- 0:26so welcome back to this nptl online
- 0:28course on Logistics and supply chain
- 0:30management I'm Dr vikas takur from IIT
- 0:32kakur so uh in the last session we were
- 0:35discussing about the tools for improving
- 0:38the logistics efficiency and uh in that
- 0:40we discussed the very first tool is plan
- 0:43do check act cycle uh given by Professor
- 0:46uh Edwards Deming and now we'll continue
- 0:50with the seven QC tools uh in this
- 0:53session and we'll discuss about the
- 0:55quality Circle 5S approach and
- 0:57benchmarking how these Concepts can be
- 0:59used used to improve the overall
- 1:01Logistics
- 1:03performance so these are the seven
- 1:05quality tools uh given by Professor K
- 1:08ishik Kaba and uh you can see uh we have
- 1:12uh the cause effect diagram then we we
- 1:16we can use flow chart we can use check
- 1:19sheets then par charts histograms
- 1:22control charts and Scatter diagram so
- 1:26this is the complete set of tools which
- 1:28can be uh used just starting with the
- 1:34diagnosing the problem and reaching to
- 1:37the end solution how we can Implement
- 1:40that uh solution and that problem can be
- 1:42solved even you can track the
- 1:44performance as well after implementing
- 1:47that solution you can track the
- 1:49performance so these seven QC tools will
- 1:52just go through how these can be used in
- 1:55a sequence so that we can analyze our
- 1:58complete problem so very first is
- 2:01flowchart right in the last session as I
- 2:05talked about uh a Control process where
- 2:08we we talked about some process and then
- 2:11we we saw that this process is giving
- 2:15some output we are processing and then
- 2:18this output is being compared with some
- 2:20standards and if de any deviation is
- 2:24there yes so then we are taking the
- 2:27corrective and preventive action and
- 2:29again going with the change in process
- 2:32change in raw material change in output
- 2:34all technology if it is no we will
- 2:37continue with the same process this is
- 2:39again a kind of flow chart I'm just
- 2:41giving you all the steps right so this
- 2:45is a kind of decision making stage I can
- 2:47highlight this decision making like this
- 2:49if any process I'm doing I can highlight
- 2:51like this if this is the start uh this
- 2:54is how it is highlighted the end is
- 2:57highlighted like this right so the I
- 3:01means different uh shapes we are using
- 3:04just to uh represent different stages in
- 3:07that flowchart now why flowchart is used
- 3:10just to you know have the quick
- 3:12understanding of the uh any process okay
- 3:16how it is happening so it will give you
- 3:18the better Clarity visibility instead of
- 3:20Reading Writing the long paragraphs
- 3:23right so this is one example you can see
- 3:26here on your screen how the
- 3:27manufacturing company of electronic
- 3:30gadgets they are doing with assembly is
- 3:32starting here so step one component they
- 3:34are checking second stage maybe assembly
- 3:37line is there there are so many
- 3:38different stages they are doing assembly
- 3:41on those stages then decision point is
- 3:44whether quality check is needed or it is
- 3:46error free right or uh 100% inspection
- 3:50or maybe uh the quality uh inspection is
- 3:53not required right if it is required
- 3:55we'll go for check sheet we'll do the
- 3:57sampling we'll pick some samples out of
- 3:59the product and then we'll check whether
- 4:02any defect is
- 4:03identified if it is identified then
- 4:06again we need
- 4:08to we need to go for the assembly we
- 4:11need to check the component whether
- 4:13component is faulty or there is
- 4:15something wrong with the assembly line
- 4:17right so if no nothing is required test
- 4:20is required we'll continue with the
- 4:22final product and then final product
- 4:24testing happens so then again there is
- 4:27decision Point whether this final is
- 4:30okay or not then final assembly is
- 4:32happening production is complete and
- 4:33this is the complete end so see in the
- 4:36flowchart how easily you can understand
- 4:39how the things are flowing in the in the
- 4:41logistics Network also we need we have
- 4:43discussed this complete flow chart right
- 4:46from your first supplier how things are
- 4:49moving through your transportation
- 4:51Network reaching to your manufacturing
- 4:53facility then again through all the long
- 4:56chain of your sto uh stockholders
- 4:59forward agent wholesalers distributor
- 5:02retailers reaching to the End customer
- 5:05right so that also flowchart uh you can
- 5:08just draw the flowcharts right now what
- 5:10inferences we can make out of that so
- 5:13this is reveals bottlenecks and in
- 5:15efficiency so flowchart will help you to
- 5:18identify where is the problem so how
- 5:21bottlenecks you can identify I'll give
- 5:23you very small example let's say I have
- 5:26designed these five stages in the
- 5:28assembly so product is entering here
- 5:31leaving here this is finished good is
- 5:33leaving here raw material is entering
- 5:35here maybe on different stages we are
- 5:37using some more components on on that
- 5:40stage right so then in terms of that raw
- 5:43material will can enter any stage new
- 5:45raw material obviously sub assembly will
- 5:47move through this conveyor belt now
- 5:49let's say for processing this stage we
- 5:52are taking 5 seconds for this 6 seconds
- 5:544 seconds then maybe uh 8 seconds and
- 5:58then maybe you are taking again 6
- 6:01seconds this is how you have designed
- 6:04now through this flow chart you can
- 6:06easily identified that this can be your
