  1. 0:00[Music]
  2. 0:02In this lesson of drawing a residential
  3. 0:04building permit set, we're tackling
  4. 0:05detailed opening schedules, the windows
  5. 0:07and doors that can make or break your
  6. 0:09approval. I'll show you how to use
  7. 0:10Rayon's block library, draw custom
  8. 0:12blocks, and format schedules like a pro.
  9. 0:14And by the end of it, you'll have a
  10. 0:15polished door and window schedule ready
  11. 0:17for submission. Let's dive in. Welcome
  12. 0:19back to drawing a residential building
  13. 0:21permit set. I'm Chris, an architect
  14. 0:23based in the UK. And in this lesson,
  15. 0:25we'll be focusing on detailed opening
  16. 0:27schedules, a crucial component of any
  17. 0:29permit set. These schedules clearly
  18. 0:31document which windows and doors are
  19. 0:32being added or replaced, ensuring that
  20. 0:34your design complies with municipal
  21. 0:36requirements. Because exterior
  22. 0:38modifications often fall under strict
  23. 0:40regulations, opening schedules are not
  24. 0:42only best practice, they're also
  25. 0:44frequently mandatory for approval. In
  26. 0:46this session, we'll expand the detail
  27. 0:48and rigor of our permit set, building
  28. 0:50toward a complete and approvable
  29. 0:51package. Together, we'll be covering
  30. 0:54leveraging Rayon's extensive block
  31. 0:56library, over 10,000 blocks with front,
  32. 0:58top, and side views to create
  33. 1:00professional schedules, drawing custom
  34. 1:02opening blocks to match project specific
  35. 1:04needs, best practices for organizing and
  36. 1:07formatting schedules, and enriching
  37. 1:09blocks with metadata to generate
  38. 1:11accurate and automatic tables. By the
  39. 1:13end of this lesson, you'll have a
  40. 1:14polished door and window schedule with
  41. 1:16the level of precision and documentation
  42. 1:18that municipalities expect. Everything
  43. 1:21will be demonstrated in Rayon Design, a
  44. 1:23browser-based design platform that I've
  45. 1:25used to create this entire course. Rayon
  46. 1:27takes you seamlessly from initial
  47. 1:28sketches through to professional permit
  48. 1:30sets. It's free to use, so if you
  49. 1:32haven't already, set up your account at
  50. 1:34rayon.design. Download the free permit
  51. 1:36set template linked below. Follow along
  52. 1:38by customizing the free template below
  53. 1:40to your own project. If you'd like more
  54. 1:42personalized guidance, you can also book
  55. 1:43a one-to-one demo through the link in
  56. 1:46the description. And finally, don't
  57. 1:48forget to like, comment, and subscribe
  58. 1:50for more lessons in this series, as well
  59. 1:52as future tutorials. Let's dive in.
  60. 1:54Okay, so here's where we left off last
  61. 1:57time. So, we have all our sheets. We
  62. 1:59have our um front cover, our legend, our
  63. 2:02site plan, then we've got our proposed,
  64. 2:04and our existing floor plans. Um, and
  65. 2:07then, if you remember in the last
  66. 2:08lesson, we looked at the elevations and
  67. 2:10sections. So, this is all within the
  68. 2:13paper canvas. And I'm going to create a
  69. 2:15new model canvas for our windows and
  70. 2:18doors. So we'll go up to the left here,
  71. 2:20go to canvases, create a new model
  72. 2:22canvas.
  73. 2:24Windows and doors.
