  1. 0:00Hello, my dear friend. Today, you and I
  2. 0:02are going to talk about a very
  3. 0:04fascinating topic: construction control
  4. 0:06.
  5. 0:06>> As-built documentation.
  6. 0:08>> What kind of beast is that? Yes, exactly
  7. 0:10. People have a common problem. When
  8. 0:12they start maintaining a newly built, or
  9. 0:15even not-so-newly built house, they find
  10. 0:18that contractors come in, start drilling
  11. 0:21or sawing into a wall, and then
  12. 0:23utilities get damaged. They might
  13. 0:25puncture radiant floor heating or damage
  14. 0:27the electrical wiring.
  15. 0:28I’m not even mentioning cutting
  16. 0:30low-voltage lines and all those other
  17. 0:32issues, right up to the destruction of
  18. 0:34load-bearing structures.
  19. 0:36Like those stories where a partition
  20. 0:37wall was torn down in a building, and
  21. 0:39then the apartment block tilted a little
  22. 0:41. Part of this is due to the fact that
  23. 0:44people simply don't have the as-built
  24. 0:46documentation on hand.
  25. 0:48So, today we will figure out what
  26. 0:50as-built documentation is, what problems
  27. 0:53arise for people later on from its
  28. 0:55absence, how to handle this issue so
  29. 0:58that you do have this documentation, and
  30. 1:01most importantly, how it affects the
  31. 1:03lifespan of your future or current home
  32. 1:06.
  33. 1:07My name is Mikhail Kirchenko. I have
  34. 1:09been working in architectural and
  35. 1:11interior design for over 20 years at my
  36. 1:13studio.
  37. 1:15And our dear lead engineer, Konstantin,
  38. 1:17who has been doing construction
  39. 1:19engineering and site supervision for
  40. 1:21those same damn many years. Let’s dive
  41. 1:24in. I’ll make a quick remark.
  42. 1:27This was an unplanned episode.
  43. 1:30Kostya and I were rewriting the third
  44. 1:32block of construction control, called "
  45. 1:34Erecting the Shell," and we were
  46. 1:35planning to discuss lintels. But Kostya
  47. 1:37, as always, ran in with a fresh story,
  48. 1:40so we had to create something useful for
  49. 1:42YouTube.
  50. 1:44If you are interested in learning how to
  51. 1:46independently control construction and
  52. 1:48supervise a building site, please check
  53. 1:50the link to Boosty in the description.
  54. 1:53Go in and start learning.
  55. 1:55But today, Kostya, we are still going to
  56. 1:56address the question.
  57. 1:58Let’s figure out: what is as-built
  58. 2:02documentation?
  59. 2:04The definition.
  60. 2:09I see. We are now going to sort out the
  61. 2:11definition of what as-built
  62. 2:12documentation is.
  63. 2:14And what its absence leads to. Let’s go
  64. 2:17.
  65. 2:18>> As-built documentation is a set of
  66. 2:20documents with which the contractor who
  67. 2:22performed the work confirms that the
  68. 2:24work was carried out in accordance with
  69. 2:26the project.
  70. 2:28Or, if there were any deviations from
  71. 2:29the project, they are noted there just
  72. 2:31the same.
  73. 2:32And it shows how the construction
  74. 2:34structures, utility networks, building
  75. 2:36envelope, and roofing were actually
  76. 2:38executed.
  77. 2:39>> And now, a question. But he was building
  78. 2:41according to the blueprints, so there
  79. 2:43wouldn't be any "mess-ups." Build
  80. 2:44according to the drawing. Why isn't the
  81. 2:45project itself the as-built
  82. 2:47documentation?
  83. 2:48>> Because the project is how we see it in
  84. 2:50an ideal world. That is, it’s our ideal
  85. 2:52picture, our vision.
  86. 2:54But it never happens that in any kind of
  87. 2:57construction—whether it's a high-rise, a
  88. 2:59low-rise, or linear infrastructure, it
  89. 3:02doesn't matter—it never happens that all
  90. 3:04architectural and engineering solutions
  91. 3:07are executed exactly as planned.
  92. 3:09Right.
  93. 3:11Exactly as in the design, because
  94. 3:13sometimes, while work is being done, a
  95. 3:15thought comes a little later: "Why am I
  96. 3:17doing this here?"
  97. 3:19I mean, it all seems logical on paper,
  98. 3:21but when you see, for example, the
  99. 3:23utility line installed there, you think
  100. 3:25: "Wait, I wanted to put something here
  101. 3:27, like a flower vase, or maybe add an
  102. 3:29extra toilet later."
  103. 3:31And as a rule, certain additions arise.
  104. 3:33Or a person might say: "I want another
  105. 3:35partition here, or to shift this one, or
  106. 3:37could I have an opening made in this
  107. 3:38wall?" Accordingly, there are always
  108. 3:40some nuances that emerge during the
  109. 3:42course of construction and installation
  110. 3:44work.
  111. 3:45>> In other words, while building, some
  112. 3:47nuances may arise.
  113. 3:49Take the example of building a house,
  114. 3:51say, using monolithic technology. There
  115. 3:54is a monolithic pillar, right.
  116. 3:56There is specific formwork for it,
  117. 3:58calculated in the project, but the
  118. 4:00contractor brings different formwork and
  119. 4:03says: "Dude, I can't make this pillar
  120. 4:05exactly to the dimensions, I'll make it
  121. 4:08a bit larger, or for instance, I'll use
  122. 4:10more rebar while keeping the
  123. 4:12cross-section, because we can't maintain
  124. 4:14a 180mm wall, so we'll make it 220mm."
  125. 4:18This is exactly the case when, during
  126. 4:21construction, based on
  127. 4:23>> actual technical capabilities, the
  128. 4:25project is realized. This is where
  129. 4:27things can change, quite literally,
  130. 4:28during the construction of your home.
  131. 4:31The contractor simply, well, not exactly
  132. 4:33as drawn in the project—because a
  133. 4:34project is an idealized solution after
  134. 4:36all—
  135. 4:38>> introduces
  136. 4:39>> changes to the project, essentially,
  137. 4:41>> and builds with deviations from that
  138. 4:43project. Whether this is critical or not
  139. 4:46varies from case to case. Okay, sorry
  140. 4:48for interrupting, but you really need to
  141. 4:51understand these specific nuances.
  142. 4:54And most often, as I understand it, most
  143. 4:56of the as-built documentation and
  144. 4:58corrections occur during the
  145. 4:59installation of utility networks.
  146. 5:02>> Yes, not just those, actually, but even
  147. 5:04the load-bearing structures as well.
  148. 5:06There are situations where, again, with
  149. 5:09the layout of partitions, when a person
  150. 5:11sees one picture on paper—it's like when
  151. 5:13you go to a store, or rather open some
  152. 5:16marketplace, and you see a nice coat or
  153. 5:18a beautiful scarf.
  154. 5:20So, uh, you order it, you come in, you
  155. 5:22try it on, but it's different—the way it
  156. 5:24feels, the way it looks—and you’ve
  157. 5:26already built it up in your head, and
  158. 5:28well, you just don't like it. You're not
  159. 5:30going to take it, right? It’s the exact
  160. 5:31same thing with a house; you’re building
  161. 5:32it for yourself. You put up some
  162. 5:34partitions, made a room, and the
  163. 5:35dimensions seem fine, but when you step
  164. 5:37into the space, you realize, oh,
  165. 5:39something’s not quite right. "Can we
  166. 5:41just shift this partition over here by
  167. 5:43half a meter?""I found this great wall
  168. 5:45unit, a perfect kids 'wall unit.""It
  169. 5:47would fit right here.""But I'm 5
  170. 5:49centimeters short, move the partition."
