  1. 0:03Listen, you were watching, where were
  2. 0:05you even looking?
  3. 0:06The human factor is the most important
  4. 0:08thing.
  5. 0:09Why don't we go with something cheaper?
  6. 0:11Is he getting square footage or is he
  7. 0:13getting a peaceful life?
  8. 0:1590%is work organization, as well as
  9. 0:18technical client functions.
  10. 0:26Let's move to the block where we have
  11. 0:28the client. And we have construction of
  12. 0:33the site, meaning it moves to the site
  13. 0:35manager, to this part, and the site
  14. 0:37manager directly oversees everyone
  15. 0:39under him during the house construction
  16. 0:40. So, you need to tell us what a site
  17. 0:46manager's functions are, what you
  18. 0:48perform, what you cover.
  19. 0:50In my 9 years of work experience, I
  20. 0:53went from foreman to chief engineer.
  21. 0:56And at every stage of my profession,
  22. 0:58there were always different functions,
  23. 1:00but someone was always missing. When I
  24. 1:02was a site superintendent, there was a
  25. 1:05foreman or there wasn't, a chief
  26. 1:06engineer, or there wasn't a site
  27. 1:08superintendent and so on. So, my
  28. 1:10functions shifted a little bit into
  29. 1:12each other. I no longer see a clear
  30. 1:15boundary. Now I will tell you how the
  31. 1:17structure works specifically for you.
  32. 1:20Is that good or bad? I'll say that
  33. 1:25given my extensive experience, it comes
  34. 1:27easily to me here, but in reality, if I
  35. 1:29were a novice site manager, I probably
  36. 1:31wouldn't have managed.
  37. 1:33Because right now, for you, a site
  38. 1:35manager is everything.
  39. 1:37Yes.
  40. 1:38He's technical supervision, he's a
  41. 1:40foreman, he's a procurer, he handles
  42. 1:43logistics, and also technical
  43. 1:44documentation.
  44. 1:46Yes, how I combined everything into one
  45. 1:49.
  46. 1:49Yes, a site manager, yes. Professional
  47. 1:52report.
  48. 1:56The first main task is organizing the
  49. 1:58workflow.
  50. 1:59Uh-huh.
  51. 2:00That is, I receive and study the design
  52. 2:02working documentation and bring it to
  53. 2:05the crew.
  54. 2:07The site manager develops and
  55. 2:09coordinates the action plan and the
  56. 2:10work schedule. To ensure there's no
  57. 2:15downtime, let's say, so he always
  58. 2:17monitors this schedule and corrects it
  59. 2:19in time. Next, he works with the
  60. 2:24surveyor on the layout of the
  61. 2:26structures and ensures the supply of
  62. 2:28materials to the site, and accordingly
  63. 2:30organizes the construction site. That's
  64. 2:35it, work begins. The second main task
  65. 2:38is his control. Quality control of the
  66. 2:41work performed. This includes checking
  67. 2:44hidden work, like reinforcement, rebar
  68. 2:47diameter, the mesh, these are physical
  69. 2:49parameters, everything must comply with
  70. 2:52the design. There are moments when
  71. 2:55there is a discrepancy between what is
  72. 2:57on paper and what is on site. For this,
  73. 2:59the site manager must promptly work
  74. 3:01with the designers, make changes,
  75. 3:03provide a solution, and so that the
  76. 3:05work doesn't stop, you need to see
  77. 3:07everything in advance. So, the crew are
  78. 3:11the hands that perform the work, and
  79. 3:13the site manager is the person who
  80. 3:15manages these hands and organizes this
  81. 3:17work.
  82. 3:20He effectively acts as a liaison
  83. 3:22between the manager, which is himself,
  84. 3:24the technical customer, the designers,
  85. 3:27and the crew itself. He is accountable
  86. 3:30to everyone.
  87. 3:31The third function, his main task, is
  88. 3:33the handover of the project. This
  89. 3:35involves submitting the completed work
  90. 3:37to the technical supervisor and
  91. 3:38preparing all the as-built
  92. 3:40documentation, such as passports, test
  93. 3:41reports, certificates, and diagrams he
  94. 3:43prepared in advance with the engineer.
  95. 3:45Why do you think the crew's cost is
  96. 3:47lower while yours is higher? I mean, it
  97. 3:50increases automatically, doesn't it?
  98. 3:53I still believe it comes down to
  99. 3:55responsibility, especially if he is
  100. 3:57representing an organization. If I were
  101. 4:01to look ahead, I would choose a company
  102. 4:03. A company that has its own cameras.
  103. 4:06What client pain points does a site
  104. 4:08manager address? I mean, what exactly
  105. 4:11do you handle? Do clients even have any
  106. 4:13pain points?
  107. 4:15Of course, I save them from having to
  108. 4:17be on-site every day to supervise. I
  109. 4:20take those functions upon myself.
  110. 4:23Do you think a site manager for the
  111. 4:24building envelope and one for interior
  112. 4:26finishing should be different? Can it
  113. 4:28be the same person, or do they lack the
  114. 4:30necessary expertise?
  115. 4:31Well, if they have the experience, then
  116. 4:34yes. If the building category isn't a
  117. 4:38frame house or something simple, with a
  118. 4:40budget of 12 to 15 million, I think it
  119. 4:42can be managed. But if the house costs
  120. 4:4725 million or more, it’s better to
  121. 4:49separate them, right?
  122. 4:52Well, that’s just like general
  123. 4:54handymen. When everyone specializes in
  124. 4:56their own area, that’s the best
  125. 4:58option. Did I understand correctly that
  126. 5:02a general construction manager and an
  127. 5:04interior finishing manager are two
  128. 5:06different people because the expertise
  129. 5:08for the exterior envelope is specific,
  130. 5:09while the interior is completely
  131. 5:11different? And there are thousands of
  132. 5:15nuances involved there.
  133. 5:17A general construction manager is
  134. 5:19called that precisely because they
  135. 5:21oversee everything from start to finish
  136. 5:23, from the foundation to the handover.
  137. 5:28Their job isn't necessarily to know
  138. 5:30everything to absolute perfection.
  139. 5:33Everything. Their job is to control the
  140. 5:36processes.