- 6:10bottleneck because it is taking 8
- 6:12seconds almost double of the last stage
- 6:16this also taking 6 seconds again 2
- 6:19seconds more than that so if I'll take
- 6:21this stage only between this and this
- 6:24this person will process two products at
- 6:27that time but this will pass only one
- 6:29prodct product right so that means in
- 6:33the end only 50% semi products semi
- 6:37finished products he is able to pass who
- 6:40is sitting on this fourth number stage
- 6:43and rest 50% will be the uh pending you
- 6:47can say pending stock is there on his
- 6:50stage so that means this is the
- 6:52bottleneck and restricting your
- 6:55efficiency how we can do improve that we
- 6:58can we need to think whether we can go
- 7:00for parallel stage the person is also
- 7:03sitting there so that half of the 50% of
- 7:05the product he will process 50% of the
- 7:08product he will process right and if
- 7:11dedicated two workstations are not
- 7:13required maybe temporarily we can
- 7:16assign uh the other workstation and then
- 7:19we can go so this is how the process
- 7:21flow chart will help you to streamline
- 7:23the uh things throughout your
- 7:26distribution Network throughout your
- 7:27packaging if some big pack packets are
- 7:29taking time small packets or delicate
- 7:31items are taking time and then because
- 7:34you are shipping all the products
- 7:36related to one pin code and then all
- 7:38those different types of products are
- 7:40there so how you can be more efficient
- 7:43Saving Time right so this will help you
- 7:45to understand that and then you can
- 7:47obviously uh the process which is taking
- 7:50longer you can uh make decision on that
- 7:52so more informed decision will be there
- 7:55so action taken you can reduce the
- 7:57bottlenecks you can opt op imiz time
- 8:00consuming process right and then
- 8:02additional training is provided to the
- 8:04line worker to be more efficient maybe
- 8:07we will stretch these workers who are
- 8:10taking five or six seconds to be more
- 8:12efficient maybe in that way or maybe we
- 8:14can change some technology also in that
- 8:17way so that the it can be comparable to
- 8:20somewhere 4 to 4.5 seconds so that all
- 8:24the stages are uniformly designed so
- 8:26that there should not be any pending
- 8:28work on any stage right then it will
- 8:30help you to check the quality also
- 8:33because let's say on this stage
- 8:36particular two stage very critical stage
- 8:38and most of the complaints let's say
- 8:40like we talked about the packaging
- 8:41related complaints are coming from this
- 8:44stage so then we need to increase the
- 8:49inspection here see the very this is uh
- 8:54uh misconception that quality
- 8:57means checking no quality we should
- 9:02Target in such a way that quality should
- 9:04be seized after some time quality team
- 9:07should work towards that after some
- 9:10duration there should not be any
- 9:12requirement of the inspection right so
- 9:15we should build the quality in the
- 9:17design of the product we should build
- 9:18the quality in the design of the
- 9:20packaging we should build the quality in
- 9:22the process where we are doing the
- 9:23packaging where we are transporting
- 9:25where we are keeping in the warehouses
- 9:28why the inventory is outdated why it is
- 9:30expired in the warehouse why our system
- 9:33did not give the alarming uh situation
- 9:36that now only few days are left few
- 9:38weeks are left and you need to rotate
- 9:41the stock right so that indication our
- 9:44warehouse automatically should be it
- 9:46should be circulated to all the
- 9:48stakeholder so that that inventory can
- 9:50be consumed first in the market second
- 9:53point is the second tool is check sheets
- 9:56so usually check sheet uh you might have
- 9:59seen check sheets in day routine life if
- 10:01you are traveling through maybe train
- 10:05through air so after completing your uh
- 10:08Journey they are sending you one kind of
- 10:10feedback form check sheet so you can
- 10:13evaluate as per how the staff was
- 10:16dealing with you the clean lless the
- 10:19services provided on on the plane and
- 10:22then all those things right so so that
- 10:25it will give them you know uh kind of
- 10:27direct touch that uh you are inter in
- 10:29with the customer and in that way you
- 10:31can somewhere you can also get a chance
- 10:33to improve your services right so check
- 10:35sheet is a kind of thing Dr isikawa has
- 10:38given this concept of collect this is a
- 10:40way of collecting the data right so
- 10:42through your check sheeet you can
- 10:43collect the data where the Falls are
- 10:45happening check sheet is also uh like we
- 10:48designed that most of the complaints are
- 10:50coming from packaging so you can see
- 10:53number of occurrences if Monday we see
- 10:56bottle brokens two right cap loose
- 11:01Monday nothing Tuesday two in that way
- 11:04we can see missing label also we have so
- 11:07this is a kind of check sheet so in the
- 11:09end we can analyze why this is happening
- 11:12if on one stage consistently something
- 11:14is happening wrong order that means who
- 11:17is the operator where is the location
- 11:20date section everything we so that we
- 11:22can identify the problem where the
- 11:25problem is like we identified initially
- 11:27now I have given you that image you can
- 11:29just relate with that example very basic
- 11:32example why we need to find out that the
- 11:36B very basic root cause right and damage
- 11:39while packaging how many times we did
- 11:41that and what are the reasons maybe in
