  1. 0:00in this video we're going to be taking a
  2. 0:01look at 200 Ultra hard PMP practice
  3. 0:05questions and from the length of this
  4. 0:07video you can see this video is going to
  5. 0:09be a long one so in this video I'm going
  6. 0:11to be answering some of the hardest PMP
  7. 0:14practice questions out there if you can
  8. 0:16get at least a 70% on this exam I think
  9. 0:19you're going to pass your your PMP exam
  10. 0:21pretty easily I'm Andrew ramal I am the
  11. 0:24author of the world's bestselling PMP
  12. 0:26study guide PMP exam prep simplified and
  13. 0:29I'm also the creator of Udi's
  14. 0:31bestselling PMP course with over 370,000
  15. 0:34enrollments combined with my books my
  16. 0:37videos and my live courses I've helped
  17. 0:39over 500,000 students pass the current
  18. 0:43PMP exam so with that in mind let's go
  19. 0:45ahead and get started on this but before
  20. 0:47I get there I want to just point out a
  21. 0:48couple things number one this took an
  22. 0:51enormous amount of time and this is a
  23. 0:53compilation video of all the videos that
  24. 0:55came before if you notice I released
  25. 0:57them in series of 10 so what I did is I
  26. 0:59just combine all of them now into this
  27. 1:01giant compilation video another thing is
  28. 1:04that it took a lot of time a lot of time
  29. 1:07a lot of effort to write these questions
  30. 1:09and to make this video so if you guys
  31. 1:11don't mind clicking on the like button
  32. 1:12subscribing to the channel would help us
  33. 1:14out a lot if you appreciate the work and
  34. 1:16effort that goes into this if you want
  35. 1:18more questions like you're about to see
  36. 1:20and more explanations to these questions
  37. 1:22check out the link below to the Tia exam
  38. 1:24simulator which now has about 1,000
  39. 1:27practice questions that you can try
  40. 1:29including multiple full length uh Mach
  41. 1:31exam micro exams uh mini exams and so on
  42. 1:35you can check that out with video
  43. 1:36explanations all done by me and with
  44. 1:39that in mind guys let's just dra dive
  45. 1:41right into it and start off with
  46. 1:43question one keep in mind this is a
  47. 1:44compilation video so let's keep going
  48. 1:46let's get to question one all the way to
  49. 1:49200 all right here we go question number
  50. 1:52one now again these questions are meant
  51. 1:53to be difficult all right a project
  52. 1:55manager is planning the construction of
  53. 1:57a new Public Library the community and
  54. 2:00project stakeholders are having
  55. 2:02difficulty agreeing on the key features
  56. 2:04to be included in the final design what
  57. 2:06should the project manager do facilitate
  58. 2:08a workshop Workshop to gather input from
  59. 2:11all stakeholders Define the difference
  60. 2:13between essential and non-essential
  61. 2:15features involve design consultant to
  62. 2:18mediate stakeholder
  63. 2:20discussions identify the root cause of
  64. 2:22the stakeholder inability to agree on
  65. 2:25the project scope now you really have to
  66. 2:27not a mindset on this question because
  67. 2:29you you can see in the question that we
  68. 2:31have it says the community and
  69. 2:34stakeholders there's some kind of
  70. 2:36difficulty going on here uh to help
  71. 2:39identify the features now if there is a
  72. 2:41problem on a project one of your most
  73. 2:44important thing to do is to ensure you
  74. 2:47understand the problem the first thing
  75. 2:49we're going to do before we solve a
  76. 2:51problem is to identify how did this
  77. 2:53problem come about what's going on here
  78. 2:57can can there be potential or multiple
  79. 2:59Sol Solutions how did we get to this
  80. 3:02problem these are questions you should
  81. 3:03be asking yourself now there's something
  82. 3:06very unique about D if you learn the
  83. 3:08mindset you understand that D
  84. 3:10understands the problem because look
  85. 3:12he's looking for the root cause of the
  86. 3:14problem the problem is their inability
  87. 3:16to agree on the scope something about a
  88. 3:20b and c is telling you something you see
  89. 3:23it's they all have something in common
  90. 3:25this is an action you're actually going
  91. 3:27to hold a workshop you're going to
  92. 3:29Define the differences first of all you
  93. 3:31should never be the one choosing what's
  94. 3:34right for the project and what's wrong
  95. 3:35for the project in this one you're
  96. 3:37choosing between what's the essential
  97. 3:38and non-essential that's generally your
  98. 3:40product owner your project sponsor your
  99. 3:42customers does that not
  100. 3:44you involveed Design Consultants now
  101. 3:46you're bringing in other people without
  102. 3:48even understanding the actual root cause
  103. 3:51the main cause of the problem so
  104. 3:53remember now when it comes to this exam
  105. 3:55the mindset says don't take an action
  106. 3:58unless you saw
  107. 4:00the problem unless you understand the
  108. 4:02problem all right no actions without
  109. 4:05understanding the problem assess the
  110. 4:07situation okay very good s a number one
  111. 4:10done all right we got 199 more to
  112. 4:14go question two a project manager
  113. 4:17convenes an emergency session with the
  114. 4:18software development team to address
  115. 4:21significant bugs that are delaying the
  116. 4:22Project's delivery the product owner
  117. 4:25suggest conducting a root cause analysis
  118. 4:27to identify the underlying issues what
  119. 4:29what should the project manager do
  120. 4:31collaborate with the team to discuss the
  121. 4:33RCA suggestions and decide collectively
  122. 4:35on the next step okay getting the team
  123. 4:38involved encourage a a lead developer to
  124. 4:41take charge of the RCA fostering Team
  125. 4:43anony all right letting the team work by
  126. 4:45themselves coordinate with the quality
  127. 4:47assurance lead to refine testing
  128. 4:49processes and B based on the RCA outcome
  129. 4:52all right bringing more people in
  130. 4:54organize the session to ensure all team
  131. 4:56members contribute their insights
  132. 4:58potential Solutions okay okay not not a
  133. 5:00bad answer you're letting everybody
  134. 5:02contribute okay so let's take a look at
  135. 5:05this question now this is the an agile
  136. 5:08project how do I know this because I can
  137. 5:11see it says product owner this
  138. 5:12immediately tells me that this is an
  139. 5:14agile uh project and the product owner
  140. 5:18suggesting something that the team
  141. 5:20should be
  142. 5:21following in a situation like this if
  143. 5:24there's some kind of solution or
  144. 5:25somebody wants the team to do something
  145. 5:28you have to let the team decide if they
  146. 5:30want to do it or not remember something
  147. 5:33on an agile project the team is
  148. 5:35self-leading they're
  149. 5:37self-directing you don't you're not a a
  150. 5:40dictator to the team as you would on a
  151. 5:42traditional project so the best answer
  152. 5:44here is let the team
  153. 5:46decide work with the team to discuss the
  154. 5:50RCA suggestion and let them decide if
  155. 5:53they want to implement it or not the
  156. 5:55rest of them is pretty much
  157. 5:56implementation notice first of all be
  158. 5:59never do be this is giving away your
  159. 6:01work if it ever comes like to a point on
  160. 6:04this exam where it says well let
  161. 6:06somebody else deal with it while you
  162. 6:08just watch it's never the answer never
  163. 6:11give away your work coordinate with a
  164. 6:14quality now you're bringing in more
  165. 6:15people and it seems like you're
  166. 6:17basically going to implement this RCA
  167. 6:19outcome don't do that organize is the
  168. 6:22ultimate contributed insights and
  169. 6:24potential solutions to what this one is
  170. 6:26very a little vague we're not sure what
  171. 6:28it's talking about
  172. 6:30but it seems like they're coming up with
  173. 6:32their own Solutions here the best thing
  174. 6:33the question is addressed in this
  175. 6:35RCA so the best thing here is bring the
  176. 6:38RCA to them as a suggestion and say hey
  177. 6:40do you want to implement this or not let
  178. 6:42the team decide is the model of the
  179. 6:44story here remember on an agile project
  180. 6:47the team decides how how they want to do
  181. 6:50the work the team decides what methods
  182. 6:52they're going to do the work because
  183. 6:54they're a self-leading self-directing
  184. 6:56team question
  185. 6:58three a project manager over seeing the
  186. 7:00launch of a new e-commerce platform
  187. 7:02discovers that the finance department
  188. 7:04has concerns about not being involved in
  189. 7:06the cost estimations and their potential
  190. 7:09impact on the project Returns what
  191. 7:11should the project manager do first
  192. 7:13amend the stakeholder engagement plan to
  193. 7:15better integrate Finance in future plans
  194. 7:18all
  195. 7:19right document the exclusion of the
  196. 7:21finance team as a risk to project
  197. 7:23success all right maintain the project
  198. 7:25timeline the plan and financial review
  199. 7:27before the Final Phase okay organize a
  200. 7:30meeting with the finance team to
  201. 7:32understand the concerns all right
  202. 7:34similar to somewhat similar to that
  203. 7:36first question because if you
  204. 7:38notice uh the finance department they
  205. 7:41have some kind of concern all right they
  206. 7:43weren't involved and whoever came up
  207. 7:44with the budgets and they think it's
  208. 7:46going to affect what what we're going to
  209. 7:47get back from the project notice this
  210. 7:50one particularly says what should you do
  211. 7:52first again this one has a very similar
  212. 7:57theme all right and the a lot of these
  213. 7:59choices have a very similar team but one
  214. 8:01is very uniquely different the answer
  215. 8:04here is of course D you see if you
  216. 8:07notice a is this before you before you
  217. 8:12understand their concern before you
  218. 8:14understand what really happened here
  219. 8:16you're already amending the engagement
  220. 8:18plan don't do that never take an action
  221. 8:20first document the exclusion of the
  222. 8:22finance team is a risk to the project
  223. 8:24success it might
  224. 8:26be all right it might be an exclusion
  225. 8:28but before we even document that risk we
  226. 8:30need to understand that
  227. 8:32risk maintain never do nothing if you
  228. 8:36get a choice where it says maintain it
  229. 8:39um keep doing what you're
  230. 8:41doing uh then that's not the answer so
  231. 8:44the moment I say like maintain the
  232. 8:45timeline well the timeline could be
  233. 8:47affected by this the best thing we
  234. 8:49should do first is let's go and meet
  235. 8:50with the team understand their concerns
  236. 8:53that will we have a better way of
  237. 8:54determine what action we should take
  238. 8:58next question number four as part of a
  239. 9:02project to integrate a new security
  240. 9:04feature into an online shopping platform
  241. 9:07stakeholders have shown concerns over
  242. 9:10understanding the integration process
  243. 9:11during the planning phase what should
  244. 9:14the project manager do to in hands
  245. 9:16stakeholders understanding of the
  246. 9:18integration all right so we are
  247. 9:20integrating we're putting something into
  248. 9:22operations we're getting something out
  249. 9:23there what should we do well schedule
  250. 9:26regular demonstration session during
  251. 9:27each Sprint to show progress integration
  252. 9:30steps sure arrange for the technical
  253. 9:32team to provide a detailed explanation
  254. 9:34before each Sprint
  255. 9:35begins organize a training session to
  256. 9:38educate stakeholder technical aspects of
  257. 9:40the
  258. 9:40integration provide detailed
  259. 9:42documentation on the integration process
  260. 9:44prior to the start of each Sprint phase
  261. 9:46well if you understand the world of
  262. 9:48agile this one is pretty simple because
  263. 9:51what we should be doing in every single
  264. 9:53Sprint is we should be doing the Sprint
  265. 9:56review meetings and that's what this is
  266. 9:58really asking asking you all right
  267. 10:01notice stakeholders have concerned
  268. 10:03because they don't understand this
  269. 10:04integration process during the planning
  270. 10:06stage so what should you do well do
  271. 10:08regular demonstrations with them explain
  272. 10:11to them what the project is doing this
  273. 10:13way you can show the progress of what we
  274. 10:15have done and how it's working they
  275. 10:18don't need a detail stakeholders
  276. 10:21especially like customers don't want
  277. 10:22detailed documentation they might not be
  278. 10:25able to understand especially if it's
  279. 10:26very
  280. 10:27technical they don't need to be educated
  281. 10:29on the technical aspects it's more for
  282. 10:31like your team members arrange with the
  283. 10:33technical team they don't need a
  284. 10:35detailed explanation before each Sprint
  285. 10:37they just need to understand what's
  286. 10:38going on you remember something
  287. 10:41customers really don't care about the
  288. 10:43technical aspects of things they care
  289. 10:44about the functionality of things if
  290. 10:47you're building a website for me I
  291. 10:48really am not interested in how the back
  292. 10:51end works I don't need to know what
  293. 10:52codeing language you use I don't need to
  294. 10:54know what forms you were using or
  295. 10:56functions all I need to know is does it
  296. 10:58work so keep that in
  297. 11:00mind all right best answer there was
  298. 11:04a question five a project manager is
  299. 11:07preparing for the Sprint planning
  300. 11:09sessions for a new feature in a Health
  301. 11:12Care system this meeting aims to
  302. 11:14determine the amount of work for the
  303. 11:16upcoming Sprint while two pieces of
  304. 11:18information are essential for the
  305. 11:19project manager ensure the meeting is
  306. 11:22productive and efficient so now you're
  307. 11:26doing a meeting we know we're working on
  308. 11:28an ad job project because we got this
  309. 11:30upcoming Sprint this word alone tells me
  310. 11:33um Sprint Sprint plan is going to be an
  311. 11:36agile project so what are two essential
  312. 11:39things that we should have for our
  313. 11:40meetings remember this is the Sprint
  314. 11:43planning session remember what the
  315. 11:45Sprint planning session is what's the
  316. 11:47input to that Sprint planning session
  317. 11:48what's going to be the output of it best
  318. 11:51answer here is going to be if you
  319. 11:54understand it it's going to be first of
  320. 11:56all team performance metrics and a
  321. 11:58detail
  322. 11:59product backlog how do we get here well
  323. 12:02first of all understand what a Sprint
  324. 12:04planning session is the Sprint planning
  325. 12:05session is where the team decides how
  326. 12:08much or what work they're going to do
  327. 12:10how much and what work they're going to
  328. 12:11do in the next Sprint the output is the
  329. 12:14Sprint backlog so for them to
  330. 12:17determine what work they're going to do
  331. 12:19they're going to need a product backlog
  332. 12:22generally should have the user stories
  333. 12:23in it by now the next thing they're
  334. 12:25going to need is how fast they work
  335. 12:27they're going to need that performance
  336. 12:29metrics or what's known as the team
  337. 12:30velocity why do they need that because
  338. 12:33for them to determine how much work they
  339. 12:35can do from the product backlog they're
  340. 12:37going to have to know how fast they do
  341. 12:40work previously how fast they generally
  342. 12:42work how many points they do per
  343. 12:43iteration or per Sprint they don't
  344. 12:47necessarily updated risk assessment
  345. 12:49product Marketplace goal that's more of
  346. 12:52like your sales and markeet in current
  347. 12:54project phase timeline the thing with
  348. 12:57agile projects you're not going to
  349. 12:58really have like pH and timelines laid
  350. 13:00out like that they're building it based
  351. 13:01on prioritization of the work in the
  352. 13:04product
  353. 13:05backlog all right this one here was
  354. 13:06choose
  355. 13:08to question number six a project manager
  356. 13:13is leading an interet by biotechnology
  357. 13:17research project characterized by
  358. 13:20significant am
  359. 13:22ambiguity big word there
  360. 13:25unpredictability a suggestion has been
  361. 13:27made to introduce a system to engage the
  362. 13:29quality of the project outputs
  363. 13:32effectively what hybrid technique should
  364. 13:34the project manager employ to ensure
  365. 13:36quality assurance so key word here is we
  366. 13:38got to basically it's what are we going
  367. 13:40to do to ensure we have good quality
  368. 13:42assurance combine weekly Sprints with
  369. 13:45quarterly external audits to validate
  370. 13:47project standards H quarterly external
  371. 13:50audits
  372. 13:51huh merge traditional Milestone reviews
  373. 13:55with agile Sprint
  374. 13:57demonstrations okay adapt paer
  375. 14:00programming and customer feedback
  376. 14:01sessions okay integrate continuous
  377. 14:04integration tools with formal quality
  378. 14:06control checkpoints now we have to
  379. 14:09understand that when it comes to Quality
  380. 14:10quality is meeting customers
  381. 14:12satisfaction High customer satisfaction
  382. 14:14good quality product the ultimate test
  383. 14:16of quality is a satisfied
  384. 14:19customer so how can we do this how can
  385. 14:22we ensure that we introduce a system
  386. 14:25that has high quality what which one
  387. 14:27here leads to high quality would it be
  388. 14:30quarterly external audits would it be
  389. 14:34Milestone reviews and Sprint
  390. 14:36demonstrations would it be peer
  391. 14:38programming customer feedback or
  392. 14:40integrate continuous integration tools
  393. 14:43with formal quality checkpoints best
  394. 14:45answer here guys is going to be peer
  395. 14:46programming and customer feedback if
  396. 14:49you're wondering how do you get that
  397. 14:50well understand what peer programming is
  398. 14:52so this is used in extreme programming
  399. 14:54we do cover this in the agile section of
  400. 14:56the course when one guy writes the code
  401. 14:58the other guy checking the code if the
  402. 15:00code is consistently checked as it's
  403. 15:02being written the code is less likely to
  404. 15:04have bugs and the question is is the
  405. 15:07customer feedback getting accepted into
  406. 15:09the project that's customer feedback the
  407. 15:12best way to make a customer happy with a
  408. 15:14product is to get the customer involved
  409. 15:16in the development of the product get
  410. 15:18feedback as you're developing the
  411. 15:20product making this the best answer we
  412. 15:23don't like this one here first of all
  413. 15:24it's it's quarterly and this one doesn't
  414. 15:26involve your customer the best way to
  415. 15:28make something really good for our
  416. 15:29customers to get them
  417. 15:31involved although I like this one here
  418. 15:33with agile Sprint demonstrations the
  419. 15:35problem here is Milestone reviews and
  420. 15:36we're not sure how long those Milestone
  421. 15:38reviews are continuous integration this
  422. 15:41one here is not this is integration
  423. 15:42tools and it's not bringing customers in
  424. 15:45customers will give us the best way that
  425. 15:48will tell us what we're doing right what
  426. 15:50we're doing wrong and this is the best
  427. 15:52way in order to produce quality
  428. 15:55products question seven uh project
  429. 15:59managers are overseeing a software
  430. 16:01development project where the team has
  431. 16:02prioritized creating a new user
  432. 16:04authentication system in the current
  433. 16:06Sprint Midway through the Sprint two
  434. 16:08developers Express a desire to divert
  435. 16:11their efforts to optimize in database
  436. 16:13queries anticipating future performance
  437. 16:15Botts what should you do next I want to
  438. 16:18point out this is a tough question by
  439. 16:20the way allocate time for developers to
  440. 16:23present their optimization proposal at
  441. 16:25the next Sprint planning
  442. 16:27meeting reinforcing importance of
  443. 16:29adherent to the Sprint's primary goal of
  444. 16:31completing the authentication
  445. 16:33system request a special session to
  446. 16:35assess the potential impact of the
  447. 16:37database optimization on future Sprints
  448. 16:40support the developers initiative by
  449. 16:42allocating a small portion of their time
  450. 16:44to start preliminary work on the
  451. 16:47database this one is a tough question
  452. 16:50this one tests your ability to
  453. 16:52understand agile principles and the
  454. 16:54agile principles tells us that once a
  455. 16:58Sprint starts
  456. 16:59what should you do you should do the
  457. 17:01work in the Sprint don't change the team
  458. 17:04don't change the work when somebody when
  459. 17:06they're coming to you in a Sprint and oh
  460. 17:08we want to do this we want to go here I
  461. 17:09want to go here the best thing you can
  462. 17:10do is to keep them on track and keep
  463. 17:12them to finish the Sprint goal that's
  464. 17:15what B is and that's what we
  465. 17:17need everything else is not completing
  466. 17:20the goal everything else is allowing
  467. 17:21them to go and do this database thing
  468. 17:24allocate time for developers to present
  469. 17:25their optimization of the now you're
  470. 17:28allocating time that's taken away from
  471. 17:29the Sprint goal request special session
  472. 17:32once again same thing supported now if
  473. 17:36you support it and you allocate a small
  474. 17:37time once again you're making them work
  475. 17:40something that is not on the Sprint goal
  476. 17:42on they once they finish the Sprint if
  477. 17:44the team feels like this is something
  478. 17:45that needs to get done maybe it's added
  479. 17:47to the product backlog and maybe they
