- 0:03The logical framework, also known as the logical framework methodology, is a project management tool
- 0:08used in the design, planning, execution, and evaluation of projects, in this video
- 0:13we are going to explain what it is for and how to do your logical framework project. in 10
- 0:18steps the methodology was developed in 1969 by the usaid that the united states agency for
- 0:25international development in response to an analysis of the results of previous projects
- 0:29where it was concluded that there were deficiencies and that it was necessary to create a tool
- 0:33to improve the results of future projects subsequently organizations and entities such as the
- 0:38Inter - American development Bank 20 the German cooperation agency for development etc
- 0:43is and many South American governments Caribbean adopted the logical framework approach many of
- 0:48these adaptations trained variations in methodology and soft methodology created
- 0:52by the gts this indicates that the hollow frame used over Everything in development projects at
- 0:57the state or government level, however, some private organizations and educational institutions
- 1:02have started the methodology so but what is the logical framework with the logical framework methodology
- 1:07achieves is to conceptualize, plan, execute and control a project with an objective-
- 1:13based approach communication between stakeholders and orientation towards beneficiaries, but what
- 1:19then has been the difference between the logical framework matrix and the logical framework methodology
- 1:22is simple, the result, the methodology is the matrix, that is, the methodology is composed of a
- 1:29series of steps such as analysis. of the problem, the analytical structure, the
- 1:33narrative summary, as we follow the steps, we manage to complete the
- 1:38logical framework matrix, but then for the matrix, the matrix is a summary of the project, it explains what is
- 1:44intended with the project and how it is to be done along with the assumptions you face and the way
- 1:48to monitor and eva This is vital when, for example, you want to present the essence of the project to
- 1:54a potential investor, some follow the logical framework approach in seven steps, others do it
- 1:59in 15, we are going to do it in 10 steps and the result will be the matrix, fill out
- 2:05the combo completely. Each step will be deepened in different videos, that is, for each step there we take
- 2:11back the activities and tasks for that step of the methodology if in the example of a logical framework
- 2:16we could have approached it with a social development project as is commonly done with
- 2:20educational institutions This time we will do it with a private company because I believe
- 2:26that for a methodology of this complexity and for it to have its first approach with
- 2:29it, handling a case study where it is not necessary to have knowledge of the issues that address a
- 2:34social problem facilitates understanding, so I think this example will help you to
- 2:39get a solid foundation in the methodology and of course it is necessary. or go a little
- 2:44deeper, so it will be necessary for you to review the posts of ingenuity company step number one of
- 2:50the logical framework methodology is the analysis of those involved in this step we identify
- 2:54the groups of actors that are affected by the project either directly or indirectly Not
- 3:00only do we define who they are, we also think about their interests, expectations and needs to
- 3:04define intervention strategies that allow us to have their support or to propose actions
- 3:09against their opposition. Step number 2 is the problem tree, it is important to make ourselves aware
- 3:15that we are starting from a problematic situation. or of a certain need but has not yet
- 3:20been characterized, it may be that much of what was mentioned before is caused by a root problem
- 3:25or what seems to be a problem is actually a consequence of another larger cause
- 3:29to have clarity of the problem situation we will use then the tree of problems with this
- 3:34tool we will be able to represent the situation pro problem locating in its causes in the roots
- 3:39the central conflict in the trunk and the effects in the leaves of the tree step number 3 is the
- 3:46tree of objectives in the also known tree of solutions the causes become means
- 3:51and the leaves become ends we go from a current negative state to a desired positive state
- 3:57which means that the central problem of the project changes towards the central purpose
- 4:04the fourth step is the analysis of alternatives in this step we stop dreaming and we take
- 4:09action how we are going to achieve change the situation and density in the problem tree towards what we
- 4:14want in the objectives tree we do it in this step we identify the alternatives
- 4:19or set of means that can mean strategies to solve the problem situation
- 4:24what we do is take the means of the Objectives tree and define actions that
- 4:29allow me to reach that medium, later we define and apply the criteria that we believe are
- 4:34pertinent according to Join the nature of the problem for example cost versus benefit or social
- 4:39impact this to filter and leave only those optimal alternatives with which we are going to work
- 4:44in the following steps step number 5 in the analytical structure of the project in this step
- 4:49we take the work of the tree of problems and objectives together with the analysis of alternatives
- 4:53to outline the relationship of the optimal strategy or alternative with the objectives and actions
- 5:00in the analytical structure of the project begins to build the relationship of hierarchical levels
- 5:04that is org in the logical framework matrix the organization of the levels in the matrix is
- 5:09like this the first level we take the activities in the second level we have the components third level
- 5:15is the purpose and the fourth level is the end the sixth step is the narrative summary this is where
- 5:22we begin to create the logical framework matrix The narrative summary is the first column of the 6th
- 5:27step, it is more than the ordering of the levels of the analytical structure. a of projects on the
- 5:32logical framework matrix in other words, each level of the structure is a row of the logical
- 5:37framework matrix end purpose components and activities are the rows of the logical framework matrix the
- 5:43end is a medium-term impact represents the contribution that is achieved to have the project
- 5:47completed and can be composed of one or more elements the purpose is the central objective of the
- 5:53project and there should only be one the project is completed once the purpose is achieved