  171. 5:51>> Kostya, to avoid that, you have to do
  172. 5:52the damn design first.
  173. 5:53>> You have to. Well, we're just looking at
  174. 5:55all sorts of different options right now
  175. 5:57. Uh, let me be clear, I don't like
  176. 5:59people who start moving walls around
  177. 6:02on-site in reality. You can't do that,
  178. 6:04guys. There should be specialized people
  179. 6:07for that. There are designers—we are an
  180. 6:09architectural and design studio, after
  181. 6:10all—who will draw up a plan and explain
  182. 6:12to you exactly where everything will go
  183. 6:14. And then, with their help, you give
  184. 6:16instructions to the planners and
  185. 6:18builders about moving walls.
  186. 6:20You shouldn't just move walls by eye.
  187. 6:22By the way, if you need professional
  188. 6:24designers, there will be a link in the
  189. 6:25description.
  190. 6:26And, accordingly, when something gets
  191. 6:28out of control—out of the project's
  192. 6:30control, that is—that’s what as-built
  193. 6:32documentation is for. It is intended for
  194. 6:34those who performed the construction and
  195. 6:37installation work or the layout of the
  196. 6:39utility networks. Very often, our
  197. 6:41projects are carried out without utility
  198. 6:43network designs, without any engineering
  199. 6:45plans.
  200. 6:47A crew comes in, lays everything out,
  201. 6:49then the screed guys come, cover it all
  202. 6:51up, and everyone leaves happily.
  203. 6:53Yeah. And then, what are you supposed to
  204. 6:56do with that? Where is my pipe here? And
  205. 6:59where is the electricity for my outlet?
  206. 7:02>> Actually, we’ve arrived at the issue
  207. 7:05that a lack of accurate representation
  208. 7:08makes it hard to work with that reality
  209. 7:11later on. What are the most amusing
  210. 7:12negative consequences you’ve encountered
  211. 7:14? I have a couple of stories myself.
  212. 7:16>> Yeah.
  213. 7:17Yes, I’d also like to conclude with the
  214. 7:19simplest way to put it.
  215. 7:22As-built documentation is the completed
  216. 7:24construction and engineering solutions
  217. 7:26transferred onto paper.
  218. 7:28The final result. It’s essentially a
  219. 7:29second project.
  220. 7:30>> Uh-huh. I can just imagine a crew from,
  221. 7:33say, Shmovit coming in to do your wiring
  222. 7:35, and you ask them for as-built
  223. 7:37documentation.
  224. 7:38And they’re like:
  225. 7:41"
  226. 7:41>> No, well, again, you could just as
  227. 7:42easily say:' Oh, dear crew, I'll draw it
  228. 7:44up myself. '" If you look at it, the
  229. 7:46services of a site engineer or a
  230. 7:47surveyor don't cost that much on the
  231. 7:48scale of the entire construction project
  232. 7:50.
  233. 7:51A person simply comes, takes all the
  234. 7:52measurements, checks everything, and
  235. 7:53writes it all down clearly and precisely
  236. 7:55. The developer or the client themselves
  237. 7:56can do this for their own peace of mind
  238. 7:57, just to have everything on record.
  239. 7:59Accordingly, there is nothing left for
  240. 8:01them to do but to sign and confirm. If,
  241. 8:04again, we are doing everything with an
  242. 8:06eye on the budget,
  243. 8:06>> it is desirable to do it responsibly.
  244. 8:08>> Right. Yes. Therefore,
  245. 8:10>> on how to do this correctly, we will
  246. 8:12talk about it in the second part. Let's
  247. 8:14follow the rules of the genre a little
  248. 8:16bit.
  249. 8:17You and I need to tell a few funny
  250. 8:18stories.
  251. 8:19>> What people run into, and why it is
  252. 8:21desirable in one way or another to first
  253. 8:23raise the tension, then explain how to
  254. 8:25do it right. Here is what. And you have
  255. 8:27already sketched out how to do it.
  256. 8:28>> I arrive, a complaint comes in from an
  257. 8:31owner, well, a new building, a complaint
  258. 8:33comes from a new...
  259. 8:34>> a new residential building.
  260. 8:35>> A residential building, a residential,
  261. 8:36apartment building. An apartment
  262. 8:37building. A complaint comes in from a
  263. 8:39property owner, from an apartment owner
  264. 8:41. The pipes are leaking, it was done
  265. 8:44poorly, bad, bad. Well, I arrive, open
  266. 8:46up the floors, let's see what you have
  267. 8:47there under the laminate. Like, the
  268. 8:48laminate swelled up, everything, chaos.
  269. 8:50And in there...
  270. 8:51>> Ah, uh, a small point right away, this
  271. 8:53is the client, he did the renovation
  272. 8:55himself,
  273. 8:56>> yes,
  274. 8:56>> and his laminate swelled up and the
  275. 8:58floors leaked. He calls you. My pipes
  276. 9:01are leaking.
  277. 9:01>> Yes, yes. The utility systems were done
  278. 9:04poorly
  279. 9:04>> in the house.
  280. 9:05>> Neighbors flooded the house, pipes are
  281. 9:07leaking, we start arriving, we start
  282. 9:09looking into it.
  283. 9:10>> Well, in short, the area is already
  284. 9:11opened up. Everything is already opened
  285. 9:12, that is, it's all prepared, the
  286. 9:13laminate swelled up, there are photos of
  287. 9:15the swollen laminate, everything, I
  288. 9:16arrive, he says he opened the area, well
  289. 9:17, he says there was mold and something
  290. 9:19else. That is, he starts, starts telling
  291. 9:21me. I say, let's remove the laminate a
  292. 9:22little bit further, let's look at how
  293. 9:24our pipes are there, where they go, and
  294. 9:25what's what. In short, we open up under
  295. 9:28the laminate for some reason. Well,
  296. 9:29apparently, they had some kind of super
  297. 9:31technology. Two sheets of gypsum, two
  298. 9:33sheets of plywood placed between each
  299. 9:34other. And these two sheets of plywood,
  300. 9:36well, apparently for soundproofing.
  301. 9:38Maybe someone just wanted something like
  302. 9:39conditionally wooden floors for
  303. 9:40themselves.
  304. 9:41Under this, these two sheets of plywood
  305. 9:43are overlapped and fastened with screws
  306. 9:45.
  307. 9:46>> Are you serious?
  308. 9:48>> Well. Well, accordingly, you can simply
  309. 9:50guess the rest. The guys, the finish
  310. 9:52workers, when they were laying all this
  311. 9:54, used screws that were nice and long so
  312. 9:55that the screed would hold firm—bang,
  313. 9:57bang, bang, bang, bang. And it's just a
  314. 9:59sieve, you know, made of pipes. There.
  315. 10:02Uh, accordingly, we had to open
  316. 10:03everything up in the hallway. We open up
  317. 10:04the floor screed. Well, naturally, a
  318. 10:06hole from a screw. Everything looks nice
  319. 10:07, everything is by the book.
  320. 10:08>> And what about the quality?
  321. 10:10>> Ah, oh.
  322. 10:12>> Oh.
  323. 10:12>> Oh.
  324. 10:14>> This is probably one of the most common
  325. 10:16stories that happens with buried utility
  326. 10:19lines, because anything we've poured
  327. 10:21concrete over is buried.