- 11:44the weekend the uh defects are more
- 11:47maybe people are in uh rush to you know
- 11:50leave the workstation to go for their
- 11:52weekend plans and all that that can be
- 11:54one of the reason maybe Monday um uh
- 11:57more faults are coming complaints are
- 11:59coming because uh just they are coming
- 12:01after enjoying their weekend so it is
- 12:03little difficult to concentrate back on
- 12:05the workstation and all those things
- 12:07maybe right so this is a way how you
- 12:10this is just one tool to collect the
- 12:12data so first your flow chart you can
- 12:15understand the complete process second
- 12:17just check sheet is required to just
- 12:19record the data where the faults are
- 12:22happening and what is the frequency of
- 12:24those faults right and simple one case
- 12:27is there you can just see a man
- 12:29manfacturing company produces electronic
- 12:30components and they are tracking where
- 12:33the problem is so date of production you
- 12:36can find out when exactly that complaint
- 12:38happened type of defect is there any
- 12:41defect with the manufacturing process
- 12:43soldiering issue or maybe component
- 12:45misaligned or maybe damaged component
- 12:48faulty your packaging or maybe faulty
- 12:52process so location of defect like I
- 12:55told you it was done in a shift B shift
- 12:58dshift or or at what which workstation
- 13:01workstation fifth or 10th or 12th or
- 13:03which one is responsible so that we can
- 13:05increase the sampling or inspection rate
- 13:07at that particular stage or we can think
- 13:10of giving the training to that person
- 13:12who is working on that stage where those
- 13:14faults are occurring right we can find
- 13:17out the shift then operator we can find
- 13:19out specifically so that if special
- 13:21attention is required and if this is
- 13:24somewhere around the industry average we
- 13:27need not to bother much about that but
- 13:29still we should go for the regular
- 13:30training then of all the staff obviously
- 13:33or if it is something out of the box
- 13:36things are happening and many faults are
- 13:38coming so then we need to identify the
- 13:41particular person so that we can go with
- 13:43the things with that particular person
- 13:45only so what actions we can take we can
- 13:47identify the root cause of the defects
- 13:49and if it is happening somewhere in the
- 13:51manufacturing in the uh loading of the
- 13:54truck in unloading in storing in the
- 13:57cold storage or while packaging the
- 13:59product then then those stages you can
- 14:02Define and specific quality check sheet
- 14:04you can prepare related to those right
- 14:07so then targeted training program like I
- 14:10told you if this is the problem with
- 14:11some particular operator you can do this
- 14:14is not only the only the person can be
- 14:16at fault let's say you have completely
- 14:18automated Warehouse so robots are
- 14:20working so even then if it is The Fault
- 14:22With the machine so sometimes that can
- 14:24also happen continuously working
- 14:27continuously machine is working bear and
- 14:29can happen so then you need to check for
- 14:31that also right so results will be you
- 14:34can see the Improvement in quality when
- 14:36you will be implementing uh uh the
- 14:38identified root cause right so common
- 14:41type of defects you can find out so in
- 14:44that way you can build a sustainable
- 14:47environment of quality management
- 14:49through your Logistics distribution so
- 14:51in the end this is one acknowledgement
- 14:54you will get from the end stakeholder of
- 14:57that uh distribution Network if you are
- 15:00doing all the you are ticking all the
- 15:02points in the check sheets now third
- 15:05tool is histogram now we recorded the
- 15:09data now histogram will give you the
- 15:11pictorial representation that this is
- 15:13Fault one this is Fault 2 this is Fault
- 15:17three so this is like what is the
- 15:19frequency of these faults 5 10 15 20
- 15:23like this quick view I can get
- 15:26right and let's say uh you can compare
- 15:29month-wise as well January we have three
- 15:32faults let's say for January month so
- 15:36let's say we have
- 15:39uh like this so fault one fault two
- 15:44fault three February
- 15:51again so this one 2 3 like likewise you
- 15:55can continue so I can just see uh in any
- 15:59month this fault two is very high and
- 16:02next is Fault three so first I should
- 16:05prioritize fault two then I should pay
- 16:07attention to fault three then I should
- 16:09move to fault one so this will give you
- 16:11quick indication where you should go so
- 16:14histogram will help you to in that way
- 16:16so this is one case restaurant chain
- 16:19they want to enhance the both food
- 16:21quality and customer satisfaction
- 16:23obviously then you need to talk about
- 16:26the delivery time how they can do that
- 16:28right so they have collected some data
- 16:31and uh they have organized this data how
- 16:34many times they are making the delivery
- 16:37between 10 to 15 minutes how many times
- 16:39between 15 to 20 minutes 20 to 25
- 16:41minutes so these many times you are
- 16:42making the delivery so this is a quick
- 16:45review that you can analyze that you are
- 16:48taking the maximum time here and here so
- 16:51somewhere here normal distribution curve
- 16:53also you can draw on that right
- 16:56so uh this will help you to understand
- 16:59understand where you need to fasten up
- 17:00the things where you need to go for
- 17:03maybe half cook item you can keep with
- 17:05you so that order if those kind of