  74. 2:27Okay. And I want to bring in a view of
  75. 2:30the floor plans to start with. So we'll
  76. 2:32go to layers, we'll go to view, we'll go
  77. 2:35to existing and proposed plans. And you
  78. 2:38can see here that creates my window. And
  79. 2:42if I double click in there, I have my
  80. 2:45proposed ground floor and my proposed
  81. 2:47first floor. So we'll make sure they are
  82. 2:50one to one. And then I will command and
  83. 2:53drag. So that's our ground floor. I just
  84. 2:56copy across for our first floor. We then
  85. 2:59want to start tagging our windows and
  86. 3:01doors. So that's basically giving them
  87. 3:03an ID number. So a reference number so
  88. 3:07we understand which door we're talking
  89. 3:08about rather than saying oh you know the
  90. 3:10door that's next to this thing or that
  91. 3:11thing. They just have an ID number which
  92. 3:13is the way we do things in terms of best
  93. 3:15practice. So we can go to blocks. We can
  94. 3:17go to libraries. Um again we'll go down
  95. 3:20to uh title blocks and annotations.
  96. 3:24We'll find a tag and we can drag that
  97. 3:26in. Just scale it up. I'll just change
  98. 3:30the color of this. So I can go into the
  99. 3:32block. I can click the lines and I can
  100. 3:35change the style. So maybe I'll make
  101. 3:38these kind of a bright blue color
  102. 3:43with the color set. I'll just create a
  103. 3:45new layer called tags. I will place
  104. 3:50that on the tag layer. And then we'll
  105. 3:53just populate these next to each and
  106. 3:56every door and window.
  107. 4:00Okay. And then you'll notice if you
  108. 4:02click on the block itself, it has an
  109. 4:04instance property already within it. So
  110. 4:07you have a tag name and a tag number. So
  111. 4:10I can change the tag name um to D for
  112. 4:13door or W for window and then I can
  113. 4:16change the number depending on which
  114. 4:17instance of the door it is. So we could
  115. 4:20start with D1 over here. We could then
  116. 4:22say maybe the front door is D2,
  117. 4:26that door is D3, D4, D5, and so on. And
  118. 4:31I can do exactly the same thing with the
  119. 4:32windows. So we can change the D to a W
  120. 4:37and then W1,
  121. 4:40W2,
  122. 4:42W3,
  123. 4:44W4,
  124. 4:46and so on. So now you've tagged all of
  125. 4:48your windows and doors. each is
  126. 4:50identified by a separate um name and
  127. 4:52number. So with all those windows and
  128. 4:54doors tacked um we're now going to
  129. 4:57decide which are being replaced and
  130. 4:58which are being retained um because they
  131. 5:01will have a different um reference
  132. 5:03point. So for the project we are
  133. 5:05proposing to change all external windows
  134. 5:08and doors and that's to increase their U
  135. 5:10value. So at the moment they're just old
  136. 5:12single glazed um timber frame windows
  137. 5:15and we're looking to increase the
  138. 5:17thermal properties and introduce double
  139. 5:19glazing to those. So we know all the
  140. 5:21external windows and doors are going to
  141. 5:23be replaced. Um and then internally
  142. 5:25we've decided that the ground floor
  143. 5:27internal doors are staying as is. Um and
  144. 5:30the upstairs that's where we're
  145. 5:32introducing new windows and doors. So in
  146. 5:34terms of what we're trying to
  147. 5:35communicate, we don't need to reference
  148. 5:37out those ground floor doors because
  149. 5:39they're just staying as is. So a note
  150. 5:40will do. In creating our plans, we've
  151. 5:42used the rayon block library. So those
  152. 5:45are windows and doors that have been set
  153. 5:46up with not only a plan view, but a
  154. 5:48section and elevation view already set
  155. 5:50up. So I'm just going to show you how
  156. 5:52they work. So if we look back into my
  157. 5:54blocks, so these are the blocks that are
  158. 5:56populated within the model, we can see a
  159. 5:58number of the windows and doors that
  160. 6:00have been used. And any of the elements,
  161. 6:02any of the blocks that have that little
  162. 6:03purple symbol next to them, they have a
  163. 6:06front and side view. So take this one
  164. 6:07for example, the single casement. I can
  165. 6:09just drag and drop this here to show you
  166. 6:11what I mean. So, I've got the plan view
  167. 6:13there, but I also have an elevation view
  168. 6:17as well and a section view. So, that's
  169. 6:20the intent behind the window. We can see
  170. 6:22that plan, section, elevation without
  171. 6:24having to draw anything. That's just
  172. 6:26drag and drop into our drawing sheet.