  141. 5:39These are the ideal conditions where,
  142. 5:40as Alexander said, you have an elite
  143. 5:42team, and you need to have all those
  144. 5:44specialized crews on hand. But when we
  145. 5:49look at the reality, when we start a
  146. 5:51project, the client usually wants to
  147. 5:52save money. So they bring in crews that
  148. 5:57might be cheaper. And accordingly, in
  149. 6:01that case, the manager has to get
  150. 6:02hands-on and know every nuance and
  151. 6:04detail, because what else can they do
  152. 6:06when the claims start coming in?
  153. 6:09Wait, we are talking about houses
  154. 6:11around 200 square meters, right? I mean
  155. 6:13, good, high-quality houses, really
  156. 6:15good quality ones.
  157. 6:17What kind of cost savings are we
  158. 6:18talking about here? About 90%savings on
  159. 6:22the projects we worked on. I mean,
  160. 6:25every foreman, oh, every client wants
  161. 6:28to save money when building a 200 m²
  162. 6:30house. Even though he knows he’ll
  163. 6:35sell it for millions, he really wants
  164. 6:37to save and squeezes the crews and
  165. 6:38everyone else to the max. That's all.
  166. 6:43Because he understands he has 10 rubles
  167. 6:45today. And tomorrow he wants to sell it
  168. 6:47for 20. But he needs to save at this
  169. 6:49very stage, and that's it. And so, in
  170. 6:54my worldview, I understand that a
  171. 6:56structural foreman is for general
  172. 6:57construction, while a finishing foreman
  173. 6:59is a completely different skill set and
  174. 7:01a completely different person. No
  175. 7:05matter how many people I’ve seen or
  176. 7:07noticed, sure, ask Alexey if he can
  177. 7:09build monolithic houses exactly as well
  178. 7:12as I can. No, but ask Alexey if he can
  179. 7:14do the finishing perfectly. Yes, he can
  180. 7:17. 100%.
  181. 7:21So, we should better explain why it’s
  182. 7:22better for the client to separate these
  183. 7:24things and why it’s better to turn to
  184. 7:26one group for general construction and
  185. 7:28another for interior finishing. Or if
  186. 7:32it’s a company, then maybe go with a
  187. 7:34company. I’ll split this function
  188. 7:40again: a structural foreman is a person
  189. 7:42who needs a qualified foreman or master
  190. 7:44beneath him to perform their function
  191. 7:46perfectly.
  192. 7:50Well, let’s put it this way. I worked
  193. 7:52as a technical supervisor. There were
  194. 7:54four of us technical supervisors for
  195. 7:55one project. Four technical supervisors
  196. 7:58for one project. And each of us
  197. 7:59performed our own function. There was
  198. 8:01general construction. That’s
  199. 8:03foundations and everything related to
  200. 8:05concrete and walls. There was a
  201. 8:07technologist. All pipelines, gas, water
  202. 8:10, steam, and everything else. And then
  203. 8:14there was an electrical technical
  204. 8:16supervisor who covered all the
  205. 8:17electricity. And there was also an
  206. 8:20instrumentation and control specialist,
  207. 8:22so four supervisors for one building,
  208. 8:24you see? And that’s how it works; if
  209. 8:27we take the structure, here we have "
  210. 8:29divide and conquer." We separated the
  211. 8:32tasks and got a good result. So
  212. 8:35we are talking now about hiring a
  213. 8:37company to build a house.
  214. 8:40We are talking now about a foreman with
  215. 8:42a crew. We are not talking about a
  216. 8:44company right now. We are talking about
  217. 8:46the fact that if a client approaches a
  218. 8:50foreman with a crew.
  219. 8:52Foremen are different. Most likely, the
  220. 8:56foreman they find without a company
  221. 8:57will simply act as a crew leader. He
  222. 9:01will just supervise the execution of
  223. 9:03work and that’s it. And all other
  224. 9:07tasks, like supply chain management and
  225. 9:09documentation compliance or adjustments
  226. 9:11, will fall on the client.
  227. 9:14So, it doesn't rise to that level here,
  228. 9:17right? Meaning the foreman won't get
  229. 9:19involved in the projects, won't think
  230. 9:21about how to save the client money or
  231. 9:23what the best technology is. We’ve
  232. 9:26never actually worked with a company,
  233. 9:28because, as you say, the client is
  234. 9:29always trying to save money. They see
  235. 9:32that we’re taking on certain
  236. 9:33functions, so a company here—well,
  237. 9:36back in the day, let's say—a company
  238. 9:38wasn't needed by the client here. And
  239. 9:44so, we often resort to either hiring a
  240. 9:46foreman with his own crews, or I’ve
  241. 9:48had the experience of just hiring
  242. 9:50people at the bottom of the market rate
  243. 9:52, because the client—well, it wasn't
  244. 9:54lawful back when we were building the
  245. 9:56first site. That is, of course, an
  246. 10:01incredible headache in every way. Next,
  247. 10:04we’ll take the foreman, the foreman,
  248. 10:05the foreman for the Roseni, as was
  249. 10:07already mentioned here. What you just
  250. 10:09said, Alexander, those are the
  251. 10:11requirements the company has for you,
  252. 10:13and you’re ready to fulfill them. But
  253. 10:15how do you distinguish a foreman you
  254. 10:17picked up on the market—just some guy
  255. 10:19who, for example, built a house for
  256. 10:21someone I know—when he arrives,
  257. 10:23construction starts, he brings you a
  258. 10:25crew, and that’s where the split
  259. 10:27between a "normal" and "not normal"
  260. 10:29foreman begins. A normal person, and I
  261. 10:31know guys like this, takes a project,
  262. 10:33analyzes it first, approaches it
  263. 10:34scrupulously, and says: "Guys, there
  264. 10:36are these specific nuances, this part
  265. 10:38is unfeasible, and for this, let's look
  266. 10:40here, let's tweak that, and so on."
  267. 10:42That’s the first type of person. He
  268. 10:44can also take on all the procurement.