- 17:07products are there which are in
- 17:08continuous supply and demand so then you
- 17:11can manage in that way and you can
- 17:13minimize the time right so your
- 17:15histogram will help you to understand
- 17:17that so realtime performance monitoring
- 17:20system can be implemented by tracking
- 17:23the delivery
- 17:24times so once you will Implement that
- 17:27you can see now the delivery Peak if 25
- 17:32to 30 minutes you can further reduce it
- 17:34if you are finding out the bottleneck
- 17:37and you will be more consistent it will
- 17:39not be like this that sometimes you are
- 17:41here taking more time sometimes here so
- 17:43that you can be more consistent in that
- 17:46way right and when you are consistent so
- 17:48customer satisfaction see if one day I'm
- 17:51providing services within 5 minutes and
- 17:54next day I'm providing services in two
- 17:56uh 25 minutes so see same customer if
- 17:59coming to you so obviously if I got
- 18:01first day 5 minute Services anywhere you
- 18:04are taking 25 minutes I will be highly
- 18:07dissatisfied right if on an average
- 18:10continuously consistently you are taking
- 18:1215 to 20 minutes maybe whenever I'm
- 18:14coming to your store I know that this
- 18:17person will take average this much time
- 18:19so mentally I'm prepared that way right
- 18:21so that is also kind of thing that you
- 18:24know customer mind and psychology it's
- 18:27very difficult so the same situation
- 18:30sometime customer may take as a positive
- 18:32sometimes may take as negative so again
- 18:35I told you as per month Jan Feb March
- 18:39you can uh Analyze This there is another
- 18:42way these are the
- 18:44defects right and when these defects
- 18:47happen that also this is day shift one
- 18:50shift two shift three so all the time
- 18:53you can see that reasonably shift one
- 18:56defects are very high right and then
- 18:59shift two defects are also increasing
- 19:02okay so what are those defects this is
- 19:05wrong color doesn't light up when you
- 19:08turned on did not turn on right too
- 19:11small or maybe size not fitting right so
- 19:15put the wrong label on that or wrong
- 19:17size information so that way you can
- 19:20just find out you can this see how
- 19:23quickly you instead of going through the
- 19:25long tables and then information data
- 19:28you can just just uh get the picture in
- 19:31no time
- 19:32right now the now you collected
- 19:35information what is the frequency of
- 19:37occurring those faults now I need to
- 19:40prioritize which one is the Fault which
- 19:43is happening very frequently and this is
- 19:46parto principle 8020 rule which says
- 19:48that your 80% of the problems are
- 19:51because of 20% of the reasons and this
- 19:54is almost applicable in every phase
- 19:58everywhere
- 19:59maybe in your life as well you see
- 20:01majorly our life is affected by 20% of
- 20:04the
- 20:05decision uh your education which uh uh
- 20:09line you are into that will decide your
- 20:11total career business then uh whether
- 20:14you are going uh for your own venture or
- 20:17you are uh uh going to provide the
- 20:19services that is another decision second
- 20:22decision third who will be your life
- 20:24partner fourth after retirement what you
- 20:26will do four five decisions so that
- 20:29means these 20% decisions are affecting
- 20:31your and these are so big decisions if
- 20:34one goes wrong your whole life will be
- 20:37disturbed so that way 80% is their
- 20:40weightage right so same thing happens in
- 20:43almost every area if you talk about
- 20:46inventory I'm keeping inventory for any
- 20:48product let's say car so 20% item will
- 20:51be there components will be there who
- 20:53are carrying the maximum you know price
- 20:56cost and rest 80% items are are only
- 20:59contributing 20% so this is ABC analysis
- 21:02of inventory management we'll do in
- 21:04further sessions right so paratto
- 21:07diagram will histo diagram is just will
- 21:10arrange that these are the faults like
- 21:13this they will uh we can arrange in
- 21:15paror chart and then we can see these
- 21:1720% of those problems if these are the
- 21:21problems problem one problem two problem
- 21:23three problem four problem like this so
- 21:26these 20% of the problem which are
- 21:3080% customers are facing right so we can
- 21:34easily prioritize that now this tool is
- 21:36used to prioritize those issues whether
- 21:39the issues are mostly related with
- 21:40packaging or issues are mostly related
- 21:43with Transportation issues are mostly
- 21:45related with the outdated inventory
- 21:47because of warehouse management or maybe
- 21:50the outdated inventory in the warehouse
- 21:54right so you can just see scratched
- 21:58screen battery issues and missing
- 22:01components so if I'll just combine these
- 22:04three so you can see how much part these
- 22:07three are giving you somewhere here
- 22:1180% right so only these issues and uh if
- 22:15you'll solve these 20% issues your 80%
- 22:19problem will be solved right so parto
- 22:22chart is a very very beautiful tool to
- 22:25analyze the situation in that way right
- 22:28so others so many may be there so even
- 22:31if you'll try to address even then you
- 22:34cannot because obviously any process
- 22:37cannot be 100% error free so in that way
- 22:41you should uh Focus first on those 20%
- 22:44which can be you know uh addressed so
- 22:47scratch screen or battery issues are
- 22:49very prominent so immediately you can
- 22:52where that scratches are happening maybe
- 22:55in the storage or maybe when you are
