had that
  381. 13:49kind of buffer built in so so can you
  382. 13:51share your experience with like resource
  383. 13:54allocation and um resource management
  384. 13:56for the projects that you've LED so
  385. 13:59resource management is kind of a fun one
  386. 14:01because as a project manager you're
  387. 14:03always fighting you're always fighting
  388. 14:04for resources because um you you either
  389. 14:07have U you know a budget number that
  390. 14:10needs it's not realistic not realistic
  391. 14:13and you need 20 people uh but you're
  392. 14:15given 10 so you're always having to do
  393. 14:17that and and what I kind of find is as
  394. 14:22long as you are upfront because when you
  395. 14:25first start in project management it's
  396. 14:26very difficult to to kind of get your
  397. 14:28hands around the fact that you're going
  398. 14:30to be that you were underresourced um
  399. 14:32once you've done it a couple times and
  400. 14:34it's normally that first one that where
  401. 14:36you're completely under resourced and
  402. 14:37you didn't know it right off the bat
  403. 14:39that you think okay now I really need to
  404. 14:42talk about resource management at the
  405. 14:44beginning not not the middle or anything
  406. 14:46like but the beginning of the project
  407. 14:47and identify that Resource Management so
  408. 14:50once you once you kind of identify that
  409. 14:53resource management and and those those
  410. 14:55holes that you have what you can do is
  411. 14:57really bring them to the Forefront as
  412. 14:59quickly as you can I mean as project
  413. 15:01managers you you don't run the company
  414. 15:03but you can definitely say listen you
  415. 15:06want to make x amount of dollars on this
  416. 15:08with this resource I can't make that
  417. 15:10money um but you have to have that
  418. 15:12knowledge and you have to have the
  419. 15:13experience to really identify that and
  420. 15:15like I said your first couple yeah it
  421. 15:18might be a little bit rough it might be
  422. 15:19a little rough on those first couple
  423. 15:20because you know most projects that
  424. 15:23you're given you are underresourced and
  425. 15:26you know they want to pull x amount of
  426. 15:28money out of it yeah it's it's fun so so
  427. 15:31can you discuss your experience with
  428. 15:32budget management for the projects that
  429. 15:34you oversee uh well I've I've had budget
  430. 15:37management all the way from p&l on the
  431. 15:39entire project all the way down to um
  432. 15:42you're not handling anything just send
  433. 15:43me your bills so um budget management is
  434. 15:47is one of those things it is so job
  435. 15:50specific that you just a lot of times
  436. 15:52you don't even know if you're going to
  437. 15:53end up with it um whenever you come into
  438. 15:55a project um we have a project that we
  439. 15:58they're talking about doing um down at
  440. 16:00an airport down there and they're
  441. 16:01talking about basically handing you the
  442. 16:03p&l and basically saying this is it so
  443. 16:05you're handling every line item you're
  444. 16:07having every budget item you're having
  445. 16:09to identify what the budget items are
  446. 16:11you know in the original scope and
  447. 16:13everything else like that so sometimes
  448. 16:15you have to do that um I would
  449. 16:19say most of the time that's not the case
  450. 16:22most of the time you're kind of in the
  451. 16:23middle you have the p&l they have given
  452. 16:26you the items they have given you the
  453. 16:28budgets and that you have to fit within
  454. 16:30those budgets so you know if my dirt
  455. 16:33is a number of 1.2 million and I can get
  456. 16:37my dirt guy at 800,000 and he and I can
  457. 16:41make sure that all of his scope in there
  458. 16:43well I have 400,000 for another budget
  459. 16:45item that might be a little lower might
  460. 16:48be let's put it this way might be a
  461. 16:50little
  462. 16:51tighter it's always nice to have that
  463. 16:53buffer yeah and I'm a big fan of buffers
  464. 16:57um and the biggest thing about buffers
  465. 17:00is just when you're when you take your
  466. 17:02scope and you take your contract and you
  467. 17:05make sure they line up yes and I can't
  468. 17:07tell you how many times I've had where
  469. 17:10the scope and the contract don't line up
  470. 17:13and and you're like oh well I'm I made
  471. 17:16saved 400,000 on this job on this on
  472. 17:19this line item and it's like not really
  473. 17:21because now you have time and materials
  474. 17:23for all the stuff that you didn't cover
  475. 17:25in the scope so so one of the things
  476. 17:28that project managers have to do and
  477. 17:29like their teams have to do is engage
  478. 17:31with Excuse me various types of
  479. 17:34stakeholders and so they can be internal
  480. 17:37external they can have like high power
  481. 17:39and influence or low power and influence
  482. 17:41how do you engage with stakeholders and
  483. 17:44can you share a time where you might
  484. 17:46have had a difficult stakeholder and
  485. 17:47what did you do to either mitigate them
  486. 17:50or bring them aboard and want to be a
  487. 17:53part of the project so I did uh I don't
  488. 17:56know if you're familiar with fresh and
  489. 17:57easys I built I was project manager for
  490. 18:00pretty much all of them in Arizona and
  491. 18:02probably half of them in California um I
  492. 18:05was the director of a company that we
  493. 18:07did all all that work um and the the
  494. 18:12specific owner rep from Tesco was a he
  495. 18:16was a he was a challenge um he was a