  328. 10:24>> Yeah, and they couldn't have verified
  329. 10:25that right away, could they? Because
  330. 10:27they were doing the renovation in the
  331. 10:28summer, when there's no need for heating
  332. 10:29, no need for anything. So, they got it
  333. 10:31done, screwed everything in, and then
  334. 10:33they turn the heat on. Da-da-da-da-da-da
  335. 10:35.
  336. 10:36Well, the system should have been
  337. 10:37pressure tested, right?
  338. 10:38>> Ah, well, apparently it wasn't really,
  339. 10:40the water wasn't really circulating
  340. 10:42there much. Maybe they didn't even touch
  341. 10:43the boiler. Well, they did the repairs,
  342. 10:45finished the work, then they came back.
  343. 10:47>> And hello.
  344. 10:48>> A super common story. The second most
  345. 10:51super common story is electrical.
  346. 10:53>> Yeah, the electrical stuff, that's...
  347. 10:55...
  348. 10:55>> that happens to every furniture
  349. 10:57assembler.
  350. 10:58If you are watching this video, my dear
  351. 11:00friend, and you've worked with your
  352. 11:02hands on construction sites, please
  353. 11:03write down the most insane stories
  354. 11:05you've had.
  355. 11:07A buddy of mine had a...well, his junior
  356. 11:10colleague didn't end up in the hospital
  357. 11:13, but he ended up with a nervous
  358. 11:15breakdown because he takes the tool, and
  359. 11:18they tell him: "There are no wires in
  360. 11:20the wall here."
  361. 11:22They had waved some kind of magical
  362. 11:24device around there. He starts hammering
  363. 11:27away with his rotary hammer and,
  364. 11:28naturally, the hammer kicks back at him
  365. 11:30.
  366. 11:31The building loses power because there
  367. 11:32shouldn't have been any, but for some
  368. 11:34reason, the main building power cable
  369. 11:35was running right there. They revived
  370. 11:37the guy, calmed him down, and said: "
  371. 11:39It's all good, we're moving over 20
  372. 11:42centimeters.""Are you sure? Is it right
  373. 11:43? Is there nothing there?" He starts
  374. 11:45drilling. Five minutes later, his rotary
  375. 11:48hammer kicks back again. He just sends a
  376. 11:50signal, leaves, and the building loses
  377. 11:52power again. And they go, "Oh, we also
  378. 11:54had one more cable."
  379. 11:56That was common building property, by
  380. 11:57the way. A week later, this guy comes
  381. 11:59back and says: "Did you check everything
  382. 12:00?""Yes."
  383. 12:02The company is standing there, maybe a
  384. 12:03manager or someone. Well okay, back in
  385. 12:05those days there weren't really any
  386. 12:06managers. Those were the days.
  387. 12:09>> So he says, everyone is standing there
  388. 12:10together, saying: "No, everything is f
  389. 12:11***ing great." The guy takes the rotary
  390. 12:14hammer and says: "Alright, there is
  391. 12:15definitely nothing here at all."
  392. 12:18He starts drilling. And they go: "Damn,
  393. 12:21we had a backup one there too." Exactly
  394. 12:24.
  395. 12:25I don't know what kind of perverse
  396. 12:27torture this is, because the whole
  397. 12:29building got caught in the crossfire.
  398. 12:33That guy quit construction. But that
  399. 12:36happens too. Utilities get buried.
  400. 12:40And these could be major power lines,
  401. 12:43not to mention punctured sewage, water
  402. 12:45supply, or networks; as you understand,
  403. 12:47you need to know where your utilities
  404. 12:49are.
  405. 12:51But there is one more point, which I
  406. 12:53mentioned at the very beginning about
  407. 12:55as-built documentation.
  408. 12:59Even in residential construction, you
  409. 13:01need to know, guys, you’re building a
  410. 13:04house based on one plan, and two years
  411. 13:07later, you get a brilliant idea to put a
  412. 13:10loft hatch in from inside the house.
  413. 13:15And the stories where people punch holes
  414. 13:18in load-bearing walls without
  415. 13:19reinforcing them, or adding openings
  416. 13:22without strengthening them, weakening,
  417. 13:24so to speak, some pillar.
  418. 13:27Like the story of, "Why the hell did
  419. 13:29they draw a brick column here in the
  420. 13:30middle of the room?"
  421. 13:33when they tore it down and the ceiling
  422. 13:35collapsed inward, or the structure
  423. 13:37started sagging because it turns out it
  424. 13:39was, damn it, a load-bearing column that
  425. 13:41all the beams—oops, all those floor
  426. 13:43slabs were actually resting on.
  427. 13:46Why are we talking about beams and floor
  428. 13:48slabs today? Recalling that story.
  429. 13:51You can, by ignoring the house's
  430. 13:54structure and not maintaining this
  431. 13:56as-built documentation, violate—how
  432. 13:59should I put it?
  433. 14:01—the very essence, the structure of the
  434. 14:03house. Especially when making
  435. 14:05adjustments to foundation work or adding
  436. 14:07extensions—blunders are everywhere.
  437. 14:10Not puncturing a sewer line while
  438. 14:11building an extension—that’s something
  439. 14:14that, in all likelihood, will be a
  440. 14:15rarity.
  441. 14:16Consequently, as-built documentation, as
  442. 14:19we have already figured out.
  443. 14:22This is not just a question of the near
  444. 14:24future, so you can finish your repairs,
  445. 14:26but so you can safely operate this house
  446. 14:29, and if necessary, reconstruct, expand
  447. 14:31, finish, or upgrade it.
  448. 14:34And moreover, since people are becoming
  449. 14:36more and more savvy now, when you sell
  450. 14:38your real estate—you decided to sell the
  451. 14:41house and move—if you have as-built
  452. 14:43documentation and you show people what
  453. 14:45it's made of, it will validate the value
  454. 14:48of your property.
  455. 14:49Because some friends are already
  456. 14:51predicting that this kind of situation
  457. 14:53might occur in the secondary market.
  458. 14:56You’re buying a house, and the person
  459. 14:59selling it, for the bank to approve the
  460. 15:01mortgage, will be told, "Hell, I don't
  461. 15:04believe that what you have is what's
  462. 15:06written in the BTI passport."
  463. 15:08The design is worthless. Either provide
  464. 15:11the as-built documentation or an expert
  465. 15:12report on the building structures. That
  466. 15:14will cost money. And at the same time,
  467. 15:17for those same banks, this documentation
  468. 15:19serves as confirmation that everything
  469. 15:21was done according to the blueprint,
  470. 15:23correctly and properly. And this
  471. 15:25preserves the value of your real estate
  472. 15:27. In other words, you can blow this off
  473. 15:29now, but you might regret it very much
  474. 15:32later. Accordingly, to avoid any regrets
  475. 15:34later, we need to understand how this is
  476. 15:36actually done.
  477. 15:36>> I can even give you some rough price
  478. 15:39estimates right now to add to that. Say
  479. 15:41, for a house of about 100-150 square
  480. 15:43meters.
  481. 15:44>> A set of as-built documentation, if you
  482. 15:46offload it to a contractor, will cost
  483. 15:48around 50,000 rubles. Well, just based
  484. 15:51on the latest estimate.
  485. 15:52>> Uh-huh. For the engineering systems. So
  486. 15:54, this whole package is prepared.
  487. 15:56>> An inspection for the same house would
  488. 15:58be 250,000 rubles.
  489. 15:59>> That's a slightly different price.
  490. 16:01>> A slightly different price.
  491. 16:02I mean, it's incomparable if we prepare
  492. 16:05these documents right away; the costs
  493. 16:08are completely different.
  494. 16:11And it's not a burden for the person
  495. 16:13doing the work, because they finish it
  496. 16:15immediately, mark everything, sign off
  497. 16:17on it, and move on.