- 22:57packaging the screens where that or
- 23:00maybe when you are finally you are
- 23:01cleaning that or maybe when you are your
- 23:03engineer is installing at the uh site
- 23:07location right then scratches are where
- 23:09the scratches are happening so you need
- 23:11to find out the reasons again you need
- 23:13to do the root cause analysis and the
- 23:15next tool will be root cause analysis
- 23:17only right we'll see how we'll find out
- 23:18the root cause so once it is done we can
- 23:21fix these issues and you can reduce your
- 23:24defects by 80% just focusing on 20% of
- 23:27the problems and in terms of that you
- 23:30can improve the customer feedback and
- 23:33returns will be minimized obviously
- 23:35right so this is how it will work now
- 23:37this is the fifth tool which we'll use
- 23:39to you
- 23:41know uh to find out the root cost like
- 23:45this is decreased customer satisfaction
- 23:49and maybe this is happening because of
- 23:51uh the scratches are happening on the
- 23:53screen during
- 23:56packaging right now now what can be the
- 23:59reasons let us forget this this this is
- 24:01fishborn diagram given by Professor
- 24:03Ishikawa and this is head of the fish
- 24:06and these are different branches you can
- 24:08just see like a fish it is this diagram
- 24:11is there so why uh like the first
- 24:16example if I'll go to that very basic
- 24:17example that problem is with packaging
- 24:20right this is the problem now we
- 24:22identified this problem can be because
- 24:24of the Manpower working on the
- 24:26workstation because of the technology we
- 24:28we are using on that workstation because
- 24:30the because of the equipment we are
- 24:33using to packet that because of the
- 24:35working conditions are not
- 24:40good because of the fault in the raw
- 24:42material because of so many other issues
- 24:45like so these issues we will list now if
- 24:48the problem is mostly happening because
- 24:50of Manpower we'll ask again why Manpower
- 24:54problem is there
- 24:56maybe did not undergo
- 24:58the proper training maybe not happy with
- 25:02the work environment maybe Disturbed
- 25:05with personal life maybe not the right
- 25:09skills at that job maybe related to
- 25:12salary maybe related to health issues so
- 25:16many things can be there this related to
- 25:19Manpower only so we identified the first
- 25:22reason then substages we'll find out the
- 25:25next stage reason then training if if he
- 25:29is not trained properly why that person
- 25:32is placed at that situation again we'll
- 25:34find out the reasons who can be at fault
- 25:37so HR team as fault maybe the placement
- 25:40team at fault maybe the induction people
- 25:43who did induction for that maybe at
- 25:46fault right so if it is the problem of
- 25:49HR how we can why that happened so HR
- 25:53need to change the policy so this is
- 25:55fishborn diagram where we'll try to find
- 25:57out the reasons on the further stages so
- 26:00that we can find out the main problem
- 26:03and this is also known as cause effect
- 26:05diagram so once you will identify the
- 26:07problem major categories under people
- 26:10problem with the process or equipment
- 26:12like I discussed or environment is not
- 26:15right then you can find out the
- 26:16subcategories also right and then you
- 26:19need to do the brainstorming session you
- 26:22need to ask by we usually call it fivey
- 26:26analysis or 3 y analysis or 7 y analysis
- 26:31means we'll ask why this happened seven
- 26:33times first we'll find out the answer
- 26:36then why that happened second will find
- 26:38out the answer then why that thing
- 26:39happened so we'll keep on asking the
- 26:42buys until until we are reaching at the
- 26:45root cause right so the potential causes
- 26:48we can identify with the help of this
- 26:51fish one diagram and then we need to
- 26:54take the corrective action additional
- 26:56staff we need to optimize the workflow
- 26:58or we need special training so obviously
- 27:01when we will find out the root cause so
- 27:04now the employe will feel motivated he
- 27:07will feel connected to the organization
- 27:09and then in that way the overall
- 27:11performance complaints will reduce
- 27:14performance will increase and in that
- 27:16way customer satisfaction which was the
- 27:18initial problem can be increased and in
- 27:21which will result in the ultimate
- 27:24customer loyality right so this is how
- 27:26fish diagram can help us scatter diagram
- 27:30again now maybe we
- 27:33identified uh three solutions to one
- 27:36problem that first I need to revise the
- 27:39compensation of that
- 27:41person then I need to provide him health
- 27:45insurance kind of thing I need to
- 27:47provide him the maybe the other housing
- 27:50facilities or uh maybe the education
- 27:54facility to the children maybe I need to
- 27:57uh enrich his job or enlarge his job
- 28:01whatever these are the three solutions
- 28:03you suggested to your management right
- 28:06now I want to track whether if I
- 28:08increase the compensation from point A
- 28:11to point B what is the
- 28:14performance whether the performance has
- 28:16increased like this like this like this
- 28:19or still the performance is like this
- 28:21right so if it is not how I can find out
- 28:24with the help of scatter diagram so
- 28:27let's go if if the problem is like this
- 28:29this is the solution let's say this is
- 28:30the solution I am implementing and this
- 28:33is the
- 28:34result I am increasing the compensation
- 28:39here and I'm looking for the result
- 28:41result in terms of number of