  173. 6:29Exactly the same thing with the door. We
  174. 6:31can just drag that door in. And you can
  175. 6:33see there the purple icon. I also have
  176. 6:35an elevation
  177. 6:37and a section view of that door already
  178. 6:40set up. So again, as standard,
  179. 6:42everything is drawn for you. You just
  180. 6:44then need to communicate dimensions or
  181. 6:46the design intent. Okay. Now that we've
  182. 6:48explored the ray on block library, let's
  183. 6:49take a look at how we can create a
  184. 6:51custom opening block to match our
  185. 6:52project specific needs. So in this
  186. 6:54project, for example, we have a curved
  187. 6:56bay window at the front. I'll just jump
  188. 6:58back and show you. We have this curved
  189. 7:00bay window which obviously in plan has
  190. 7:02that curve to it and in elevation has a
  191. 7:04series of faceted panels. Now obviously
  192. 7:06in plan we can create our own block for
  193. 7:09that purpose and I want to show you how
  194. 7:10we do that. So a block for all intents
  195. 7:12and purposes is just a collection of
  196. 7:14information. So we can draw a couple of
  197. 7:16curves for example. So let's just trace
  198. 7:20um our current window outline. We can
  199. 7:24offset create the thickness of the
  200. 7:26window. Say uh 50 mil the other way.
  201. 7:34So in plan that's our very basic window
  202. 7:36form. If I highlight that and then right
  203. 7:39click I can turn that into a block and
  204. 7:40that means I can use it across the
  205. 7:42model. Then with that block created I
  206. 7:44want to right click and go to edit. Now
  207. 7:46you can see that little circle that
  208. 7:48little white one in the center. That's
  209. 7:49my insertion point. So at the moment
  210. 7:51that's a spot insertion point. That
  211. 7:53means it just it comes in the insertion
  212. 7:55point is central to that block to make
  213. 7:57it cut through a wall which is obviously
  214. 7:59what a window and door does. They're
  215. 8:01hosted in the walls. We can change it to
  216. 8:03a segment. So I can then set my segment
  217. 8:06on my center line like that. And then I
  218. 8:08will show you if I draw a wall and then
  219. 8:11I even just drag this into that
  220. 8:14position, align it centrally. That's now
  221. 8:16cutting through my wall. So that
  222. 8:18obviously now is acting as a window just
  223. 8:20like any of the standard windows within
  224. 8:22the block library and that's cutting
  225. 8:24through our wall. So and exactly the
  226. 8:26same with the elevation. So I've just
  227. 8:28brought the line work in for that bay
  228. 8:30window. I can highlight that line work.
  229. 8:32I can select block and then you'll see
  230. 8:35it appear in my block library on the
  231. 8:36left hand side. I can even rename that
  232. 8:38and call that you know bay window and
  233. 8:42then that could be used on another
  234. 8:43project say and even with this I can say
  235. 8:46what type of view it is. So top, front
  236. 8:48or side. And similarly with the plan, I
  237. 8:50can go to the block there. I can rename
  238. 8:53that bay
  239. 8:55plan
  240. 8:57and then select that as the top view.
  241. 9:01And then exactly the same thing with the
  242. 9:02section. So you know just like we drew a
  243. 9:05section with our guidelines.
  244. 9:16So we can draw a very basic section and
  245. 9:19again turn that into a block. So you can
  246. 9:21see that there I can rename as bay
  247. 9:24window section and then set that as a
  248. 9:28side view. So in essence I'm basically
  249. 9:30creating a set of information that sits
  250. 9:32parallel to my standard window blocks or
  251. 9:35door blocks. And with those drawn I can
  252. 9:37then share them amongst the rest of my
  253. 9:39team for different projects. For
  254. 9:41example, so say you were working on a
  255. 9:43proposed building um and you designed a
  256. 9:46certain window, you know, you knew all
  257. 9:47the sort of manufacturers's information.