  480. 17:49they can do it in the next
  481. 17:52spread question number eight a project
  482. 17:55manager is overseeing the development of
  483. 17:57an enterprise resource planning system
  484. 17:58system and is decided that a combination
  485. 18:01of scrum and can band methodologies
  486. 18:03would be most effective however the
  487. 18:06product owner is unsure about how to
  488. 18:08begin optimizing and prioritizing work
  489. 18:10what should the project manager what
  490. 18:13should the project manager
  491. 18:14do uh guide the product owner on
  492. 18:17developing and optimizing a
  493. 18:19comprehensive product backlog okay have
  494. 18:21team members explained the integration
  495. 18:23of scrum and kban principles to the
  496. 18:25product owner to enhance understanding
  497. 18:28all right
  498. 18:29recommend the product the the project
  499. 18:31team use visual management tools to
  500. 18:33improve workflow teach the product to Le
  501. 18:36how to map out process flows to better
  502. 18:37understand task sequences okay what are
  503. 18:40we going to do here so this one here
  504. 18:42test of durability in the PMP exam
  505. 18:45objectives you have to know about
  506. 18:46training people on somebody doesn't know
  507. 18:48how to do something don't do it for them
  508. 18:50the mindset tells you if somebody knows
  509. 18:52how to do something do not make them do
  510. 18:54somebody else role don't make somebody
  511. 18:56else come in and do their role teach
  512. 18:58them how to do their role and the best
  513. 19:00thing here we can do is teach the
  514. 19:01product owner hey if you're prioritizing
  515. 19:05work you're going to be using that
  516. 19:06product
  517. 19:08backlog how to begin organizing and
  518. 19:11prioritizing work it's all organizing
  519. 19:13and prioritizing work is all about in
  520. 19:15that product backlog so work with the
  521. 19:18product owner on that now have the team
  522. 19:20member explain don't give away this is
  523. 19:23part of your job notice how you're
  524. 19:24giving away to work recommend the team
  525. 19:28the team it shouldn't be here when it
  526. 19:29comes to prioritizing work that's the
  527. 19:32product owner's job the team should
  528. 19:33never prioritize a product backlog teach
  529. 19:36the product own I like this to map out
  530. 19:38process flows but this doesn't teach him
  531. 19:40about prioritizing
  532. 19:42work make an a the best
  533. 19:46answer okay how are you guys doing so
  534. 19:48far you guys uh doing okay these
  535. 19:50questions are a little difficult
  536. 19:52hopefully you know actually they're lot
  537. 19:54difficult hopefully you guys are doing
  538. 19:55well by the way don't forget to click on
  539. 19:57that subscribe button
  540. 19:59question number nine a project manager
  541. 20:02is leading a team on a critical
  542. 20:03marketing campaign for a major Pro uh
  543. 20:06product launch after unexpected last
  544. 20:09minute changes the team worked over time
  545. 20:12to meet tight deadlines the sponsors
  546. 20:14allocated a monetary award to recognize
  547. 20:16the team efforts based on the project
  548. 20:19management practice what is the most
  549. 20:20appropriate action for the project
  550. 20:22manager distribute the entire War to the
  551. 20:24team of who work the longest hours
  552. 20:26organize a team build and Retreat to
  553. 20:27enhance moral future projects use the
  554. 20:30award to fund professional development
  555. 20:32opportunity to benefit the team in
  556. 20:33future projects decide how to distribute
  557. 20:35the award based on informal feedback
  558. 20:38from the team now this is a tough
  559. 20:42question there's two choices here that I
  560. 20:44want you guys to eliminate right away
  561. 20:47distribute the word now you're giving
  562. 20:49away the entire word to one person not
  563. 20:51because you work the longest hours
  564. 20:53doesn't mean you did the most
  565. 20:55work when you're doing a question like
  566. 20:57this and I'm sure you're going to get
  567. 20:58one or two like this on the test anytime
  568. 21:01you have to create an award system
  569. 21:03there's a couple things to number one
  570. 21:04there's a couple things to keep in mind
  571. 21:05number one it has to be fair all right
  572. 21:08and number two it has to be be public
  573. 21:10you can't come up with a system and hide
  574. 21:11it from people and it has to be fairly
  575. 21:15allocated so let's see what we got so
  576. 21:17we're going to eliminate this one here
  577. 21:19right off the bat this is the throwout
  578. 21:22answer decide how to distribute based on
  579. 21:25informal feedback from the team this is
  580. 21:27probably something you want more of a
  581. 21:29feedback so we got two we're going to go
  582. 21:30away it now comes the tough
  583. 21:33one do we organize a team build and
  584. 21:36Retreat to enhance more for future
  585. 21:37projects or do we use the award to fund
  586. 21:40professional that to benefit them so
  587. 21:41which one do you think is going to
  588. 21:42benefit them more in the future the best
  589. 21:45answer here is C this one here is going
  590. 21:47to make them learn more and it's going
  591. 21:49to benefit them more in the in the
  592. 21:51future and future projects versus team
  593. 21:54building to retreat to enhance for the
  594. 21:56moral of future projects although it's
  595. 21:58not a bad answer C helps future
  596. 22:03projects next question number 10 a
  597. 22:06project manager is overseeing the
  598. 22:07construction of a new
  599. 22:09community uh Recreation Center which
  600. 22:12needs to be developed quickly to meet
  601. 22:13the community's expectation the team is
  602. 22:15skilled stakeholders are engaged and the
  603. 22:17community is excited about the new
  604. 22:20facility what should the project manager
  605. 22:22to to prioritize timely completion
  606. 22:24assign more resources to critical tasks
  607. 22:26without consulting the team develop a
  608. 22:29milestone based plan ensuring regular
  609. 22:31stakeholder involvement and
  610. 22:32communication okay monitor Daily
  611. 22:35Progress in a way that integrates input
  612. 22:36from team members to ensure alignment
  613. 22:38with project goals all right request an
  614. 22:41extension of the on the project deadline
  615. 22:43from sponsor okay there's a couple of
  616. 22:45answers here so we're building a uh a
  617. 22:48center we know that we have a lot of
  618. 22:50Engagement stakeholders skilled
  619. 22:52everybody seems to be doing great you
  620. 22:54got your team is uh skilled here you got
  621. 22:56your stakeholders are engaged
  622. 22:57everybody's exced it sounds great but we
  623. 22:59want to finish this thing quickly what
  624. 23:01can we do it's a trick question the
  625. 23:03answer here is actually B now assign
  626. 23:07more resources never do something
  627. 23:09without consulting the team especially
  628. 23:11the team is doing the work so that was a
  629. 23:12throwout answer there's no need to
  630. 23:13request a deadline unless you're going
  631. 23:15to go over to the
  632. 23:17schedule those two answers are
  633. 23:19automatically
  634. 23:20eliminated now monitor Daily Progress in
  635. 23:23Array that integrates input from the
  636. 23:25team this is the something daily is
  637. 23:29probably going to take up a lot of time
  638. 23:31and integrates input from the team to
  639. 23:32ensure alignment with goals okay but the
  640. 23:34best the best person to get involvement
  641. 23:36to ensure this the project is correct is
  642. 23:39stakeholder engagement stakeholder
  643. 23:42involvement a milestone base helps to
  644. 23:44keep the project on schedule and of
  645. 23:46course good
  646. 23:47communication so the key point of this
  647. 23:50question that I want you guys to
  648. 23:52understand is that in this
  649. 23:53question and a lot of these questions
  650. 23:55we're going to be doing and we have done
  651. 23:57not to take older engagement stakeholder
  652. 24:00involvement is the key to success on
  653. 24:01projects it's the key to a lot of the
  654. 24:03answers as we can see here on this
  655. 24:06question question number 11 by the way
  656. 24:09I'm just going to be reading the
  657. 24:10question and the answers the moment you
  658. 24:11see the question on the screen please
  659. 24:13pause the video answer it and then see
  660. 24:14me answer it uh with explanations all
  661. 24:17right question number 11 a project
  662. 24:20manager has begin has begun a complex
  663. 24:22airport Expansion Project although the
  664. 24:25project is in the initiating phase the
  665. 24:27sponsor keeps asking asking for concrete
  666. 24:29dates for the most important project
  667. 24:31Milestones when will the project manager
  668. 24:33be able to provide the requested
  669. 24:35information now keep in mind this
  670. 24:38question is a little confusing because
  671. 24:39it does specify that you're in that
  672. 24:42initiating section of the project but
  673. 24:44this person wants concrete dates a after
  674. 24:47the initial risk assessments are
  675. 24:48completed to estimate timelines okay at
  676. 24:52the end of the plan in Phase once detail
  677. 24:54schedule and risk assessments are
  678. 24:56completed okay Journey EX ution phase
  679. 24:59when the project is on the way and
  680. 25:01progress can be measured all right once
  681. 25:03the project Charter signed as is
  682. 25:05outlined initial Milestone answer here
  683. 25:08is going to be B now here's
  684. 25:10why first of all notice it wants the the
  685. 25:14sponsa wants concrete dates even though
  686. 25:17they're in the initiating phase of the
  687. 25:19project you cannot get concrete
  688. 25:21information in the initiating section
  689. 25:23keep in mind for your exam the
  690. 25:25initiating is all high level high level
  691. 25:27scope high level schedule high level
  692. 25:30budget high level risk all of that
  693. 25:33belongs in the project Charter itself so
  694. 25:36you have to wait till the end of Planet
  695. 25:38that's the whole objective of Planet the
  696. 25:40whole objective of planet is to spend a
  697. 25:42lot of time and determine what's the
  698. 25:45best schedule do those expert judgment
  699. 25:47do those bottomup estimations break down
  700. 25:50to work in the WBS and so on uh after
  701. 25:54initial an initial risk assessment is
  702. 25:55not going to give you concrete
  703. 25:57information to a is wrong you don't need
  704. 25:59to wait till the execution that's the
  705. 26:01point of planning now once the charter
  706. 26:04is signed it doesn't mean that any of
  707. 26:06the real planning work has got the tror
  708. 26:08signed the project is authorized but you
  709. 26:10really haven't done all the work yet
  710. 26:11it's not till the planning when you
  711. 26:13really do the work making B the best
  712. 26:16best
  713. 26:18answer question 12 a project manager is
  714. 26:21overseeing a large infrastructure
  715. 26:23project in a hierarchal organization the
  716. 26:26team members are used to receiving
  717. 26:28direct instructions and their
  718. 26:29performance reviews are based on task
  719. 26:32completion percentage after discussing
  720. 26:34with the sponsor the project manager
  721. 26:35realizes that some task needs to be
  722. 26:38reassigned to meet the next Milestone
  723. 26:40this change could be perceived as
  724. 26:42negative reflection on the current uh
  725. 26:45assignes
  726. 26:46performance what should the project
  727. 26:48manager do a assign the task to the most
  728. 26:51skilled member without farther
  729. 26:52discussion okay behold the meeting to
  730. 26:55explain the changes and collaborate on
  731. 26:56reassigning tasks all right
  732. 26:59see privately ask a senior member to
  733. 27:01take over the task and inform the others
  734. 27:03of the reassignment all right send an
  735. 27:05email to the team outlining the task
  736. 27:06changes and reasoning behind them okay
  737. 27:09follow the mindset on this particular
  738. 27:11question because if you notice in the
  739. 27:13question we have team members they're
  740. 27:15receiving direct instructions and
  741. 27:17performance reviews are based on task
  742. 27:19completion now something changed they
  743. 27:21realized that some tasks uh need to be
  744. 27:24reassigned in the next Milestone this of
  745. 27:26course can affect them so when something
  746. 27:28is affecting the team what does the
  747. 27:30mindset tell you well let's go over this
  748. 27:31here best answer is hold a meeting and
  749. 27:35explain the changes to them part of the
  750. 27:37mindset is to confront your problems
  751. 27:41right don't step away from your problems
  752. 27:43don't hide problems never hide anything
  753. 27:46from
  754. 27:47anyone notice this one is assign the
  755. 27:49task to the most skilled Team part of
  756. 27:52the mindset tells you shouldn't just go
  757. 27:53and assign task work with the team try
  758. 27:56not to do work by yourself but be
  759. 27:58collaborative and bring people into the
  760. 28:00decision-making process a you're
  761. 28:03basically doing that by yourself B now
  762. 28:07you're meeting with the team you're
  763. 28:08working with them never give away your
  764. 28:10work I keep saying this over and over in
  765. 28:12all my mindset videos never give away
  766. 28:14your work never actually tell somebody
  767. 28:17else to do it never ask a sponsor never
  768. 28:19ask the the pmo Never Give It Away to a
  769. 28:22senior team member send an email to the
  770. 28:25outline and the changes and the reason
  771. 28:27although I like like this
  772. 28:30notice B and D is basically the same
  773. 28:32thing in this one you're sending an
  774. 28:34email and you're letting them know the
  775. 28:36reason in this when you're holding a
  776. 28:38meeting and you're working in a
  777. 28:40collaboration so which way is better
  778. 28:41sending out an email or working with the
  779. 28:43team in a collaborative manner B is
  780. 28:47definitely better than
  781. 28:49C question 13 a project manager is
  782. 28:53leading a City Park renovation project
  783. 28:55during a status meeting with City
  784. 28:56officials the project manager provides
  785. 28:58an update about a significant
  786. 29:00deliverable some of the officials
  787. 29:02claimed they were not informed about
  788. 29:04this deliverable what should the project
  789. 29:06manager do next confirm if the scope
  790. 29:08statement have been updated to include
  791. 29:10the deliverable okay meet with these
  792. 29:13officials to review the communication
  793. 29:15plan and cify deliverables all right
  794. 29:17check the attendance records of these
  795. 29:18officials at prior project meetings Okay
  796. 29:21d review the project documents to ensure
  797. 29:23the deliverable was communicated follow
  798. 29:26the mindset once again on this one here
  799. 29:27let's see what it says here best answer
  800. 29:29here guys is going to be once again is
  801. 29:32to confront your problems if you have
  802. 29:34something on your project that's going
  803. 29:35on that you feel is negative meet with
  804. 29:38people talk to people is going to be the
  805. 29:40best answer now there's one thing I want
  806. 29:43to point out here is if something seems
  807. 29:45like you're doing it out of malicious
  808. 29:47reasons or something seems like it's
  809. 29:49it's going to negatively impact the
  810. 29:51project it's probably not going to be
  811. 29:53the answer that's what C is notice check
  812. 29:56the attendance records of these people
  813. 29:57attended meetings it seems like you're
  814. 30:00checking to see if they show up so you
  815. 30:01can like crucify them or prosecute them
  816. 30:04or something like that probably not the
  817. 30:06best answer confirm if the project scope
  818. 30:09has been updated to include the
  819. 30:11deliverable well the best thing here to
  820. 30:14do is before you do that meet with them
  821. 30:15and make sure that they even know what
  822. 30:17they're talking about or what if they
  823. 30:19understand what this deliverable is
  824. 30:20about review the project documentation
  825. 30:22to ensure the deliverable was
  826. 30:26communicated before you do this this all
  827. 30:28right before notice it says what you do
  828. 30:30next before you do this meet with them
  829. 30:33first make sure you review the
  830. 30:35communication plans with them all right
  831. 30:38question number 14 a project manager is
  832. 30:41overseeing the construction of a new
  833. 30:43office buildin a key stakeholder
  834. 30:45complains that they never received the
  835. 30:47structural Integrity test status report
  836. 30:49the project manager provides the report
  837. 30:51and the stakeholder notices that an
  838. 30:53important aspect of the structure was
  839. 30:56not tested what tool should the project
  840. 30:58manager have used to prevent this
  841. 31:01situation the communication log
  842. 31:04requirements traceability Matrix
  843. 31:07stakeholder register or the quality
  844. 31:09management
  845. 31:11plan okay so let's take a look at the
  846. 31:14answer here notice you're looking for
  847. 31:16prevent something like this from
  848. 31:17happening so you got to go back in time
  849. 31:19watch the keyword is prevent here so we
  850. 31:21got to go back in time and the best
  851. 31:23answer here is going to be stolder
  852. 31:26register this was a tough one I agree if
  853. 31:28you got this one wrong don't feel bad
  854. 31:30notice a key stakeholder the main
  855. 31:32complaint is what they never received
  856. 31:36the test report they never received the
  857. 31:39report
  858. 31:41now what document outlines the
  859. 31:44communication needs of a particular
  860. 31:47stakeholder it's the stakeholder
  861. 31:49register not the communication
  862. 31:51management plan the communication
  863. 31:53management plan tells what communication
  864. 31:56will take place at what time
  865. 31:58when it's going to take place how it's
  866. 31:59going to take place who's going to set
  867. 32:01it who's going to give it to them the
  868. 32:02stakeholder register is a different
  869. 32:04document this one says who the
  870. 32:05stakeholders are and their communication
  871. 32:08requirements so this makes it the best
  872. 32:10answer now a communication log is all
  873. 32:12Communications on the project this is
  874. 32:14telling us what happened this is not
  875. 32:16going to prevent this from happening The
  876. 32:18traceability Matrix tell us who gave us
  877. 32:21what requirement that's not going to
  878. 32:23help you in this particular one it's not
  879. 32:24asking for that the whole problem is
  880. 32:26somebody didn't get a communication
  881. 32:28the quality management plan says how you
  882. 32:30plan to meet your quality requirements
  883. 32:32this is not a quality requirement thing
  884. 32:34here this is more of a somebody didn't
  885. 32:36get a particular
  886. 32:39report question 15 a project manager is
  887. 32:43overseeing the development of a new
  888. 32:44Health Care Facility the project team is
  889. 32:47struggling to understand some critical
  890. 32:49aspects of the project scope a senior
  891. 32:52subject matter expert from the
  892. 32:53organization headquarter is available
  893. 32:55for one week what should the project
  894. 32:57manager do to benefit from theem
  895. 33:00presence all right a conduct a workshop
  896. 33:03with the to address the team challenges
  897. 33:05all right discuss with the the specific
  898. 33:08scope issues the team is facing okay
  899. 33:11arrange for the to provide training
  900. 33:13sessions to the team all
  901. 33:15right have the to review the project
  902. 33:17documentation for alignment okay so this
  903. 33:20one here follow the mindset on this one
  904. 33:22to get this one correct and the best
  905. 33:24answer
  906. 33:25is if you got C you are doing it correct
  907. 33:29okay here's why I tell I keep telling
  908. 33:31you guys you need to be collaborative
  909. 33:35you need not don't do things by yourself
  910. 33:38if you're not included the team and
  911. 33:40you're just doing the work by yourself
  912. 33:42and you're making your own decision it's
  913. 33:43probably not the best answer that's not
  914. 33:45good servant leadership that's more of
  915. 33:46like a being like a dictator and you're
  916. 33:48making all the decisions for the team so
  917. 33:50let's go through this notice this one is
  918. 33:53conduct a workshop with the to address
  919. 33:55the team challenges this is you're doing
  920. 33:58a workshop with the it doesn't say you
  921. 34:00include the team here this is just you
  922. 34:02and the working
  923. 34:05together if you're going to be
  924. 34:06addressing the team challenges it's best
  925. 34:08to have the team involved in your
  926. 34:09Workshop but that's not what that is
  927. 34:11discuss with the SM the specific scope
  928. 34:13once again you're not involved in the
  929. 34:16team have the before you have them
  930. 34:18review the doc meet with the team if
  931. 34:21you're going to only have the for a week
  932. 34:23there's nothing here that says uh review
  933. 34:26that is there is that there's an
  934. 34:27alignment problem all right that they're
  935. 34:31just having some critical aspects of the
  936. 34:32scope but we're not sure what the
  937. 34:34alignment is so the best thing is bring
  938. 34:36the if you have an bring them in to help
  939. 34:38train the team so that way they can have
  940. 34:40a better understanding of the project
  941. 34:44scope question number 16 a project
  942. 34:48manager is leading an agile project
  943. 34:50developing a new customer relation
  944. 34:52management
  945. 34:53system Midway through the project the
  946. 34:55team receives feedback from the legal
  947. 34:57team regarding new data protection laws
  948. 35:00that the project might adhes
  949. 35:03to which two action should the project
  950. 35:06manager take next all right I want to
  951. 35:08point out that this is a multi- uh