- 28:43complaints reduced number of complaints
- 28:46or you can say because this is
- 28:48positively increasing we cannot say in
- 28:49that way here we can say when there is
- 28:51negative uh correlation in this case we
- 28:55can say the result in terms of
- 28:57productivity
- 28:59so if I increase the compensation
- 29:02productivity is
- 29:04increased if I increase the compensation
- 29:07your number of complaints coming from
- 29:09the
- 29:11markets decreased so that means this
- 29:14component solution is working
- 29:17fantastically on that particular
- 29:19situation if the points are like
- 29:21staggered like this so that means there
- 29:23is no relationship even if you are
- 29:25increasing the compensation the employee
- 29:28is not motivated enough that he is
- 29:31somewhere performing of the average or
- 29:34whatever he was doing earlier right so
- 29:36this is the scatter diagram you can see
- 29:38number of training programs you did and
- 29:41job performance you can see still uh
- 29:44there is uh increasing Trend so that
- 29:46means you can suggest that training
- 29:49programs will help you to increase the
- 29:51overall
- 29:53performance so you can just see uh xaxis
- 29:58your independent variable byx is your
- 30:00dependent variable and regular checks
- 30:02you can track and you can improve the
- 30:04overall
- 30:06performance the last tool is control
- 30:08chart now control chart is that you are
- 30:11doing your process let's say at this
- 30:13mean this is the middle line
- 30:16right so you are
- 30:18recording your uh process at this level
- 30:22and how your process is moving like this
- 30:24so you will Define your upper limit as
- 30:26well upper control limit and lower
- 30:28control limit as long as your process is
- 30:32within this range right so you will say
- 30:35this is controlled but if it'll go
- 30:38beyond this range we need to stop and we
- 30:40need to take the corrective action right
- 30:43so this is control chart statistically
- 30:46we are this tool was given by Professor
- 30:49shot and uh here we are statistically
- 30:51controlling the quality right so how
- 30:53many times we are breaking the packaging
- 30:57how many times product wrong product
- 30:59delivered right so if there are this is
- 31:02the average and because we are allowing
- 31:04some defects up to some level plus minus
- 31:08let's say to be very specific sometime
- 31:10we are saying three sigma right so upper
- 31:13control limit lower control limit as
- 31:15long as you are within that range you
- 31:17are okay so in in when we'll discuss
- 31:20about the manufacturing unit
- 31:21specifically we'll talk about how we'll
- 31:24we are setting these plusus 3 uh Sigma
- 31:27for
- 31:28differentiating the assignable cause and
- 31:30common cause of variation right so here
- 31:32only as long as we are within the set
- 31:34limits we are okay with the quality
- 31:36right so we need to find out whether the
- 31:38common cause of variation or special
- 31:40cause if it is common cause we cannot
- 31:42remove that common cause there will be
- 31:45small variation right so that we cannot
- 31:48that is sometimes uh because of
- 31:51environmental condition sometimes
- 31:52because human intervention is there
- 31:54human it's not completely automated
- 31:56right even automation is there after
- 31:58some time maybe be and tear so we are
- 32:00not getting the exactly same parameters
- 32:03so parameters keep on changing so this
- 32:06we cannot remove but special cause if
- 32:09something the big problem is happening
- 32:12then we need to take the corrective
- 32:13action right so we need to identify
- 32:16whether the cause is special cause or
- 32:18common
- 32:20cause so you can see once we'll
- 32:23Implement these control charts we can
- 32:26reduce the variation in the quality of
- 32:29the products delivered this is how the
- 32:31complete all the tools can be identified
- 32:34I have discussed flow chart then you
- 32:37want to see the big picture how things
- 32:38are happening check sheets are used for
- 32:40data collection these all tools are used
- 32:42for data analysis here you will record
- 32:44the errors how frequently they are
- 32:46happening scatter diagram how uh results
- 32:50if you'll Implement some solutions how
- 32:52the results are improving you can use
- 32:54control charts to be within the range
- 32:57then problem identification you can do
- 33:00fish one analysis cause and effect
- 33:02diagram and in the end you can
- 33:03prioritize the solution as well for the
- 33:05same problem if you are finding two
- 33:07three solutions so that those Solutions
- 33:09also you can prioritize so another
- 33:11approach is quality Circle this is
- 33:13voluntarily group and not very formal
- 33:16right so maybe 8 to 10 peoples are part
- 33:19of that voluntarily group and they are
- 33:22discussing on some issue let's say the
- 33:24issue like we talked about related to
- 33:27Packaging
- 33:28so they will maybe voluntarily people
- 33:30one or two person will come from
- 33:32production Department one or two people
- 33:34will come from quality Department
- 33:36voluntarily one or two people will come
- 33:39from R&D Department from maintenance
- 33:42department from training and development
- 33:45department like this right so who are
- 33:48directly indirectly are linked with that
- 33:50particular problem now they will meet
- 33:53regularly okay this is a kind of quality
- 33:55Circle they will meet regularly they
- 33:58will find out the solution do the
- 34:00brainstorming sessions we'll come up