  498. 16:19>> Alright, then we should figure out the
  499. 16:21next stage now. Which one? How, so to
  500. 16:24speak, the major construction companies
  501. 16:27do it.
  502. 16:28We have market leaders who do it like
  503. 16:30professionals, and then, say, the
  504. 16:32mid-range person who might have bought a
  505. 16:35design but doesn't hire anyone for
  506. 16:37supervision, managing the construction
  507. 16:40themselves.
  508. 16:41And for the really hardcore DIYers who
  509. 16:44built without blueprints, just by eye.
  510. 16:46They probably don't care anyway. Fine.
  511. 16:48No, we'll give them some advice too;
  512. 16:49we'll show them how it can be done.
  513. 16:50Let's start with the professional way.
  514. 16:53>> The whole thing.
  515. 16:54Since as-built documentation is a very
  516. 16:56important document, a house cannot be
  517. 16:58put into operation without it; the house
  518. 16:59being built cannot be commissioned
  519. 17:01without this set of as-built
  520. 17:02documentation, because...
  521. 17:04>> this includes multi-story residential
  522. 17:05buildings,
  523. 17:06>> yes, multi-story residential buildings,
  524. 17:07office buildings, anything that goes
  525. 17:09through the State Construction
  526. 17:10Supervision Inspection must go through
  527. 17:11as-built documentation.
  528. 17:13They arrive for an inspection, first
  529. 17:15look at the as-built documentation, and
  530. 17:17only then go to see the actual object,
  531. 17:19what has been built, or they do it in
  532. 17:21parallel. It just depends on what is
  533. 17:23more convenient for them. And without it
  534. 17:24, without the as-built documentation,
  535. 17:25you cannot hand over the object. Meaning
  536. 17:27you cannot put the house into operation
  537. 17:28so that people can move in.
  538. 17:30To this end, the Ministry of
  539. 17:32Construction and Rostekhnadzor have
  540. 17:34developed a large number of standard
  541. 17:36templates where everything is specified
  542. 17:38regarding what you must do and what the
  543. 17:40minimum set of documents you must
  544. 17:42provide is. Just everything at a minimum
  545. 17:45. They've even released it. Just imagine
  546. 17:47, they released it specifically so you
  547. 17:49don't have to look through scattered
  548. 17:51orders like this. SP, a code of practice
  549. 17:53. What to monitor? What kind of
  550. 17:56>> What’s it called? 543
  551. 17:58>> I’ve got SP 543
  552. 18:03>> The set of as-built documentation, what
  553. 18:05it should look like, the minimum
  554. 18:06operations to be carried out, and the
  555. 18:08oversight of construction control—
  556. 18:09everything is already written out.
  557. 18:11Just take it, read it, and follow this
  558. 18:14document. But it was released, well,
  559. 18:16recently. Well, how recent? Two years
  560. 18:18ago. As usual, everyone missed it, no
  561. 18:20one looks at it, no one pays attention,
  562. 18:22and they never bring these sets, these
  563. 18:25sets of as-built documents.
  564. 18:27I’m flipping through it now, checking
  565. 18:29the registry. Right, look, guys, I’m
  566. 18:31just opening the document, taking a
  567. 18:32screenshot, and saying: just fulfill at
  568. 18:34least what’s in this table. I’m telling
  569. 18:36you, I’m not asking for anything more
  570. 18:37than that. Just do the minimum required
  571. 18:40set. I mean, people are just too lazy to
  572. 18:41even open it.
  573. 18:42>> So it’s SP 500...
  574. 18:44>> 543 construction control. Well, there
  575. 18:46are a bunch of other numbers too. I
  576. 18:47don’t remember the exact numbers right
  577. 18:48now. There. But it’s SP 543 construction
  578. 18:51control. Cool. Then here’s a quick tip.
  579. 18:57Guys, those who are into professional
  580. 18:59construction and finishing—I’m not
  581. 19:02talking about, let’s say, fly-by-night
  582. 19:04crews, but anyone who claims to be
  583. 19:07serious in this world—let’s start
  584. 19:09getting used to the idea that if you’re
  585. 19:12building a house for someone for 10, 15
  586. 19:14, or 20 million, then just add the cost
  587. 19:17of hiring people to do the as-built
  588. 19:19documentation for 50k into your price,
  589. 19:21damn it.
  590. 19:23Yeah, well...
  591. 19:24>> Make it an add-on service for the client
  592. 19:26, hell, spread that cost out, it doesn’t
  593. 19:29matter. It covers your ass from legal
  594. 19:31proceedings; it can protect you from a
  595. 19:34lot, by the way. And at the same time,
  596. 19:37it gives the person confidence that you
  597. 19:39did the job properly.
  598. 19:41>> We...yeah, the whole point here is what
  599. 19:42? We aren't taking anyone’s side. Not
  600. 19:44the contractors' side, and not the
  601. 19:46clients 'side. Our main goal in what
  602. 19:48we’re talking about now is to make sure
  603. 19:50everyone is satisfied with the final
  604. 19:52service, which...
  605. 19:53>> that means everyone is dissatisfied.
  606. 19:54>> Yeah, yeah.
  607. 19:55>> Okay, actually, right now I am playing
  608. 19:56for the client's side, the homeowner
  609. 19:58who’s going to live there.
  610. 20:00>> Well, this is a huge plus for him too.
  611. 20:04What else is the point? You said, right
  612. 20:06, a 20-million house.
  613. 20:07>> Can I share a little pain?
  614. 20:09>> Go ahead.
  615. 20:10>> Something that, dammit, just happened to
  616. 20:11me recently. They finished all my
  617. 20:13electrical work, everything. But then
  618. 20:15the gate lighting went out. And the
  619. 20:17problem is, I had the gate installed
  620. 20:20along with the electrical work. By a
  621. 20:23third-party contractor.
  622. 20:24>> Uh-huh.
  623. 20:25>> But he didn't give me the documentation
  624. 20:26. I have everything for the electrics,
  625. 20:28except for that. And damn, we looked for
  626. 20:30it. Then we found out it was in the
  627. 20:33as-built documentation from the
  628. 20:35electrical contractor.
  629. 20:36It's just that I don't know a damn thing
  630. 20:38about electricity.
  631. 20:39He even included and noted that he had
  632. 20:40installed the relay that needed
  633. 20:42connecting, but the other contractor was
  634. 20:43supposed to connect it and didn't.
  635. 20:45So, accordingly, that wasn't reflected
  636. 20:47anymore. But in the as-builts, we
  637. 20:49eventually found
  638. 20:50>> that point.
  639. 20:51>> You just mentioned a house worth 20
  640. 20:53million, right?
  641. 20:54But do you know that even for work
  642. 20:56costing 600,000 rubles, there absolutely
  643. 20:58must be as-built documentation. That’s
  644. 21:01if we’re talking about something
  645. 21:02municipal. Moving a utility pole,
  646. 21:05>> the cost is, I don't know, 150,000
  647. 21:06rubles. They took everything, relocated
  648. 21:08it, removed it, moved it away, dug
  649. 21:11trenches. Be so kind as to provide the
  650. 21:12as-built documentation. That’s if the
  651. 21:14city requests it, but here you're
  652. 21:15talking about a 20 million house. Wow,
  653. 21:17that's something. I mean, it's
  654. 21:18incomparable because the individual
  655. 21:19housing market is wild. Everyone tries
  656. 21:21to do everything without control, just
  657. 21:24to get easy money and run off to some
  658. 21:26other project. Unfortunately, that
  659. 21:28happens too. Yeah. As-built
  660. 21:30documentation is really, really, really
  661. 21:31necessary. So, let's go over the
  662. 21:33necessary, the minimum set and map it
  663. 21:35out. Well, besides what they said should
  664. 21:38be there, yes, they’ll read that. But
  665. 21:40right now, let's say, for, like,
  666. 21:42>> the average person,
  667. 21:44>> in simple words, what is it actually for
  668. 21:46, and what should minimally be included
  669. 21:47in this document, and what is each one
  670. 21:49for?