  258. 9:49It all worked really well for you. That
  259. 9:51could then be set within a block and
  260. 9:53then you could implement that across
  261. 9:54multiple projects. So that's the base
  262. 9:56information created. Now let's look at
  263. 9:58creating a schedule to clearly convey
  264. 10:00our windows and doors. We'll be
  265. 10:02following the best practice for
  266. 10:03organizing and formatting these
  267. 10:05schedules. So let's get started. Okay,
  268. 10:07with those drawn, we now want to create
  269. 10:09a schedule. So, it's going to be a
  270. 10:11visual schedule, one that shows um
  271. 10:13illustratively the design intent behind
  272. 10:15the window. So, like we've got the plan
  273. 10:16section and elevation, but we also want
  274. 10:18to be able to um show the tag, the
  275. 10:21title, which distinguish it as a
  276. 10:23separate element, and also the
  277. 10:24specification. So, things like the
  278. 10:26opening, the material, and the finish.
  279. 10:28So, I want to start out by drawing a
  280. 10:30frame around my element. And we'll
  281. 10:33create a series of frames. In essence,
  282. 10:36we'll create a title and then we'll
  283. 10:38create a series of subheadings.
  284. 10:46In terms of our tag, that will be the
  285. 10:49same as we've got the window and door
  286. 10:50tags. Um, so we'll create just a piece
  287. 10:54of text.
  288. 10:56We'll call that W1 as an example. Um,
  289. 11:01I'll make that slightly larger. I'll set
  290. 11:03a style. We also call that heading for
  291. 11:05example.
  292. 11:07And again we'll have a title. So we'll
  293. 11:10call that bay window. So that's really
  294. 11:12just a description about um what it is.
  295. 11:16Uh and then we'll have some subheadings.
  296. 11:18So again I'll change um the style. Maybe
  297. 11:22make that smaller again. Create a sub
  298. 11:25heading
  299. 11:26style. Copy those down. And we'll have
  300. 11:30something like uh opening. So that
  301. 11:33describes, you know, how the thing
  302. 11:34opens. Frame glass. So if or if there
  303. 11:39isn't glass finish, and then we'll have
  304. 11:42hardware. So hardware is the the hinges
  305. 11:45um or the handles. So those are our
  306. 11:47subheadings. And then whatever that is
  307. 11:49will appear in those those next um
  308. 11:52column. So this is where it gets
  309. 11:53interesting. So we want to have metadata
  310. 11:56and that allows that block to be able to
  311. 11:59be edited. So you can change it for that
  312. 12:02change specification. So we can if we
  313. 12:05make this whole thing a block including
  314. 12:08the frame create a block and then that
  315. 12:11allows us to have instance properties.
  316. 12:13So we're going to add a property. So I
  317. 12:15can add um tag for example um and that
  318. 12:19will be a text type. We'll save that.
  319. 12:23Then I can go into my block and I can
  320. 12:26click on my tag.
  321. 12:28I'll double click on that text um and
  322. 12:30instead of it just being um a dumb piece
  323. 12:33of text, you know, just a written out
  324. 12:35element, I can add a variable. So then
  325. 12:37go to instance and then I can find my
  326. 12:40tag. So that then will replace it with
  327. 12:42this little instance element. So we
  328. 12:45create done
  329. 12:47again and then you'll see there on the
  330. 12:50right hand side that tag I can now fill
  331. 12:53it in from there. And that means that
  332. 12:57say I duplicate this framework. So for
  333. 13:01my next window or door, instead of it
  334. 13:03adjusting my original um block and
  335. 13:06changing that, it can then change to D1
  336. 13:10for example. So you're making the
  337. 13:12framework um smart. And I can do exactly
  338. 13:15the same thing with all of the rest of
  339. 13:17my parameters. So I can click on my
  340. 13:19block. I can add um uh name for example
  341. 13:25and then I can add all of these open
  342. 13:27things. So opening
  343. 13:30frame
  344. 13:32glass
  345. 13:34finish
  346. 13:36and hardware and then go back and plug
  347. 13:39that into those text elements. So again,
  348. 13:43go back in here, find my instance, find
  349. 13:46the um title or name, and then the same
  350. 13:50with the um openings.