  269. 10:47Of course, we understand that
  270. 10:48procurement costs a certain amount on
  271. 10:50his end. He earns money on that, but
  272. 10:53it's also a great function that the
  273. 10:55client shouldn't have to take on at all
  274. 10:57. Right. And the second side is when
  275. 11:00the foreman isn't really a foreman but
  276. 11:02a middleman; he has several different
  277. 11:04crews he’s already worked with. He
  278. 11:06knows who to put on this site, who on
  279. 11:08that one, and who on the other. He sets
  280. 11:10up the crew. His task is to draw up an
  281. 11:13estimate and push it to the client. The
  282. 11:16crew arrives at the site and
  283. 11:18construction begins. It’s important
  284. 11:22to talk about how much the foreman
  285. 11:24controls, and how information is passed
  286. 11:26from the client directly to the crew,
  287. 11:28right? It should only happen through
  288. 11:31the foreman. But it often happens that
  289. 11:34when the foreman arrives at the site
  290. 11:35with a crew and the crew starts working
  291. 11:37, you already see mistakes. Well, for
  292. 11:40instance, as professionals in this
  293. 11:42field, we see the mistakes, we stop
  294. 11:44them. This, this, and this. You can’t
  295. 11:47do it like that. The foreman looks at
  296. 11:49the situation and says, "Oh, well, it's
  297. 11:51being controlled here, so I’m not
  298. 11:53needed." And that’s when the guy
  299. 11:57starts getting pushed off the project,
  300. 11:59when the client controls the crew. The
  301. 12:02client will then hold the foreman
  302. 12:03accountable, and the foreman will say,
  303. 12:05"Look, you were watching, where were
  304. 12:07you looking?" This shifting of blame,
  305. 12:08I’m just saying that this is exactly
  306. 12:10what shouldn't be called a foreman.
  307. 12:13This is a middleman with a crew who
  308. 12:15makes his margin but does absolutely
  309. 12:17nothing on-site, and you can’t get
  310. 12:19anything out of him.
  311. 12:21Ouch,
  312. 12:22you won't be able to hold him
  313. 12:23accountable for anything later. It will
  314. 12:25be a guaranteed conflict, you’ll try
  315. 12:27to confront him, but what will he say:
  316. 12:29"What about me? You were watching,
  317. 12:30weren't you? You seem like a
  318. 12:32knowledgeable person, right?" That’s
  319. 12:34it. So, this is exactly the bottom of
  320. 12:36the topic we’re discussing, the
  321. 12:38bottom of this foreman-with-a-crew
  322. 12:40setup. And there are truly competent
  323. 12:43foremen who essentially replace a
  324. 12:45construction company for you, who
  325. 12:47manage the project precisely and
  326. 12:48scrupulously, but there are only a few
  327. 12:50of them, and they are always referred
  328. 12:52by word of mouth. Right. And here it is
  329. 12:57important to discuss what the client
  330. 12:59wants to save a little on in the market
  331. 13:01, how it differs from a company, and
  332. 13:03how much higher their price is compared
  333. 13:05to a company's. This is the main market
  334. 13:10competition between a great foreman
  335. 13:12with well-established crews who manages
  336. 13:15a project clearly, and companies which,
  337. 13:17as clients think, have bloated staff,
  338. 13:19maybe no responsibility, a $ 10,000
  339. 13:22charter capital, and so on. So, this
  340. 13:25I will answer your question right now.
  341. 13:28How did I do it? You take this
  342. 13:30artificial intelligence,
  343. 13:31Uh-huh.
  344. 13:32You log your functions into it for two
  345. 13:34months, what you do. And every day you
  346. 13:36come and say that I did this, this,
  347. 13:38this, and this. And at the end of two
  348. 13:43months, you get the result of that
  349. 13:44analysis. And based on that analysis,
  350. 13:48unfortunately, or fortunately, 90%, for
  351. 13:51example, for me, is organizing the work
  352. 13:53. And also, these are the functions of
  353. 13:55a technical supervisor. That is what we
  354. 13:57are arriving at. So we are saying now
  355. 13:59that in this structure, we need another
  356. 14:01person, either a technical supervisor,
  357. 14:03like Yevgeny mentioned. If a foreman is
  358. 14:08willing to take on the role of a
  359. 14:09technical client and organize
  360. 14:11subcontractors, then yes, then it would
  361. 14:13be possible to compete with a company,
  362. 14:15provided he assumes those
  363. 14:16responsibilities. But if that person is
  364. 14:21willing to do it all for a minimum cost
  365. 14:23, when in fact 15%should be allocated
  366. 14:25for technical oversight, that’s an
  367. 14:27issue.
  368. 14:28Look, those are two different sides,
  369. 14:30right? The technical client is on the
  370. 14:32client's side, while the foreman is on
  371. 14:34the contractor's side. Those are two.
  372. 14:35Well, you need to understand who is
  373. 14:37working for what, right, and whose
  374. 14:38interests they are actually looking out
  375. 14:39for here. Right. And if the technical
  376. 14:41client acts on behalf of the client and
  377. 14:43puts pressure on the contractor, then
  378. 14:45the contractor will say he’s taken on
  379. 14:47those functions. He’ll claim he’s
  380. 14:50taken them on, but he will be defending
  381. 14:51his own position. If a client wants to
  382. 14:55get the highest quality and find
  383. 14:57nuances they can't get out of the
  384. 14:58foreman, the foreman will just push
  385. 15:00back against them. That is
  386. 15:04everywhere we talk about the fact that
  387. 15:05the human factor is the most important
  388. 15:07thing. And here you have to realize
  389. 15:11that there are foremen who understand
  390. 15:13that they want to work every single day
  391. 15:14. If they do a good job for the client,
  392. 15:19they will be referred to others. So, if
  393. 15:23I walk onto a site and see that my
  394. 15:24project has retaining walls with
  395. 15:26three-meter wide footings, and I
  396. 15:28realize that physically this isn't
  397. 15:29necessary because the project came from
  398. 15:31who knows where and it's completely
  399. 15:33useless, then I will tell the client
  400. 15:35about it. And I will say it because I
  401. 15:39am acting on the client's side here,
  402. 15:40because I know that tomorrow they will
  403. 15:42refer me to one more person and then
  404. 15:43another. And in this case, my family
  405. 15:46will always be fed, because I will
  406. 15:48always have work, and I will fulfill my
  407. 15:50functions and complete my task. And
  408. 15:53that's it. But now we have returned,
  409. 15:56perhaps, to the point where we need to
  410. 15:58ask: how do you distinguish a
  411. 15:59high-quality foreman from a low-quality
  412. 16:01one? Well, we usually torture them. And
  413. 16:08there are different methods of torture.
