  1. 0:01[Music]
  2. 0:02[Applause]
  3. 0:04hi this is me my name is Hamid Chay and
  4. 0:07I've been involved with a number of
  5. 0:08software development projects over the
  6. 0:09years at a number of different companies
  7. 0:11and I've come to recognize scrum as one
  8. 0:13of the best Agile development practices
  9. 0:15in Ed today in this fast-paced video I
  10. 0:18want to show you why scrum is so great
  11. 0:20and how you can get started with scrum
  12. 0:21in under 10 minutes I'll cover all the
  13. 0:23core scrum Concepts like product
  14. 0:25backlogs team rolls Sprints burndown
  15. 0:28charts and more so get ready to be
  16. 0:30bombarded with information let's say
  17. 0:32this is the product we want to build for
  18. 0:34this product we get all kinds of feature
  19. 0:36requests from customers Executives or
  20. 0:38even other team members in scrum
  21. 0:40features are written from the
  22. 0:41perspective of the end user therefore
  23. 0:44features are known as user Stories the
  24. 0:46collection of all these user stories is
  25. 0:48called the product backlog another way
  26. 0:50to think of the product backlog is to
  27. 0:52think of it as a wish list of all the
  28. 0:53things that would make this product
  29. 0:55great once we have our wish list or the
  30. 0:57product backlog we need to start
  31. 0:59planning which specific spe ific user
  32. 1:00stories we're going to be putting into a
  33. 1:02particular release of our product but
  34. 1:04we're getting ahead of ourselves let's
  35. 1:05back up a bit to build this product we
  36. 1:08need to have one or more people in our
  37. 1:09team who are going to play a variety of
  38. 1:11roles first we need her she plays the
  39. 1:13role of product owner and helps make
  40. 1:15sure the right features make it into the
  41. 1:17product backlog representing the users
  42. 1:19and customers of the product she helps
  43. 1:21set the direction of the product then we
  44. 1:23need this guy he's the scrum master and
  45. 1:25his job is to make sure the project is
  46. 1:27progressing smoothly and that every
  47. 1:29member of the team has the tools they
  48. 1:30need to get their job done he sets up
  49. 1:32meetings monitors the work being done
  50. 1:34and facilitates release planning he's a
  51. 1:36lot like a project manager but that's
  52. 1:38such a boring title so we'll call him a
  53. 1:40scrum Master to imply he knows some
  54. 1:41Jiu-Jitsu and the rest of the team has
  55. 1:44similar roles to other development
  56. 1:45processes these guys build the product
  57. 1:48while these guys test it to make sure it
  58. 1:49works right these guys use it and
  59. 1:52hopefully pay for it and these guys they
  60. 1:54generally get in the way but it turns
  61. 1:55out you can't build many products
  62. 1:57without them but let's get back to this
  63. 1:59release plan to plan and release the
  64. 2:01team starts with this the product
  65. 2:03backlog and they identify the user
  66. 2:04stories they want to put into this
  67. 2:06release these user stories then become
  68. 2:08part of the release backlog the team
  69. 2:10then prioritizes the user stories and
  70. 2:12estimates the amount of work involved
  71. 2:14for each item sometimes larger user
  72. 2:16stories are broken down into smaller
  73. 2:18more manageable chunks the collection of
  74. 2:20all the estimates provides a rough idea
  75. 2:22of the total amount of work involved to
  76. 2:24complete the entire release a quick side
  77. 2:26note about estimates there are a lot of
  78. 2:28techniques for creating good estimates
  79. 2:30some prefer estimating in story points
  80. 2:32where estimates are made relative to
  81. 2:34building a small component with a known
  82. 2:36level of difficulty unfortunately story
  83. 2:38points don't answer the question of when
  84. 2:40will my project ship I found that the
  85. 2:42best technique is to estimate work in
  86. 2:44hours but to use some standards in how
  87. 2:46estimates are done for example things
  88. 2:49that take less than a day to complete
  89. 2:50will be estimated as 1 Hour 2 hours 4
  90. 2:53hours or 8 hours every item will fall
  91. 2:55into one of those buckets there will be
  92. 2:57no 3-hour estimates for example a 3 3