  952. 35:11selection question and you're going to
  953. 35:12be doing what's next all right direct
  954. 35:14the product owner to prioritize the data
  955. 35:16protection features and future Sprints
  956. 35:18okay request detailed information with
  957. 35:19new laws from the legal department all
  958. 35:21right have the legal team implement the
  959. 35:24compliance measures all right plan the
  960. 35:26immediate integration compliance
  961. 35:28requirements to mitigate any legal
  962. 35:30issues all right conduct an impact
  963. 35:32analysis for the team to understand how
  964. 35:34this law affects your project basically
  965. 35:37okay what did you get best answer here
  966. 35:40remember to choose two the first one I
  967. 35:42got is B and the second one I got is C
  968. 35:46here's why now before we take action
  969. 35:50before this law is implemented the first
  970. 35:52thing you guys got to do is you guys got
  971. 35:54to say what is this law about so let's
  972. 35:56go and learn about the law
  973. 35:58the next thing you got to do is before
  974. 35:59something is implemented you got to
  975. 36:01understand how it's going to impact the
  976. 36:02project that's e those are the two
  977. 36:05answers
  978. 36:06now once you do B and
  979. 36:09E maybe then you want to speak to the
  980. 36:12product
  981. 36:13owner uh maybe then you want to plan how
  982. 36:15to integrate this all into the project
  983. 36:18all right that's what you got to
  984. 36:19remember don't take an action just like
  985. 36:22that assess the situation see what's
  986. 36:24going on understand what's happening
  987. 36:26around you before taking an action this
  988. 36:29is a type of an action notice your
  989. 36:31talent to prioritize the work you just
  990. 36:34can't implement the compliance measures
  991. 36:37without understanding that C and D
  992. 36:39without understanding how it's going to
  993. 36:40affect your project making B and E the
  994. 36:43best
  995. 36:45answer question number 17 a project
  996. 36:49manager is initia a new software
  997. 36:51development project for a client known
  998. 36:53for their vague requirements and
  999. 36:55challenging communication all sit sound
  1000. 36:57align this so this client always gives
  1001. 36:59you vague requirements and it's hard to
  1002. 37:01communicate the previous interactions
  1003. 37:03with this clients have led to
  1004. 37:04misunderstanding about the scope okay
  1005. 37:07what strategy should the project manager
  1006. 37:08Implement to prevent this so you're
  1007. 37:10looking to what can we do to stop this
  1008. 37:11from even
  1009. 37:13happening apply a phase development
  1010. 37:15approach to validate the scope at each
  1011. 37:18at each Milestone okay collaborate with
  1012. 37:21a product owner to establish a clear
  1013. 37:23minimum viable product all right enhance
  1014. 37:26team client communication ation protocol
  1015. 37:28to ensure better Clarity and feedback
  1016. 37:30okay sounds good Implement a strict
  1017. 37:32deliverable schedule schedules to force
  1018. 37:35Clarity and client interaction all right
  1019. 37:37follow the mindset on this but you have
  1020. 37:39to know your agile practices in order to
  1021. 37:41get this one correct because the best
  1022. 37:42answer here is going to be be the
  1023. 37:45minimum viable product and your exam
  1024. 37:47likes this concept of minimum viable
  1025. 37:49product before I I get before I give you
  1026. 37:51the answer why there's one answer you
  1027. 37:53should have
  1028. 37:55eliminated if you ever get a question
  1029. 37:58and some of the choices sounds negative
  1030. 38:00like forcing people telling people they
  1031. 38:03have to do
  1032. 38:04something it's probably never going to
  1033. 38:06be the right answer if you're firing
  1034. 38:08somebody it's never going to be the
  1035. 38:10right answer never be negative if
  1036. 38:12something sounds negative or sounds bad
  1037. 38:15or sounds like you're pushing people to
  1038. 38:17do something probably not the right
  1039. 38:19answer let's see notice this Choice here
  1040. 38:23says Implement strict deliverables to
  1041. 38:25force CL never do anything to force
  1042. 38:29anyone throw that right off the bat a
  1043. 38:31phase development approach to validate
  1044. 38:33the scope well this notice at the end of
  1045. 38:36each Milestone Milestones can take a
  1046. 38:37long
  1047. 38:39time you want something much more
  1048. 38:41quicker now this is where this question
  1049. 38:43got tricky a good percentage of you
  1050. 38:46probably went with C notice this one
  1051. 38:50here is team client communication so I
  1052. 38:52like this answer better Clarity and
  1053. 38:55feedback I like this good but you know
  1054. 38:58what's better you know what is better
  1055. 39:00than just speaking with the client is
  1056. 39:02giving them a product and have them give
  1057. 39:04you back feedback notice vague
  1058. 39:08requirements vague requirements the way
  1059. 39:10to beat vague requirements is with a
  1060. 39:12minimum viable product keep in mind what
  1061. 39:15a minimum viable product is it's a
  1062. 39:17product that you release to your
  1063. 39:18customers that has very it has basic
  1064. 39:21usable functionality but it doesn't have
  1065. 39:23all the functionality when you give this
  1066. 39:25to the clients they're more likely to
  1067. 39:27use it and they'll tell you what they
  1068. 39:29like and what they don't like so this is
  1069. 39:32really good because what this does is
  1070. 39:34that it really pushes the client to tell
  1071. 39:37you things to change things to update
  1072. 39:40things to remove the best way to get
  1073. 39:43somebody involved is is to give them the
  1074. 39:44thing to use versus communicating just
  1075. 39:47communicating with them so the best
  1076. 39:50answer here is going to be your minimum
  1077. 39:52viable
  1078. 39:54product 18 in the middle of software
  1079. 39:58development project following a
  1080. 40:00predictive uh life cycle a significant
  1081. 40:03portion of the software is set for
  1082. 40:04incremental delivery to the client the
  1083. 40:07experienced team responsible for this
  1084. 40:09portion has expressed the desire to take
  1085. 40:11on more decision-making responsibilities
  1086. 40:13traditionally handled by the project
  1087. 40:15manager after each delivery what should
  1088. 40:18you do a schedule a meeting with Senior
  1089. 40:20Management to seek their guidance or
  1090. 40:22adjust in the decision-making process B
  1091. 40:25support the team initiatives to take on
  1092. 40:27decision-making responsibilities while
  1093. 40:29retaining final approval authority C
  1094. 40:32maintain the traditional decision-making
  1095. 40:34structure with the project man receives
  1096. 40:35all decisions regardless of team's uh
  1097. 40:39Readiness D consult with sponsor explore
  1098. 40:42the option of delegating key postd
  1099. 40:44delivery decisions with the team choose
  1100. 40:46the best answer don't forget this is a
  1101. 40:48predictive or a traditional life cycle
  1102. 40:50best answer here the mindset should have
  1103. 40:52eliminated a couple choices right off
  1104. 40:54the bat for you such as go on a senior
  1105. 40:57management never go to Senior Management
  1106. 40:58for guidance they hired you to do the
  1107. 41:00project not for you to go and ask them
  1108. 41:02how to do it so is your sponsorer that's
  1109. 41:05a type of Senior
  1110. 41:06Management the sponsor wants the output
  1111. 41:09they don't need they don't need to come
  1112. 41:10and help you do your project never give
  1113. 41:12away your work now you got two answers B
  1114. 41:16support the team initiatives on
  1115. 41:17decision- making sounds good maintain
  1116. 41:19the
  1117. 41:20traditional if you get a question on
  1118. 41:23your exam and the choice one of the
  1119. 41:25choices says leave it alone don't do
  1120. 41:28anything um like maintain the TR
  1121. 41:32maintain a plan maintain the current
  1122. 41:33structure if you read the choice and it
  1123. 41:35seems like okay this choice is not doing
  1124. 41:37anything to the question it's leaving
  1125. 41:40whatever they were doing before it's not
  1126. 41:42the answer so you notice maintain this
  1127. 41:45traditional decision-making structure so
  1128. 41:48then you're not this answer really
  1129. 41:50doesn't do anything to the question
  1130. 41:52making this the best answer bring the
  1131. 41:54team support the team right support the
  1132. 41:57team team Initiative for making but
  1133. 41:58remember it is a predictive project and
  1134. 42:01in the predictive project you probably
  1135. 42:03have that final critical decision making
  1136. 42:05in an agile project is generally the
  1137. 42:07team using it remember agile project
  1138. 42:10really utilize that servant leader
  1139. 42:11mentality versus traditional project
  1140. 42:14probably
  1141. 42:17not 19 a project manager is overseeing
  1142. 42:20the development of a new software tool
  1143. 42:22although the tool isn't fully finished
  1144. 42:24the product owner has decided to release
  1145. 42:26an early version the minimum viable
  1146. 42:28product a key stakeholder the vice
  1147. 42:31president of marketing is unhappy with
  1148. 42:32the limited feature in in the launch
  1149. 42:35what should the produ project manager do
  1150. 42:37to ensure a better satisfaction for your
  1151. 42:39future release so they're asking what
  1152. 42:41can we do now to fix problems later work
  1153. 42:45with the team and stakeholders to adjust
  1154. 42:47future
  1155. 42:48release uh future release timelines
  1156. 42:50based on expectations okay set up a
  1157. 42:54process where stakeholders can provide
  1158. 42:56feedback before future releases are
  1159. 42:58finalized all right take control of the
  1160. 43:00communication with the stakeholders to
  1161. 43:01ensure everyone understands ask the
  1162. 43:03sponsor to resolve the disagreement
  1163. 43:05between the product owner and the vice
  1164. 43:06president of marketing okay best answer
  1165. 43:09here you could use the mindset and
  1166. 43:10eliminate a couple of these choices
  1167. 43:12right off the bat let's see what the
  1168. 43:13best answer here is now work with the
  1169. 43:17team notice that you know if you're if
  1170. 43:19you're going through these questions and
  1171. 43:21you're up to number 20 you've done the
  1172. 43:23first 10 you you you're getting the
  1173. 43:25theme here right you're always working
  1174. 43:27with people you're always collaborating
  1175. 43:29with someone you're meeting with the
  1176. 43:31team you're meeting with the sponsor
  1177. 43:33right uh to get the project approve all
  1178. 43:36right don't go to the sponsor to to help
  1179. 43:38you with your work so always collaborate
  1180. 43:42notice D act a sponsor to resolve never
  1181. 43:45give away your work don't go to the
  1182. 43:46sponsor and says go do this never do
  1183. 43:48that take control notice this take
  1184. 43:51control where take now you
  1185. 43:55are it's an agile project how do you
  1186. 43:57know well they're using a minimum viable
  1187. 43:59product all right it doesn't necessarily
  1188. 44:01have to say it's an agile project but by
  1189. 44:03reading this you can tell it's an agile
  1190. 44:05project when it's an agile project you
  1191. 44:07should be working with the team be a
  1192. 44:08servant leader on that agile project if
  1193. 44:11you start taking control of stuff you're
  1194. 44:13not really a servant leader at that
  1195. 44:15point so let's eliminate that set up a
  1196. 44:17process St can provide although I like
  1197. 44:19this the team should be involved in
  1198. 44:23it uh so this is a good answer but it
  1199. 44:26let the team bring people in notice
  1200. 44:28you're setting up the process by
  1201. 44:30yourself here probably not a good idea
  1202. 44:32let's bring the team in let's bring the
  1203. 44:34stakeholders in because in this one
  1204. 44:35you're working with the team and the
  1205. 44:37stakeholders to adjust future timelines
  1206. 44:40all right all right last question in
  1207. 44:42this
  1208. 44:44video question 20 a project manager is
  1209. 44:47overseeing an adile project for
  1210. 44:49developing a new mobile application
  1211. 44:51within a large tech company initially
  1212. 44:53the project manager planned to use email
  1213. 44:55for all project communication
  1214. 44:57however the product owner suggest using
  1215. 44:59a specialized project management tool
  1216. 45:02that better integrates with agile
  1217. 45:04workflow what should the project manager
  1218. 45:06do okay so in this question the product
  1219. 45:09owner wants you to use a particular tool
  1220. 45:11on your project what do we
  1221. 45:13do a evaluate how the new communication
  1222. 45:16tool could impact the current timelines
  1223. 45:18and workflow before making a decision
  1224. 45:20okay update the communication management
  1225. 45:22plan to fully adapt the products owner's
  1226. 45:24preferred tool and inform the team of
  1227. 45:26the change all right have the team test
  1228. 45:29the proposed tool on a small part of the
  1229. 45:31project before deciding whether to
  1230. 45:33implement it across the
  1231. 45:35team D continue using email for major
  1232. 45:39announcement but use the new tool for
  1233. 45:41daily agile interactions with the team
  1234. 45:44now the mindset should have eliminated
  1235. 45:47almost every choice and given you the
  1236. 45:49full answer hopefully you guys got this
  1237. 45:51one correct let's go see why some of
  1238. 45:53these choices was pretty easily
  1239. 45:55eliminated making the end
  1240. 45:57C here's why Number One D get rid of
  1241. 46:01this because in this one nothing is
  1242. 46:03really happening you're still using this
  1243. 46:05and the product owner wants you to use
  1244. 46:07their specialized tool by you doing D
  1245. 46:10you're not giving a product owner
  1246. 46:11anything you're not really assessing
  1247. 46:12much and you're making the decisions all
  1248. 46:14by yourself you're making a decision to
  1249. 46:16use the email you're making a decision
  1250. 46:19to only use the tool part of it a
  1251. 46:23notice uh before making a decision once
  1252. 46:25again you're making a decision you're
  1253. 46:27not getting anyone involved you're
  1254. 46:29evaluating it you're doing this by
  1255. 46:31yourself you're not being that servant
  1256. 46:32leader you're not
  1257. 46:34collaborating update the communication
  1258. 46:36manag now you're just implementing the
  1259. 46:37tool you're just bypassing a whole team
  1260. 46:39here you're like hey you know what I'm
  1261. 46:40just going to implement this you guys
  1262. 46:43you guys can pound salt or Rock what's
  1263. 46:45that say you guys can pound salt you
  1264. 46:47guys can pound sand there you go you
  1265. 46:49guys can pound sand we're going to be
  1266. 46:50doing this versus C says have the team
  1267. 46:54tested bring them and let them decide
  1268. 46:57whether it's good to implement all right
  1269. 47:00here we go guys question number 21 by
  1270. 47:02the way I do want to point out that uh
  1271. 47:04if you haven't take a look at the other
  1272. 47:06videos see how you're doing on these
  1273. 47:07Ultra hard questions these questions are
  1274. 47:09purposely made to be difficult these are
  1275. 47:12probably going to be more difficult than
  1276. 47:14you would see on the actual test let's
  1277. 47:17keep going all right question number 21
  1278. 47:20during the development of a new
  1279. 47:21cloud-based analytical platform the team
  1280. 47:24has risen concerns about certain product
  1281. 47:27backlog items that are challenging to
  1282. 47:30implement due to Technical and resource
  1283. 47:32limitations what should the project
  1284. 47:34manager recommend for the product owner
  1285. 47:36to do now this is a good question
  1286. 47:39because if you notice on this particular
  1287. 47:41question you have a problem and then
  1288. 47:44it's asking what the product owner
  1289. 47:46should do with a particular problem it's
  1290. 47:48a very unique question a prioritize and
  1291. 47:50address the impediment based on the
  1292. 47:52impacts on the most valuable features on
  1293. 47:55the platform okay conduct a risk
  1294. 47:57assessment to evaluate how the
  1295. 47:59impediment might affect the project
  1296. 48:01timeline all right Implement a phase
  1297. 48:05based approach to solving the issue
  1298. 48:07starting with those imp that those that
  1299. 48:09impact the current Sprint remove the
  1300. 48:11items and add new items okay so what
  1301. 48:15should we be doing here now first of all
  1302. 48:18I want you guys to realize that it says
  1303. 48:21it's asking what the project manager
  1304. 48:24should recommend the product owner do
  1305. 48:27and this alone tells you the answer to
  1306. 48:29this if you read carefully you should
  1307. 48:31have gotten a here's why because first
  1308. 48:34of all you should eliminate some some
  1309. 48:37choices number one you should never just
  1310. 48:39remove items because of problems if
  1311. 48:41those items are high value items you
  1312. 48:44shouldn't just go about removing them
  1313. 48:46maybe you should solve those problems
  1314. 48:48first maybe if you can never solve them
  1315. 48:50maybe then you can remove them but let's
  1316. 48:52get get rid of this Implement a
  1317. 48:55phase-based approach
  1318. 48:57uh to solve the to solving the issues
  1319. 49:00starting with the impact on the current
  1320. 49:01Sprint there's not much here about that
  1321. 49:03current Sprint conduct the risk
  1322. 49:05assessment you're not going to ask the
  1323. 49:07product owner to conduct the risk
  1324. 49:09assessment that's something you and the
  1325. 49:11team should be doing don't recommend the
  1326. 49:12product owner to do it the product owner
  1327. 49:15is really responsible to prioritize the
  1328. 49:18work and the product backlog right now
  1329. 49:21what they should be doing the product
  1330. 49:22owner should be taught that you know
  1331. 49:24what maybe you want to change the
  1332. 49:26priority based on some of those impact
  1333. 49:28on there so work with the product owner
  1334. 49:30on this making that the best
  1335. 49:33answer all right question
  1336. 49:3622 a project manager new to Agile
  1337. 49:40methodologies is overseeing the
  1338. 49:42development of a software tool observing
  1339. 49:45that other projects stumble without a
  1340. 49:48well- defined scope and completion
  1341. 49:50criteria leading to continuous scope
  1342. 49:52expansion the project manager wants to
  1343. 49:55prevent similar issues what proactive
  1344. 49:57steps should the project manager take to
  1345. 50:00establish Clarity and prevent scope
  1346. 50:03creep okay good question they're really
  1347. 50:05asking here uh about preventing scope
  1348. 50:09creep okay create a detailed timeline
  1349. 50:12with Milestones to monitor project
  1350. 50:14progress and control
  1351. 50:16changes okay introduce a rigorous change
  1352. 50:19management process to evaluate and
  1353. 50:21approve additional features okay promote
  1354. 50:24regular synchronization meetings between
  1355. 50:26the project team to discuss project
  1356. 50:28schedule and what work to do first all
  1357. 50:30right organize workshops with all
  1358. 50:32stakeholders to collaboratively create
  1359. 50:36the project Charter and clearly define
  1360. 50:38the definition of done okay guys this I
  1361. 50:42thought was a pretty easy question
  1362. 50:44here's why and but it's still difficult
  1363. 50:46but I thought it was pretty easy and the
  1364. 50:47reason why is because if you notice it's
  1365. 50:50an agile
  1366. 50:53project if you're following agile
  1367. 50:56methodology IES you're not going to have
  1368. 50:58a rigorous change management approach
  1369. 51:01you're not going to be just controlling
  1370. 51:03changes like
  1371. 51:04that c is not a bad answer but C is
  1372. 51:08talking about the
  1373. 51:09schedule right discuss project schedule
  1374. 51:12not the work right this is about scope
  1375. 51:15creep so let's get rid of that now what
  1376. 51:18addresses scope creep what
  1377. 51:21addresses uh Clarity on the scope
  1378. 51:25there's nothing that in my opinion that
  1379. 51:27does a better job of addressing the
  1380. 51:30clarity of the work than a minimum
  1381. 51:33viable product and a definition of done
  1382. 51:36so in this one here we have the
  1383. 51:38definition of done because if you notice
  1384. 51:40the definition of done is really when
  1385. 51:41they Define what is it that they
  1386. 51:43actually want how does the team know
  1387. 51:44when they're finished how does how how
  1388. 51:46does the team know what our product has
  1389. 51:48hit a certain criteria or a certain
  1390. 51:50performance or look a certain way for
  1391. 51:52them to be done best answer is d
  1392. 51:5823 throughout a project it becomes
  1393. 52:01apparent that team members from
  1394. 52:03different departments have different
  1395. 52:05different perspectives on what the final
  1396. 52:07outcome of the project should be what
  1397. 52:10should the project manager do first
  1398. 52:13facilitate a session to revise and
  1399. 52:16clarify the project goal with the entire
  1400. 52:19team okay meet with the sponsor to
  1401. 52:21ensure alignment to the project
  1402. 52:23objectives all right make sure the
  1403. 52:25project outcome is aligned with the
  1404. 52:27project Charter and scope statement all
  1405. 52:29right assign the department heads the
  1406. 52:32responsibility of resolving the issue
  1407. 52:34okay so in this particular one keep in
  1408. 52:36mind what are you going to do first all
  1409. 52:38right you have team members from
  1410. 52:40different departments they have
  1411. 52:41different perspectives what should we do
  1412. 52:43first best answer here is to bring them
  1413. 52:46together
  1414. 52:47yes part of the mindset when it comes to