  414. 16:10What’s the first torture?
  415. 16:13The first torture is that we show other
  416. 16:14foremen how we are torturing one of
  417. 16:16them. 98 percent leave immediately.
  418. 16:21Well, understanding that the same thing
  419. 16:23is about to happen to them.
  420. 16:24Well, at least by a checklist and by
  421. 16:26the spine, yes. We run through all of
  422. 16:28that there. If we're being serious, I
  423. 16:32don't check foremen anymore; I have a
  424. 16:34technical director who handles that
  425. 16:36issue.
  426. 16:37Uh-huh.
  427. 16:39We’ll just delve deeper now and move
  428. 16:41on to the company structure, who is
  429. 16:43responsible for what, and what my role
  430. 16:45is there now.
  431. 16:46and what I actually know and what I
  432. 16:48don't know.
  433. 16:48Uh-huh.
  434. 16:49That's why what I started with just now
  435. 16:51before, when you were checking foremen,
  436. 16:52was there anything?
  437. 16:54Well, I checked via photos. Like, on a
  438. 16:57Nokia, you know, I’d look at what
  439. 16:59work had been done. Yeah. And only in
  440. 17:01practice, only in practice. Like, right
  441. 17:03away, I’d just start them. And it's
  442. 17:06also important, by the way, if a
  443. 17:08foreman from a crew came to me, I’d
  444. 17:10look at their gear, what they were
  445. 17:12wearing, what tools they had or didn't
  446. 17:14have, what they arrived in—that’s
  447. 17:16the primary thing I could see. And
  448. 17:19there is this illusion. A foreman
  449. 17:22arrives. Let's say in a Land Cruiser
  450. 17:26200, right? Oh, basically, a
  451. 17:29double-edged situation can arise for
  452. 17:32the client, right,
  453. 17:33the client.
  454. 17:34Like, it's expensive—since he drives
  455. 17:36such a car, he must be charging a ton.
  456. 17:40But you could reason differently, that
  457. 17:42he, um, well, he takes care of his car.
  458. 17:47The car is clean, yes, it's expensive,
  459. 17:49and he knows his own worth and the
  460. 17:51worth of his work, and that's the other
  461. 17:54side of the coin, actually.
  462. 17:57He has a lot of work.
  463. 17:58And he has a lot of work, that's true.
  464. 18:01The reason I’m telling you this is
  465. 18:03that I’ve been in that situation
  466. 18:05myself, when I arrived there in...oh, I
  467. 18:07see.
  468. 18:08And you have an Infiniti,
  469. 18:11I see.
  470. 18:122.5 liters, right? Well, not started
  471. 18:16yet.
  472. 18:17Let's add, Evgeny, um, you need to look
  473. 18:20at it in at least two layers. The
  474. 18:23technical layer and the ethical layer.
  475. 18:27Technically, we can check him somehow,
  476. 18:29right: by talking to him, asking him
  477. 18:31some professional questions, bringing
  478. 18:33him to the site for that first week, or
  479. 18:35at least, I don't know, giving him some
  480. 18:37project so he can explain if he
  481. 18:39understands anything at all or not. Uh,
  482. 18:42give him a situation that actually
  483. 18:44happened on your site, how he would
  484. 18:46solve it, and so on. So, just listen,
  485. 18:48in principle, to that story. The
  486. 18:50ethical layer. Well, you know, like, in
  487. 18:53any case, someone is interviewing this
  488. 18:56person there. And the client themselves
  489. 18:58is also the one who is interviewing.
  490. 19:00They look the person in the eye, at the
  491. 19:02very least. You know, well, your eyes
  492. 19:04will never deceive you. If you really
  493. 19:08want to understand who is standing in
  494. 19:09front of you, you know it from the
  495. 19:11first minute. The price he quotes might
  496. 19:16just outweigh all these stories, making
  497. 19:18you think: "What if it doesn't?" Maybe
  498. 19:21let's go for something cheaper. "And,
  499. 19:23well, this is an important point. And
  500. 19:25ethically, it will be tested further
  501. 19:27down the line in the work,,well, later
  502. 19:29on. And here I would suggest setting
  503. 19:31checkpoints as soon as possible. That
  504. 19:33is, as soon as we reach a certain
  505. 19:35checkpoint, that first clash of
  506. 19:37interests occurs, and we see how he
  507. 19:39delivers that work, how responsibly he
  508. 19:41acts, whether he is on the client's
  509. 19:43side, or if he is just covering himself
  510. 19:45as much as possible, just trying to get
  511. 19:47it done quickly:" Give me the money,
  512. 19:49sign the acts, and we're off. "That's
  513. 19:51it. So, this is the only way to check
  514. 19:53it.
  515. 19:54I mean, until you start, you can't
  516. 19:56verify it.
  517. 19:56You're unlikely to check the ethical
  518. 19:58side otherwise. Again, I’ll say,
  519. 20:00there has to be a certain level of
  520. 20:02discernment. The technical supervisor
  521. 20:04should also take this upon themselves.
  522. 20:06The technical supervisor’s role
  523. 20:08involves a high level of discernment
  524. 20:11regarding foremen, team leaders, other
  525. 20:13people, suppliers, and so on. And they
  526. 20:15can spot a lie from a mile away. So,
  527. 20:18this will save the end client, who is
  528. 20:20paying the money, from these problems.
  529. 20:23May I, as the client, draw my own
  530. 20:25conclusions after all your discussions?