  93. 2:59hour item would fall into the 4-Hour
  94. 3:01bucket larger items will be estimated as
  95. 3:032 days 3 days 5 days or 10 days again
  96. 3:07all estimates in between will fall into
  97. 3:09the next larger bucket extremely large
  98. 3:11items are similarly estimated in months
  99. 3:141 2 3 or 6 months but the reality is
  100. 3:17that such items will need to be broken
  101. 3:19down substantially before work actually
  102. 3:21begins we'll come back to these
  103. 3:22estimates in just a minute but for now
  104. 3:24let's get back to this the release
  105. 3:26backlog with a prioritized set of user
  106. 3:28stories and the estimated amount of work
  107. 3:30at hand we're now ready to plan out
  108. 3:32several Sprints to get the work done
  109. 3:34Sprints are short duration Milestones
  110. 3:36that allow teams to tackle a manageable
  111. 3:38chunk of the project and get it to a
  112. 3:40ship ready State Sprints generally range
  113. 3:42from a couple of days to as much as 30
  114. 3:44days in length depending on the products
  115. 3:46release Cycles the shorter the release
  116. 3:48Cycles the shorter each Sprint should be
  117. 3:50and you want to have at least two to as
  118. 3:52many as a dozen Sprints in a given
  119. 3:54release so at this point we can take our
  120. 3:56release backlog and split it up into
  121. 3:58several of these Sprint backlogs one of
  122. 4:00the most important things to remember
  123. 4:02about Sprints is that the goal of each
  124. 4:04Sprint is to get a subset of the release
  125. 4:06backlog to a ship ready state so at the
  126. 4:08end of each Sprint you should have a
  127. 4:10fully tested product with all the
  128. 4:11features of the Sprint 100% complete
  129. 4:14since Sprints are very short but a
  130. 4:16realistic representation of part of the
  131. 4:18product a late finish of the Sprint is a
  132. 4:20great indicator that the project is not
  133. 4:22on schedule and something needs to be
  134. 4:24done therefore it's extremely important
  135. 4:26to monitor the progress of each Sprint
  136. 4:28with this a burndown chart the burndown
  137. 4:31chart is the number one reason for
  138. 4:33scrums popularity and one of the best
  139. 4:35project visibility tools to ensure a
  140. 4:36project is progressing smoothly the
  141. 4:38burndown chart provides a day-by-day
  142. 4:40measure of the amount of work that
  143. 4:42remains in a given Sprint or release in
  144. 4:44this graph you can see that the amount
  145. 4:46of work remaining bounces up and down
  146. 4:48from day to day but is generally
  147. 4:50trending towards zero because historical
  148. 4:53information is provided in the burndown
  149. 4:54chart it's easy to see if the team is on
  150. 4:56the right track using the burndown chart
  151. 4:59the team can quickly calculate this the
  152. 5:01slope of the graph which is also called
  153. 5:03the burn down velocity this is the
  154. 5:05average rate of productivity for each
  155. 5:07day for example A team's rate of
  156. 5:09productivity might be that on a typical
  157. 5:11day they finish approximately 50 hours
  158. 5:12of work knowing that it's possible to
  159. 5:15calculate an estimated completion date
  160. 5:17for the Sprint or even for the entire
  161. 5:19release based on the amount of work
  162. 5:20remaining what's great about the
  163. 5:22burndown chart is that we can compare
  164. 5:24our actual velocity and projected
  165. 5:26completion date to what the team needs
  166. 5:28to do in order to finish on time
  167. 5:30this is perhaps the most useful piece of
  168. 5:32knowledge that any team member product
  169. 5:33owner or product executive can have
  170. 5:35about the project because knowing
  171. 5:37whether or not the project is on track
  172. 5:39early in the schedule can help teams
  173. 5:40make the proper adjustments necessary to
  174. 5:42get the project on track the burndown
  175. 5:44chart provides empirical proof that the
  176. 5:46project is on track or if it's going to
  177. 5:48be late so let's talk a little about
  178. 5:50where the data for this incredibly
  179. 5:52useful burndown chart comes from as you
  180. 5:54recall part of the release planning
  181. 5:55process was to create an estimate for
  182. 5:57each user story in the release backlog