  1415. 52:50this exam is bring people together and
  1416. 52:55solve problems don't go away from them
  1417. 52:58don't run from a problem never kick the
  1418. 53:00can down the road in other words don't
  1419. 53:02give away the problem or push the
  1420. 53:04problem off and never do nothing all
  1421. 53:06right if one of the choices says leave
  1422. 53:07the problem fix it later it's never the
  1423. 53:09answer so you notice in this one
  1424. 53:12here we have facilitate session to
  1425. 53:16clarify the goals let's bring everybody
  1426. 53:18together and let's have everybody
  1427. 53:20understand what the problem is never go
  1428. 53:22to the sponsor meet to a sponsor to
  1429. 53:25ensure a line the sponsor already knows
  1430. 53:27the objectives this has nothing to do
  1431. 53:29with the sponsor this is team members
  1432. 53:31this doesn't address the problem make
  1433. 53:33sure the outcome is aligned with the
  1434. 53:34charter and scope statement this is a
  1435. 53:36problem with team members assign the
  1436. 53:39department there's nothing here with
  1437. 53:40department heads it's with the team
  1438. 53:41members best answer here was
  1439. 53:44a 24 a project manager is overseeing the
  1440. 53:48construction of a new manufacturing
  1441. 53:50facility when an econom economic
  1442. 53:52downturn May suddenly threaten the
  1443. 53:55projects
  1444. 53:57viability what should the project
  1445. 53:58manager do adjust the Project's
  1446. 54:01Financial forecast to account for the
  1447. 54:03economic downturn suggest to the
  1448. 54:05sponsorer that the project should be
  1449. 54:07postponed redirect some project
  1450. 54:09resources to support other essential
  1451. 54:12projects identify and document a new
  1452. 54:13risk and create a re and create
  1453. 54:16mitigation strategies all right let's
  1454. 54:18see what the answer is now this one not
  1455. 54:20that difficult you have to read
  1456. 54:21carefully when you look at questions
  1457. 54:23look at this you have to look and
  1458. 54:25understand that with you see something
  1459. 54:27that says may when you look at something
  1460. 54:29that says might that's a risk if you see
  1461. 54:33something that will
  1462. 54:34happen or or has happened and it's
  1463. 54:37affecting a project that's an issue so
  1464. 54:39in this particular one since we know
  1465. 54:41this is a risk we're going to have to
  1466. 54:43identify which we're doing here we want
  1467. 54:45to document this new risk probably in
  1468. 54:48the risk register and then we want to
  1469. 54:49create a mitigation strategy to how to
  1470. 54:52address it now I want you guys to
  1471. 54:54understand that
  1472. 54:56you shouldn't take an action just like
  1473. 54:58that the project manager mindsets says
  1474. 55:01don't take an action right away right
  1475. 55:04you notice for first of all this is a
  1476. 55:07construction project so it's more likely
  1477. 55:09a traditional project and because it's a
  1478. 55:11traditional project you never take
  1479. 55:13actions right away because if you go and
  1480. 55:15you change a plan you change a schedule
  1481. 55:17you change a scope you're going to need
  1482. 55:19what a change request and none of the
  1483. 55:21other choices even begins to address
  1484. 55:23that so the best answer here is this
  1485. 55:25notice this is an action notice never go
  1486. 55:29to the sponsor or never postpone a
  1487. 55:31project just like that you have to
  1488. 55:33assess it do can't just redirect
  1489. 55:35resources you're basically shutting the
  1490. 55:36project
  1491. 55:38down 25 a project manager is starting a
  1492. 55:41highway Expansion Project the State
  1493. 55:44Transportation Department requested an
  1494. 55:46initial environmental impact assessment
  1495. 55:48after after which they'll
  1496. 55:51decide whether to continue a team member
  1497. 55:55suggests planning for the full Project
  1498. 55:57based on past Trends what should the
  1499. 55:59project manager do first notice
  1500. 56:02first advise the team member to focus on
  1501. 56:05the current deliverable okay review the
  1502. 56:08charter to confirm the high level scope
  1503. 56:10all right develop a detail plan for the
  1504. 56:12entire project for the entire Project
  1505. 56:14based on history all right confirm with
  1506. 56:16the stakeholders and plan the full
  1507. 56:18project scope this was a very tough
  1508. 56:21question there was one choice you could
  1509. 56:23have eliminated and I'm just going to
  1510. 56:24eliminate it right off the bat never do
  1511. 56:26nothing thing this one here shuts down
  1512. 56:27the team say just do the current work
  1513. 56:30the problem with this thing here is that
  1514. 56:32you're starting a project right it's
  1515. 56:35still in that initiating phase now what
  1516. 56:39you should be doing first is assess
  1517. 56:43review look at things don't take an
  1518. 56:45action right away notice that this is an
  1519. 56:49action confirm with the stakeholders and
  1520. 56:53plan the full scope you have you can't
  1521. 56:54do that you have to wait for this
  1522. 56:56assessment to be
  1523. 56:58done the best thing here you can do is
  1524. 57:01just review the scope and confirm the
  1525. 57:03high level scope for now and wait until
  1526. 57:05the assessment is done if not you
  1527. 57:07wouldn't be able to proceed on the
  1528. 57:09project this was a very tricky
  1529. 57:11question uh it was trying to push you to
  1530. 57:13do something that you shouldn't be doing
  1531. 57:16but keep in mind it says what to do
  1532. 57:17first and you know one of the things you
  1533. 57:19never do first is just take an
  1534. 57:21action right off the bat
  1535. 57:2426 a project manager is overseeing the
  1536. 57:27upgrade of an old manufacturing system
  1537. 57:30to a new automated solution aligning
  1538. 57:33with the organizational operational
  1539. 57:36process changes the project Charter is
  1540. 57:38approved and the pmo has provided
  1541. 57:40templates for all new projects what
  1542. 57:43should the project manager
  1543. 57:45prioritize well what are we going to be
  1544. 57:47prioritizing here all right so we just
  1545. 57:49started this new thing we got the
  1546. 57:51charters approved pmos approved the
  1547. 57:53template choices a align the project
  1548. 57:57plan with the organization strategic
  1549. 57:59goals working closely with Senior
  1550. 58:01Management
  1551. 58:02okay develop a training and
  1552. 58:04communication management plan in turn
  1553. 58:06collaboration with the team all right
  1554. 58:09collaborate a detailed budget and
  1555. 58:11schedule regular reviews with the
  1556. 58:13finance team okay collaborate with the
  1557. 58:16operation departments to minimize
  1558. 58:18disruption during the upgrade this was a
  1559. 58:19tricky question you notice the charter
  1560. 58:22is
  1561. 58:23approved you have all the templates what
  1562. 58:26should you prioritize well the next
  1563. 58:28thing you do is make the plan right so
  1564. 58:30which one here is going to help you make
  1565. 58:31a plan and who should you make the plan
  1566. 58:33with that's the that's how you're going
  1567. 58:35to get the answer the answer here is B
  1568. 58:38here's
  1569. 58:39why align the plan with the Strategic
  1570. 58:43goals cool but you're never going to
  1571. 58:45work with Senior Management on a plan
  1572. 58:47Senior Management doesn't sit there and
  1573. 58:48help you come up with detailed plans
  1574. 58:51remember a project plan is a very
  1575. 58:53detailed
  1576. 58:54document now create a detailed budget
  1577. 58:57with the finance department you do this
  1578. 58:58with your team not the finance
  1579. 59:00department or the operation Department
  1580. 59:02what you should do is collaborate with
  1581. 59:04the team and the way to collaborate is
  1582. 59:06to have good communication so maybe one
  1583. 59:08of the first things you develop is that
  1584. 59:10communication management plan kind of a
  1585. 59:12tricky question but that is the best of
  1586. 59:14these four choices now I do want to
  1587. 59:16point out that sometimes you're doing
  1588. 59:19practice questions minds or anybody's
  1589. 59:21and you're like well that choice kind of
  1590. 59:24suck Andrew
  1591. 59:26the question is is it the best of the
  1592. 59:29four the choice doesn't have to be
  1593. 59:31amazing or the choice doesn't have to be
  1594. 59:34the only one that's correct the choice
  1595. 59:36has to be better than the other three
  1596. 59:38choices that are there if it's four
  1597. 59:40remember the game is to choose the best
  1598. 59:41choice not the correct choice and I I
  1599. 59:44keep telling students this all the time
  1600. 59:47they'll tell me Well Andrew that choice
  1601. 59:49is not going to really do anything is it
  1602. 59:52better than the other three and they'll
  1603. 59:54be like yeah it is okay then that's the
  1604. 59:55answer remember it's the best of the
  1605. 59:57four choices keep that in
  1606. 1:00:02mind
  1607. 1:00:0327 a project manager has just completed
  1608. 1:00:06the development of a new city park and
  1609. 1:00:08is preparing to transition transition
  1610. 1:00:10the project to the city maintenance uh
  1611. 1:00:13Department before closing the project
  1612. 1:00:16what should the project manager do
  1613. 1:00:17verify all project deliver has met
  1614. 1:00:20according to the project plan okay
  1615. 1:00:22conduct the final inspection with the
  1616. 1:00:23sponsor to Ure all tasks is the WBS are
  1617. 1:00:26complete
  1618. 1:00:28okay ensure all project documentation is
  1619. 1:00:30completed and archive conduct a final
  1620. 1:00:34performance review with the stakeholders
  1621. 1:00:36so really good question very difficult
  1622. 1:00:39answer best answer here is going to be B
  1623. 1:00:42now hold your horses don't go crazy I
  1624. 1:00:44know a lot of people got this one wrong
  1625. 1:00:47here it's not in closing it says before
  1626. 1:00:52closing on a traditional project
  1627. 1:00:56what do you do before closing what is
  1628. 1:00:58the process that comes before closing
  1629. 1:01:00verify scope right you should do um
  1630. 1:01:05control quality then do verify scope
  1631. 1:01:08verify scope is when you generally bring
  1632. 1:01:10the customer and or sponsorer to verify
  1633. 1:01:13the work has been done then you can
  1634. 1:01:15close the project Which choice best
  1635. 1:01:19gives you that b gives you that ensure
  1636. 1:01:23all document is complete and archived
  1637. 1:01:24that's in the Clos in final performance
  1638. 1:01:27review that's the performance of the
  1639. 1:01:29project performance not the deliverable
  1640. 1:01:31performance that's en
  1641. 1:01:33closing there were two good answers is
  1642. 1:01:35either a or b verify the objectives has
  1643. 1:01:38been met according to the plan but
  1644. 1:01:41before you do that that's also a part in
  1645. 1:01:42closing before you do that you need to
  1646. 1:01:44verify the inspection of the work in the
  1647. 1:01:47process of verify scope one of the tools
  1648. 1:01:50is inspection and the output is a
  1649. 1:01:51verified deliverable if you have no clue
  1650. 1:01:54what I'm talking about check out the
  1651. 1:01:55course check out my course link below to
  1652. 1:01:58learn all about those
  1653. 1:02:01processes before I get to uh 28 if
  1654. 1:02:05you're enjoying this video and you're
  1655. 1:02:06learning a lot how to Ace your exam can
  1656. 1:02:08you do me a quick favor can you click on
  1657. 1:02:10the like button can you um subscribe to
  1658. 1:02:12the channel it really helps us out like
  1659. 1:02:15if I'm begging you here if you can do
  1660. 1:02:16that for us would be amazing doesn't
  1661. 1:02:19cost you much it's and by the way it's
  1662. 1:02:20free to do that it's absolutely free
  1663. 1:02:22like it doesn't cost you anything to do
  1664. 1:02:24that um
  1665. 1:02:2628 a project manager needs to prioritize
  1666. 1:02:29multiple projects within a portfolio and
  1667. 1:02:32requires accurate budget estimates the
  1668. 1:02:35process must align with adob principles
  1669. 1:02:37one insuring reliable financial plan how
  1670. 1:02:40should the how should the budget for
  1671. 1:02:42each project be
  1672. 1:02:45estimated okay calculate the cost by
  1673. 1:02:48estimating individual Tas estimate for
  1674. 1:02:50the team considering the current
  1675. 1:02:52workload all right leverage the combined
  1676. 1:02:55expertise of the projects of the sponsor
  1677. 1:02:58product owner and agile coach to deive
  1678. 1:03:00budget estimates okay use analytical
  1679. 1:03:02software to model potential costs based
  1680. 1:03:05on predictive analysis and historical
  1681. 1:03:07all right have the productor conduct a
  1682. 1:03:09thorough requirements analysis with the
  1683. 1:03:10team to forecast project budget this one
  1684. 1:03:13not too difficult read the section in my
  1685. 1:03:15study guide or in the course that talks
  1686. 1:03:17about how do you do Agile estimated an
  1687. 1:03:19agile estimated is really comes down to
  1688. 1:03:22since it's heavily people built it comes
  1689. 1:03:24down to how much you're paying everybody
  1690. 1:03:26and how long they're going to be on the
  1691. 1:03:27project and how many Sprints they are
  1692. 1:03:29there's a couple there's a couple
  1693. 1:03:30answers here to to throw out have the
  1694. 1:03:33product owner conducted never give away
  1695. 1:03:35your work this is based on predictive
  1696. 1:03:38analysis no good leverage the expertise
  1697. 1:03:41of the sponsor product owner and agile
  1698. 1:03:43coach the best expertise the the actual
  1699. 1:03:46cost of the agile project lies in how
  1700. 1:03:48much money you're paying your workers
  1701. 1:03:51that's why you're going to use a it's
  1702. 1:03:53how much agile is heavily people it's
  1703. 1:03:56not so much so in a product project
  1704. 1:03:58where a lot of the cost may be
  1705. 1:04:00associated with materials like if you're
  1706. 1:04:02building a building sheetrock is going
  1707. 1:04:03to be a big cost or steal Adar projects
  1708. 1:04:06are mostly done by people so you're
  1709. 1:04:08leveraging the cost of the team make an
  1710. 1:04:11a the best
  1711. 1:04:13answer 29 a project manager is
  1712. 1:04:16overseeing a large scale agile project
  1713. 1:04:20to develop a new e-commerce platform at
  1714. 1:04:23the Project's retrospective the team
  1715. 1:04:25discusses that the product owner's
  1716. 1:04:27expectation for the Sprint deliverables
  1717. 1:04:29were not fully met what proactive
  1718. 1:04:31measure should the project manager have
  1719. 1:04:33taken initiate a kickoff project
  1720. 1:04:35Workshop to ensure all team members are
  1721. 1:04:37trained on agile tools and techniques
  1722. 1:04:40used for the project okay establish a
  1723. 1:04:43risk management framework that
  1724. 1:04:45specifically addresses potential
  1725. 1:04:47misalignments between team outputs and
  1726. 1:04:49stakeholders okay develop an integration
  1727. 1:04:52plan to systematically align development
  1728. 1:04:54work with ongoing marketing and sales
  1729. 1:04:57strategy D ensure the project vision and
  1730. 1:04:59objectives to each Sprint were
  1731. 1:05:01communicated to all team
  1732. 1:05:03members
  1733. 1:05:05okay now you have to read this one very
  1734. 1:05:09carefully all right notice join a
  1735. 1:05:11retrospective they discuss the productor
  1736. 1:05:14expectations we're not met it's it's a
  1737. 1:05:17question that's making you look
  1738. 1:05:20backwards it's what measur should have
  1739. 1:05:23been taken right it's what you got to
  1740. 1:05:25read the question do they want the
  1741. 1:05:27solutions to go forward or do they want
  1742. 1:05:29the solutions that could have fix this
  1743. 1:05:31problem in this particular one it's what
  1744. 1:05:34should have been
  1745. 1:05:36done notice if the team is working and
  1746. 1:05:39not sure of what the work should have
  1747. 1:05:42been done that should have been
  1748. 1:05:43clarified from the start they should
  1749. 1:05:45have known what the project Vision was
  1750. 1:05:47what the main objectives was that should
  1751. 1:05:49have been clearly communicated to ensure
  1752. 1:05:51all members know what you know what is
  1753. 1:05:53it that they should have been
  1754. 1:05:53accomplishing
  1755. 1:05:56this one says a uh a project kickoff
  1756. 1:05:58Workshop kickoff workshops are generally
  1757. 1:06:00done once at the beginning of the
  1758. 1:06:02project not just throughout this is not
  1759. 1:06:04a it's nothing here about
  1760. 1:06:06risk it already happened right to
  1761. 1:06:09potential
  1762. 1:06:12misalignment develop an integration plan
  1763. 1:06:14to systematically
  1764. 1:06:16align uh development work and ongoing
  1765. 1:06:19they already noce they are first of all
  1766. 1:06:22they do the standup meeting but this is
  1767. 1:06:23with marketing and sales it's the
  1768. 1:06:26product owner that's not expectation so
  1769. 1:06:28that was a throw off making D the best
  1770. 1:06:31answer all right last question in this
  1771. 1:06:33video we're doing number 30 a project
  1772. 1:06:35manager is leading the development of a
  1773. 1:06:38new customer support software support
  1774. 1:06:40Software System dur to Sprint a
  1775. 1:06:43developers encounters ambiguity
  1776. 1:06:46regarding the acceptance criteria of a
  1777. 1:06:48feature what should the project manager
  1778. 1:06:49do come be a meeting with the stering
  1779. 1:06:51committee to discuss the feature
  1780. 1:06:54initiate a discussion the discussion in
  1781. 1:06:56the next team meeting to gather
  1782. 1:06:57Collective input refer the question to
  1783. 1:06:59the technical architect to provide an
  1784. 1:07:01expert interpretation collaborate with a
  1785. 1:07:04product owner to resolve the ambiguity
  1786. 1:07:05and the acceptance criteria this one
  1787. 1:07:07here you have to understand agile
  1788. 1:07:09principles making D the best answer you
  1789. 1:07:12see you got to understand where this
  1790. 1:07:14acceptance criteria come from who
  1791. 1:07:15defines the work basically and that's
  1792. 1:07:17the product owner if the team is not too
  1793. 1:07:19sure of what the work should be the team
  1794. 1:07:22doesn't know what it should look like or
  1795. 1:07:24or how it should perform how it should
  1796. 1:07:26what report it should output that is
  1797. 1:07:30part of the product owner to help to
  1798. 1:07:31find that Mak can this the best answer
  1799. 1:07:34this is a the stering committee the
  1800. 1:07:36accepting criteria doesn't come from
  1801. 1:07:38there it comes from the from the product
  1802. 1:07:39owner and the next to gather input it's
  1803. 1:07:43not that the team is having a problem
  1804. 1:07:45it's the team to the product owner not
  1805. 1:07:47the team within themselves you don't
  1806. 1:07:49want to go to a technical architect you
  1807. 1:07:51need to go to the product owner they're
  1808. 1:07:53the one that's going to create that
  1809. 1:07:54acceptance criteria guys question 31
  1810. 1:07:58during the execution phase of a project
  1811. 1:08:00develop of a development project the
  1812. 1:08:02team encounters te a technical challenge
  1813. 1:08:05that jeopardizes the schedule the
  1814. 1:08:07scheduled delivery of key
  1815. 1:08:08functionalities the technical team has
  1816. 1:08:11indicated a delay what should the
  1817. 1:08:13project manager do next schedule an
  1818. 1:08:15emergency meeting with all stakeholders
  1819. 1:08:17to brainstorm
  1820. 1:08:19Solutions initiate a quick training
  1821. 1:08:21session for the technical team to
  1822. 1:08:23enhance their problem solving
  1823. 1:08:26capabilities record the problem its
  1824. 1:08:28impact and urgency in the project issue
  1825. 1:08:30log for struct structure tracking
  1826. 1:08:33organize a team building event to boost
  1827. 1:08:35moral and encourage Innovative thinking
  1828. 1:08:37for problem this question here is pretty
  1829. 1:08:40easy because if you notice this is not a
  1830. 1:08:43risk this is an issue now this question
  1831. 1:08:47does take a lot of the mindset though
  1832. 1:08:48because if you notice I just mentioned
  1833. 1:08:50it's an issue and if there is an issue
  1834. 1:08:52you have to make sure that you put it
  1835. 1:08:54into the issue log now I want to point
  1836. 1:08:56out a couple things here that's really
  1837. 1:08:57important to know first of all you can't
  1838. 1:09:01do training sessions on Tech to the
  1839. 1:09:04technical team the project manager
  1840. 1:09:06doesn't or generally doesn't have the
  1841. 1:09:10technical skills to train a technical
  1842. 1:09:12team this exam makes that assumption
  1843. 1:09:15that you don't have that technical skill
  1844. 1:09:17so B is definitely
  1845. 1:09:19wrong schedule an emergency meeting with
  1846. 1:09:22all I want you guys to be careful of
  1847. 1:09:24this word all all stakeholders that
  1848. 1:09:27includes Senior Management regulatory
  1849. 1:09:29bod you're going to schedule a meeting
  1850. 1:09:30with all anytime you see that word all
  1851. 1:09:33in a choice think to yourself
  1852. 1:09:36H I really have to think about this
  1853. 1:09:38because all literally means all you're
  1854. 1:09:39going to invite everybody everybody
  1855. 1:09:41every single stakeholder you probably
  1856. 1:09:43want to do this with your technical team
  1857. 1:09:46or the team themselves not with all
  1858. 1:09:50stakeholders now organize a team
  1859. 1:09:52building event there's nothing here that
  1860. 1:09:54talks about moral and encouragement the
  1861. 1:09:57team doesn't doesn't say that the team
  1862. 1:09:59is is feeling demoralized or something
  1863. 1:10:02like that so this doesn't even answer
  1864. 1:10:04the question but this is an issue and
  1865. 1:10:06this is the best way to solve
  1866. 1:10:09issues during a pivotal project phase it
  1867. 1:10:12is revealed that critical stakeholders
  1868. 1:10:14did not attend a meeting focus on