  531. 20:28Look, here is what I want to see first
  532. 20:30and foremost as a client. Think of it
  533. 20:34like a simple analogy, like buying a
  534. 20:36car. I need to see a concrete base, for
  535. 20:42instance, the cost of work by stages,
  536. 20:44that is the base for the client. And
  537. 20:49second, almost mandatory, is the cost
  538. 20:51of materials by stages. And then the
  539. 20:55extras, because trying to cram
  540. 20:57everything into 100 rubles, as you
  541. 20:59initially discussed for the total cost,
  542. 21:01well, that's just competing with
  543. 21:03independent crews. And in some areas,
  544. 21:07yes, a construction company will
  545. 21:09perform the work more efficiently and
  546. 21:11quickly because they have qualified
  547. 21:13specialists. Based on my company's
  548. 21:17experience, one person working for a
  549. 21:19year can produce 10 items an hour,
  550. 21:21while a newcomer might only produce one
  551. 21:23. Yes, a construction company saves
  552. 21:27money on this and does it with higher
  553. 21:29quality. So, regarding the extras. The
  554. 21:31first is the materials purchaser. As
  555. 21:40builders or manufacturers, you can
  556. 21:42offer the client the option to hire,
  557. 21:44whether on a salary or per-job basis, a
  558. 21:46purchaser from your staff or a
  559. 21:48contractor who will calculate the
  560. 21:50preliminary estimate for me and try to
  561. 21:52save costs at various stages of
  562. 21:54construction. Meaning, it shows me that
  563. 22:03by the time we got to this point, the
  564. 22:05materials have become cheaper. Or I
  565. 22:07found a better material, or found a
  566. 22:09different manufacturer, so let's swap
  567. 22:11them. And that would be fair for the
  568. 22:14client. Oh, so this material purchaser
  569. 22:17should manage the budget for the client
  570. 22:19throughout the entire construction
  571. 22:21phase. And next, we return to the site
  572. 22:24manager or other specialists. Honestly,
  573. 22:27I’m getting confused by your
  574. 22:28abbreviations. Is it a site manager, a
  575. 22:31technical supervisor, or just a project
  576. 22:34manager? So, they should provide
  577. 22:38periodic reports to the client. It
  578. 22:43could be daily or weekly, by agreement,
  579. 22:45and they must answer questions because
  580. 22:47the client can't be an expert in your
  581. 22:49field. I saw a hole in the wall. As the
  582. 22:53client, whether I visited the site or
  583. 22:55saw it online, they showed it to me. I
  584. 22:57have to ask," What is this hole for? "
  585. 22:59And they should give me an answer. Or
  586. 23:02take a pause, ask the person who made
  587. 23:04the hole, and then give me an answer?
  588. 23:07That would be fair. So, that is the
  589. 23:09site manager's primary function. It’s
  590. 23:11not that the site manager must know
  591. 23:13everything, like why expensive
  592. 23:14materials were delivered or why they
  593. 23:16weren't on time. The purchaser should
  594. 23:18be responsible for that. So, I hire the
  595. 23:20site manager for a specific fee as well
  596. 23:23. If you quoted me a price and said,"
  597. 23:25Either you be the site manager yourself
  598. 23:27or pay us for one, "that would be fair.
  599. 23:30And it would be clear to me how much
  600. 23:31this site manager is making off me.
  601. 23:37I’m just looking at it like this: in
  602. 23:39most cases, you hold round tables and
  603. 23:41always look from one side; as
  604. 23:43manufacturers and specialists, you
  605. 23:45speak your own technical language, but
  606. 23:47you probably need to invite more people
  607. 23:49who are your potential clients. And you
  608. 23:56will see the other side of the coin,
  609. 23:58completely without any grievances.
  610. 24:01People will just explain what it is
  611. 24:02that I actually want. It’s like going
  612. 24:07to a doctor and saying," You know, a
  613. 24:09pandemic is coming, what should we do?
  614. 24:14"And you’re sitting there talking
  615. 24:16about how you need to close things off,
  616. 24:18lock things down, isolate people, and
  617. 24:20so on. But ask the people if they even
  618. 24:24want to be isolated. And, I will be
  619. 24:28brief. Lastly. I’ve already suggested
  620. 24:31this to Vitaly and Matvey at some point
  621. 24:33. This involves creating a user manual
  622. 24:38for the house or product you've built,
  623. 24:40including warranties for specific
  624. 24:42equipment or systems, and handing it
  625. 24:44over to the client. It's a great
  626. 24:49concept: for instance, if I build a
  627. 24:51pool, I just hand over a folder. It
  628. 24:55could be in digital format, or it could
  629. 24:57be printed, it doesn't matter. Nowadays
  630. 25:00, with artificial intelligence, it can
  631. 25:02be done quickly, so you don't end up in
  632. 25:04a situation where someone asks:" Where
  633. 25:06are your wires hidden? "" Which side
  634. 25:08can I install extra light fixtures on?
  635. 25:11"And I have no idea. Then the testing
  636. 25:13with the drill begins. Did I hit it or
  637. 25:15not? Oops, okay, it's fine. The
  638. 25:18painting is hung.
  639. 25:18I will answer your question now. How
  640. 25:20are we doing this now? We have as-built
  641. 25:23documentation that tracks how we build
  642. 25:25the house from start to finish. We also
  643. 25:29have a 3D scanner, a 3D laser scanner,
  644. 25:32which we use once the electricians and
  645. 25:34plumbers have installed all their
  646. 25:36systems. This device is set up. It
  647. 25:38costs about 100,000 rubles. That's what
  648. 25:41the team charges. They use this scanner
  649. 25:44to create a complete as-built survey of
  650. 25:46all the wires present, which is then
  651. 25:47handed over to you and overlaid onto
  652. 25:49the existing floor plans. So, this pain
  653. 25:53point exists for clients, but it is now
  654. 25:55solvable. The only question is whether
  655. 25:57the client is willing to pay 100,000–
  656. 26:00150,000 rubles upfront. For having
  657. 26:01their 200 m² house fully scanned in 3D
  658. 26:04to provide them with an as-built survey
  659. 26:06. That's all there is to it. But I
  660. 26:07think in this case, it's much cheaper
  661. 26:09than damaging a very expensive
  662. 26:11renovation. It's way cheaper,
  663. 26:12significantly so.
  664. 26:13Well, there are two options here. I
  665. 26:15started with this at the very beginning
  666. 26:17. When buying a car, you either take
  667. 26:19the base model and say:" I need this, I
  668. 26:21need that, but I don't need this. "
  669. 26:23Uh-huh.