  671. 21:50I’ll go through the minimum, the minimum
  672. 21:52documents now, so people understand why
  673. 21:54it’s needed. On a construction site,
  674. 21:56there must be at least two logs when
  675. 21:58carrying out construction and
  676. 21:59installation work. Or
  677. 22:01>> we’re talking about grown-ups now.
  678. 22:03>> Yeah.
  679. 22:03Not just...yes, listen, look, the
  680. 22:05general work log, the general work log
  681. 22:07is the log where, well, where the
  682. 22:09progress of construction is recorded.
  683. 22:11Meaning, who?
  684. 22:13>> Who is it? The contractor organization.
  685. 22:14>> The contractor organization, yes. The
  686. 22:15foreman must record every day what work
  687. 22:18he performed. If he didn't perform any
  688. 22:19work, it’s written there as such. No
  689. 22:21work was performed. And he puts his
  690. 22:23signature and the date.
  691. 22:25In this work log, the client can write,
  692. 22:27or the design supervisor, or...well,
  693. 22:30mostly the client.
  694. 22:31>> What the hell?
  695. 22:32>> Yeah. Right. No, here you can write: "
  696. 22:33You did this incorrectly, please clean
  697. 22:35up the trash after yourselves." Yeah.
  698. 22:36And put the date. So there is a column
  699. 22:38for that. There. Or, for example, you
  700. 22:41poured the concrete incorrectly, or
  701. 22:42didn't pour it right. In short, you can
  702. 22:44write down your comments. What is this
  703. 22:46for? This is, this is history. The
  704. 22:48history of the project's construction.
  705. 22:50Later, when, uh,
  706. 22:52>> we open the logbook, when, you know, you
  707. 22:54start saying "you didn't bring us" or "
  708. 22:56you didn't build on time," well, why
  709. 22:57didn't you? Everything is in the logbook
  710. 22:59, dates and everything are clearly
  711. 23:00written down.
  712. 23:01>> Let's all write it down together. It's
  713. 23:03called
  714. 23:04>> a general work log.
  715. 23:06>> General
  716. 23:07>> abbreviated as GWL. It really is the
  717. 23:09history of the project's construction.
  718. 23:11>> Yes, ideally it should be at every
  719. 23:13construction site.
  720. 23:14>> Yes,
  721. 23:15>> it is the history
  722. 23:16>> of your construction. Well, actually,
  723. 23:17yes, it even records things like the air
  724. 23:19temperature. Everything is recorded.
  725. 23:21>> Why the air temperature?
  726. 23:22>> What do you mean why? It started raining
  727. 23:24, efflorescence. Why were you working in
  728. 23:26the rain, just hammering away at the
  729. 23:27masonry? Why?
  730. 23:28>> I need to work faster, and the crew is
  731. 23:30standing around.
  732. 23:31>> There. There. Yes, the crew is standing
  733. 23:32, I rushed to get it done, not covering
  734. 23:34anything, nothing. And then the guy
  735. 23:35comes, and everything is running down
  736. 23:36like this, the mortar has only partially
  737. 23:38set. And, accordingly, all the "
  738. 23:39surprises" that come from that. Oh, yes
  739. 23:41. Oh, there. But here you can
  740. 23:42immediately say, "Guys, you did the
  741. 23:44masonry on this date, but look at that
  742. 23:46date." It was raining
  743. 23:47>> and minus 20, look at that,
  744. 23:50>> right? And minus 20 later. What are you
  745. 23:51doing? Why?
  746. 23:53>> You shouldn't interfere with their work
  747. 23:55process, but they must also understand
  748. 23:57what they are doing. The second log, the
  749. 23:59material incoming inspection log.
  750. 24:01It's very often neglected, but this log
  751. 24:04, well, we even did a video about
  752. 24:07material acceptance, remember? This is a
  753. 24:10very important document. If it's
  754. 24:11supplied material, that is, material
  755. 24:14bought by the client, or if the
  756. 24:16contractor buys it themselves, this log
  757. 24:18notes that the person responsible for
  758. 24:21construction at this specific site
  759. 24:23received the material from the client or
  760. 24:25brought it themselves and wrote that the
  761. 24:28material is good to go,
  762. 24:30>> yeah, yeah, good to go, we'll build on,
  763. 24:32yeah...
  764. 24:33>> well, so either they say, yes, note, the
  765. 24:36material is bad, I won't accept it.
  766. 24:39If they accepted the material, built
  767. 24:41with it, and then said, "Yeah,
  768. 24:42everything was broken and chipped, the
  769. 24:44material is crap, why did you even buy
  770. 24:45it?"
  771. 24:46What's the point, we could have used
  772. 24:47better stuff. "And we should have bought
  773. 24:49that other one instead." He'll say: "My
  774. 24:50friend, look, you accepted it yourself,
  775. 24:52you agreed to work with this material
  776. 24:54yourself." And
  777. 24:56>> did you accept it with no complaints
  778. 24:57about the quality of the material? None
  779. 24:59.
  780. 25:00If the material has a hidden defect, for
  781. 25:02example, some kind of hairline crack or
  782. 25:04something else, that is, it appeared
  783. 25:05later, then that's a claim for the
  784. 25:07material supplier.
  785. 25:09But why did you lay the slab with a
  786. 25:11crack in the first place? Well, that
  787. 25:13happened on a job site too. I arrive,
  788. 25:15and damn, the slab has a crack. Why did
  789. 25:17you lay it? They brought it from the
  790. 25:19factory. I say: "Where does it say that
  791. 25:20they brought you a cracked slab?" It
  792. 25:22doesn't. You accepted it. Accepted it.
  793. 25:24>> You broke it.
  794. 25:25>> It's your slab, you broke it, that's it
  795. 25:26, you broke it, you bought it. Well,
  796. 25:27they repaired it later.
  797. 25:29>> That costs money too,
  798. 25:30>> right? Well, yes, naturally, it also
  799. 25:31costs money. They chased the concrete,
  800. 25:33inserted reinforcement. There.
  801. 25:35So this work, I mean, this is also a
  802. 25:37very important document. Although often
  803. 25:39, even on large construction sites, well
  804. 25:41, it's becoming less common now,
  805. 25:42naturally, because this is a document
  806. 25:44that the State Construction Supervision
  807. 25:46is very strict about. These are the
  808. 25:48first two documents. They look at where
  809. 25:49the incoming inspection log is, that you
  810. 25:50accepted everything, that everything is
  811. 25:52confirmed to be fine, and the general
  812. 25:53work log. So these are two essential
  813. 25:55documents.
  814. 25:55>> In-incoming log, no.
  815. 25:58>> Incoming inspection log. Next comes the
  816. 26:00following document. Certificate of
  817. 26:02concealed works.
  818. 26:04>> Is it one for everything?
  819. 26:05>> No, it's for every single piece of work
  820. 26:07. Let's define what concealed works are
  821. 26:11. Is it like we were working, working,
  822. 26:13and nobody saw it?
  823. 26:14Is it like those virtual contractors: "
  824. 26:16Yeah, we've been working here for 3
  825. 26:17weeks, nobody showed up at the site, but
  826. 26:19this is concealed work because it's
  827. 26:20being prepared or not?"