  496. 18:19challenge but we did an enormous about
  497. 18:21of business and we and and and he did it
  498. 18:24uh and and he respected us but I don't
  499. 18:28not quite sure that he ever liked us um
  500. 18:30and so the best thing that that we ever
  501. 18:32did is identified exactly okay what
  502. 18:36would what would this person like what
  503. 18:37would they you know what what is what
  504. 18:40makes this person tick and so what we
  505. 18:42identified was he liked certain things
  506. 18:45um he he liked um the numbers to be
  507. 18:48round numbers he didn't like um you
  508. 18:51know
  509. 18:5362,000 he lik 60 or 70 and so and so we
  510. 18:57identified kind of some of the these
  511. 18:59things that he really kind of hit on and
  512. 19:02and really and and really did and then
  513. 19:05we identified one of my project managers
  514. 19:07that actually really got along with him
  515. 19:09very well and so we kind of said okay
  516. 19:12well then we're going to shift a little
  517. 19:13bit of this a little bit of this other
  518. 19:16work onto this project manner moved a
  519. 19:19little bit of his projects off and then
  520. 19:21it kind of made him the person that that
  521. 19:23dealt with this person um and it worked
  522. 19:26out fantastic I mean we we
  523. 19:29there are a lot of fresh and easys that
  524. 19:31poed up in a short amount of time
  525. 19:33believe me so so what would you consider
  526. 19:36your most successful project and why my
  527. 19:40most successful
  528. 19:43project everybody has their Sentinel
  529. 19:46project so my Sentinel project is
  530. 19:48probably the the uh Plaza Hotel in
  531. 19:50Denver Colorado
  532. 19:53I when we topped it out it was
  533. 19:57unbelievable
  534. 19:58Colorado is a beautiful place and we
  535. 20:00topped it out in a snowstorm with a
  536. 20:02crane that we had brought up from Denver
  537. 20:04Colorado it was it's it was stunning it
  538. 20:06was unbelievable um we built it for the
  539. 20:08Pras and so we I mean they spared no
  540. 20:12expense and it was just a really cool
  541. 20:13thing um so that's
  542. 20:17my Mountain I guess you could say but
  543. 20:20truthfully I'm prouder that I can drive
  544. 20:23around Phoenix Arizona and any part of
  545. 20:25town and I can say I built that I built
  546. 20:28built that I did that that entire
  547. 20:31subdivision of 700 homes out there I did
  548. 20:34all the Land Development for that I
  549. 20:37there's not a street around that I can't
  550. 20:39drive around and identify a project that
  551. 20:41I've had my hands in and it's just it's
  552. 20:43a great feeling it is a great feeling no
  553. 20:46that's absolutely wonderful because you
  554. 20:48can see the
  555. 20:50tangible results of your hard work and
  556. 20:52dedication exactly so what would you
  557. 20:55consider your most meaningful project
  558. 20:57and why um most meaningful project I did
  559. 21:01um I I've I've done a lot of uh
  560. 21:03volunteering work and stuff like that
  561. 21:04and so you know Habitat for Humanity is
  562. 21:06just a great thing I like going in and
  563. 21:09just helping them out um I haven't done
  564. 21:11it in a few years because I have other
  565. 21:13volunteer things that I do but Habitat
  566. 21:15Humanity is is kind of one of those
  567. 21:17things where it's just I have a skill
  568. 21:20that I can really help them out with um
  569. 21:23so that was good I I I enjoyed I enjoyed
  570. 21:27Habitat for Humanity stuff
  571. 21:29so if you could give advice to your
  572. 21:32younger self or if you want to give
  573. 21:33advice to Future project managers excuse
  574. 21:36me future project managers like these
  575. 21:38students that are watching this
  576. 21:40interview what would you want to tell
  577. 21:41them um I think that the biggest thing
  578. 21:44is is that you know the technical the
  579. 21:46technical aspect of of project
  580. 21:47management is is phenomenal um and you
  581. 21:50need that technical expertise there's no
  582. 21:53question about it because I couldn't do
  583. 21:55what I do without that teex technical
  584. 21:57expertise
  585. 21:59but the most important thing you have to
  586. 22:01be able to do is be be a person that can
  587. 22:03get along with people because you deal
  588. 22:06with every style of person across the
  589. 22:09board um I am a huge fan of not
  590. 22:14self-help books I guess you could say or
  591. 22:16anything like that but I have read um
  592. 22:19Dale Carnegie's uh how to win friends
  593. 22:21and influence people probably 15 times
  594. 22:24um yes it was done in the 30s and it's
  595. 22:27an old book and everything else like
  596. 22:28that but the simple fact is is every
  597. 22:31concept that he has in that book you can
  598. 22:33bring to work and you will
  599. 22:35succeed well thank you so much top for
  600. 22:37taking the time to share your
  601. 22:39experiences your wealth of knowledge for
  602. 22:41our students and for this um for your
  603. 22:44work in the construction industry and as
  604. 22:46a project manager so thank you so much
  605. 22:48thank you very much appreciate it all
  606. 22:49right

About this transcript

This page contains the full transcript of PMG Interview with Todd Selman by Christopher Glover, generated from the public captions YouTube serves with the video. The transcript has 4,529 words across 606 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.

Free YouTube transcript tool

YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, caption language selection, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.