- 34:02with the results right so uh and then
- 34:05we'll suggest those results to the uh
- 34:08higher management now if it is related
- 34:10to packaging let's say packaging we need
- 34:13to change the raw material right so this
- 34:16can be one of the suggestion so R&D
- 34:18people will also say about raw material
- 34:20how we can improve in a better B right
- 34:23then quality people will also say
- 34:25whether the quality will be improved or
- 34:27if you are changing changing the raw
- 34:28material it will degrade the quality
- 34:30further right then so all will check the
- 34:33feasibility even accounting department
- 34:35will be there with their accounts that
- 34:37this will add the cost further we cannot
- 34:39afford that like these many arguments
- 34:42can be there so in the end you all the
- 34:45members uh what are the members there is
- 34:48top management their role is to support
- 34:51the QC right whatever suggestion they
- 34:54are giving they need to sanction the
- 34:56budget to implement those Solutions so
- 34:58that they can feel uh you know motivated
- 35:02they should provide the award kind of
- 35:03system and uh there if their uh
- 35:07suggestions are being implemented so
- 35:09next time they will also be willing to
- 35:11you know meet on these kind of informal
- 35:14teams as a informal teams and then they
- 35:16will try to solve so many in in
- 35:18manufacturing units these these kind of
- 35:20groups are very very common right then
- 35:23steer Committee of maybe senior people
- 35:25will be there who will be you know
- 35:27evaluating those quality Circle whe
- 35:29whether really that quality circle is
- 35:31required for that particular problem or
- 35:33not what are the objectives whether they
- 35:35are within the guidelines of broader
- 35:37guidelines of the organization or they
- 35:39are giving some out out of the box
- 35:41suggestion which suggestion is okay we
- 35:43can Implement can reduce the problem
- 35:46drastically but then what about the cost
- 35:49what about the other ethical constraints
- 35:51what about other legal constraints
- 35:53whether we can go for that or not right
- 35:55there is coordinator who who will will
- 35:57be coordinating between quality Circle
- 36:00higher management whatever suggestion
- 36:01they will give they will give that
- 36:03person is going to coordinate with them
- 36:05and will keep the track of activities
- 36:08whatever they are doing okay then there
- 36:10is
- 36:11facilitator the he will be the senior
- 36:14officer of the department and uh uh he
- 36:17will be uh arranging all the necessary
- 36:20you know training programs and uh he
- 36:22will develop the set up the links
- 36:24between the quality circles and my
- 36:26management and will ensure the
- 36:27participative culture so this is the
- 36:29main role of facil facilitator leader
- 36:33obviously uh will be one person who will
- 36:35be leading that team will be defining
- 36:37the problem various aspects of that uh
- 36:40that problem what can be you know the
- 36:43redressal schemes so in that way he's
- 36:46going to elaborate with the team and
- 36:48obviously with the team members who are
- 36:50the ultimate stakeholders coming up with
- 36:53the suggestions brainstorming sessions
- 36:55giving up their feedbacks and then the
- 36:57leader will combine that and obviously
- 36:59that cross questioning and all those
- 37:02things will be there so that we can
- 37:03validate the solution in the end whether
- 37:05we can really go for those Solutions or
- 37:08not so the fourth tool is 5S philosophy
- 37:12which is Japanese ter Ser C cisu and we
- 37:16can Implement for housekeeping so that
- 37:20uh the inventory can be managed within
- 37:22the warehouse in a proper way and we can
- 37:25sustain that proper way the first first
- 37:27is sorting you should sort your material
- 37:30because sorting is very much required in
- 37:32Warehouse where you need to sometimes
- 37:34you are sorting pin code buys sometimes
- 37:36you are sorting product wise sometimes
- 37:38you are sorting as per the requirements
- 37:40of the product right Cold Storage
- 37:42products will be stored in that area and
- 37:45rest of the products will be stored
- 37:46delicate items how you should handle
- 37:48where you should store those items right
- 37:50so how you are designing the Shelf space
- 37:52and all that set in order you need to uh
- 37:56set in order all the it Ms as per size
- 37:58as per uses or as per product nature
- 38:01shine you need to maintain uh the
- 38:04cleanliness of the workplace so that uh
- 38:07smooth function can be ensured and
- 38:09accidents can be reduced standardize
- 38:12once it is done you need to standardize
- 38:14the process so that repetitively you
- 38:17should be able to do that it's not one
- 38:19day you are setting in order and next
- 38:21day everything is again on the back
- 38:24track Q are so sustaining once the
- 38:26system is standardized you need to
- 38:28sustain that for forever right so this
- 38:31is how this approach of housekeeping can
- 38:33be very helpful when we are managing our
- 38:36inventory within the
- 38:38warehouses so the last one is
- 38:40benchmarking like I told you
- 38:43so you decided your kpis then these kpis
- 38:49you will find out uh the kpi of the best
- 38:54player in the market and find out the
- 38:58gaps between you there is one approach
- 39:00of balance scorecard we'll try to cover
- 39:03that as well with the respect to I'll
- 39:06try to design with respect to the supply
- 39:08chain Logistics management so this is