  351. 13:54So again, just change that text to the
  352. 13:57tag, and then you'll see it disappear,
  353. 13:58and I'll show you where it goes in a
  354. 14:00second.
  355. 14:01Okay, so that's been completed. And now
  356. 14:03I can then fill in the information on
  357. 14:06the instance properties rather than
  358. 14:08directly into the block. So the frame we
  359. 14:11could say is a uh softwood
  360. 14:15timber.
  361. 14:17The finish is something like semig gloss
  362. 14:22brow 904.
  363. 14:24Hardware
  364. 14:25uh stainless steel
  365. 14:28hinges and handles
  366. 14:32glass double glazed units. You know, I
  367. 14:36could tell a U value, for example,
  368. 14:38opening uh top hung top hung opening.
  369. 14:43Um, and then we've got the title, which
  370. 14:45is bay window. And you can see there
  371. 14:49that some of those um, uh, text elements
  372. 14:52are overhanging the area. So, we just go
  373. 14:55back in here, select that, and then we
  374. 14:57can drag over that zone. But the great
  375. 15:01thing is is that I can adjust that um,
  376. 15:03as I see fit. So if I wanted to add
  377. 15:06something to that, so double glazed
  378. 15:11units with ceramic frick for example.
  379. 15:15Yeah, I just adjust that there and then.
  380. 15:17So that sits as a block, you know, I can
  381. 15:20see it in my block library down here.
  382. 15:24Um, and then I can use that as a
  383. 15:26framework moving forward. So again, I
  384. 15:28can move it over here.
  385. 15:30I'll just move my example door. And then
  386. 15:33I can change those elements and say okay
  387. 15:36the frame now is a hardwood frame for
  388. 15:39example and the finish is stained timber
  389. 15:43veneer. The tag is now D one. The
  390. 15:48hardware are concealed
  391. 15:52hinges.
  392. 15:55Glass it's not applicable cuz it's a
  393. 15:57solid timber door. Opening side hung.
  394. 16:02Uh, and we'll call that internal door.
  395. 16:07So, it basically gives us a framework to
  396. 16:09be able to fill out that's standardized
  397. 16:12across the project. And again, you can
  398. 16:14use this, you can set it up in your
  399. 16:16office, set it as a standard block, and
  400. 16:18then it can be just implemented
  401. 16:20throughout multiple projects. Okay. So,
  402. 16:22I've just spent time um finalizing my
  403. 16:24schedule. So, you can see here that
  404. 16:26we've got all that information. We've
  405. 16:28got the plan, the section, the
  406. 16:30elevations, those dimensions. Um, and
  407. 16:32then we have all our information. So,
  408. 16:34our openings, our glass, our frame,
  409. 16:36finish, and hardware. Um, and basically
  410. 16:39I've identified each of the different
  411. 16:42windows across the project. Um, and
  412. 16:44depending how many repeats you have, you
  413. 16:47can decide on whether you have a type.
  414. 16:49So say this window um for example
  415. 16:51appeared multiple times, I would only
  416. 16:53draw it once and I would name it as a
  417. 16:55type um with multiple instances. But on
  418. 16:58this project we have a quite a lot of
  419. 17:00variety. Um so you can see all those
  420. 17:02here and exactly the same thing with the
  421. 17:05doors. So we've got the elevations and
  422. 17:07the plans, all the dimensions, and then
  423. 17:10all of that specification information as
  424. 17:12well. And because we've set all of those
  425. 17:14elements up as blocks, they've been
  426. 17:15incredibly easy and consistent to
  427. 17:18implement across the project. And that's
  428. 17:20what you want. You want clear
  429. 17:21formatting. You want that information
  430. 17:23clearly communicated, easily visually
  431. 17:26shown, um, so there's no ambiguity.