  670. 26:24Or you say:" Give me the highest trim
  671. 26:26level you have, calculate how much it
  672. 26:28costs. "But you still have to break
  673. 26:31down the costs for the foreman, the
  674. 26:33procurement officer, and, I don't know,
  675. 26:35the creation of a brand book. To avoid
  676. 26:42any issues with the client, we now
  677. 26:44break everything down to the last screw
  678. 26:46and provide an estimate for a specific
  679. 26:47stage of work, making it much easier to
  680. 26:49work with them later and sign off on
  681. 26:51the volumes of work. This includes the
  682. 26:57foreman's work as well. He reports on
  683. 27:00the actual work done at the site,
  684. 27:01whether it's excavation, other tasks,
  685. 27:03or providing as-built documentation,
  686. 27:05which the teams submit themselves.
  687. 27:07Everything is transparent and honest.
  688. 27:10It’s better for us to earn a
  689. 27:11percentage here; this percentage is set
  690. 27:13, and the client either accepts it or
  691. 27:15they don't. And then he understands
  692. 27:18that we are trying to be on his side,
  693. 27:20because if we save money here, he will
  694. 27:22be able to finish the house. And that
  695. 27:25means that, uh, internally we will get
  696. 27:27the result we wanted. We want to
  697. 27:30eventually be able to visit him and
  698. 27:31have tea or coffee together. That’s
  699. 27:33all. I mean, that is our position. As
  700. 27:36for the photos, he didn't mention it,
  701. 27:37but we provide a daily photo and video
  702. 27:39report, and we show what we did and how
  703. 27:41we did it, right down to using a tape
  704. 27:43measure. Then, when they want to
  705. 27:47inspect us, which happens sometimes, a
  706. 27:48technical supervisor is called in, they
  707. 27:50arrive, we immediately give them the
  708. 27:52full folder, they look through it and
  709. 27:54can see at every stage whether
  710. 27:56everything is done correctly or not,
  711. 27:57and that's it. So we provide the full
  712. 28:00picture here. But here, perhaps, we
  713. 28:02didn't start talking about it, as it's
  714. 28:04more for companies. Most likely, this
  715. 28:07is when you come to a company and it
  716. 28:08provides you with such a service.
  717. 28:11That’s how it seems to me.
  718. 28:12Plus a general estimate, uh, let's say,
  719. 28:15broken down by specific specialists, so
  720. 28:18as not to compete, again, with the
  721. 28:20crews. You wanted 100 rubles. Here is
  722. 28:22100 rubles. It's budgeted, right? You
  723. 28:25wanted add-ons, here is what the
  724. 28:26add-ons cost. This will allow you in
  725. 28:28the future, uh, to separate things, as
  726. 28:30in the joke you told—it's not that
  727. 28:32the whole suit is bad, but that
  728. 28:34specifically this foreman sewed the
  729. 28:36buttons on poorly. And you, uh, having
  730. 28:39figured it out, let's say, at internal
  731. 28:42meetings, who did what wrong, you won't
  732. 28:44tell everyone that, guys, we built a
  733. 28:46bad house. But specifically, you,
  734. 28:49foreman, failed to do your job in this
  735. 28:51spot. Take financial or disciplinary
  736. 28:52responsibility, I don't know, maybe a
  737. 28:54pat on the back. Yes, that works pretty
  738. 28:56well too.
  739. 28:57Not bad.
  740. 28:58You were talking about crews and
  741. 29:00responsibility. A crew is only
  742. 29:01responsible for its own scope of work.
  743. 29:03Whatever was provided to us, that's
  744. 29:05where we install the windows. If
  745. 29:07there’s no flat surface, we can’t
  746. 29:09just bend the windows to match the wall
  747. 29:11or anything else. But in my opinion,
  748. 29:15you didn't touch on the issue that when
  749. 29:18there are many crews, or if a foreman
  750. 29:20comes in with their own scope of work
  751. 29:22with their own crews and then others
  752. 29:24come in, well, in the end, first, it's
  753. 29:26impossible to find who is responsible,
  754. 29:28who messed up, at what moment, and who
  755. 29:30is to blame. And second is the presence
  756. 29:36of materials on-site; who is
  757. 29:38responsible for them, who holds the
  758. 29:40financial liability. A crew arrives,
  759. 29:44they drop something, maybe there were
  760. 29:46glass sets worth 15 million there. Then
  761. 29:50plasterers or welders come and ruin
  762. 29:52them. Who is to blame here? Whose
  763. 29:55responsibility is it? Is it the
  764. 29:56client's responsibility for not
  765. 29:58covering it up? Or is it the welders,
  766. 30:00who should have covered it for some
  767. 30:02reason? Uh, with some kind of tarp, but
  768. 30:04they didn't do it, or maybe they
  769. 30:06weren't supposed to. Who should do what
  770. 30:08there is absolutely unclear. And now,
  771. 30:14as we smoothly transition to companies,
  772. 30:16that zone of responsibility will become
  773. 30:18clearer, as well as what the client
  774. 30:20actually receives: do they just get
  775. 30:22square footage, or do they get a
  776. 30:24peaceful life during these months of
  777. 30:26construction and, in the near future,
  778. 30:28for many years to come while their
  779. 30:30family lives there? 22 years ago, in
  780. 30:352004, one of the first cottages we were
  781. 30:38building, we came in hungover in the
  782. 30:41morning and made a mistake of 0.4
  783. 30:43meters. We set the foundation, we set
  784. 30:48the foundation 40 cm too low.
  785. 30:51We dug too deep,
  786. 30:53yes, we made the cushion, set the slabs
  787. 30:55, reached the zero level, and realized
  788. 30:57that our zero was 40 cm lower. So, yes,
  789. 31:04a nuance, a simple nuance. And in the
  790. 31:09end, I used the money I had earned from
  791. 31:11that job to buy bricks, raised the
  792. 31:13plinth by 40 cm, and on top of that,
  793. 31:15backfilled it with sand to the required
  794. 31:17level.
  795. 31:19You really got into a mess there.
  796. 31:21Yes, that was one of my first major
  797. 31:23blunders, where I really lost a
  798. 31:25significant amount of money. But it
  799. 31:28taught me a lot and gave me great
  800. 31:30experience. You could have run away.
  801. 31:33I could have, I could have run away and
  802. 31:35not paid, yes. But the fact is that,
  803. 31:38perhaps thanks to this, the client told
  804. 31:40others about me, and I ended up
  805. 31:42building almost 12 houses in that area.
