  1. 0:00How to bid commercial construction jobs.  In this video, I'm going to talk to you
  2. 0:05about the process for the general  contractor to bid for the project,
  3. 0:09and it will also apply to subcontractors bidding  to be awarded the actual trade specific scope
  4. 0:15for the general contractor. So when we  look at commercial construction projects,
  5. 0:20we're fascinated by the bridges, the laboratories,  the hospitals, but what goes behind goes on
  6. 0:25behind the scenes in the bidding process.  We're going to talk about that right now.
  7. 0:36Okay, so when we talk about bidding a commercial  construction project, there's two general ways
  8. 0:42to go about this. First of all, it's the general  contractor bidding to be awarded the project from
  9. 0:47the building owner, and then the subcontractor  to the general contractor. Let me give you a
  10. 0:52high level overview of both. First of all, if you  are bidding a commercial construction project and
  11. 0:58you are doing it with your team, you are going  to learn all about it, because it is an intense
  12. 1:03process. First of all, you'll have your RFP or  RFQ. It's the request for proposal or request
  13. 1:11for qualifications, right? It may be heavier on  the price side or the qualification side. There's
  14. 1:16lots of different formats, but typically it's  broken down into the written proposal and the
  15. 1:22actual interview. I love both. Written proposal  process, you're going to gather with the team,
  16. 1:28have a team lead, really shape a single  message, and then delegate to the other
  17. 1:33proposal participants. I'll call them before we  get to the interview team, and they are going to
  18. 1:39help put together a written proposal as subject  matter experts that really answer the questions
  19. 1:45and make sure that you are communicating  the aspects of price and qualifications and
  20. 1:52approach to the building owner so that you can be  selected, and then go on to the interview. It's an
  21. 1:57absolutely amazing process. And what I would say  is you have to shape a compelling message. You
  22. 2:03have to follow the hero's journey. There's lots of  really good books about that. You have to be very,
  23. 2:08very clear and interesting to keep their interest  throughout reading the proposal. And you have to
  24. 2:15start planning and solving problems for their  project. Now let's go into the interview. This
  25. 2:20is crazy cool. Everything you say needs to be  turned into sound bites. You need to have amazing
  26. 2:26visuals, and you need to know what you're talking  about and talk to their needs. So you will go
  27. 2:33through an interview preparation process and then  get into the interview and again, start showing
  28. 2:38them how you're going to solve their problems and  take care of their needs, but you're going to do
  29. 2:43it with love for the selection committee, with  high energy, hopefully at the right time of day,
  30. 2:49and you're going to do it without the fear and  without the nervousness and really go in there
  31. 2:53and win that interview. Now, when we're pricing  this, I'm going to go through the exact steps
  32. 2:58there, but it's basically the same when you're a  subcontractor or when you're a general contractor,
  33. 3:04the steps that you will follow for pricing. But  let me talk real quick about subcontractors. You
  34. 3:09are either going to be bidding the project based  on an instruction to bidders and a bid package,
  35. 3:15or you might have to interview as well. The key  thing the general contractor is looking for in
  36. 3:21this interview is to make sure that you have the  right team, the right approach, the right price,
  37. 3:25the right schedule. And the biggest thing that  we worry about with trade partners is that you
  38. 3:30actually can deliver on your promises. And we  want to really make sure that you are the right
  39. 3:36fit for this process, so whether you're a GC or a  subcontractor. Now let me go through the specific
  40. 3:42steps you'll follow when you're bidding at either  level. So number one, understand the project
  41. 3:48requirements. What is it that you're building?  This is not just crack open the plans or know what
  42. 3:53type of building it is. We at Elevate and lean  tax and lean bill. We really go on a deep dive on
  43. 3:59this. We attempt to understand the building, all  of the numbers that quantify what goes into that
  44. 4:04building, we will do a page flip look at different  one off areas. Are there any overhangs? Are there
  45. 4:10any high bay ceilings? Are there any special types  of form work? Is this a postage stamp site like
  46. 4:15we're going to get a really good feel for what  this building actually is before we go into the
  47. 4:20bidding process. Number two, and I love this,  go do a site visit and assess what's going on
  48. 4:27on the actual project site. And you know what's  even cool, actually, let me say this the right
  49. 4:31way. Even cooler than just going to the site is  going out there and calling in a blue stake ahead
  50. 4:37of time. And then this sounds silly. You'll at  least want to do this once you've won the job,
  51. 4:42but one of the cool things that you can do  is do some preliminary layout and find out
  52. 4:46how that building is going to sit on the actual  lot. You definitely have to do that once you've
  53. 4:51been awarded the project. I would actually lay  out the entire structure and see how it overlays
  54. 4:55with the utilities, but you definitely want to at  least get a feel for the site. And here's. I want
  55. 5:00you to look for look at soils, conditions,  neighbors, access, and I want you to see if
  56. 5:05any utilities need to be relocated. Do you need  shoring these are all things that you can loop
  57. 5:10into your written proposal and your interview to  start solving problems right away. Number three,
  58. 5:16you're going to want to start estimating costs.  Obviously you're going to want material costs,
  59. 5:20labor costs, equipment costs. You'll break  it out as your general conditions, which is
  60. 5:24basically your insurance, bonds and your staff,  your general requirements, which is anything