  828. 26:22>> No, it's a little bit different. For
  829. 26:24example, the simplest thing: we lay
  830. 26:27electrical routes, then they get covered
  831. 26:30by plaster, we tie rebar, then it gets
  832. 26:32covered by concrete.
  833. 26:35So, concealed works are those works that
  834. 26:37are covered by subsequent layers or
  835. 26:39structures and which cannot be checked
  836. 26:41simply by, say, opening a lid and
  837. 26:43looking, "aha, everything is clear."
  838. 26:46Without destroying the structure or the
  839. 26:49finishing layers that lie on top of it.
  840. 26:51So, everything that we cover and cannot
  841. 26:54access is concealed work.
  842. 26:55>> All right.
  843. 26:57But nowadays there are super-technical
  844. 26:59tools, pew-pew lasers, sonars, you know
  845. 27:01, non-destructive testing equipment.
  846. 27:04>> I've already talked about this. 250,000
  847. 27:06rubles. for an inspection.
  848. 27:07>> Oh, it's expensive, so expensive,
  849. 27:08>> be my guest. Yes, so either buy the
  850. 27:10devices yourself individually. Same goes
  851. 27:12for rebar. All those guys running around
  852. 27:14with these fancy little beepers, saying
  853. 27:16everything is identified there,
  854. 27:17everything is wonderful. But for the
  855. 27:19most part, I've worked with many of
  856. 27:21these beepers, these things, both
  857. 27:23expensive and cheap, I've seen it all.
  858. 27:25Yeah. It's all nonsense. They work
  859. 27:27poorly, they work with large margins of
  860. 27:29error. The most accurate method to
  861. 27:30determine what kind of rebar is embedded
  862. 27:32in reinforced concrete is to break open
  863. 27:34the concrete.
  864. 27:36Break off a piece of the reinforced
  865. 27:37concrete, measure the rebar, and then,
  866. 27:39accordingly, start repairing it. This is
  867. 27:41the most reliable way.
  868. 27:42>> It's a frustrating way, because if
  869. 27:43everything is fine, you're like: "Why
  870. 27:45did I even break it?"
  871. 27:46>> We once had a shopping center we were
  872. 27:49building back in the day. The
  873. 27:52contractors finished the work and didn't
  874. 27:54present the hidden work to anyone. We
  875. 27:57said: "Okay, either hire an expert who
  876. 27:59confirms it for you, or open up the
  877. 28:01rebar and show us that everything is
  878. 28:03fine there." They hired an expert, and a
  879. 28:06guy ran around on this slab with a new
  880. 28:09device, beeping something. In short, he
  881. 28:11probably tried to figure something out
  882. 28:12for 3 days; in the end, they opened it
  883. 28:14up, broke it open, and then poured it
  884. 28:15again. But it doesn't get identified
  885. 28:17properly. Rebar is hard to identify
  886. 28:18because there are so many nuances. Metal
  887. 28:20sticking out here, a whole bunch of
  888. 28:22other stuff over there. That's why
  889. 28:23hidden works exist. For this, a
  890. 28:25certificate is drawn up.
  891. 28:26This certificate states what was done,
  892. 28:29what work was performed, and what
  893. 28:31materials were used.
  894. 28:33Well, for example, the rebar, 12mm rebar
  895. 28:36, such-and-such grade, and here is its
  896. 28:38passport. Here we poured it with
  897. 28:40concrete, and here is the passport for
  898. 28:41the concrete. And three people sign it:
  899. 28:43the client, the contractor, and a third
  900. 28:45person. If you have a design supervision
  901. 28:47contract, which I recommend everyone to
  902. 28:49do, there's also the signature of the
  903. 28:50design supervisor, who verifies that the
  904. 28:52client has inspected it. Aha, good, well
  905. 28:54, either they looked at it themselves,
  906. 28:55or hired a construction supervisor.
  907. 28:56>> Is it design supervision or construction
  908. 28:58control?
  909. 28:58>> These are two different people. Design
  910. 29:00supervision and construction control. So
  911. 29:02how
  912. 29:02>> four signatures then?
  913. 29:04>> No, look, if we take, if we take it
  914. 29:06seriously, what signatures should be
  915. 29:08there?
  916. 29:09There is a representative of the client
  917. 29:12for construction control issues. That is
  918. 29:15, the client can hire a person who will
  919. 29:17come. Then
  920. 29:18>> construction control can come.
  921. 29:19>> Well yes, construction control from the
  922. 29:21client. There you go. Then the
  923. 29:22contractor's representative, just the
  924. 29:24contractor's representative. And then
  925. 29:25the customer's representative for
  926. 29:27construction control issues. That is,
  927. 29:29the contractor must also have their own
  928. 29:30construction control. And here is the
  929. 29:32next person, this will be the fourth one
  930. 29:34, yes, this is the author's supervision
  931. 29:36.
  932. 29:36>> Uh-huh. Author's supervision is
  933. 29:38considered optional, well, that is, it's
  934. 29:40up to the customer whether to contract
  935. 29:42it or not. So. But I recommend it to
  936. 29:44everyone, because the author's
  937. 29:45supervisor will come and say: "You did
  938. 29:47this wrong here, and this part is a bit
  939. 29:49off."
  940. 29:50He looks at whether the completed work
  941. 29:53matches the design. And, accordingly,
  942. 29:55did you understand what just happened
  943. 29:57with this document? In this document,
  944. 29:59you can later simply look it up and see
  945. 30:01, aha, the concrete they laid is the
  946. 30:03right one. And the certificate was
  947. 30:05attached to it. So the person is
  948. 30:07confident that they have the right
  949. 30:08materials, here is the reinforcement,
  950. 30:10here is the certificate for it. And so,
  951. 30:12accordingly, everyone signed, everyone
  952. 30:14is involved, everyone saw everything. No
  953. 30:15one will say: "No, I didn't see anything
  954. 30:17. No, no, I don't know anything." Or "
  955. 30:18Yes, the concrete was different, they
  956. 30:20brought bad concrete." You signed the
  957. 30:23incoming control log, yes you did. You
  958. 30:24attached the certificate, yes you did.
  959. 30:26Buddy, you
  960. 30:26>> The concrete is good.
  961. 30:27>> The concrete is good, you just did a bad
  962. 30:29job with it.
  963. 30:30Well, that's what I'm saying, it makes
  964. 30:32all relationships transparent.
  965. 30:34And accordingly, no one is in the dark.
  966. 30:36Everyone came, talked, nodded their
  967. 30:37heads, but it's scary to put a signature
  968. 30:39if you just put a signature, saying that
  969. 30:41everything was fine there.
  970. 30:43But when you arrive and everyone takes a
  971. 30:45look: "Aha, sign that you did a good job
  972. 30:47, sign that you did it. Everything is
  973. 30:48correct." And the person immediately
  974. 30:50thinks: "Well, I'll fix this a bit, yes
  975. 30:52, I agree." Yes, yes, yes, this needs to
  976. 30:53be corrected.
  977. 30:55"Well, the responsibility falls, because
  978. 30:57an as-built survey, well, the full name
  979. 31:00is as-built geodetic scheme in
  980. 31:01construction, but they call it simpler.
  981. 31:04As-built scheme. It is
  982. 31:06>> why is it geodetic?
  983. 31:08>> Well, because according to the strict
  984. 31:10rules, it should be done by a surveyor.
  985. 31:13This is a person who works with
  986. 31:14measuring instruments, tachymeters,
  987. 31:16theodolites, levels, that is, those who
  988. 31:19are directly involved in measurements at
  989. 31:21the construction site.