  432. 17:29Rayon also has smart properties that can
  433. 17:31be added onto blocks in order to avoid
  434. 17:33manual counting, summing, and listing of
  435. 17:36objects or square meters. For the next
  436. 17:38part, I will demonstrate how to add
  437. 17:39properties to a few of our opening
  438. 17:41blocks. For those of you that want to
  439. 17:42streamline this process, this is
  440. 17:44particularly recommended for large
  441. 17:46projects where procurement and takeoff
  442. 17:48reports can become very complex and
  443. 17:50manual mistakes can occur. When using
  444. 17:52properties in Rayon directly on blocks,
  445. 17:54it streamlines your schedule creation
  446. 17:56process. So, I've shown you metadata in
  447. 17:59terms of the blocks that we're using for
  448. 18:02um the window and door schedule, but I
  449. 18:04want to show you that you can implement
  450. 18:05metadata to the actual blocks of the
  451. 18:08windows and doors themselves. And this
  452. 18:10is really really important if you're
  453. 18:11working on a large project for example,
  454. 18:13you want to count loads of things, you
  455. 18:15know, you want to avoid um mistakes, you
  456. 18:18know, people doing it manually. This is
  457. 18:19a really great thing to do. So I can
  458. 18:21jump back into my existing and proposed
  459. 18:23plans. Um and I'll show you these ones
  460. 18:25as an example. So the doors here, as an
  461. 18:28example, the block that's been submitted
  462. 18:32is a door EU70. So that's a standard
  463. 18:35rayon door. So we can look at that. We
  464. 18:37have that front view. they have that
  465. 18:38side view and you can see here if I
  466. 18:40double click on the block you can see
  467. 18:42those custom properties on the right
  468. 18:44hand side so at the moment there's view
  469. 18:46um standards whether it's an EU or a US
  470. 18:49door um whether it appears on a model
  471. 18:51canvas or a paper canvas um but you also
  472. 18:53have things like brand so I could say
  473. 18:56what the manufacturer of that door was
  474. 18:59for example maybe we've got beautiful
  475. 19:01Italian doors from Lu Aldi and maybe we
  476. 19:05want to put the price in for example So
  477. 19:08we could put price
  478. 19:11and then we go to properties select
  479. 19:14price and we say
  480. 19:175,000
  481. 19:19um as an example. So that information
  482. 19:22will be present in any of those blocks
  483. 19:25where it's used multiple times. And
  484. 19:28exactly the same thing for the window.
  485. 19:30So we can select the window here. Again
  486. 19:33this is a standard window that's been
  487. 19:34used within rayon. can go into that
  488. 19:36block family um and I can add those
  489. 19:39elements into there. So a window
  490. 19:41manufacturer
  491. 19:43ideal combi for example um I can add a
  492. 19:47property again price
  493. 19:51and you can see that anytime that
  494. 19:53instance is created you have that
  495. 19:56metadata as well but what use is that
  496. 19:58metadata so we can go over here and
  497. 20:01where we have all our different elements
  498. 20:02so layers and blocks we also have tables
  499. 20:05and I can create a new table so I'm
  500. 20:08going to call that um windows and doors.
  501. 20:13And you can see here
  502. 20:15in our categories, it's it's basically
  503. 20:18looking at the model canvas, all of the
  504. 20:20stuff that's there, um and giving us a
  505. 20:23list of it. So, currently, it's listing
  506. 20:25out all the walls, all the zones, and
  507. 20:26all the block instances. So, all the
  508. 20:28block instances are the windows, the
  509. 20:29furniture, you know, anytime we've
  510. 20:31dragged a block onto that space. So,
  511. 20:33let's get rid of the walls and the zones
  512. 20:35and only show um the block instances. So
  513. 20:38now it's currently showing that we've
  514. 20:40got 479 different types of elements um
  515. 20:44different blocks within the canvases.