  1869. 1:10:16confirming the project strategic
  1870. 1:10:18alignment and expected business
  1871. 1:10:20benefits resulting in their feedbacks
  1872. 1:10:23being overlooked this over site had led
  1873. 1:10:26to conflicts within the decision-making
  1874. 1:10:28process what should the project manager
  1875. 1:10:31do
  1876. 1:10:32first so couple things you notice it
  1877. 1:10:35says what are you doing first initiate a
  1878. 1:10:38discussion to directly address and
  1879. 1:10:40understand the concern all right
  1880. 1:10:43distribute a detail meeting summary and
  1881. 1:10:45request written feedback from the absent
  1882. 1:10:49shareholders okay conduct a formal risk
  1883. 1:10:52assessment to evaluate the impact of
  1884. 1:10:54Missin cers input develop a contingency
  1885. 1:10:57plan to navigate potential project
  1886. 1:11:00delays or changes all right what do you
  1887. 1:11:03guys have now notice it says what should
  1888. 1:11:04you do first now anytime there's a
  1889. 1:11:07conflict on a project part of the
  1890. 1:11:09mindset it tells us is to bring people
  1891. 1:11:12together address the conflict and solve
  1892. 1:11:14the conflict this one here does exactly
  1893. 1:11:16that I mean it literally says directly
  1894. 1:11:18address and understand the root cause
  1895. 1:11:21part of the mindset is never take action
  1896. 1:11:23against a
  1897. 1:11:24problem even in the pmo guide it gives
  1898. 1:11:26you the list of things you have to do it
  1899. 1:11:28literally says understand the problem
  1900. 1:11:30before solving the problem get to the
  1901. 1:11:31root cause of the problem why are we
  1902. 1:11:33having this problem who started this
  1903. 1:11:35problem where did this problem come from
  1904. 1:11:37these are things you're thinking about
  1905. 1:11:38before solving the
  1906. 1:11:40problem now the problem here is that
  1907. 1:11:42they didn't attend the meeting never do
  1908. 1:11:45something that is that sounds negative
  1909. 1:11:49not this in B you did you're
  1910. 1:11:51Distributing a detail meeting summary
  1911. 1:11:53and request written feed Fe back from
  1912. 1:11:55the so this is kind of negative in my
  1913. 1:11:58opinion it's like well then give me
  1914. 1:12:00feedback on this you weren't
  1915. 1:12:02here this is notice a form of risk
  1916. 1:12:05analysis uh to evaluate the impact of
  1917. 1:12:08missing shareholders input this is not a
  1918. 1:12:11risk they've already missed it all right
  1919. 1:12:13this is an issue they missed it develop
  1920. 1:12:15a contingency plan to navigate potential
  1921. 1:12:17delays we're not sure what delays it yet
  1922. 1:12:20all right this is let the conflicts
  1923. 1:12:21within but it doesn't say there's only
  1924. 1:12:23any delays here this answer is a
  1925. 1:12:2933 during a critical phase of the
  1926. 1:12:31project the pivotal team member informs
  1927. 1:12:33the project manager of their impended
  1928. 1:12:36resignation intended to sub submit their
  1929. 1:12:38notice to their line manager soon this
  1930. 1:12:40Revelation comes at a time when their
  1931. 1:12:42contribution is critical to meeting the
  1932. 1:12:44Project's upcoming deadline what should
  1933. 1:12:46the project manager
  1934. 1:12:48do have a senior team member do a
  1935. 1:12:50meeting to reassess task allocation and
  1936. 1:12:53address any concern update the project
  1937. 1:12:55risk register to reflect the potential
  1938. 1:12:57impact on the project timeline brief the
  1939. 1:13:00stakeholders on the situation to set
  1940. 1:13:02realistic expectations about potential
  1941. 1:13:04delays proactively collaborate with all
  1942. 1:13:07members to formulate a plan for
  1943. 1:13:08transition and mitigate project
  1944. 1:13:10disruption okay so it's asking here what
  1945. 1:13:13are we going to do notice that is the
  1946. 1:13:15the main thing
  1947. 1:13:17here so notice that this person is
  1948. 1:13:20leaving all right they're intending to
  1949. 1:13:21submit uh and it comes at a time when
  1950. 1:13:24it's going to when their distribution is
  1951. 1:13:26critical so what are we going to do the
  1952. 1:13:28best thing here you can do guys is to
  1953. 1:13:29meet with the team be proactive work
  1954. 1:13:32with the team come up with a plan of how
  1955. 1:13:34we can transition and mitigate any kind
  1956. 1:13:37of disruptions now they had another good
  1957. 1:13:39choice here but it wasn't a have a
  1958. 1:13:42senior never give away your work if a
  1959. 1:13:44choice seems like you're giving away
  1960. 1:13:46that work to someone it's probably never
  1961. 1:13:48good never right answer update the r to
  1962. 1:13:50reflect the potential impact on the
  1963. 1:13:52project
  1964. 1:13:53timeline this kind of affect more than
  1965. 1:13:55the project timeline although I like
  1966. 1:13:57this answer this is just a project
  1967. 1:13:59timeline and you shouldn't just do the
  1968. 1:14:01impact assessment yourself you probably
  1969. 1:14:03want to work with your team members on
  1970. 1:14:05that not just you because somebody
  1971. 1:14:07leaving not just can it impact the
  1972. 1:14:08timeline it can also Impact
  1973. 1:14:11scope brief the stakeholders uh
  1974. 1:14:13stakeholding situation said realistic
  1975. 1:14:15about potential delays how do you know
  1976. 1:14:17about the delays how do you know there
  1977. 1:14:18will be a delay in B and C you're
  1978. 1:14:21thinking there's going to be a delay but
  1979. 1:14:23you haven't even worked with the team
  1980. 1:14:24maybe the team can handle the work and
  1981. 1:14:25there wouldn't be a delay
  1982. 1:14:27correct making D the best
  1983. 1:14:30answer 34 in a software development
  1984. 1:14:34project as the team moves into into the
  1985. 1:14:37development phase they decide to utilize
  1986. 1:14:40time tracking to estimate efforts with
  1987. 1:14:43one hour of effort equaling one point
  1988. 1:14:47some tasks are estimated at Five Points
  1989. 1:14:49While
  1990. 1:14:50others extend up to 200 points to
  1991. 1:14:53enhance the project accurate accy in
  1992. 1:14:55scheduling what should the project
  1993. 1:14:56manager encourage the team to do a
  1994. 1:15:01recommend divide dividing task into
  1995. 1:15:03subtasks to improve man manageability
  1996. 1:15:07and estimation
  1997. 1:15:09accuracy B have the team use new
  1998. 1:15:12estimate and technique that better
  1999. 1:15:13reflects the complexity C encourage the
  2000. 1:15:16adaptation of a fixed point system for
  2001. 1:15:18all
  2002. 1:15:19tasks have the team D have the team
  2003. 1:15:21recolor point system to better different
  2004. 1:15:25simple and complex
  2005. 1:15:27now you really have to use the mindset
  2006. 1:15:30on this if you put the mindset on this
  2007. 1:15:32it wasn't that difficult so let me show
  2008. 1:15:34you guys what the mindset here is the
  2009. 1:15:35best way to do this is to have them
  2010. 1:15:38recommend first of all recommend you
  2011. 1:15:42really shouldn't just tell the team what
  2012. 1:15:44to do this is D you're telling them what
  2013. 1:15:47to do this is a you're telling them what
  2014. 1:15:50to
  2015. 1:15:51do work with the team all right
  2016. 1:15:54recommend
  2017. 1:15:55in order for estimation to be accurate
  2018. 1:15:58the work has to be broken down to
  2019. 1:16:00smaller chunks subdividing the work
  2020. 1:16:03decompose the work we do decomposition
  2021. 1:16:06in both agile and traditional projects
  2022. 1:16:08so we would recommend to do more
  2023. 1:16:11decomposition encourage it a fixed point
  2024. 1:16:14for all tasks
  2025. 1:16:16again there's no way you can have a fix
  2026. 1:16:19point system for all tests this one
  2027. 1:16:20doesn't even make
  2028. 1:16:22sense uh and again be care careful with
  2029. 1:16:25that word all make an a the best answer
  2030. 1:16:28there 35 a tech startup is gearing up to
  2031. 1:16:32launch a groundbreaking app by the
  2032. 1:16:35upcoming summer however during the
  2033. 1:16:38initial planning they encounter
  2034. 1:16:40uncertainty in Project
  2035. 1:16:43specifications they're not sure how
  2036. 1:16:46stakeholders will use the product what
  2037. 1:16:48should the project manager take to
  2038. 1:16:51ensure the project stays on track
  2039. 1:16:55incorporate insights from technology
  2040. 1:16:58Consultants establish a comprehensive
  2041. 1:17:00Rich management framework to anticipate
  2042. 1:17:03and mitigate potential delays assess the
  2043. 1:17:05team and proposing a minimum viable
  2044. 1:17:08product organize Workshops the project
  2045. 1:17:11team to list to solidify the Project's
  2046. 1:17:15technical requirement okay so you notice
  2047. 1:17:20uncertainty dur specification what can
  2048. 1:17:23help on certainty that's the key word
  2049. 1:17:27the best way to do that is an MVP a
  2050. 1:17:30minimum viable product so what an MVP is
  2051. 1:17:33is a thing that you release it's not the
  2052. 1:17:35full product it doesn't have all the
  2053. 1:17:37features but it has a bunch of usable
  2054. 1:17:39features it it's something you build you
  2055. 1:17:42give to your customers they use it they
  2056. 1:17:44utilize it they tell you if you're going
  2057. 1:17:48right if you're going wrong what to
  2058. 1:17:50change what to update this is one of the
  2059. 1:17:52best way to address any uncertainty on a
  2060. 1:17:55project this is the only choice that
  2061. 1:17:57actually deals with that we can this the
  2062. 1:17:59best answer in corporate insights we
  2063. 1:18:02don't want technology Consultants
  2064. 1:18:03uncertainty should come from your
  2065. 1:18:05customers not
  2066. 1:18:07Consultants yes a framework is good but
  2067. 1:18:10it says mitigate delays there's much
  2068. 1:18:12more than delays here it's scope not
  2069. 1:18:16schedule workshops with the development
  2070. 1:18:19team you know what the development team
  2071. 1:18:22needs to work with the customers not
  2072. 1:18:23just with themselves best answer is
  2073. 1:18:27C anyway we are now up to question 35 if
  2074. 1:18:31you're enjoying this video and you're
  2075. 1:18:32learning a lot I would really appreciate
  2076. 1:18:35if you can click on that like button
  2077. 1:18:36doesn't cost anything it's absolutely
  2078. 1:18:38free but we put a lot of time and effort
  2079. 1:18:40into making these questions in this
  2080. 1:18:42video so if you appreciate the time and
  2081. 1:18:44effort we put in all we ask for is at
  2082. 1:18:46least clicking on the like button and
  2083. 1:18:47subscribe to the channel click the
  2084. 1:18:49notification Bell that way when the next
  2085. 1:18:50video comes out questions 41 to 50
  2086. 1:18:53you'll be you'll be the first to know
  2087. 1:18:5636 during a large scale event planning
  2088. 1:18:59project the project manager notices a
  2089. 1:19:02growing list of logistical challenges
  2090. 1:19:06reported by various team members
  2091. 1:19:08although these challenges have been
  2092. 1:19:10acknowledged in team meetings few have
  2093. 1:19:12been effectively resolved leading to
  2094. 1:19:14potential risk for the event success
  2095. 1:19:17what should the project manager
  2096. 1:19:18doing schedule additional planning
  2097. 1:19:21sessions specifically focus on
  2098. 1:19:23logistical challenges
  2099. 1:19:25assign a dedicated team to focus solely
  2100. 1:19:29on identifying and res resolving
  2101. 1:19:31logistical issues
  2102. 1:19:33prioritizing the logistical challenges
  2103. 1:19:36based on their their potential impact on
  2104. 1:19:38the event increase the frequency of Team
  2105. 1:19:41meetings to ensure more regular updates
  2106. 1:19:43on challenges all right let's see what
  2107. 1:19:46we're going to do here guys the best
  2108. 1:19:47answer here is going to be c not sure if
  2109. 1:19:51you got that but let's see why so let's
  2110. 1:19:52look back look back at the question
  2111. 1:19:55there's a growing list of logistical
  2112. 1:19:58challenges they've been acknowledged in
  2113. 1:20:00meetings but they haven't really been
  2114. 1:20:02resolve this is leading to potential
  2115. 1:20:05risks so schedule additional session
  2116. 1:20:07specifically focus on this logistical
  2117. 1:20:09challenge this was a good answer I'm
  2118. 1:20:11going to show you why that one is wrong
  2119. 1:20:12in a second though assign a dedicated
  2120. 1:20:15team to solely identify and resolve
  2121. 1:20:16these that just never just give away to
  2122. 1:20:18work for the team you have to work with
  2123. 1:20:20the
  2124. 1:20:20team increase the frequ the meeting is
  2125. 1:20:24not going to just do this it you need to
  2126. 1:20:26challenge the the logistics notice
  2127. 1:20:29schedule additional planning
  2128. 1:20:31sessions this is the problem we don't
  2129. 1:20:33need plan maybe we can do maybe
  2130. 1:20:35additional meeting this is planning
  2131. 1:20:36sessions eliminating that the best
  2132. 1:20:38answer here is you have to start
  2133. 1:20:40prioritizing this when you have notice
  2134. 1:20:43potential risk when there's a risk the
  2135. 1:20:45risk has to be
  2136. 1:20:47prioritized prioritize it based on their
  2137. 1:20:49impact on the event that would be the
  2138. 1:20:51best thing here that you should be doing
  2139. 1:20:53now if you're wondering well shouldn't
  2140. 1:20:55you be working with the team on that
  2141. 1:20:57that is true and I would like that
  2142. 1:20:59choice but C is the best of these four
  2143. 1:21:01here you don't need additional planning
  2144. 1:21:04sessions that's wrong a dedicated team
  2145. 1:21:07never give away to work and increase the
  2146. 1:21:09frequency is not going to help it so the
  2147. 1:21:11best thing here to do with risk is to
  2148. 1:21:12prioritize
  2149. 1:21:14them 36 37 I mean during the execution
  2150. 1:21:18phase of an urban development project
  2151. 1:21:20the project manager uses email updates
  2152. 1:21:23to keep all stakeholders
  2153. 1:21:25in the city and form feedback indicates
  2154. 1:21:28that some stakeholders find the
  2155. 1:21:30information either too technical or to
  2156. 1:21:34General what should you do first
  2157. 1:21:36initiate a one-on-one briefing for
  2158. 1:21:38stakeholders needing detailed
  2159. 1:21:40explanations organize a workshop to keep
  2160. 1:21:42them
  2161. 1:21:43inform email the specific evaluate the
  2162. 1:21:45specific needs of the stakeholders
  2163. 1:21:47launch or Project Blog that provides
  2164. 1:21:49updates in varying level of details best
  2165. 1:21:52answer here is before
  2166. 1:21:55you sent it out you know the first thing
  2167. 1:21:58you should really be doing is to
  2168. 1:22:00understand what are the needs of the
  2169. 1:22:01stakeholders and you should tailor the
  2170. 1:22:03communication to each individual
  2171. 1:22:06stakeholder a one-on-one briefing will
  2172. 1:22:09take forever because we know it's an
  2173. 1:22:10urban project and it could be a lot of
  2174. 1:22:12stakeholders a workshop a workshop some
  2175. 1:22:15of them may want some of them may not
  2176. 1:22:17want launch a Project
  2177. 1:22:20Blog although I like this maybe you want
  2178. 1:22:22to do c I would do c maybe then do B so
  2179. 1:22:26they have varying level of details but
  2180. 1:22:29evaluate their needs
  2181. 1:22:32first 38 during the deployment phase of
  2182. 1:22:35a new telecommunication Network the
  2183. 1:22:37project encounters significant delays to
  2184. 1:22:40identify mitigate these delays what
  2185. 1:22:42action should the project manager
  2186. 1:22:44take increase the frequency of project
  2187. 1:22:46status meetting to enhance
  2188. 1:22:49communication reallocate resources to
  2189. 1:22:51the most delayed aspect of the project
  2190. 1:22:54adust the timeline to accommodate
  2191. 1:22:55unexpected delay facilitate a
  2192. 1:22:57collaborative session with the team to
  2193. 1:22:59pinpoint and tackle the delays all right
  2194. 1:23:01this here I think is a pretty easy
  2195. 1:23:02question if you've been following me so
  2196. 1:23:04far through all throughout these uh 38
  2197. 1:23:07questions so
  2198. 1:23:08far this one here is pretty simple
  2199. 1:23:10because if there's a problem on the
  2200. 1:23:12project ask the team to help you that's
  2201. 1:23:15the best answer you're not going to just
  2202. 1:23:18increase status meetings without working
  2203. 1:23:21with the team never just reallocate
  2204. 1:23:23resource without the team and you just
  2205. 1:23:25can't adjust timelines as needed uh
  2206. 1:23:28especially you're going to on a on a
  2207. 1:23:30traditional project you're going to need
  2208. 1:23:31to change request work with the team to
  2209. 1:23:34solve the
  2210. 1:23:36problem
  2211. 1:23:3839 a key stakeholder request that
  2212. 1:23:41project manager delivers a critical
  2213. 1:23:43infrastructure component two weeks ahead
  2214. 1:23:45of schedule the project manager assesses
  2215. 1:23:47the situation and determine that
  2216. 1:23:50accessing the schedule is possible by
  2217. 1:23:53overlapping Pro certain
  2218. 1:23:56processes what is the most effective
  2219. 1:23:58course of
  2220. 1:23:59action a re-evaluate the project scope
  2221. 1:24:03to identify non-essential elements that
  2222. 1:24:05can be postponed adjust the timeline by
  2223. 1:24:08sequencing work to allow for parallel
  2224. 1:24:10activity increase the budget to allow
  2225. 1:24:12for overtime and additional resources
  2226. 1:24:15use advanced technology to automate
  2227. 1:24:18automate certain construction process
  2228. 1:24:20this one here is tricky one very tricky
  2229. 1:24:22here's why
  2230. 1:24:25this is when you're running when you're
  2231. 1:24:27doing overlapping
  2232. 1:24:29activities okay this is called Fast
  2233. 1:24:31Tracking not Crush fast tracking will
  2234. 1:24:34decrease time it increases the risk but
  2235. 1:24:37it generally doesn't increase cost and
  2236. 1:24:40because it's incre it doesn't really
  2237. 1:24:41increase the cost you don't need c not
  2238. 1:24:44to mention C would require a change
  2239. 1:24:47request now noce reevaluate to identify
  2240. 1:24:51that can be if you're going to postpone
  2241. 1:24:53parts of the scope that also needs to
  2242. 1:24:54change your
  2243. 1:24:55request automated technology for certain
  2244. 1:24:58construction this goes beyond the scope
  2245. 1:25:00of the
  2246. 1:25:01question first of all you can if you
  2247. 1:25:04could you can just go into a timeline
  2248. 1:25:07and run things in parallel you don't
  2249. 1:25:08need to change request to readjust
  2250. 1:25:11activities you can readjust activities
  2251. 1:25:13as long as the schedule is not changing
  2252. 1:25:15that's fine if it gets a little shorter
  2253. 1:25:17that's fine too but remember if you're
  2254. 1:25:19going to be extending that schedule you
  2255. 1:25:21might need a change request 39 best B
  2256. 1:25:24best
  2257. 1:25:25answer last question guys is 40 at the
  2258. 1:25:29onset of a software development project
  2259. 1:25:31the project manager is tasked with divis
  2260. 1:25:34dividing devising a strategy for for
  2261. 1:25:37assessing the contribution of each
  2262. 1:25:39developer these assessments are to be
  2263. 1:25:42compiled and presented to the
  2264. 1:25:44organization leadership at the project
  2265. 1:25:47conclusion watch of the project manager
  2266. 1:25:49what should be the project manager Next
  2267. 1:25:52Step arrange for regular one one
  2268. 1:25:54meetings with each developer to discuss
  2269. 1:25:56and document in their
  2270. 1:25:58progress okay develop clear Quantum
  2271. 1:26:03fiable uh criteria for evaluating
  2272. 1:26:06developers performance and communicate
  2273. 1:26:08these standards all right utilize
  2274. 1:26:11software development metrics like lines
  2275. 1:26:14of code to directly measure developers
  2276. 1:26:17productivity okay conduct Anonymous
  2277. 1:26:20surveys among team members to gather
  2278. 1:26:22insights on individual contributions
  2279. 1:26:24all right this one here this is more of
  2280. 1:26:26an Ethics
  2281. 1:26:28question when it comes to ethics be fair
  2282. 1:26:32be upfront let people know what's being
  2283. 1:26:34assessed and it has to be fair and this
  2284. 1:26:37question in particular is saying what do
  2285. 1:26:39you do
  2286. 1:26:40next the next thing you should be doing
  2287. 1:26:44is coming up with a clear criterias
  2288. 1:26:48quantifiable criterias that's easily
  2289. 1:26:50measured measured with numbers is great
  2290. 1:26:53and then communicate them to the team so
  2291. 1:26:55everybody knows about
  2292. 1:26:56them people say a meeting with each
  2293. 1:26:59developer you probably want to do B
  2294. 1:27:02number one maybe then do a once you've
  2295. 1:27:06done a maybe then you can sit down with
  2296. 1:27:07the developers but you need to be clear
  2297. 1:27:10first you need to come up with your
  2298. 1:27:12criteria before sitting down with them
  2299. 1:27:14you need to know what to look for before
  2300. 1:27:15sitting down with them making this a
  2301. 1:27:17better answer than
  2302. 1:27:18this you don't need to utilize software
  2303. 1:27:21development metrics like line of codes
  2304. 1:27:23what if some people don't some people
  2305. 1:27:25are very productive and they don't have
  2306. 1:27:26as much line of codes as others you
  2307. 1:27:28don't need Anonymous survey amounts them
  2308. 1:27:30then they start to evaluate each other
  2309. 1:27:32you need to have clear and even before
  2310. 1:27:34you do a survey you need to do B first
  2311. 1:27:37making this the best answer all right
  2312. 1:27:38question 41 at the beginning of a new
  2313. 1:27:40Environmental Conservation project a key
  2314. 1:27:43stakeholder expressed concerns over a
  2315. 1:27:45Project's approach fearing it wouldn't
  2316. 1:27:47meet the intended environmental goals
  2317. 1:27:49and will exceed the initial forecast
  2318. 1:27:53what should the project man manager do
  2319. 1:27:54first all right we got this key word
  2320. 1:27:56there first organize a meeting with the
  2321. 1:27:58stakeholder to understand the concerns