  990. 31:23For example, a linear network, a sewer
  991. 31:25system is laid, they check all the
  992. 31:26elevations. Whether the building is laid
  993. 31:28out evenly, he sets up a total station,
  994. 31:30a level, or a theodolite, checks the
  995. 31:31angle, everything is fine, everything is
  996. 31:32aligned, the windows are in line.
  997. 31:35That is, this is already his zone of
  998. 31:36responsibility; he takes on the
  999. 31:37responsibility that everything is
  1000. 31:39correct, that he performed all the
  1001. 31:40measurements, everything is good, and he
  1002. 31:42issues an as-built drawing here.
  1003. 31:44There you go. More often it's done—well
  1004. 31:46, on large construction sites, a
  1005. 31:48surveyor is 100%working there. On small
  1006. 31:50sites, like individual housing
  1007. 31:51construction, the site manager himself,
  1008. 31:52accordingly, makes these as-built
  1009. 31:53drawings. They do it as follows. The
  1010. 31:55project is taken, the sheet is pulled
  1011. 31:57out, copied, or simply copied or printed
  1012. 32:00. Nowadays, just PDF it and that's it.
  1013. 32:02So you print the sheet and, in fact,
  1014. 32:04right with a pen, he marks it." Okay,
  1015. 32:07here it didn't turn out to be 2600 for
  1016. 32:10me, but 2550, it shifted by 5 cm, the
  1017. 32:13line veered off, "so he actually marks
  1018. 32:16it as it was installed. Accordingly, he
  1019. 32:19takes this as-built drawing and takes
  1020. 32:21this report." Here, guys, is my passport
  1021. 32:23, here's the second passport, here's the
  1022. 32:26rebar. "" Look here, here is the
  1023. 32:27as-built drawing. "" Everything is
  1024. 32:29correct. "" It's done here exactly the
  1025. 32:30same as on the paper. "Everyone says:"
  1026. 32:32Okay, everything is correct, pour it,
  1027. 32:35fill it, plaster it, close it up. "They
  1028. 32:38folded it, put it away, and it sits
  1029. 32:39there for 2 years.
  1030. 32:41Then you go:" Damn, where was that
  1031. 32:44backup cable of mine here?
  1032. 32:46"There you go.
  1033. 32:48It's taken out of the suitcase and
  1034. 32:50opened." Ah, so, here is this reference
  1035. 32:53point from the window. "" Aha,
  1036. 32:54everything is clear. "There you go. And
  1037. 32:56if you didn't check that there's a
  1038. 32:57crooked reference point here, they wrote
  1039. 32:592600 instead of 550, and you fell for it
  1040. 33:01, well, that means you're the fool
  1041. 33:03yourself.
  1042. 33:04>> But why does it only sit for 2 years? It
  1043. 33:05doesn't sit longer.
  1044. 33:06>> Well, for example, I just said that
  1045. 33:08conditionally, after 2 years,
  1046. 33:09>> maybe 22 years. Well, it won't sit for
  1047. 33:11anyone for 22 years. There you go. It's
  1048. 33:13just that after 2 years you will 100%
  1049. 33:14forget how everything was done, how the
  1050. 33:16pipe was laid, how the sewage system is
  1051. 33:17, where it lies in the ground, at what
  1052. 33:19depth it lies, and where that wiring is
  1053. 33:20, where the wire veered off or something
  1054. 33:22else; somewhere here my wire veered, and
  1055. 33:24here I ran it diagonally.
  1056. 33:25But how? I mean, how can all this be
  1057. 33:27taken? And all this, accordingly, is all
  1058. 33:29recorded on paper. And everyone
  1059. 33:31confirmed this. And the customer,
  1060. 33:32including the customer, confirmed that"
  1061. 33:33Yes, guys, yes, I confirm everything,
  1062. 33:35everything is as it is. "You closed all
  1063. 33:36the documents, reviewed everything,
  1064. 33:38everything looks good. And this is where
  1065. 33:39, my dear construction contractor, you
  1066. 33:41have a better chance of getting paid on
  1067. 33:42time.
  1068. 33:43>> Yes. Well, yes. Accordingly, there is
  1069. 33:44as-built documentation, and the
  1070. 33:45inspection certificates for hidden works
  1071. 33:46are signed. That is, the client, by
  1072. 33:47signing the certificate, says:" That's
  1073. 33:49it, I accept the work. "Or the client’s
  1074. 33:51construction supervisor. That’s it, the
  1075. 33:53work is accepted. Everything is good,
  1076. 33:54guys, go ahead and pour.
  1077. 33:56Later on, you won't get a letter, no one
  1078. 33:57will say:" You did the reinforcement
  1079. 33:59work poorly, here are 500,000 more
  1080. 34:00complaints, "when everything is already
  1081. 34:01poured.
  1082. 34:02He says:" Wait, you accepted it, here is
  1083. 34:04your signature. "You accepted it, you
  1084. 34:05said everything was fine, you were
  1085. 34:07satisfied. What questions could there be
  1086. 34:08now? In short, it's insurance for the
  1087. 34:10builders
  1088. 34:11>> and, yes, for them as well. It is
  1089. 34:13insurance for absolutely everyone. And,
  1090. 34:14accordingly, transparent relationships.
  1091. 34:16If, for example, you want to sell this
  1092. 34:17house to someone later, as you say,
  1093. 34:18through a bank or escrow, here is the
  1094. 34:20set of as-built documentation. Here is
  1095. 34:21everything we've done, here are all the
  1096. 34:22signatures, here are all the passports,
  1097. 34:24and here is what everything is made of.
  1098. 34:25>> Good. We've covered the maximum level,
  1099. 34:28let's say.
  1100. 34:30How should things work when building a
  1101. 34:32private residential house under a small
  1102. 34:35contractor or with those" wild "crews,
  1103. 34:38as you call them?
  1104. 34:40>> Well, maybe not quite" wild, "maybe
  1105. 34:42somewhat semi-civilized ones.
  1106. 34:43>> It's simple here. Uh
  1107. 34:46An incoming quality control log is
  1108. 34:49mandatory. It's just insurance for
  1109. 34:51everyone that you brought the right
  1110. 34:52materials and that no one has any claims
  1111. 34:54against them. That everything is just
  1112. 34:56fine. It costs pennies at any bookstore
  1113. 34:57or stationery shop.
  1114. 34:58You can print it from the internet, just
  1115. 35:00download it there, please, it's all in
  1116. 35:02the free public domain—download, print,
  1117. 35:04and sign.
  1118. 35:06And if you don't need such a super-set
  1119. 35:08of documentation, then you can at least
  1120. 35:10settle for as-built diagrams, at least
  1121. 35:12as-built diagrams. That is, we take them
  1122. 35:14from the project just the same, we print
  1123. 35:16out one sheet.
  1124. 35:18If no engineering network project was
  1125. 35:19developed, we just take the floor plan
  1126. 35:21of our house, print it, and mark the
  1127. 35:23networks on it.
  1128. 35:25If you're doing it yourself, for example
  1129. 35:27, or the foreman is doing it, they mark
  1130. 35:29these networks, draw how they laid them
  1131. 35:31, or you draw it after them; you went in
  1132. 35:34, measured everything, and that's it—
  1133. 35:36this document remains.
  1134. 35:38So, this as-built diagram stays with you
  1135. 35:40, you file it, and everyone signs it. If
  1136. 35:42nobody wants to sign it and everyone
  1137. 35:43refuses. Well, just keep it for yourself
  1138. 35:46, file it away, and that's it. And it
  1139. 35:48lies there just as calmly.