  806. 31:45There you go.
  807. 31:45We also messed up on the 7024 Muar
  808. 31:48color, or 7024 usually isn't Muar, but
  809. 31:50we let the client down, and they
  810. 31:52probably won't give us any more
  811. 31:54projects there until it's fixed. So, do
  812. 31:59I understand correctly that you
  813. 32:00installed the windows, cleared them
  814. 32:02with the site manager, and it turned
  815. 32:04out that...
  816. 32:05Well, that's exactly the company vs.
  817. 32:07non-company, crew vs. non-crew issue.
  818. 32:09We communicated with the site manager.
  819. 32:11We didn't have access to the client
  820. 32:13because they were someone very
  821. 32:14important, very serious, and there was
  822. 32:16no access to them. We coordinated with
  823. 32:19the site manager and signed everything.
  824. 32:21But when we brought the structures, the
  825. 32:22client came out and said the color was
  826. 32:24wrong. It was 7024, but not Muar, and
  827. 32:26it was supposed to be Muar. And as a
  828. 32:28result, we had to take these structures
  829. 32:29back for repainting and reworking.
  830. 32:31Minus 600,000.
  831. 32:32Who provided the technical
  832. 32:33specifications? The site manager.
  833. 32:34The site manager, yes.
  834. 32:35And the site manager said," What about
  835. 32:37me? He doesn't like it, goodbye. "
  836. 32:38That is not a site foreman.
  837. 32:40Well, that’s something for..." Moiré
  838. 32:41"and" Non-moiré "won't understand a
  839. 32:43thing. It’s either just shiny or
  840. 32:45it’s not shiny. Right?
  841. 32:47Matte or shiny windows. That’s the
  842. 32:49whole difference. Also, colleagues,
  843. 32:52we’re talking about these zones of
  844. 32:54responsibility, saying the crew is
  845. 32:56responsible, and that’s it. Well,
  846. 32:58that’s like living in certain
  847. 33:00illusions. Like hoping, or relying on
  848. 33:03some probability that this crew...
  849. 33:05it’s an uncontrollable process,
  850. 33:07really. A crew or a foreman with a crew
  851. 33:11will come, and they will be responsible
  852. 33:13to some degree. Or they won't. The
  853. 33:20client, the customer, will project
  854. 33:22themselves onto them, thinking" I am
  855. 33:24responsible, I have this level of
  856. 33:26standards, so they must be the same or
  857. 33:28higher. "But that is an illusion. You
  858. 33:32can easily make a huge mistake here,
  859. 33:34and it’s just one click from
  860. 33:36enchantment to disappointment. Well,
  861. 33:40the same goes for companies—if
  862. 33:41we’re talking about Krasnodar, there
  863. 33:43are so many developers who built houses
  864. 33:45for sale. And when you can see the
  865. 33:47street through the gaps between the
  866. 33:48blocks, well, the company built that
  867. 33:50too, so much for" responsibility. "You
  868. 33:52can harbor illusions about a company,
  869. 33:54too.
  870. 33:55But does a company have specific goals?
  871. 33:57Goals to build as cheap as possible and
  872. 33:59sell as dear as possible.
  873. 34:00Exactly. Are there other goals?
  874. 34:03I’m not against it, I’m just saying
  875. 34:05illusions can exist there and here.
  876. 34:06That’s all true. Actually,
  877. 34:08listen, this battle, it gets more views
  878. 34:10. Come on, come on, fight, fight, fight
  879. 34:12on camera!
  880. 34:13No, no, we’re not actually talking
  881. 34:15about different things here. We’re
  882. 34:16talking about the same thing.
  883. 34:18Interacting with a foreman who is
  884. 34:19competent and understands what we’re
  885. 34:21talking about and what I’m taking
  886. 34:22money for, rather than a customer who
  887. 34:24has to prove why it’s 100,000 more
  888. 34:26expensive, roughly speaking, and why,
  889. 34:27and what I’m providing for that.
  890. 34:29Wait, you’ve already taken 600,000
  891. 34:31from the foreman. No, no, well, I agree
  892. 34:34, the experience is already there. The
  893. 34:37result—that’s not experience,
  894. 34:39that’s the result of cooperation,
  895. 34:40we’re still working with him, just
  896. 34:42next time I’ll be...
  897. 34:43minus 600,000.
  898. 34:45The signatures next time will be more
  899. 34:47attentive. Meaning you signed, I took
  900. 34:48the responsibility off myself, and then
  901. 34:50, well, I can’t do anything about it.
  902. 34:52Well, that was the foreman’s
  903. 34:54responsibility that was...
  904. 34:55Yes, yes, the foreman is like...not to
  905. 34:58harbor illusions. But the foreman is
  906. 34:59responsible. So what? And I have the
  907. 35:01construction and the lost sum of money,
  908. 35:03because we signed it in the contract.
  909. 35:05Wait, let's. What if you had received a
  910. 35:08technically correct assignment from the
  911. 35:10company at that moment? We are talking
  912. 35:13about doing the job right now.
  913. 35:15The question is, who is going to be
  914. 35:17held responsible? The signatures are
  915. 35:19there, but in the end, I have a 15
  916. 35:21million project and I’m still short
  917. 35:23500,000. And it turns out that, just
  918. 35:25like you described yourself, I put in
  919. 35:27my own revenue just to at least recover
  920. 35:29the costs for the product.
  921. 35:31You just said whether it’s more
  922. 35:33convenient for you to work with a site
  923. 35:35manager or a company. That’s what I
  924. 35:37want to tell you.
  925. 35:38He is much more comfortable working
  926. 35:39with a site manager,
  927. 35:40because it would have been the same
  928. 35:41story with the client. The client would
  929. 35:43have just said," Basically, I don’t
  930. 35:44know what Moire is. "What do you mean?
  931. 35:46What do you mean? I didn't understand
  932. 35:47what Moire was, roughly speaking, yes.
  933. 35:49I thought matte was Moire. There.
  934. 35:51A site manager's company. The main
  935. 35:52thing is that the competence is
  936. 35:53sufficient for the technical assignment
  937. 35:54. Pete should have enough, and the
  938. 35:56person who handles the transfer of the
  939. 35:57technical assignment should too.