  2322. 1:28:00and identify potential involvements all
  2323. 1:28:02right launch a pilot phase to
  2324. 1:28:04demonstrate the project Effectiveness
  2325. 1:28:06and adjust based on early
  2326. 1:28:08results C enhance communication with the
  2327. 1:28:11stakeholder by providing regular updates
  2328. 1:28:14and involving them more closely in
  2329. 1:28:16Project planning process outline the
  2330. 1:28:18long-term benefits and sustainability
  2331. 1:28:20impacts of the project emphasizing its
  2332. 1:28:23alignment with broader environmental
  2333. 1:28:25objectives all right the best answer
  2334. 1:28:27here is going to be a now let me you
  2335. 1:28:30know we went over this a lot in the
  2336. 1:28:32previous question but you notice there's
  2337. 1:28:34some kind of concern there's some kind
  2338. 1:28:37of a problem on this notice somebody's
  2339. 1:28:39expressing
  2340. 1:28:42concern and anytime you as a project
  2341. 1:28:44manager is faced with some stakeholder
  2342. 1:28:47having some kind of issue or they're
  2343. 1:28:49having some kind of concern or they
  2344. 1:28:51don't like something if the question
  2345. 1:28:52says what to do first first don't take
  2346. 1:28:54an action against it is to review meet
  2347. 1:28:57with that stakeholder see what's going
  2348. 1:28:59on assess the situation just don't go
  2349. 1:29:01out and Tak an action until you really
  2350. 1:29:03understand you know what this concern is
  2351. 1:29:05about so that's this one organize a
  2352. 1:29:07meeting with the stakeholder because you
  2353. 1:29:09want to understand what that concern is
  2354. 1:29:11now why is the others wrong well launch
  2355. 1:29:12a pilot program without even
  2356. 1:29:15understanding what the concern is you're
  2357. 1:29:16taking an action don't take an action
  2358. 1:29:18without understanding the concern you're
  2359. 1:29:20enhancing communication it doesn't
  2360. 1:29:22really say there's a communication
  2361. 1:29:24problem the guy doesn't have a problem
  2362. 1:29:26with communication he has a problem with
  2363. 1:29:27the Project's approach so that's not it
  2364. 1:29:31outline the long-term benefit I'm not
  2365. 1:29:32sure what this is going to do it doesn't
  2366. 1:29:34really state that it doesn't do the
  2367. 1:29:36long-term benefit the problem here is
  2368. 1:29:39the the approach not really the
  2369. 1:29:40objectives which is what D is so D
  2370. 1:29:42doesn't even address this all right
  2371. 1:29:45pretty easy one I think that one it was
  2372. 1:29:46kind of easy if you have the mindset
  2373. 1:29:48down you're starting to get it I think
  2374. 1:29:49this is getting a little easy for
  2375. 1:29:52you 42
  2376. 1:29:55in the midst of implementing a new
  2377. 1:29:56healthcare it system a project manager
  2378. 1:29:59faces a challenge the initial phase
  2379. 1:30:02involved in the upgrade of the existing
  2380. 1:30:03software is behind schedule impacting
  2381. 1:30:07the sub subsequent software
  2382. 1:30:10implementation phase due to Shared
  2383. 1:30:11technical uh teams what course of action
  2384. 1:30:14should the project manager take so in
  2385. 1:30:16this one you're facing a
  2386. 1:30:18challenge um you're behind schedule so
  2387. 1:30:21you got you got some problems here
  2388. 1:30:24negotiate with other project managers
  2389. 1:30:26for temporary resource Shar and to
  2390. 1:30:28expedite the hardware upgrade all right
  2391. 1:30:30initiate an assessment to evaluate the
  2392. 1:30:32impact of the delay of the overall
  2393. 1:30:34project timeline all right implement the
  2394. 1:30:36reward system for the technical team to
  2395. 1:30:37incentivize faster completion engage a
  2396. 1:30:40consultant to provide expert advice on
  2397. 1:30:43streamlining the hardware now in this
  2398. 1:30:45one here this is also one where you have
  2399. 1:30:48to be careful with your actions so you
  2400. 1:30:50notice the answer here is going to be B
  2401. 1:30:54you see before you go out and you
  2402. 1:30:57negotiate for other resources you
  2403. 1:30:59implement some reward system or you do
  2404. 1:31:02some kind of Consulting you really got
  2405. 1:31:04to understand well exactly how does this
  2406. 1:31:08really affect the project you just can't
  2407. 1:31:10say well okay it seems like we're behind
  2408. 1:31:12schedule right we're behind schedule and
  2409. 1:31:15it's impacting some things but how is it
  2410. 1:31:17affecting the budget how is this
  2411. 1:31:19whatever is happen how is it affecting
  2412. 1:31:20the budget in this one we're just
  2413. 1:31:22talking about time so do your assessment
  2414. 1:31:25before taking an
  2415. 1:31:27action
  2416. 1:31:2843 at the midpoint of renew renewable
  2417. 1:31:31energy project the project manager is
  2418. 1:31:33faced with conflict between the design
  2419. 1:31:35team and the environmental Consultants
  2420. 1:31:38regarding the feasibility of the
  2421. 1:31:39proposed turbine
  2422. 1:31:41placement the design team believes the
  2423. 1:31:43placement will optimize energy
  2424. 1:31:46Productions while the environmental
  2425. 1:31:47Consultants warned could lead to
  2426. 1:31:50significant eological
  2427. 1:31:52disruptions a lot of big words on this
  2428. 1:31:54one what should the project manager take
  2429. 1:31:56to resolve this
  2430. 1:31:57conflict okay so you got some issues
  2431. 1:32:01here between two teams right between the
  2432. 1:32:04design team and the environmental
  2433. 1:32:07consultant so you got issues between
  2434. 1:32:09them what do you do well proceed with
  2435. 1:32:12the Design's recommendation okay to
  2436. 1:32:14maximize energy output organize a
  2437. 1:32:16collaborative session discuss the impact
  2438. 1:32:18find a compromise okay consult uh
  2439. 1:32:20commission independent review of the
  2440. 1:32:22turbine's placement poon decision on a
  2441. 1:32:24turbine until farther data okay the best
  2442. 1:32:27thing here is when you have a problem
  2443. 1:32:28between people is to try to help them
  2444. 1:32:31resolve it because you don't want to
  2445. 1:32:33choose a side choosing a side would be
  2446. 1:32:35considered forcing that means the answer
  2447. 1:32:38here is bringing them together and have
  2448. 1:32:40them come up with a good solution now
  2449. 1:32:42compromising is not the best solution
  2450. 1:32:44here but I don't want you to go out and
  2451. 1:32:46take an action without them being
  2452. 1:32:47involved you
  2453. 1:32:49notice here you did something without
  2454. 1:32:51them being involved here you did
  2455. 1:32:53something without them you you just made
  2456. 1:32:54your own decision the best thing to do
  2457. 1:32:56is to work with the teams and work with
  2458. 1:32:58the teams to come up with
  2459. 1:33:00Solutions 44 after a new project is
  2460. 1:33:04executed uh executed an executive
  2461. 1:33:07suggest incorporating new add-on to
  2462. 1:33:09provide more function to the product
  2463. 1:33:11what should the project manager do
  2464. 1:33:13update the product immediately to
  2465. 1:33:15include the suggested scenario without
  2466. 1:33:17formal approval note the suggestion for
  2467. 1:33:20inclusion in a separate risk assessment
  2468. 1:33:22document integrate this executive
  2469. 1:33:24feedback into an appendix of the current
  2470. 1:33:27report encourage the executive to
  2471. 1:33:30formalize the suggestions to a change
  2472. 1:33:31request process now in this one here you
  2473. 1:33:34notice it says that the the new project
  2474. 1:33:36is executed the best assumption here is
  2475. 1:33:38to go with that this is a traditional
  2476. 1:33:40project and if anybody wants to put on a
  2477. 1:33:42new add-on which is going to be a scope
  2478. 1:33:44change the best thing here is to have
  2479. 1:33:46them go through the Change Control
  2480. 1:33:48process you just can't add in add
  2481. 1:33:51something to the product which is
  2482. 1:33:52basically a scope change without going
  2483. 1:33:54through that you should never just
  2484. 1:33:57include a scope change or an add-on to a
  2485. 1:34:00product without a formula approval
  2486. 1:34:03that's not your job to approve things
  2487. 1:34:05your job is to manage the team building
  2488. 1:34:07the deliverable not approving or
  2489. 1:34:09disapproving just don't do nothing you
  2490. 1:34:12notice note the suggestion in the risk
  2491. 1:34:15analysis this these one here you just it
  2492. 1:34:18seems like you're putting things in a
  2493. 1:34:19report but you're not actually dealing
  2494. 1:34:22with the add-on itself
  2495. 1:34:2645 at the onset of an urban regeneration
  2496. 1:34:30project the project matter observes that
  2497. 1:34:32although t- moral is high meetings often
  2498. 1:34:35diverge into unrelated conversations
  2499. 1:34:38causing them to over causing them to
  2500. 1:34:40overrun and decision to be postponed
  2501. 1:34:43what is the most effective initial
  2502. 1:34:45action for the PM to take schedule
  2503. 1:34:48shorter meeting to encourage more
  2504. 1:34:50focused discussions okay designated time
  2505. 1:34:53keeper to ensure meeting ADH to schedule
  2506. 1:34:56times adhere to schedule times C
  2507. 1:35:00emphasize the meeting objectives and
  2508. 1:35:02agenda at the beginning of each
  2509. 1:35:04session introduce a digital platform for
  2510. 1:35:07a team member to share non project
  2511. 1:35:10related discussions
  2512. 1:35:12now I wrote this question very
  2513. 1:35:15particularly I wrote it in a way for you
  2514. 1:35:19to understand that it says initial
  2515. 1:35:21action it's like what is the the initial
  2516. 1:35:25thing you try should never be the
  2517. 1:35:26hardest shouldn't take the most energy
  2518. 1:35:29you should try to solve problems the
  2519. 1:35:31easiest way
  2520. 1:35:33possible and that's C how about if you
  2521. 1:35:37get in front of the meeting and you
  2522. 1:35:38emphasize what the objectives are at the
  2523. 1:35:40beginning of each session this is what
  2524. 1:35:41we got to get done guys if this fails
  2525. 1:35:45maybe then you may want to go to B maybe
  2526. 1:35:49you may want to go to A and D then but
  2527. 1:35:53remember
  2528. 1:35:54the keyword here is initial you got to
  2529. 1:35:57watch the wording of the question the
  2530. 1:35:59initial action is never to take a
  2531. 1:36:01drastic action a would literally cut the
  2532. 1:36:04meetings down D would make you get some
  2533. 1:36:07kind of whole new software B designate
  2534. 1:36:11the initial action is just to say hey
  2535. 1:36:14folks we need to stop this let's see how
  2536. 1:36:17this this is what we got to get done
  2537. 1:36:18let's stick to
  2538. 1:36:21it 46
  2539. 1:36:24Journal routine progress update sessions
  2540. 1:36:27for multinational project a project
  2541. 1:36:29manager notes that one of the key
  2542. 1:36:31technical analysts although
  2543. 1:36:33exceptionally knowledgeable really
  2544. 1:36:35contributes to group discussions and
  2545. 1:36:37despite engaging despite engaging
  2546. 1:36:40actively in private conversations okay
  2547. 1:36:42so we have somebody that is very smart
  2548. 1:36:44technical analyst and they seem to be
  2549. 1:36:48good in private but they're not very
  2550. 1:36:49good in group discussions what should
  2551. 1:36:51you do schedule a dedicated dedicated
  2552. 1:36:54session where only the technical analyst
  2553. 1:36:56presents their finding to the
  2554. 1:36:58team I'm not sure if this is going to
  2555. 1:37:00work actively solicit the analyst input
  2556. 1:37:02during meetings emphasizing the
  2557. 1:37:04importance of the expertise to the
  2558. 1:37:05Project's success create an anonymous
  2559. 1:37:08feedback mechanism where the analyst can
  2560. 1:37:11can submit their insights without
  2561. 1:37:12speaking up in mediums wait for the
  2562. 1:37:15analyst to naturally become more
  2563. 1:37:17comfortable and decide to contribute to
  2564. 1:37:19discussions at their own pace okay let's
  2565. 1:37:22see how we can can answer this this I
  2566. 1:37:24believe was a tough question and believe
  2567. 1:37:26me me and the gentleman that wrote this
  2568. 1:37:28one I wrote this one he got this one
  2569. 1:37:31wrong uh I I thought this was a really
  2570. 1:37:34good question because you really got to
  2571. 1:37:35address what the question is
  2572. 1:37:38asking okay we want what is it we want
  2573. 1:37:40out of this question we want the
  2574. 1:37:44analysts to contribute in the group
  2575. 1:37:47discussion that's the
  2576. 1:37:49problem all right what do we do about
  2577. 1:37:51this well the best thing here is to talk
  2578. 1:37:55to this person you notice it seems like
  2579. 1:37:58when people are talking to this person
  2580. 1:38:01they talk but it seems like no one is
  2581. 1:38:04talking to this person so they're not
  2582. 1:38:06actively engaging in in these meetings
  2583. 1:38:08so actively solicit the analy input
  2584. 1:38:11during the Mee and emphasize hey these
  2585. 1:38:13are great things to know now why isn't
  2586. 1:38:15the other right
  2587. 1:38:17well this here takes no action if the
  2588. 1:38:20choice is to do nothing in other words
  2589. 1:38:22leave it until the analyst feels like
  2590. 1:38:24speaking uh or gets more comfortable
  2591. 1:38:27speaking this is not you might be
  2592. 1:38:28waiting forever if the if the option is
  2593. 1:38:31to do nothing it's probably not the
  2594. 1:38:32answer crate Anonymous feedback well is
  2595. 1:38:36that for everyone or just for the
  2596. 1:38:37analyst if it's just one person it's not
  2597. 1:38:39really I I had fun writing this one if
  2598. 1:38:42the analyst is the only one speaking
  2599. 1:38:44it's not really Anonymous anymore now is
  2600. 1:38:46it schedule a dedicated session where
  2601. 1:38:48they only presents their finding to the
  2602. 1:38:50team it's the same scenario and this one
  2603. 1:38:53here just they just take you out
  2604. 1:38:55completely but he's presenting to the
  2605. 1:38:57find and to the team it's better the two
  2606. 1:38:59choices were either A or B but notice
  2607. 1:39:02this one is presents their fin night to
  2608. 1:39:04the team if you were saying this don't
  2609. 1:39:06do B because he doesn't want the analyst
  2610. 1:39:08doesn't want to talk in front of people
  2611. 1:39:10well a he's talking in front of people
  2612. 1:39:11except you're not there that's how you
  2613. 1:39:13had to read that so tricky one there b
  2614. 1:39:16is the best
  2615. 1:39:18answer by the way if you're enjoying
  2616. 1:39:20this video so far you're getting these
  2617. 1:39:22questions right you're learning
  2618. 1:39:23something can you do me a quick favor
  2619. 1:39:24you know what I'm going to ask you right
  2620. 1:39:25click on the like button subscribe to
  2621. 1:39:27the channel it would be an enormous help
  2622. 1:39:29for us you guys don't understand how
  2623. 1:39:32much this helps us out YouTube does not
  2624. 1:39:35just a quick thing YouTube uh doesn't
  2625. 1:39:39recommend our videos YouTube will push
  2626. 1:39:41our videos to the bottom if nobody likes
  2627. 1:39:43it or nobody inter or engages with the
  2628. 1:39:45channel so we could be making content
  2629. 1:39:47and no one's going to watch because no
  2630. 1:39:49one will see it and if people stop
  2631. 1:39:51watching our content we'll have to stop
  2632. 1:39:52making them so sorry to be hard on you
  2633. 1:39:54guys but we got a lot of views and not a
  2634. 1:39:56lot of likes and or subscribe sorry for
  2635. 1:39:59that guys let's go back to the
  2636. 1:40:01questions
  2637. 1:40:0347 just before the final review of new
  2638. 1:40:05software development project the project
  2639. 1:40:07manager is informed by the quality
  2640. 1:40:09assurance team that several key features
  2641. 1:40:12do not meet the predefined
  2642. 1:40:15specifications agreed upon the client
  2643. 1:40:17agreed agreed upon agreed upon with the
  2644. 1:40:19client correcting these issues will
  2645. 1:40:22delay the project deliver by several
  2646. 1:40:24weeks what should you do next remember
  2647. 1:40:26the key word prioritize the work to meet
  2648. 1:40:30the agreed specifications accepting the
  2649. 1:40:32project timeline may need to be extended
  2650. 1:40:35all right suggest a partial delivery of
  2651. 1:40:38the project to the client with
  2652. 1:40:40non-client comp uh with non-compliant
  2653. 1:40:43features to be updated in future release
  2654. 1:40:45propose a compromise on a specification
  2655. 1:40:47to the client reducing the scope to
  2656. 1:40:49match your current state consult with
  2657. 1:40:51the development team to find a faster
  2658. 1:40:52solution that could delay that could
  2659. 1:40:55reduce the delay while attempting to
  2660. 1:40:56meet the specification
  2661. 1:40:58now you got to be careful with this word
  2662. 1:41:02next it's like okay you realize we're
  2663. 1:41:05probably going to be late we're not
  2664. 1:41:06going to have everything what should you
  2665. 1:41:07do next like what are you going to do
  2666. 1:41:08right away and the best answer here is
  2667. 1:41:11going to be D meet with the team and ask
  2668. 1:41:13them hey is there can we find a faster
  2669. 1:41:16way can we get this
  2670. 1:41:18done right uh notice is informed by the
  2671. 1:41:22quality of Insurance team even if the
  2672. 1:41:25quality insurance team tells you this
  2673. 1:41:26you got to go to them and you got to say
  2674. 1:41:28to them hey can you do this any
  2675. 1:41:31quicker um and can we reduce is there a
  2676. 1:41:34way to reduce this delay and maybe then
  2677. 1:41:37you can go back and tell the client but
  2678. 1:41:39the first thing you should do not the
  2679. 1:41:40quality insurance team calls you up and
  2680. 1:41:43says this and your only thing is okay
  2681. 1:41:45let me go tell the client and move on no
  2682. 1:41:48so consult with the team let's find a
  2683. 1:41:49faster way you cannot prioritize work
  2684. 1:41:52like that that's something the team team
  2685. 1:41:53or the sponsor should be doing suggest a
  2686. 1:41:56partial delivery you never want to just
  2687. 1:41:58deliver especially with non-compliant
  2688. 1:42:00features this is something the T the the
  2689. 1:42:03um first of all you would need your
  2690. 1:42:05sponsor or your customers to approve
  2691. 1:42:08that uh propose a compromise you should
  2692. 1:42:11never like this see was the throwout you
  2693. 1:42:14know I add this in here to kill this
  2694. 1:42:16every time we write questions there
  2695. 1:42:18always going to be a few choices called
  2696. 1:42:20throwaways or I call them garbage
  2697. 1:42:23choices in other words you shouldn't
  2698. 1:42:24select that the moment it says that you
  2699. 1:42:26reduce the scope you don't have that
  2700. 1:42:29power to just reduce scope agile and
  2701. 1:42:31their traditional projects the project
  2702. 1:42:33manager doesn't have the power to just
  2703. 1:42:34remove a remove scope parts that's
  2704. 1:42:37something the sponsor or the product
  2705. 1:42:38owner should be
  2706. 1:42:40doing tough
  2707. 1:42:42question 48 during a critical phase of
  2708. 1:42:45an Agile development project a
  2709. 1:42:48specialist responsible for designing a
  2710. 1:42:51key component is unexpected required to
  2711. 1:42:54take extensive medical leave the special
  2712. 1:42:57task are now at risk of delay as they
  2713. 1:43:00were to so individual equipped with the
  2714. 1:43:02necessary expertise H sto individual
  2715. 1:43:06what proactive measure could a project
  2716. 1:43:07man have taken to mitigate the risk
  2717. 1:43:08build a cross functional
  2718. 1:43:10team distribute The Specialist task
  2719. 1:43:13amount several members from the project
  2720. 1:43:15onset okay establish a comprehensive
  2721. 1:43:19documentation practice for all project
  2722. 1:43:21task okay allocate addition funds to
  2723. 1:43:23hire temporary Specialists if needed now
  2724. 1:43:26notice it says here what proactive this
  2725. 1:43:30is the key word like what could you have
  2726. 1:43:32done to stop this or to reduce the blow
  2727. 1:43:34of this all of these choices are not too
  2728. 1:43:37bad except one of them all right like
  2729. 1:43:41allocate extra funds to hire temporary
  2730. 1:43:43specialist maybe unless you would have
  2731. 1:43:45predicted this in the risk assessment
  2732. 1:43:47the best thing here if you know agile
  2733. 1:43:49you know you should build a team of
  2734. 1:43:52generalizing
  2735. 1:43:54specialist across functional team what
  2736. 1:43:56this does is that everybody is able to
  2737. 1:44:00help each other in this one you built a
  2738. 1:44:02specialist team you went against the
  2739. 1:44:04rules of agile you want a cross
  2740. 1:44:07functional team a team where everybody
  2741. 1:44:09is capable of helping everybody else
  2742. 1:44:11this
  2743. 1:44:12reduces all kind of bottlenecks with the
  2744. 1:44:14team I Do cover this in the course so
  2745. 1:44:16make sure you check out the agile team
  2746. 1:44:18section distribute this here was
  2747. 1:44:21something that you would have probably
  2748. 1:44:22done afterwards but then it would have
  2749. 1:44:25been hard to predict who's going to be
  2750. 1:44:26in and out right this one this is the
  2751. 1:44:29throwaway Choice here to me because how
  2752. 1:44:30could you predicted this you distribute
  2753. 1:44:32just this guy's task you would have to
  2754. 1:44:34done it to everybody not just this
  2755. 1:44:35person notice does specialist tasks you
  2756. 1:44:38would have never noticed this because
  2757. 1:44:40notice it's
  2758. 1:44:42unexpectedly comprehensive practice for
  2759. 1:44:44all project tasks that would have been
  2760. 1:44:46okay but it's not this is a specialist
  2761. 1:44:48task only this person is capable of
  2762. 1:44:50doing it although I like the it's best
  2763. 1:44:53to make sure that you have a good
  2764. 1:44:56generalizing
  2765. 1:44:58specialist uh cross functional team okay
  2766. 1:45:01two more to goal in the planning phase
  2767. 1:45:04of a large software implementation