  1140. 35:49>> And won't photo documentation help?
  1141. 35:51>> That’s the most" hick "option. Third.
  1142. 35:54>> Well, it has a right to exist.
  1143. 35:55>> It has a right to exist. But what are
  1144. 35:57the difficulties here? Like you said,
  1145. 35:59the" hick "way—if you're building
  1146. 36:00everything yourself, for example, you
  1147. 36:02did it yourself, you don't want to draw
  1148. 36:04it by hand, right...
  1149. 36:05>> Well, you just put a tape measure there
  1150. 36:06and took a photo.
  1151. 36:07>> You put a tape measure there, or just
  1152. 36:08laid down a piece of a ruler. So, you
  1153. 36:10have an opening, a pipe runs through the
  1154. 36:12opening, you put a metal ruler, a
  1155. 36:13matchbox, any object that can always be
  1156. 36:15measured and looked at. So, that's
  1157. 36:17roughly how it turns out. Put it down,
  1158. 36:19click, took a photo. On the wall,
  1159. 36:21exactly the same. Put a box down, took a
  1160. 36:23photo. Any material, any element that
  1161. 36:25can later be measured to approximately
  1162. 36:27determine the distance from the photo.
  1163. 36:29>> Where are you going to get a standard
  1164. 36:31box? I honestly have no idea.
  1165. 36:32>> A lighter. I don't know what else.
  1166. 36:35>> Well, a lighter isn't standardized. Not
  1167. 36:37>> standardized.
  1168. 36:38>> I think a ruler is still easier.
  1169. 36:40>> And large, really super-large
  1170. 36:41construction sites, right? I mean,
  1171. 36:43besides the certificate for concealed
  1172. 36:44works that we talked about, they also
  1173. 36:46attach photos to them. Certificates,
  1174. 36:48photos, statements of work volumes, what
  1175. 36:50was done, with volumes and everything.
  1176. 36:52And accordingly, there, well, everything
  1177. 36:54is very serious, everything is very cool
  1178. 36:55.
  1179. 36:55>> Okay, let's put it this way.
  1180. 36:57I understand that Kostya lives in an
  1181. 36:59ideal world of pink ponies, and he
  1182. 37:00always really wants everything to be
  1183. 37:02just right.
  1184. 37:03Well, that's his job. In reality,
  1185. 37:05especially when building using the"
  1186. 37:07do-it-yourself "method or with breaks in
  1187. 37:09production cycles, it's very hard to
  1188. 37:10keep track of all this, especially when
  1189. 37:12contractors change or for small jobs.
  1190. 37:15And what is that called? Well, when you
  1191. 37:19hire someone, based on my observation
  1192. 37:21and experience, what we at least
  1193. 37:23recommend to people for construction.
  1194. 37:26First, photo and video documentation of
  1195. 37:28concealed works is mandatory—even for a
  1196. 37:31good foreman, at the end of the day,
  1197. 37:33checking that the rebar is laid properly
  1198. 37:35.
  1199. 37:36Here’s the photo and the video sent off
  1200. 37:39. You came yourself, applied a tape
  1201. 37:41measure, took a photo.
  1202. 37:43It's accessible. This is accessible to
  1203. 37:45everyone. Photo and video documentation
  1204. 37:47. And one more fairly simple method. You
  1205. 37:51probably even have design documentation
  1206. 37:54as such. Maybe we developed it for you,
  1207. 37:56maybe someone else did, maybe you bought
  1208. 37:58a ready-made project somewhere. You can
  1209. 38:00even adjust the settings.
  1210. 38:03They laid out your utilities, like the
  1211. 38:05sewer sleeve.
  1212. 38:06You arrive, tape measure in hand, and
  1213. 38:08say:" Guys, just shift this a little bit
  1214. 38:11to the design mark, that's all. "They
  1215. 38:13say:" Sure, no problem, we've moved it.
  1216. 38:15"And if there are questions, you just
  1217. 38:16mark an arrow indicating the shift to
  1218. 38:18such-and-such. Took a photo, the project
  1219. 38:22>> sewage, even if you just captured a
  1220. 38:25photo on your phone, you already have a
  1221. 38:28record and everything goes to a virtual
  1222. 38:31disk, I mean, a hard drive." Virtual "
  1223. 38:34isn't really the right word anymore.
  1224. 38:35Accordingly, I saved it to the archive.
  1225. 38:37And I certainly understand that an
  1226. 38:40incoming material inspection log is cool
  1227. 38:43, great, and all that, but at least
  1228. 38:46collect the documentation you're given.
  1229. 38:50Materials get delivered to you, get the
  1230. 38:52passports and invoices. At least collect
  1231. 38:55those, don't throw them away. I put
  1232. 38:57everything into one big folder. I hope I
  1233. 38:59never need to pull it up, but if I do, I
  1234. 39:02have it all saved.
  1235. 39:03That’s also a form of, strictly speaking
  1236. 39:06, indirect control.
  1237. 39:09>> Well yes, like you just said about the
  1238. 39:11ideal world, that's one of my most
  1239. 39:13frequent phrases on construction sites.
  1240. 39:16Guys, I'm telling you what’s right and
  1241. 39:18what’s wrong, you decide for yourselves
  1242. 39:20.
  1243. 39:22And, well, strictly speaking, yes, to
  1244. 39:24all those who love to comment that" this
  1245. 39:26isn't how it's done here, "well, go
  1246. 39:28ahead and try it yourself.
  1247. 39:30Yes, guys, the whole idea of" be your
  1248. 39:33own construction supervisor "and these
  1249. 39:35episodes with Kostya is to show that
  1250. 39:37there is a slightly more orderly world
  1251. 39:39out there.
  1252. 39:41Why is there less fighting, fewer
  1253. 39:43building collapses, problems, and wasted
  1254. 39:46money there? Because people actually try
  1255. 39:49not to repeat the mistakes that have
  1256. 39:51been made thousands of times before in
  1257. 39:53construction.
  1258. 39:55All SNiPs, GOSTs, and safety regulations
  1259. 39:57are written in blood and pain.
  1260. 40:00That's how they are formed. In other
  1261. 40:02words, when someone messes up, people
  1262. 40:05decide:" To make sure this doesn't
  1263. 40:07happen again, let's work in hard hats, "
  1264. 40:10or" let's not grab a bare wire with our
  1265. 40:13hands without checking if it's live. "
  1266. 40:16>> But hard hats, honestly, that's just a
  1267. 40:18huge pain. Because today I issued an
  1268. 40:20order because people on the site are
  1269. 40:21walking around without hard hats again,
  1270. 40:23and there are no protective barriers in
  1271. 40:25dangerous zones.
  1272. 40:26>> So, all these standards really, in the
  1273. 40:29first place, protect not just the
  1274. 40:31contractor, the client, or the worker,
  1275. 40:34they actually protect everyone.
  1276. 40:37And yes, we're sharing this so you can
  1277. 40:40at least understand which direction to
  1278. 40:42look.
  1279. 40:43And with that, my dear friend, you’ve
  1280. 40:45already been given a hint. We tell you
  1281. 40:47how it should be done, and you'll do it
  1282. 40:49wrong on your own anyway. Gentlemen,
  1283. 40:51hugs. Ladies, love you, kisses. See you
  1284. 40:54next time. Bye.

About this transcript

This page contains the full transcript of Как строители хоронят ваши миллионы: скрытые работы и схемы by BDD GROUP, generated from the public captions YouTube serves with the video. The transcript has 7,757 words across 1,284 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.