- 39:11one approach how you can uh you know uh
- 39:14identify the gaps and uh this is one
- 39:18concept of House of
- 39:21quality these two things we will go
- 39:25for right house of quality where you
- 39:27will identify your present situation
- 39:30where the best player Benchmark is so
- 39:33that you can find out the gaps right and
- 39:35best practices so that it will provide
- 39:37you the opportunities right so where you
- 39:40are lagging how you can improve your
- 39:42performance Matrix how why you are late
- 39:45than others right so your delivery is
- 39:47delayed why wrong product are shipped so
- 39:50frequently on your uh platform why that
- 39:54is happening why you are always shortage
- 39:56of inventory why there is defected
- 39:59product is uh shipped to the customer so
- 40:01there is something wrong with the career
- 40:03partner right so to define the
- 40:05benchmarking we have six steps first of
- 40:08all you need to define the objective so
- 40:11what are the area where you want to
- 40:14improve you will keep those as objective
- 40:16then you will identify those kpis let's
- 40:19first uh improve our uh uh
- 40:22Transportation sector so because
- 40:25transportation is uh cont contributing
- 40:2760 to 70% of the cost let's say so we
- 40:30need to improve that part right then
- 40:33gathered data what are Transportation
- 40:35related kpis what are our
- 40:39situation and what is the situation of
- 40:42the leader in that industry if DHL you
- 40:45are comparing delivery you are comparing
- 40:48so what is the situation of those player
- 40:50right as far as those kpis are concerned
- 40:54then you need to select the partner
- 40:56right so you need to exchange the
- 40:58information with your career Partners
- 41:00where we can work Logistics partner or
- 41:03Transportation Partners where we can
- 41:05improve and then again after Improvement
- 41:07you will analyze the data compare the
- 41:09data whether you have made the sign
- 41:11significant Improvement is there or not
- 41:14right so that you need to see again you
- 41:16will identify the opportunity that you
- 41:18have addressed the problem up to 30% but
- 41:21still you need to go further let's say
- 41:23take the next step which will maybe will
- 41:26uh again improve the situation by 50%
- 41:28and we can cut down the complaints by
- 41:30another 50% so these all are the uh uh
- 41:35tools we can use uh obviously uh we'll
- 41:38discuss some tools in uh Supply Chain
- 41:40management as well so there we will be
- 41:42covering the broader perspective so we
- 41:45can conclude that as customer focus so
- 41:49goal is to provide the best quality
- 41:51product delivered at at best experience
- 41:54that will only happen when we'll set up
- 41:56all of C these kpis in order right and
- 41:59we need to shine these kpis every day so
- 42:02that we can sustain these for a longer
- 42:04period there should be environment of
- 42:06continuous Improvement that plan do
- 42:08check act cycle should be continuous
- 42:11right employee
- 42:12empowerment QC circles employees should
- 42:16be part of that and if I'm addressing
- 42:18some problem of maybe my organization
- 42:20and I'm acknowledge in that way I'll
- 42:22feel motivated always people will come
- 42:25with their suggestions how they can and
- 42:26you be believe me in manufacturing
- 42:28industry major major problems are solved
- 42:31by those illiterate people who are
- 42:32working on the production line because
- 42:34they are continuously day and night
- 42:36doing the same repetitive action no one
- 42:39can understand better than them because
- 42:41they are continuously if you are
- 42:43producing daily 10,000 di times 10,000
- 42:46time they are doing the same operation
- 42:48so you can just imagine how efficient
- 42:50and in that way they can be
- 42:52knowledgeable in that way use of quality
- 42:55tools so you need to overnight you
- 42:58cannot use these tools you need to
- 43:00prepare your team who who can be very
- 43:03good in collecting data analyzing the
- 43:05problem and coming up with the solutions
- 43:08and then also prioritizing the solution
- 43:10which solution we can go for uh you know
- 43:12first phase second phase third phase
- 43:14product design within the product we
- 43:16should meet the customer expectation and
- 43:19you should design your process like that
- 43:22your process is not damaging the
- 43:26packaging
- 43:27right your process is not uh doing all
- 43:30the that uh screen scratches right so
- 43:33your process is should be your process
- 43:36should be defect free and then obviously
- 43:39supplier role is important how you can
- 43:42control the quality at the supplier end
- 43:44so you need to align all these players
- 43:47everywhere you need to go for the
- 43:49quality
- 43:51tools whatever we discussed and only
- 43:53then you can improve the overall
- 43:55performance so this these all are the
- 43:59references other than the books referred
- 44:01in first few sessions so that's all from
- 44:04my side thank you very much
About this transcript
This page contains the full transcript of Lecture 11 : Tools for Improving Logistics Efficiency (Contd.) by NPTEL IIT Kharagpur, generated from the public captions YouTube serves with the video. The transcript has 6,953 words across 1,017 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.
What you can do with it
Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.
Free YouTube transcript tool
YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, translation to 100+ languages, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.