  940. 35:58Transferring a technical assignment is
  941. 36:00always an interpretation. That is, damn
  942. 36:01it, the most difficult part.
  943. 36:03Evgeny, you are talking about a site
  944. 36:05manager being a person, and he says a
  945. 36:07company is easier for me. You say, it's
  946. 36:09easier for me to work with a site
  947. 36:11manager.
  948. 36:12For him, the best thing is a company
  949. 36:14and site managers. So not the client,
  950. 36:17it turns out. Your client is
  951. 36:23the site manager and the company.
  952. 36:25The company, yes.
  953. 36:26Not the direct client.
  954. 36:27Not the direct client, yes.
  955. 36:29That also has a right to exist.
  956. 36:31That’s normal. Okay.
  957. 36:32And it's actually even better, I'll
  958. 36:34tell you.
  959. 36:34Well, it's better in terms of the fact
  960. 36:36that I
  961. 36:36have less of a headache. I mean, I
  962. 36:39received a clear assignment, provided a
  963. 36:41quote without any nitpicking or
  964. 36:43anything else.
  965. 36:45You just didn't understand each other.
  966. 36:47Yes, because the client takes up much,
  967. 36:49much more time than that. Yes, because
  968. 36:52the company has it organized.
  969. 36:56I want to say something completely
  970. 36:57different: does it matter if there is
  971. 36:59one idiot or 100 idiots?
  972. 37:04Do you understand, or one smart person
  973. 37:07and 100 smart people in a company? Uh,
  974. 37:10huge knowledge, meaning when we take an
  975. 37:12error and multiply it, we get one
  976. 37:14continuous error. And if this site
  977. 37:19manager is initially incompetent, toxic
  978. 37:21, or unethical, they grow into a
  979. 37:22company and build the same kind of
  980. 37:24company. If the same mess arises around
  981. 37:28them, it doesn't matter if they worked
  982. 37:30alone as a foreman, as a site manager
  983. 37:32with two or three crews, or as a
  984. 37:34company with estimators, technical
  985. 37:36supervisors, lawyers, and so on. We are
  986. 37:38talking about something a little
  987. 37:39different. Meaning the structure,
  988. 37:42meaning increasing the structure does
  989. 37:44not mean increasing competence,
  990. 37:45responsibility, technical literacy, or
  991. 37:47ethical standards. It makes absolutely
  992. 37:51no difference. There are strong
  993. 37:53companies, strong site managers, strong
  994. 37:55crews, and so on. That is, well, it's
  995. 37:58really a conversation about completely
  996. 38:00different levels. We need to talk about
  997. 38:03the professional and ethical level. In
  998. 38:06any case, we must look at the
  999. 38:07professional and ethical layers. It
  1000. 38:09doesn't matter what level a company, a
  1001. 38:12crew, a site manager, or a specialist
  1002. 38:14is at—anyone at all. You know, people
  1003. 38:17often talked about being in a situation
  1004. 38:19where someone else solved it. I say,"
  1005. 38:21Why didn't you just run away? "
  1006. 38:23I mean, you could have spent 40 minutes
  1007. 38:26, or you could have spent another
  1008. 38:28600,000, while others, I had 25 million
  1009. 38:30. Well, you could have just disappeared
  1010. 38:33, probably, and gone somewhere for that
  1011. 38:35kind of money. You certainly could have
  1012. 38:37run away, but no, it's not like that.
  1013. 38:43And in fact, as I say, the client only
  1014. 38:45faces this when they are already
  1015. 38:47committed, meaning behind the nice
  1016. 38:49words, there should be results. If
  1017. 38:56those results aren't there, the client
  1018. 38:58can't really verify how high-quality
  1019. 39:00the work is.
  1020. 39:03Right away.
  1021. 39:03Well, first of all, right away, and
  1022. 39:05later on as well. Is this hole here a
  1023. 39:07hole, or is it a technological opening?
  1024. 39:10A hole in one spot.
  1025. 39:12Will it be there forever, or is it just
  1026. 39:13there while the work is being done? And
  1027. 39:15then, you know, everyone leaves, but
  1028. 39:17the hole stays. I think, damn, why
  1029. 39:19didn't I ask sooner? Maybe it should
  1030. 39:21have just been patched up. But everyone
  1031. 39:23just forgot, or left, or something
  1032. 39:24happened—anyway, it’s that kind of
  1033. 39:26story. And he just thinks," Damn, "and
  1034. 39:29no one is going to answer that question
  1035. 39:31for him." They definitely left it for
  1036. 39:33the air conditioner. "Just keep
  1037. 39:34thinking that, right?
  1038. 39:36But our air conditioner is in a
  1039. 39:37different spot. Uh, I guess I'll sum it
  1040. 39:40up now. If, uh, a client wants to work
  1041. 39:44with a site manager who comes with his
  1042. 39:46own crews, they need to realize they
  1043. 39:48might run into the fact that there's
  1044. 39:50only one manager, and if he gets sick,
  1045. 39:52the same chaos will start on the site.
  1046. 39:57If the manager takes on two or three
  1047. 39:59projects, he won't have enough time to
  1048. 40:01manage this one. There are likely no
  1049. 40:05guaranteed crew replacements, or
  1050. 40:07perhaps a lack of full expertise. How a
  1051. 40:09project is handled from beginning to
  1052. 40:11end. Uh, maybe, once again, we’ll
  1053. 40:15come back to the human factor. He might
  1054. 40:19be a technically competent specialist,
  1055. 40:21but he is a very poor manager, and
  1056. 40:22consequently, he cannot properly
  1057. 40:24organize the work. And often,
  1058. 40:27construction foremen think that they
  1059. 40:28don't need technical supervision. In
  1060. 40:31other words, they see him as the person
  1061. 40:33who creates problems for them. But in
  1062. 40:35fact, it is the exact opposite. Well,
  1063. 40:38there is a lack of understanding and a
  1064. 40:39lack of training, I think.

About this transcript

This page contains the full transcript of Функции и ответственность бригады/прораба и компании при строительстве дома. by 37Pro, generated from the public captions YouTube serves with the video. The transcript has 6,717 words across 1,064 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to choose a caption track available on the video.

Free YouTube transcript tool

YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, caption language selection, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.