  2768. 1:45:06project the project manager decides to
  2769. 1:45:08conduct an extensive analysis of
  2770. 1:45:10potential risk associated with the
  2771. 1:45:12Project's timeline and budget the goal
  2772. 1:45:15is to understand the likelihood of a
  2773. 1:45:17project completion within the defined
  2774. 1:45:20perimeters and to identify which
  2775. 1:45:22variable most significantly impact the
  2776. 1:45:24project outcome using many different
  2777. 1:45:27perspectives what technique should the
  2778. 1:45:28project manager apply to evaluate and
  2779. 1:45:30address the risk now so you're doing a
  2780. 1:45:32risk assessment basically you're looking
  2781. 1:45:34at the likelihood of the risk you're
  2782. 1:45:35looking at certain perimeters from
  2783. 1:45:37different perspectives
  2784. 1:45:40hm what technique are you doing here
  2785. 1:45:43well are you developing a RIS breakdown
  2786. 1:45:46structure uh conducting a sensitivity
  2787. 1:45:49analysis utilize a cause and effect
  2788. 1:45:52diagram
  2789. 1:45:53or Monte Carlo this is a straightforward
  2790. 1:45:55knowledge based question that I wrote in
  2791. 1:45:58a very difficult way best answer here is
  2792. 1:46:01going to be the this is a Monti cardo
  2793. 1:46:03simulation a Monti cardo simulation
  2794. 1:46:06looks at many many many many different
  2795. 1:46:09scenarios
  2796. 1:46:10perspectives uh or different outcomes
  2797. 1:46:13that can affect projects for example if
  2798. 1:46:16this if you have this weather event how
  2799. 1:46:18is it going to affect this project like
  2800. 1:46:19what's going to happen if the if you had
  2801. 1:46:21a category 4 hurricane category 5
  2802. 1:46:24hurricane a blizzard so you're looking
  2803. 1:46:26at all different perspectives and how
  2804. 1:46:27it's going to affect the project and
  2805. 1:46:29that really is what this is describing a
  2806. 1:46:31cause and effect diagram will tell you
  2807. 1:46:32the reasons for risks or the cause of
  2808. 1:46:36failure this is a fishbone diagram
  2809. 1:46:39sensitivity analysis starts to rank them
  2810. 1:46:41up this looks at particular impacts of
  2811. 1:46:43positive and negative risk RIS breakdown
  2812. 1:46:45structure just categorize your RIS this
  2813. 1:46:47is looking at different
  2814. 1:46:49perspectives question 50 on a project to
  2815. 1:46:53to develop a new CRM system the project
  2816. 1:46:56manager launch that that a stakeholder
  2817. 1:47:00meeting laar during the stakeholder
  2818. 1:47:02meeting that UPC that upcoming
  2819. 1:47:04regulatory changes will affect data
  2820. 1:47:07handling processes within the system the
  2821. 1:47:10change are expected to be enforced
  2822. 1:47:12shortly after the Project's planned
  2823. 1:47:14completion date what is the most
  2824. 1:47:16appropriate action for the project man
  2825. 1:47:17ensure the projects remain compliant
  2826. 1:47:19with the new regulation okay incorporate
  2827. 1:47:22the regulations into the Project's risk
  2828. 1:47:24log for future
  2829. 1:47:26analysis plan to address the regulator
  2830. 1:47:29in the next CRM system the uh
  2831. 1:47:31development integrate discussion of the
  2832. 1:47:33regulatory changes into the project
  2833. 1:47:35phases request immediate detailed
  2834. 1:47:37information during the next product
  2835. 1:47:39update Meed
  2836. 1:47:41okay best answer here now this one was
  2837. 1:47:45tricky because first of all it's not a
  2838. 1:47:48risk all right notice incorporate into
  2839. 1:47:51the Project's risk R should say risk
  2840. 1:47:54register uh but it's not a risk because
  2841. 1:47:57this
  2842. 1:47:58will affect the data handle it this leg
  2843. 1:48:02if it was like it might then you may
  2844. 1:48:04want to add it to the risk
  2845. 1:48:06register but it's not a might this is a
  2846. 1:48:09will this is something that will happen
  2847. 1:48:11it's guaranteed to happen so it's not a
  2848. 1:48:13risk risk has
  2849. 1:48:15probability now you don't want to wait
  2850. 1:48:17for the next system to be developed and
  2851. 1:48:20that's D also immediate detailing inform
  2852. 1:48:23change during the next product update
  2853. 1:48:25you got to do it right now because
  2854. 1:48:26you're going to you're going to be
  2855. 1:48:27pushing this thing out and then that
  2856. 1:48:28regulation is going to come in the best
  2857. 1:48:30thing here you can do is start
  2858. 1:48:31incorporating that regulation into what
  2859. 1:48:34you are doing question 51 during a
  2860. 1:48:37mobile application development project
  2861. 1:48:39the project manager faces significant
  2862. 1:48:42uncertainty regarding user preferences
  2863. 1:48:44and the effectiveness of proposed
  2864. 1:48:46features the initial user feedback has
  2865. 1:48:49been
  2866. 1:48:50inconclusive leading to questions about
  2867. 1:48:52the project current direction what is
  2868. 1:48:55the best course of action for the
  2869. 1:48:56project manager to ensure the project
  2870. 1:48:58aligns with users expectations finish
  2871. 1:49:02developing the application and correct
  2872. 1:49:04all features not align with users
  2873. 1:49:07expectation proceed with the creation of
  2874. 1:49:09an MVP and if you're not familiar this
  2875. 1:49:11means minimum viable product pause
  2876. 1:49:14development efforts until a
  2877. 1:49:15comprehensive market analysis provides
  2878. 1:49:18clear guidance on user preference
  2879. 1:49:20instruct the development team to
  2880. 1:49:22incorporate the most popular features of
  2881. 1:49:25complete an application to ensure
  2882. 1:49:27relevance okay best answer here is going
  2883. 1:49:30to be
  2884. 1:49:31MVP here's why first of all before we
  2885. 1:49:34get into it what's an MVP so minimum
  2886. 1:49:37viable product is something that the
  2887. 1:49:40team releases to the customers to get
  2888. 1:49:43feedback for example let's say they're
  2889. 1:49:44making this mobile application do you
  2890. 1:49:48have to release the entire mobile
  2891. 1:49:49application to the users to get feedback
  2892. 1:49:52no you you release something that's
  2893. 1:49:53minimal something that's usable it
  2894. 1:49:55doesn't have every single feature but it
  2895. 1:49:58has some of the core features something
  2896. 1:50:00that you can give them that they can use
  2897. 1:50:02they can play with they can input data
  2898. 1:50:04that way you can get great feedback on
  2899. 1:50:06it MVP is a popular topic on your exam
  2900. 1:50:09it is in the exam objective so make sure
  2901. 1:50:10you understand what it is now why is
  2902. 1:50:12this the best answer well you notice the
  2903. 1:50:15question specifically States the
  2904. 1:50:17effectiveness of these features the only
  2905. 1:50:19which TR to understand the effectiveness
  2906. 1:50:21of the features is to get the users to
  2907. 1:50:24use them they'll tell you whether those
  2908. 1:50:25features are effective now and being
  2909. 1:50:29that there's a lot of uncertainty the
  2910. 1:50:30best way to gain certainty is to have
  2911. 1:50:32the users use it give them the features
  2912. 1:50:35it wouldn't be a good idea to finish the
  2913. 1:50:37entire thing and then correct it all
  2914. 1:50:39this is more like Kick the Can down the
  2915. 1:50:41road and fix later which is something we
  2916. 1:50:42never want to do the mindset tells us
  2917. 1:50:44never kick the can down the road never
  2918. 1:50:47pause your project is part of the
  2919. 1:50:49mindset unless there's something major
  2920. 1:50:52going on on like a safety issue and
  2921. 1:50:53somebody may die or you're breaking the
  2922. 1:50:55law you shouldn't be pausing your
  2923. 1:50:56project instruct the development team to
  2924. 1:51:00incorporate the most popular features
  2925. 1:51:02but how do we know if these features are
  2926. 1:51:04even going to be effective it's not just
  2927. 1:51:06about being the popular feature best
  2928. 1:51:09answer was B 52 in anticipation of new
  2929. 1:51:13environmental regulations a
  2930. 1:51:15manufacturing project involve in two
  2931. 1:51:18distinct operational teams one using
  2932. 1:51:21traditional manufacturing methods
  2933. 1:51:23and the other employing Green Technology
  2934. 1:51:26and they need to evaluate the impact of
  2935. 1:51:27these regulations on combined
  2936. 1:51:30operation what is the most effective
  2937. 1:51:33action for the project manager to ensure
  2938. 1:51:35compliance and seamess integration okay
  2939. 1:51:37so we got two teams right we have one
  2940. 1:51:40using traditional the other one using
  2941. 1:51:42green technology and they need to
  2942. 1:51:44evaluate the impact of regulations all
  2943. 1:51:47right a organize a collaborative
  2944. 1:51:49workshop with representative from both
  2945. 1:51:51teams to discuss compliance strategies
  2946. 1:51:53okay conduct a separate workshop for
  2947. 1:51:55each team to allow for focused
  2948. 1:51:57discussion on adapting their specific
  2949. 1:52:00operation for the of the new regulation
  2950. 1:52:02facilitate individual strategy session
  2951. 1:52:04with each team to outline their approach
  2952. 1:52:06followed by a joint session okay
  2953. 1:52:09assemble a panel of regulatory experts
  2954. 1:52:11to provide guidance and recommendations
  2955. 1:52:13to both teams best answer here follow
  2956. 1:52:15the mindset on this one the best answer
  2957. 1:52:17here is always to bring people
  2958. 1:52:21together let them work together your job
  2959. 1:52:24as a project manager is to be a
  2960. 1:52:27facilitator and collaborate big
  2961. 1:52:29collaboration about everybody on a
  2962. 1:52:31project that's what a is all about you
  2963. 1:52:34never want to just do individual
  2964. 1:52:36workshops right let them just figure it
  2965. 1:52:38out on their own they have to work
  2966. 1:52:41together so especially something like a
  2967. 1:52:44regulation I like C D is definitely the
  2968. 1:52:47out of the uh you don't want to do that
  2969. 1:52:50because the team has to come up with the
  2970. 1:52:51ways to Implement that on there so let's
  2971. 1:52:54get rid of the facilitate individual
  2972. 1:52:56discussions with each team this might
  2973. 1:52:58take longer and then any which you're
  2974. 1:53:00going to follow up with a joint session
  2975. 1:53:02the best thing here to do is just to
  2976. 1:53:03bring them together and let them figure
  2977. 1:53:04it out together while you be a
  2978. 1:53:06facilitator of that meet in
  2979. 1:53:1053 the goal on a project is to foster a
  2980. 1:53:14culture of cooporation that drives the
  2981. 1:53:17teams towards exceptional
  2982. 1:53:19performance following a recommendation
  2983. 1:53:22from theany comp's founder the project
  2984. 1:53:23manager decides to adapt a servant
  2985. 1:53:26leadership approach what should the
  2986. 1:53:29project manager do to effectively embody
  2987. 1:53:32servant leadership so basically the
  2988. 1:53:35question is
  2989. 1:53:36asking what's what's servant leadership
  2990. 1:53:38principles here a Implement a
  2991. 1:53:42competitive reward system to incentivize
  2992. 1:53:44individual Excellence Drive project
  2993. 1:53:47outcome all right direct the team to
  2994. 1:53:50refine their strategies continue ously
  2995. 1:53:53until they devise an unbeatable plan for
  2996. 1:53:55the project execution all
  2997. 1:53:58right evaluate the project scrope
  2998. 1:54:01meticulously and set clear prioritized
  2999. 1:54:04goal to encourage team alignment and
  3000. 1:54:06focus all right establish a clear
  3001. 1:54:09project goals and nurture a supportive
  3002. 1:54:12environment that enables team members to
  3003. 1:54:13Excel and contribute to their fullest
  3004. 1:54:15potential now you really have to think
  3005. 1:54:17about servant leadership here the thing
  3006. 1:54:19about this question is that most of
  3007. 1:54:21these choices are technically good
  3008. 1:54:24there's one of them that's may not be a
  3009. 1:54:26good choice but three of them are
  3010. 1:54:29technically good choices now you have to
  3011. 1:54:31say well which one of those good ones
  3012. 1:54:32are servant leadership that's going to
  3013. 1:54:35be D here's why so a was the throwout
  3014. 1:54:40answer this you're creating a
  3015. 1:54:42competitive system a servant leader as a
  3016. 1:54:45servant leader you're not making a
  3017. 1:54:46competitive system you're supporting the
  3018. 1:54:49team you're not trying to make them be
  3019. 1:54:52better than each other you want a
  3020. 1:54:54generalizing specialist you don't want
  3021. 1:54:56team members feels like they have to
  3022. 1:54:58outperform the other to get something at
  3023. 1:55:00the end that's what a
  3024. 1:55:02is B direct the team to refine their
  3025. 1:55:05strategies this is not a bad thing but
  3026. 1:55:08notice you're directing the team to
  3027. 1:55:11refine their strategies until they find
  3028. 1:55:13an unbeatable plan your job is to
  3029. 1:55:15support the team not direct the team
  3030. 1:55:17evaluate the scope and said clear
  3031. 1:55:19priority you shouldn't be setting goals
  3032. 1:55:20for the team that's what the team does
  3033. 1:55:23all right prioritize goals to encourage
  3034. 1:55:26team alignment and then you're going
  3035. 1:55:27through the scope remember as a servant
  3036. 1:55:30leader what you're doing is you're
  3037. 1:55:32supporting the team technically the team
  3038. 1:55:34is
  3039. 1:55:34self-directing on these types of
  3040. 1:55:37projects the team is choosing the work
  3041. 1:55:39that they want to do remember seron
  3042. 1:55:41leadership is using ad out projects and
  3043. 1:55:42it's the team that says okay we're going
  3044. 1:55:44to do this work from the backlog that
  3045. 1:55:46comes from the top you know this is what
  3046. 1:55:48we're going to do in this Sprint and
  3047. 1:55:49you're just there to support not Direct
  3048. 1:55:5454 during the critical phase of a remote
  3049. 1:55:57operated environmental research project
  3050. 1:55:59a key analyst departs necessitating the
  3051. 1:56:03Swift uh simulation hard word to
  3052. 1:56:06pronounce of new members who lacks
  3053. 1:56:08familiarity with the Project Specific
  3054. 1:56:10challenges and objectives the extensive
  3055. 1:56:13project documentation exists yet the
  3056. 1:56:17Project's complexity might hinder the
  3057. 1:56:19rapid comprehension necessary for the
  3058. 1:56:21new Project's members task what
  3059. 1:56:24proactive measure should a project
  3060. 1:56:25manager Implement to ensure new members
  3061. 1:56:27effective integration all right this
  3062. 1:56:29this you know I didn't write this
  3063. 1:56:31question one of my team members didn't
  3064. 1:56:32this has a lot of big words in it so I
  3065. 1:56:35like this question because it's one of
  3066. 1:56:37these questions where you read it and
  3067. 1:56:39you're like what are they asking me that
  3068. 1:56:41that was my first thing when I read I
  3069. 1:56:43was like all these giant words I can I
  3070. 1:56:45barely can pronounce most of them what
  3071. 1:56:46are they asking me like I had to read
  3072. 1:56:48this one twice you will get questions
  3073. 1:56:49like this on your exam
  3074. 1:56:52uh and the first thing you do before
  3075. 1:56:53even looking at the choice you got to
  3076. 1:56:54say what are they looking for right what
  3077. 1:56:56what is it that they're asking me so a
  3078. 1:56:58couple quick things you notice that
  3079. 1:57:00there is a new member somebody is
  3080. 1:57:02leaving that's the key thing right uh
  3081. 1:57:04there's a new member but this person
  3082. 1:57:06doesn't have familiarity with this
  3083. 1:57:08particular Project Specific challenges
  3084. 1:57:10and objectives there is Project
  3085. 1:57:14documentation the question is proactive
  3086. 1:57:16measures should the project manager
  3087. 1:57:18Implement so we got to
  3088. 1:57:20remember what could we have done we're
  3089. 1:57:23not trying to fix the current problem
  3090. 1:57:25it's what could we have done to ensure
  3091. 1:57:26that this new integration this new
  3092. 1:57:28members was working well all right a
  3093. 1:57:31arrange for the new member to Shadow an
  3094. 1:57:33experienced team member for Hands-On
  3095. 1:57:34learning okay B encourage the new member
  3096. 1:57:37to study the doc thoroughly and followed
  3097. 1:57:39by a session to discuss their role all
  3098. 1:57:41right schedule a series of training
  3099. 1:57:43webinars on a projects methodology and
  3100. 1:57:45Technologies okay facilitate a workshop
  3101. 1:57:48with with the team focusing on projects
  3102. 1:57:50comp Ure all current members and new
  3103. 1:57:52member attend the question is which one
  3104. 1:57:55follows the the mindset which one brings
  3105. 1:57:58the team together which one ensures that
  3106. 1:58:01this new person is not just doing it by
  3107. 1:58:03themsel which one allows them to have
  3108. 1:58:06the team there with them well that's
  3109. 1:58:08going to be D if you think about it a is
  3110. 1:58:11more like go follow that guy you're like
  3111. 1:58:13giving away to work we don't want to do
  3112. 1:58:14that this one although I like be it's a
  3113. 1:58:17decent answer I encourage a new member
  3114. 1:58:20to study the document but this is is
  3115. 1:58:22more like hey you study that by yourself
  3116. 1:58:25you're not there with the person this
  3117. 1:58:27one here is more bringing the team
  3118. 1:58:28together series of webinars on the
  3119. 1:58:31Project's methodologies this is not
  3120. 1:58:32something that you could have done and
  3121. 1:58:35notice and Technologies this may delay
  3122. 1:58:38time the best thing here to do and
  3123. 1:58:40especially it's a
  3124. 1:58:41webinar uh this person might not be
  3125. 1:58:43participating which one drives that
  3126. 1:58:46servant leadership with drives that
  3127. 1:58:49mindset 55 in a routine progress check
  3128. 1:58:53and AD job project manager notice that a
  3129. 1:58:56lead analysis is habitu passing off less
  3130. 1:59:00complex analyst work to newer team
  3131. 1:59:02members claim it allows them to
  3132. 1:59:04concentrate on the
  3133. 1:59:06more integrate aspects of the project
  3134. 1:59:09what should the project manager do a
  3135. 1:59:12develop a rotational task assignment
  3136. 1:59:14system to ensure all members gain
  3137. 1:59:16experience across a range of tasks
  3138. 1:59:19directly assigned tasks based on the
  3139. 1:59:21complexity to Ure each team member works
  3140. 1:59:23with their capability establish a
  3141. 1:59:25mentorship program where senior members
  3142. 1:59:28guide Junior members to complex
  3143. 1:59:30tasks D organize a team discussion
  3144. 1:59:33during the next project update meeting
  3145. 1:59:36to evaluate the effectiveness of the
  3146. 1:59:37current task allegation method now let's
  3147. 1:59:40stop right here this was a tough
  3148. 1:59:42question it seems like an easy one but
  3149. 1:59:44it's not so the team came up with a way
  3150. 1:59:48of doing something that they feel is
  3151. 1:59:50effective what do you do again the team
  3152. 1:59:53is doing this themselves it's a lead
  3153. 1:59:55analyst you know it's passing passing
  3154. 1:59:57off his work to newer team members the
  3155. 1:59:59question is what do you do well here's
  3156. 2:00:01what you do first of all you don't stop
  3157. 2:00:05it you you don't know how effective this
  3158. 2:00:08is you don't this may be a great thing
  3159. 2:00:10for the team if you come in and you say
  3160. 2:00:13well let's do a rotational
  3161. 2:00:15system if you directly if you come in
  3162. 2:00:18and you say Hey you have to do it this
  3163. 2:00:20way
  3164. 2:00:22A and B puts you in charge puts you as
  3165. 2:00:25this direct project manager that says
  3166. 2:00:27hey this is where I want it done you
  3167. 2:00:29guys can't do that that just shuts the
  3168. 2:00:31team off you don't want to shut it off
  3169. 2:00:34you want to evaluate it you want to see
  3170. 2:00:35is this thing effective work with the
  3171. 2:00:37team this may be a great thing or it may
  3172. 2:00:39be a bad thing let the team work work
  3173. 2:00:42together C is also the same as a and b
  3174. 2:00:45now you are telling them what to do
  3175. 2:00:48remember the team is the Smart Ones I
  3176. 2:00:50always told you guys in the course
  3177. 2:00:51project manager we're not the Smart Ones
  3178. 2:00:53guys we are the collaborators we're the
  3179. 2:00:56facilitators this unless you know how to
  3180. 2:00:58code and and build buildings you're not
  3181. 2:01:00going to be the smart one on a project
  3182. 2:01:01we don't want to be the smart one we
  3183. 2:01:03want to be the one that collaborate on
  3184. 2:01:04the project we want to bring people
  3185. 2:01:06together we want people to get
  3186. 2:01:09along uh but we are not going to be the
  3187. 2:01:12one coding the applications so in this
  3188. 2:01:14one let this maybe maybe this is good we
  3189. 2:01:17don't know I think it's I think it's a
  3190. 2:01:18good
  3191. 2:01:19thing 56
  3192. 2:01:22as a critical update to an e-commerce
  3193. 2:01:25platform nearest completion the project
  3194. 2:01:27manager receives a last minute request
  3195. 2:01:29from stakeholders for additional
  3196. 2:01:31features that would significantly
  3197. 2:01:33enhance customer experience but require
  3198. 2:01:35extensive extra work from the team
  3199. 2:01:38potentially affected the launch timeline
  3200. 2:01:42what should the project manager do okay
  3201. 2:01:44so we got a e-commerce platform it's
  3202. 2:01:47almost finished in somebody wants to add
  3203. 2:01:49something what do you do
  3204. 2:01:53uh expedite the process by incorporating
  3205. 2:01:55the new features into the plan calculate
  3206. 2:01:58the additional cost and request an
  3207. 2:02:00immediate increase in budget reject the
  3208. 2:02:04the request outright maintain and focus
  3209. 2:02:06discuss the implementation of request
  3210. 2:02:08for development and presents feasible
  3211. 2:02:10solutions to the stakeholders follow the
  3212. 2:02:13mindset on this this is a pretty easy