  183. 5:59the collection of these estimates for a
  184. 6:01given Sprint represents the total amount
  185. 6:03of work that must be done to complete
  186. 6:04that Sprint as each team member goes
  187. 6:06through and makes progress on one or
  188. 6:08more of the user stories they simply
  189. 6:10update the amount of time remaining for
  190. 6:11each of their own items so the total
  191. 6:13amount of time remaining on the group of
  192. 6:15user stories that make up a Sprint
  193. 6:17changes on a day-by-day basis hopefully
  194. 6:19going downward until it hits zero when
  195. 6:21the Sprint is complete the burndown
  196. 6:23chart Aggregates the remaining work data
  197. 6:25and shows it visually it's brilliant
  198. 6:27because it communicates a massive amount
  199. 6:28of information in just a few seconds and
  200. 6:31that brings us to this the daily scrum
  201. 6:33the daily scrum is an essential tool to
  202. 6:35having communication flow freely between
  203. 6:37team members the idea is to have
  204. 6:39fast-paced standup meetings where team
  205. 6:41members quickly list the work they have
  206. 6:43completed since the last meeting and any
  207. 6:45obstacles in their way by meeting daily
  208. 6:47it ensures the team is always in sync
  209. 6:49and any major issues are dealt with as
  210. 6:50soon as they are known finally as each
  211. 6:53Sprint comes to a finish it's important
  212. 6:54to have a Sprint retrospective meeting
  213. 6:56where the team can reflect on what went
  214. 6:58right and areas of Improvement after all
  215. 7:00scrum is a flexible Agile development
  216. 7:02method that needs constant improving and
  217. 7:04tweaking for every team so there you
  218. 7:06have it scrum in under 10 minutes you
  219. 7:08now know all the essential Concepts to
  220. 7:10start implementing scrum inside of your
  221. 7:12organization but wait a second what
  222. 7:14about tools to help you implement scrum
  223. 7:16well it just so happens that I've spent
  224. 7:18the last 10 years building such a tool
  225. 7:20with a lot of help from these guys a
  226. 7:22group of Genius coders and design Ninjas
  227. 7:24the tool is called on time and it helps
  228. 7:26you manage your products your backlogs
  229. 7:28your team your your releases and your
  230. 7:30Sprints it gives you project visibility
  231. 7:32with burndown charts and always answers
  232. 7:34the question of who is working on what
  233. 7:37you can get started with it for free at
  234. 7:38axosoft tocom of course you could use a
  235. 7:41giant whiteboard some note cards and a
  236. 7:43bunch of different spreadsheets to track
  237. 7:45everything you could also use an advocus
  238. 7:47instead of a calculator to do math but
  239. 7:49we're getting a little off topic so
  240. 7:51let's quickly revieww everything in
  241. 7:53scrum you work with this a product
  242. 7:55backlog which is nothing more than a
  243. 7:57list of features that we call user
  244. 7:58stories you then break down the product
  245. 8:00backlog into one or more release
  246. 8:02backlogs and for a given release you
  247. 8:04further break up the release backlog
  248. 8:06into a number of Sprint backlogs which
  249. 8:08are essentially short duration
  250. 8:09Milestones throughout your project you
  251. 8:11then monitor the progress of each Sprint
  252. 8:13using these burndown charts and have
  253. 8:15daily scrum meetings to ensure
  254. 8:17everything is on track after each Sprint
  255. 8:19you have a retrospective meeting to
  256. 8:21fine-tune everything and if you want a
  257. 8:22tool to implement scrum you can use on
  258. 8:25time it'll help you ship software on
  259. 8:27time that's all there is to it oh and
  260. 8:29one last thing whether you loved or
  261. 8:31hated this video I'd love to hear from
  262. 8:33you you can reach me on Twitter or via
  263. 8:35email if you have any feedback now get
  264. 8:38going create a great team collaborate
  265. 8:40and ship software on time

About this transcript

This page contains the full transcript of Intro to Scrum in Under 10 Minutes by Axosoft, generated from the public captions YouTube serves with the video. The transcript has 1,846 words across 265 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.