  61. 5:29that you have to use to build the project from a  general requirement standpoint, anything that is
  62. 5:35needed for logistical support. Then you'll have  your subcontracts, your contingency and your fee.
  63. 5:41And you know, there's other categories in that  budget, but you're going to start estimating
  64. 5:45those and make sure that you have accurate  quantities, that you're getting trade numbers,
  65. 5:49or if you are the trade that you're providing  your own number, and if you're the GC, that
  66. 5:53you're doing your internal control estimates, and  that you're comparing those to make sure that you
  67. 5:59have multiple sets of eyes on these numbers and  that you have accurate bid numbers. Number four,
  68. 6:03you're going to propose on a timeline, obviously,  when it comes to a cost and schedule standpoint,
  69. 6:08that's whether you're the GC or you're the trade  partner. And you will definitely want to break out
  70. 6:13your estimate into different categories so you can  see the clear picture of what you're proposing.
  71. 6:18And you want to create a timeline, and in my  case, an overall macro level tax plan to show
  72. 6:24the schedule portion of this project. And I would  also include your zone maps, your logistics plans,
  73. 6:29so that you know what has fed into your general  requirements inside your budget number five,
  74. 6:35submit your bid. Now, I do want you to know that  there isn't just a one size fits all with this as
  75. 6:40a GC, you're either going to submit your initial  proposal from a cost standpoint, in the written
  76. 6:47proposal and in your interview, or you're going  to be selected on qualifications, and then you're
  77. 6:52going to enter into a CM at risk type environment  where you're going to reach A guaranteed maximum
  78. 7:00price, where you eventually submit your GMP,  and that total price, right? That aggregates the
  79. 7:07overall budget, and that is what you are at risk  for to build the project, is the GC once you are
  80. 7:13selected. Now, if you're the trade partner, people  do this differently. By the way, you can reach a
  81. 7:18GMP early or late in the design process, same  with a trade partner. You might be bidding the
  82. 7:24design development documents 50% CDs or 100% CDs,  and you might literally only give plug numbers or
  83. 7:32square foot pricing, or unit pricing up into the  100% CDs, or whenever the GC is going to bid it
  84. 7:38out and then fully bid it. Or you might have to do  a more intense process throughout but either way,
  85. 7:44strategize. The key to this is literally just  sketching this out on paper as the GC or the trade
  86. 7:50partner, and know the strategy for how you're  going to bid out, know the strategy for how
  87. 7:54you're going to bid it out in a way that gets you  the best number, that allows you to release work
  88. 7:59early enough, but doesn't waste the time of the  trade partners. And then obviously you have six
  89. 8:04your post bid follow up, where you find out if you  won the project as the GC, or you won the project
  90. 8:10as the trade partner, as the subcontractor. And  then you know, if you didn't, obviously get your
  91. 8:14lessons learned and approved from there. But  if you did, obviously it, we are off to the
  92. 8:19races. Get the feedback, but start immediately to  prepare anything that deals with your scope, your
  93. 8:25contract, long lead procurement, and preparing to  start strong on that project site. And remember,
  94. 8:31it's all about scope. Scope, scope. We do not want  scope gaps in any of these processes. And so I'd
  95. 8:37like to close up, by the way, if you've liked this  video, please like and subscribe. Let me give you
  96. 8:41some tips along the way. Number one, get accurate  subcontractor scopes and do control estimates
  97. 8:48with quantities that will allow you to compare the  pricing and make sure that it is accurate. Number
  98. 8:55two, be realistic with time frames. It takes some  time to put these bid packages together. It takes
  99. 9:00time when you're bidding out trades. It takes time  for them to send you their number in response. It
  100. 9:05takes time to create the written proposal and  do the interview. This takes time, so make sure
  101. 9:10you're being realistic with it throughout number  three, always make sure you have buffers. You
  102. 9:15have contingencies built in. You'll need buyout  contingency, you'll need contractor contingency,
  103. 9:20you'll need owner contingency make sure you have  enough buffers to where you don't get yourself in
  104. 9:25trouble. And really you're going to want to stand  out if you're going to want to win this, either as
  105. 9:29the GC to the owner or as the trade to the general  contractor, you must stand out by adding value,
  106. 9:35by making sure that you're preventing anything  that would keep the selection kit committee up
  107. 9:40at night and start planning their project from day  one, and just remember, this can be an excellent,
  108. 9:46precise and fun process if you know the strategy  and you're working as a team and you know your
  109. 9:52numbers. And so here's what I'm going to do. I'm  going to put in the description below. This is a
  110. 9:57blog post, but also offer that if you ever want.  Any help, reach out to us. We have templates.
  111. 10:02We do this all the time, and remember, we're  wanting to find the best value, not the lowest
  112. 10:09bid. Lowest bid is never lowest overall total  cost. Make sure we're doing this with high levels
  113. 10:15of communication, with high levels of double  checks, with accurate numbers and with buffers,
  114. 10:20and this should be an amazing process for you.  I hope you've enjoyed this video. On we go.

About this transcript

This page contains the full transcript of How To Bid Commercial Construction Jobs by Jason Schroeder, generated from the public captions YouTube serves with the video. The transcript has 1,962 words across 114 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.

Free YouTube transcript tool

YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, caption language selection, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.