- 5:58and it is achieved when we have the Completed components The components or products are the
- 6:03deliverables call the service or tangible products of the project only the result of
- 6:09having the activities carried out lastly the activities are the necessary to
- 6:14deliver the components of the project with the seventh step are the objectively verifiable
- 6:19indicators in the second column of the logical framework matrix we define the way to know
- 6:25the progress of the project b Regardless of the current or final progress, we create indicators to measure
- 6:30everything that is in the narrative summary and why this step is important, we can
- 6:35summarize it in two reasons, all the stakeholders of the project of interest to know about them
- 6:40must be independent and focused practical and must There are indicators to determine to what
- 6:46extent the objectives are achieved but also to monitor the progress in the project
- 6:53times.The eighth step is the means of verification to know the status of the project.It is not enough to define
- 6:59the indicators where how we are going to obtain the data and information to measure the
- 7:05response is part of the third column of the logical framework matrix with the sources the means
- 7:10of verification we evaluate and monitor the indicators defining the following aspects
- 7:14source of information recovery method responsible for collection analysis method
- 7:20and frequency step 9 are the assumptions the assumptions are all those conditions ions or
- 7:27factors that we consider to be true but that are not controllable by the project team and that in the
- 7:32event that they are not fulfilled affect the results that can go wrong everything that could lead to
- 7:38an assumption not being fulfilled considered a risk therefore both in this step we try to ensure that the assumptions
- 7:43are fulfilled so we identify everything that can go wrong before starting an item of the
- 7:48project or during its execution with interest we refer to an element of the narrative summary
- 7:53that is to say, purpose, components and activities finally step number 10 is the monitoring and
- 8:00evaluation of the project sometimes not everything goes as planned good curricula projects
- 8:05may have unforeseen or delays or that things are not being done as they should be done for
- 8:10this reason it is necessary to monitor and evaluate when doing it We seek to reduce the difference between what is
- 8:15real and what is planned, but what is the difference between monitoring and evaluation with monitoring we
- 8:21control The progress of the project and we do it only in the execution phase, aspects such as
- 8:26costs, physical progress and compliance with the times are subject to verification.We
- 8:30must also inform those involved about the results of the monitoring and take the
- 8:35pertinent actions to ensure continuity and success. of the project, therefore in the monitoring
- 8:40of we identify to what extent the activities are carried out on time and at the lowest cost, that is,
- 8:46project efficiency and the components are being produced and if the purpose is achieved, that
- 8:51is, effectiveness of the project to take corrective actions the path of the project
- 8:56that with respect to follow-up monitoring but which has been evaluating the evaluation
- 9:01of the project means putting a point d and thinking the project is working this simple question
- 9:07must be answered considering a vision of the project as a whole and not as something specific
- 9:12to what specific is the monitoring the change in the valuation we make a ref lection of what has been done
- 9:17so far and the results obtained which leads us to obtain high-level conclusions in
- 9:22addition to all this, it is necessary that you understand two very important concepts of which we have
- 9:28spoken without mentioning its real concept the vertical logic that is a sample of the validity of
- 9:34the project design with this we manage to analyze the causal links that exist between each
- 9:39of the levels of the objective column in it we consider that the project
- 9:43planning design is valid when the components are the result of having the activities done
- 9:48and Each activity is necessary to obtain the components, no activities are necessary and there
- 9:54are no others, on the other hand, when the components are obtained, the achievement of the project is
- 9:59achieved and the achievement of the project has been achieved, there is a contribution to the achievement of the end if your project
- 10:04meets these conditions. project is endowed with coherence and congruence next step
- 10:11would be the logical hor izontal, which is the concept that we must understand, is a concept
- 10:16that we have already explained in the previous steps, but without mentioning its real name, the
- 10:20indicator objectives and means of verification, so in that order they are called horizontal logic,
- 10:26why because the means of verification They must be sufficient to achieve the calculation of
- 10:31the indicators and the calculation of the indicators shows the current and final progress in achieving
- 10:36the aforementioned final objectives the steps and concepts this is the case study that
- 10:42I propose for the development of the methodology Logical framework with usain is a company that provides
- 10:47web hosting services for some time now it has been presenting a greater number of
- 10:52complaints and claims from its clients this situation has impacted on the finances of the
- 10:57company and threatens to further reduce its base Furthermore, the company has been left with an
- 11:02obsolete technological infrastructure while its competitors, who are not a few h They have modernized
- 11:07their services or are doing, in other words, columns, they have realized that they are not
- 11:13following market trends and that is having an impact on the service
- 11:17and as if that were not enough, the company has been presenting massive resignations of its employees
- 11:22with this Of course, I propose to treat this problematic situation with a project under the methodology
About this transcript
This page contains the full transcript of Desarrollo de un PROYECTO con la metodología de MARCO LÓGICO en 10 pasos by Ingenio Empresa, generated from the public captions YouTube serves with the video. The transcript has 2,098 words across 131 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.
What you can do with it
Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.
Free YouTube transcript tool
YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, caption language selection, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.