  516. 20:47This is obviously including you know
  517. 20:49furniture, trees um and doors and
  518. 20:51windows. Now a couple of things we can
  519. 20:53do. We can filter. So we can add a
  520. 20:55filter.
  521. 20:57So we can say it includes for example
  522. 21:01um window.
  523. 21:05So now it's only looking at windows for
  524. 21:07example. But we can also add new columns
  525. 21:10to that. So we can add um different
  526. 21:12elements from this metadata that we
  527. 21:14shown previously. Um so we can add price
  528. 21:18and we can add brand. So now you can see
  529. 21:21here that we have six instances of that
  530. 21:24same window that we've used across um
  531. 21:27the project. This is how much they are.
  532. 21:29This is how many of them are. And these
  533. 21:31are the brands. Um, so we could even,
  534. 21:33you know, group by the brand if we
  535. 21:35wanted to. So, say we had different
  536. 21:37brands across the project, you know, we
  537. 21:39could group all those together. And
  538. 21:40exactly the same thing with the doors,
  539. 21:42for example. So, we could um clear the
  540. 21:44filter and then add a filter in which
  541. 21:47includes um door example.
  542. 21:52And then you can see the number of doors
  543. 21:54that it's reading throughout the
  544. 21:56project. And this obviously all depends
  545. 21:58on how you set your model up, how
  546. 22:00consistent you are in terms of your
  547. 22:01naming, but it can be a really really
  548. 22:03powerful tool. And it's not just for
  549. 22:05windows and door schedules. Let me show
  550. 22:06you something else. So I can also create
  551. 22:08an area schedule for example or um it
  552. 22:11will communicate the um areas which are
  553. 22:14being listed throughout the building.
  554. 22:15Instead of looking at the categories um
  555. 22:17for the walls or the block instances, I
  556. 22:20can do it by zone. So there it lists out
  557. 22:22all of the zones which are appearing in
  558. 22:25the project and I can go there and add
  559. 22:28the area as um as a column. So the guest
  560. 22:31bedroom, the master bedroom, the kitchen
  561. 22:33dining. So that's reading those zones
  562. 22:35which are within the project. It's
  563. 22:38giving me the area schedule. And if I
  564. 22:40went back in for example, so we've got
  565. 22:41our master bedroom here. I could add a
  566. 22:44custom property um which was uh say
  567. 22:49finish for example. and we'll say uh
  568. 22:52timber planks.
  569. 22:56I can add a column to there for finish.
  570. 23:00And you can see there it then tells me
  571. 23:02what the material is. And this could be
  572. 23:03used for things like material takeoffs,
  573. 23:05which is obviously really helpful. Now I
  574. 23:07know now that there's exactly 14 square
  575. 23:10meters of timber blanks which are being
  576. 23:12used for the master bedroom. And exactly
  577. 23:14the same for the guest bedroom. I could
  578. 23:16add that zone property
  579. 23:18again. I could say it was timber
  580. 23:21planks and then I could even group by um
  581. 23:25the material and now it's giving me a
  582. 23:27sum of that total timber planks because
  583. 23:30it's being seen in both the guest
  584. 23:32bedroom and the master bedroom. So just
  585. 23:33to give an example, it has a whole raft
  586. 23:37of really powerful things which can
  587. 23:39really streamline your process and it's
  588. 23:41applicable for windows and doors. Um you
  589. 23:44can use it for furniture. So for things
  590. 23:46around procurement for example you could
  591. 23:47add metadata around the cost of
  592. 23:50elements. So you know the bed um the
  593. 23:52windows the dressing table you know
  594. 23:55whatever you want. You can add data can
  595. 23:57then be read by those tables. The other
  596. 23:59great thing about the tables is that you
  597. 24:00can export them. So you can export as a
  598. 24:03CSV or an Excel SX file and they can go
  599. 24:06to things like Excel. so you can use
  600. 24:08that data um moving forward throughout
  601. 24:11the project. With the schedules
  602. 24:12formatted and completed, let's get these
  603. 24:14onto our drawing sheets to finalize the
  604. 24:16submission. Okay, lastly, let's set the
  605. 24:19sheets up. So, um we'll jump back to our
  606. 24:21paper canvas. We've got all our drawings
  607. 24:23that were created last time. And I'll
  608. 24:24very quickly add new page, set that as
  609. 24:29an A3. Again, we can copy our title
  610. 24:32sheet across. I'm just going to set up a
  611. 24:35grid line to separate the page in half
  612. 24:38so I know everything is nicely aligned.
  613. 24:40So, first of all, we'll add in our two
  614. 24:42reference plans. So, from the existing
  615. 24:44and the proposed. So, I want to be able
  616. 24:46to see those in context with the
  617. 24:49schedule. And then I can add in my
  618. 24:52existing uh my window and door view.
  619. 24:56And again, I just want to crop this
  620. 24:58boundary. double click into there and
  621. 25:01find decent size to view these at. So I
  622. 25:05think maybe four on a page probably
  623. 25:08looks good. Now I'm less interested in
  624. 25:10the scale because this is really just
  625. 25:11about communicating the visual aspect
  626. 25:13and we have the dimensions on there. But
  627. 25:15in essence, I can then copy this across
  628. 25:18and take a view of those next pages. And
  629. 25:22obviously we can make sure everything's
  630. 25:23nicely aligned and set out. Um, but that
  631. 25:26means that if I go back into the
  632. 25:27drawings, make any changes to those
  633. 25:29schedules, make any changes to the
  634. 25:31elevation, um, those things will be
  635. 25:33updated on the sheets because I'm always
  636. 25:35looking back at those original views.
  637. 25:37Okay. And there you have it. We have all
  638. 25:39of our sheets neatly set out. We have
  639. 25:41our window and door tags. We have all
  640. 25:43that information that we were
  641. 25:45referencing. So, the opening, the glass,
  642. 25:46the frame, and the finish. Um everything
  643. 25:48is dimensioned um and neatly set out
  644. 25:51with our windows um and doors which
  645. 25:54clearly communicates the design intent
  646. 25:56and the specification for everything
  647. 25:57we're proposing to do. That brings us to
  648. 26:00the end of this lesson on creating
  649. 26:01detailed opening schedules for your
  650. 26:03residential building permit set. At this
  651. 26:05stage, your drawing should include clear
  652. 26:07and accurate door and window schedules,
  653. 26:09organized, formatted, and ready to meet
  654. 26:11municipal requirements. The next lesson
  655. 26:13is the last one for this course where
  656. 26:15we'll continue strengthening the permit
  657. 26:17package by adding final documentation
  658. 26:19and design details and finalize our
  659. 26:21documents so we have a complete set
  660. 26:23ready for approval. If you'd like to
  661. 26:25explore Rayon more deeply, don't forget
  662. 26:27you can access the free permit set
  663. 26:29template linked below or book a
  664. 26:31one-to-one demo for tailored guidance.
  665. 26:33And of course, if you found this
  666. 26:34helpful, please like, comment, and
  667. 26:36subscribe so you won't miss the upcoming
  668. 26:38lessons in this course. Thanks for
  669. 26:40joining me and I'll see you in the next
  670. 26:42and last session for this course.

About this transcript

This page contains the full transcript of How to Create a Door & Window Schedule for a Building Permit by Rayon Academy, generated from the public captions YouTube serves with the video. The transcript has 4,623 words across 670 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.

Free YouTube transcript tool

YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, translation to 100+ languages, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.