  3213. 2:02:14question although we call this one extra
  3214. 2:02:16hard Ultra hard questions this one is
  3215. 2:02:18technically not customer requests
  3216. 2:02:21something what you're going to do well
  3217. 2:02:23the first thing is what I'm going to
  3218. 2:02:24tell you what you should never do is to
  3219. 2:02:26never requ never on on your exam if
  3220. 2:02:29there is ever a choice about reject
  3221. 2:02:31something don't select it if you get
  3222. 2:02:34choices that seem negative fire somebody
  3223. 2:02:37reject something say no to this stop
  3224. 2:02:39something it's probably never the answer
  3225. 2:02:42all right so don't reject something all
  3226. 2:02:44right because you notice it's
  3227. 2:02:46significantly enhanced customer
  3228. 2:02:47experience maybe we should add that
  3229. 2:02:50in calculate the extra cost and request
  3230. 2:02:54I think B is a good answer it's
  3231. 2:02:56analyzing the change but remember it's
  3232. 2:02:59best to come up and analyze the change
  3233. 2:03:02with the team not by yourself expedite
  3234. 2:03:05it just don't incorporate things like
  3235. 2:03:07that all right without revisiting the
  3236. 2:03:09project you need to you need to analyze
  3237. 2:03:12it all right you just can't incorporate
  3238. 2:03:13like
  3239. 2:03:14that 57 in the development phase of an
  3240. 2:03:18international Public Health Project a
  3241. 2:03:20project manager faces skep iism from
  3242. 2:03:22government Partners about the project
  3243. 2:03:24duration achievement due to limited
  3244. 2:03:26visibility into the project progress H
  3245. 2:03:30what action should the project manager
  3246. 2:03:31take to address this okay so notice the
  3247. 2:03:34problem here
  3248. 2:03:36is skepticism from people from folks
  3249. 2:03:40partners because they have limited
  3250. 2:03:43visibility so you notice I read the
  3251. 2:03:45question and I have a good understanding
  3252. 2:03:47of what it's asking initiate a monthly
  3253. 2:03:50newsletter focusing on project
  3254. 2:03:52Milestones challenges okay arrange for a
  3255. 2:03:55series of workshop with the project
  3256. 2:03:56beneficiaries to directly showcase the
  3257. 2:03:59Project's impact organize a virtual
  3258. 2:04:01meeting with government Partners discuss
  3259. 2:04:03how they would like project updates to
  3260. 2:04:05be done and yield any questions okay
  3261. 2:04:07compile an extensive report on Project
  3262. 2:04:09outcomes and plan activities to be
  3263. 2:04:10distributed quarterly this is a very
  3264. 2:04:13easy question if you read it carefully
  3265. 2:04:16the the main problem here is that the
  3266. 2:04:19skepticism is coming from where limit Li
  3267. 2:04:21mited
  3268. 2:04:22visibility what is the best action
  3269. 2:04:24should take should we just determine the
  3270. 2:04:27best way the project status should be
  3271. 2:04:30visible or should we ask them first what
  3272. 2:04:32do you think we're going to do well if
  3273. 2:04:34you said hey Andrew you know what let's
  3274. 2:04:36meet with them and ask them how they
  3275. 2:04:39would like these updates to take place
  3276. 2:04:41right project progress then you're
  3277. 2:04:44absolutely correct you notice a you're
  3278. 2:04:47determining what's best for them B
  3279. 2:04:50you're determining what's best for them
  3280. 2:04:52D you're determining what's best for
  3281. 2:04:54them you know what's best for someone I
  3282. 2:04:57don't know maybe you should ask them
  3283. 2:04:58that right what's the best update to
  3284. 2:05:01your CEO what's the best update to your
  3285. 2:05:03regulatory agency how about if you ask
  3286. 2:05:06your CEO how about if you ask that
  3287. 2:05:08agency that's what C is so remember be
  3288. 2:05:12collaborative 58 during the
  3289. 2:05:15implementation phase of an Innovative
  3290. 2:05:17Mobile Banking application a significant
  3291. 2:05:20update from regulatory bodies adjustment
  3292. 2:05:23to several key features of the app
  3293. 2:05:25requires adjustment notice requires
  3294. 2:05:28adjustment the agile project manager
  3295. 2:05:31arranges a meeting with the responsible
  3296. 2:05:33regulatory officer who is new to the
  3297. 2:05:35project to discuss these required
  3298. 2:05:37changes for this adop project what
  3299. 2:05:40action should the project manager take
  3300. 2:05:42to ensure these updates are efficiently
  3301. 2:05:46integrated into the scope okay eight I
  3302. 2:05:49want you guys to keep in mind ad job
  3303. 2:05:51project right because you got to keep in
  3304. 2:05:54mind something before we look at these
  3305. 2:05:55choices the way this is going to be some
  3306. 2:05:58kind of scope change the way you manage
  3307. 2:06:00scope on traditional versus agile is
  3308. 2:06:03vastly different make sure to review the
  3309. 2:06:05course on that all right hey request
  3310. 2:06:08that the compliance officer formalize a
  3311. 2:06:09regulatory updates and write and submit
  3312. 2:06:11them for approval from the Change
  3313. 2:06:13Control Board encourage a compliance to
  3314. 2:06:15detail regulatory changes for inclusion
  3315. 2:06:17in the product backlog instruct the
  3316. 2:06:19compliance office and immediately
  3317. 2:06:20communicate the changes to the develop
  3318. 2:06:21team in the next daily scrum ask
  3319. 2:06:24compliant off to assess the plan and
  3320. 2:06:25suggest modification to accommodate the
  3321. 2:06:27new regulation best answer here is going
  3322. 2:06:30to be correct B I think this one was
  3323. 2:06:34very difficult but you have to
  3324. 2:06:36understand how changes to Agile project
  3325. 2:06:39Scopes are done we know we have to
  3326. 2:06:42include this because it's required for
  3327. 2:06:44it to be done and in order for work to
  3328. 2:06:47get done on an agile project where must
  3329. 2:06:49the work be it must be in the product
  3330. 2:06:51backlog and you notice that in in a
  3331. 2:06:56they're going through a change control
  3332. 2:06:57board there's no really change control
  3333. 2:06:59board on an aob project a was the Thro
  3334. 2:07:02answer notice you don't communicate
  3335. 2:07:06scope changes during the daily scrum the
  3336. 2:07:09daily scrum is basically just to answer
  3337. 2:07:11three question what you did yesterday
  3338. 2:07:13what you're going to do today what
  3339. 2:07:13impediments you have not to come in and
  3340. 2:07:15introduce new task and all that first of
  3341. 2:07:18all that's something that should have
  3342. 2:07:20the the real good answer here would have
  3343. 2:07:21been for the compliance officer to meet
  3344. 2:07:23with a product owner to include into the
  3345. 2:07:26product backlog and to be prioritized
  3346. 2:07:28that would have been the best answer and
  3347. 2:07:29that the best thing closest to that is
  3348. 2:07:32B the compliance officer shouldn't be
  3349. 2:07:35assessing the current plan is this
  3350. 2:07:37person a project manager do they have a
  3351. 2:07:38lot of experience probably not best
  3352. 2:07:40answer B
  3353. 2:07:4359 guys are you enjoying this session
  3354. 2:07:45did I teach you a lot did you learn a
  3355. 2:07:47lot if you did can you please click on
  3356. 2:07:48that like button subscribe to the
  3357. 2:07:50channel to learn more of pass all your
  3358. 2:07:52certification exams let's get back to
  3359. 2:07:54this 59 a project manager noticed that
  3360. 2:07:57the integration process is more
  3361. 2:07:59cumbersome than anticipated
  3362. 2:08:01significantly slowing down the project
  3363. 2:08:03progress this issue is primarily due to
  3364. 2:08:06a newly implement it protocol that was
  3365. 2:08:09designed to enhance security what should
  3366. 2:08:11you do next all right introduce
  3367. 2:08:13additional training session for the team
  3368. 2:08:16on the new it protocol okay require the
  3369. 2:08:19team to double their efforts to meet the
  3370. 2:08:21deadline despite the
  3371. 2:08:22protocol okay organize a workshop to
  3372. 2:08:25identify workarounds to the it protocol
  3373. 2:08:28that does not compromise security all
  3374. 2:08:30right initiate discussion with it
  3375. 2:08:32leadership and the team to understand
  3376. 2:08:33the protocol implementation how best to
  3377. 2:08:35facilitate the project okay notice it
  3378. 2:08:37says what you're going to do next now
  3379. 2:08:40once again I want to mention don't do
  3380. 2:08:41anything don't uh do anything that's
  3381. 2:08:44negative and one of the ne things you
  3382. 2:08:46can do that's negative is overworking
  3383. 2:08:48people if they're going to double their
  3384. 2:08:50efforts what are you going to do make
  3385. 2:08:51them work 16 hours a day so that one
  3386. 2:08:54there we can get rid of that was a
  3387. 2:08:55throut answer follow the mindset bring
  3388. 2:08:58people together is there a way for the
  3389. 2:09:01team to implement this protocol
  3390. 2:09:04correctly um is there a way that it can
  3391. 2:09:07accommodate the we don't know that yet
  3392. 2:09:09the best thing here to do the next thing
  3393. 2:09:12you should be doing is meet with
  3394. 2:09:14everyone talk with everyone be
  3395. 2:09:15collaborative in this situation that's
  3396. 2:09:18what D is maybe then you may want to do
  3397. 2:09:22c so I would do D that's number one
  3398. 2:09:26maybe then we could do c some people C
  3399. 2:09:29was also a good choice it does say it
  3400. 2:09:31does not compromise security but you
  3401. 2:09:33shouldn't go and around their protocols
  3402. 2:09:35until you really understand what this is
  3403. 2:09:36about additional training sessions you
  3404. 2:09:39know what I may I'm going to do D then I
  3405. 2:09:41may do c then a or I may do D then a
  3406. 2:09:44then C but notice the comes first so you
  3407. 2:09:47got to keep in mind anytime you see that
  3408. 2:09:49word next you're saying what comes first
  3409. 2:09:52now I want you guys to keep in mind
  3410. 2:09:54anytime you see the word NEX or what do
  3411. 2:09:55you do first basically you're going to
  3412. 2:09:57put some of these choices in order what
  3413. 2:09:59the exam is asking you in this type of
  3414. 2:10:00question is hey what do you do next what
  3415. 2:10:02do you do first well the the choices are
  3416. 2:10:05going to be things you will be doing but
  3417. 2:10:07then you have to say to yourself okay
  3418. 2:10:10which one do we do first then second
  3419. 2:10:11then third that's really what it is like
  3420. 2:10:13put them in order and then give me the
  3421. 2:10:14first one that's really what this
  3422. 2:10:15question
  3423. 2:10:16is last question as a project manager
  3424. 2:10:20for an app develop development project
  3425. 2:10:22you are approached by a stakeholder with
  3426. 2:10:24a request to add feature that mirors the
  3427. 2:10:27functionality of something develop in a
  3428. 2:10:29previous Sprint the stako is looking for
  3429. 2:10:31a quick estimation on how this addition
  3430. 2:10:33might affect schedule and cost all right
  3431. 2:10:35so we want a quick estimate here what
  3432. 2:10:38steps should you take to accurately
  3433. 2:10:40provide this all right calculate the new
  3434. 2:10:42feature impact by comparing it with the
  3435. 2:10:44total budget and adjus in based on the
  3436. 2:10:46proportion of work already
  3437. 2:10:48completed that seem quick but you might
  3438. 2:10:52be able meet with the product owner to
  3439. 2:10:53help you with the estimate schedule
  3440. 2:10:56review the agile user stories and
  3441. 2:10:57velocity metrics from previous Sprint
  3442. 2:10:59related to similar feature to estimate
  3443. 2:11:01the effort required for the new addition
  3444. 2:11:04okay initiate a detail risk analys
  3445. 2:11:06incorporate a new feature focus on
  3446. 2:11:07potential schedule overuns and budget
  3447. 2:11:10now this one here I'll tell you guys
  3448. 2:11:12something about questions like this when
  3449. 2:11:14you get a question like this all four of
  3450. 2:11:16the choices are basically wrong you know
  3451. 2:11:19the the best answer in this question
  3452. 2:11:21if somebody comes to you and says how
  3453. 2:11:23long would this take how much would it
  3454. 2:11:25cost ask the team the team is but that's
  3455. 2:11:28not the choice you see on this exam it's
  3456. 2:11:32not just about choosing the correct
  3457. 2:11:34answer it's the best of the four this is
  3458. 2:11:37a question where well what is the best
  3459. 2:11:40of these four yeah they all kind of suck
  3460. 2:11:42but you know what I got to choose one
  3461. 2:11:45right that's the the least of the
  3462. 2:11:47suckiest answer if that makes sense so
  3463. 2:11:50that's why I like this question in here
  3464. 2:11:51and of course the answer is going to be
  3465. 2:11:53C that is correct because you know why
  3466. 2:11:56when you are estimating how long some
  3467. 2:12:00something should take or how what it may
  3468. 2:12:03cost the team does it by utilizing how
  3469. 2:12:07fast the velocity metrics how fast they
  3470. 2:12:09can do work and what the work is so if
  3471. 2:12:12the work is similar to previous stories
  3472. 2:12:14then use the metrics they use that is
  3473. 2:12:16the best answer this would take too long
  3474. 2:12:19a you never use a product or to help you
  3475. 2:12:21with estimation that's something you and
  3476. 2:12:22your team does d would take too long
  3477. 2:12:24because it's a risk analysis so C may
  3478. 2:12:27not be the correct answer the best best
  3479. 2:12:30answer but it's the best of those four
  3480. 2:12:33all right let's go question 61 during a
  3481. 2:12:36complex software development project the
  3482. 2:12:38project manager notices a
  3483. 2:12:40significant significant variances
  3484. 2:12:42between the plan and actual performance
  3485. 2:12:44metrics the key deliverables are at risk
  3486. 2:12:47of being delayed due to these
  3487. 2:12:49discrepancies what should the project
  3488. 2:12:50manager do first to ensure the Project's
  3489. 2:12:52objectives are being met a adjust the
  3490. 2:12:56timeline and communicate the changes to
  3491. 2:12:57all
  3492. 2:12:58stakeholders conduct a detailed analysis
  3493. 2:13:01of the performance data to identify root
  3494. 2:13:03causes request additional resources to
  3495. 2:13:07accelerate Project work and meet
  3496. 2:13:09scheduled targets reassess the project
  3497. 2:13:12management strategies to better align
  3498. 2:13:14with current
  3499. 2:13:16challenges okay now I want you guys to
  3500. 2:13:18notice in this question that you have
  3501. 2:13:20some kind of a problem and if you notice
  3502. 2:13:23the problem is what you notice that
  3503. 2:13:25there's variances between the plan and
  3504. 2:13:28the actual work that's going on so when
  3505. 2:13:31you have a problem on a project what
  3506. 2:13:33should you do first I mean that's what
  3507. 2:13:35the question here is asking and I want
  3508. 2:13:38you guys to remember something don't
  3509. 2:13:39take actions first assess review
  3510. 2:13:43evaluate analyze and that brings the
  3511. 2:13:45answer to B yes because when there's a
  3512. 2:13:49problem on a project the first thing the
  3513. 2:13:50project manager does is not to just
  3514. 2:13:53adjust the schedule without
  3515. 2:13:55understanding what that problem is it is
  3516. 2:13:58not to hire additional resources if they
  3517. 2:14:00don't know what that problem is notice
  3518. 2:14:03they're looking at the risk management
  3519. 2:14:04strategies it's already happened it's
  3520. 2:14:06not really at risk yet uh the best thing
  3521. 2:14:09here to do is to add do a detail
  3522. 2:14:11analysis of the actual data and and
  3523. 2:14:15notice this is the risk management
  3524. 2:14:17strategies not the risk strategies not
  3525. 2:14:19the risk responses if you're thinking
  3526. 2:14:20that these are the management Str how
  3527. 2:14:22you plan to manage risk it's definitely
  3528. 2:14:24not that one B is the best answer follow
  3529. 2:14:27the mindset on this one
  3530. 2:14:30question 62 in a large infrastructure
  3531. 2:14:34project the project manager is faced
  3532. 2:14:36with the challenge of sudden regulatory
  3533. 2:14:38changes that could potentially impact
  3534. 2:14:41the scope and cost the project is
  3535. 2:14:44currently on track but these changes
  3536. 2:14:47might
  3537. 2:14:48require adjustment in project exec ution
  3538. 2:14:52what should you do first so once again
  3539. 2:14:54you have that first thing update the
  3540. 2:14:56budget and timeline okay initiate a
  3541. 2:15:00stakeholder meeting to discuss the
  3542. 2:15:01impacts and adjustments conduct a
  3543. 2:15:04comprehensive review implement the
  3544. 2:15:07regulatory changes this question is very
  3545. 2:15:09similar to what we had before now you
  3546. 2:15:12notice it says here sudden regulatory
  3547. 2:15:15changes and it says could potentially
  3548. 2:15:17impact so this is it may impact the
  3549. 2:15:20project or may not best answer here is
  3550. 2:15:22just like in the first question we just
  3551. 2:15:24did is going to be to analyze this
  3552. 2:15:27review analyze this change how is it
  3553. 2:15:30going to affect the project in what
  3554. 2:15:32areas of the project how much is it
  3555. 2:15:34going to add or even remove from the
  3556. 2:15:36scope how much is it going to add or
  3557. 2:15:38remove from the budget and if the scope
  3558. 2:15:39and budget is being affected maybe so is
  3559. 2:15:41the schedule so you just don't want to
  3560. 2:15:44just go and update without preliminary
  3561. 2:15:47assessment get a good assessment you
  3562. 2:15:49should never just go update your project
  3563. 2:15:50but just preliminary
  3564. 2:15:52assessment you don't want to meet before
  3565. 2:15:54you meet with the stakeholders you need
  3566. 2:15:56to analyze this regulation
  3567. 2:15:59yourself never Implement like this D was
  3568. 2:16:02the Trad answer if you're selected D you
  3569. 2:16:04got to do some study you got to review
  3570. 2:16:06the mindset section in the course
  3571. 2:16:09anytime you see a question that says
  3572. 2:16:11first what should you do first it's
  3573. 2:16:13probably not to fix the problem it's
  3574. 2:16:16probably not to implement what
  3575. 2:16:18somebody's asking for it's more than
  3576. 2:16:20likely to analyze ize what they're
  3577. 2:16:21asking
  3578. 2:16:22for
  3579. 2:16:2563 a project manager is overseeing the
  3580. 2:16:28construction of a new office building
  3581. 2:16:30the project is running over budget due
  3582. 2:16:32to high cost of materials the project
  3583. 2:16:35team suggests several options to cut
  3584. 2:16:38cost including using less materials that
  3585. 2:16:42may slightly reduce
  3586. 2:16:45durability simplifying the build-in
  3587. 2:16:48design or eliminate some non-essential
  3588. 2:16:50features
  3589. 2:16:51which approach should the project
  3590. 2:16:52manager use to address costs want sure
  3591. 2:16:55the building meets its intended purpose
  3592. 2:16:57now this is a definition question you're
  3593. 2:17:00not really going to get the mindset here
  3594. 2:17:01but you got to understand the
  3595. 2:17:03definition is it earn value uh is it a
  3596. 2:17:06value engineering is it critical path is
  3597. 2:17:09it earn value or is it Monte Carlo best
  3598. 2:17:11answer here is going to be value
  3599. 2:17:15engineering what is value
  3600. 2:17:18engineering value engineer is something
  3601. 2:17:20we do all the time time value
  3602. 2:17:21engineering is if I tell you guys that I
  3603. 2:17:25want you guys to go out and buy a new
  3604. 2:17:27car and you're like okay I I'll buy that
  3605. 2:17:29new car but what you're going to do is
  3606. 2:17:31if I tell you what type of car you
  3607. 2:17:33should get get a Toyota Camry that's a
  3608. 2:17:37white one that's a 2024 you know the
  3609. 2:17:39scope your objective is to get that
  3610. 2:17:41thing as cheap as possible that's value
  3611. 2:17:44engineering value engineering is about
  3612. 2:17:47how can we deliver what the customer
  3613. 2:17:49wants in the cheapest is or the most
  3614. 2:17:51cost effective way which is basically
  3615. 2:17:53what this is describing critical path
  3616. 2:17:56method this is just formulas that's not
  3617. 2:17:59what they're asking this is uh tracking
  3618. 2:18:02the statistics of how much money you're
  3619. 2:18:04spending versus how much you should have
  3620. 2:18:06spent this is earn value I'm sorry
  3621. 2:18:09critical path method is actually your
  3622. 2:18:10schedule see I miss was I looked at
  3623. 2:18:12critical path method and and said earn
  3624. 2:18:14value SN value is all the formulas
  3625. 2:18:17you're going to be using in order to
  3626. 2:18:19track your budget and see how far how
  3627. 2:18:21far you're on or off your budget
  3628. 2:18:22critical path method allows you to build
  3629. 2:18:24an entire schedule that tells you your
  3630. 2:18:27critical path on a schedule and the
  3631. 2:18:29Monti Carlo is about different
  3632. 2:18:31simulations the Monti Carlo simulations
  3633. 2:18:33is trying hundreds or thousands of
  3634. 2:18:36different simulations to come up with a
  3635. 2:18:37budget schedule or even determine
  3636. 2:18:40risks all right a is the best answer now
  3637. 2:18:43I do have a few more questions on value
  3638. 2:18:45engineer I just put that in there
  3639. 2:18:46they're going to be used mostly as a
  3640. 2:18:49term here we go question
  3641. 2:18:5264 during a project Charter review
  3642. 2:18:54session a dispute arises between the
  3643. 2:18:57sponsor and the product owner witnessed
  3644. 2:19:00by the team and other uh stakeholders in
  3645. 2:19:03this situation what should the project
  3646. 2:19:05manager do to manage a conflict and
  3647. 2:19:07continue the project propose a follow-up
  3648. 2:19:09session to address unresolved issues
  3649. 2:19:12after the meeting okay facilitate the
  3650. 2:19:14meeting actively using conflict
  3651. 2:19:16resolution strategies to manage the
  3652. 2:19:18dispute and maintain team
  3653. 2:19:21cohesion adjourn the meeting immediately
  3654. 2:19:24suggest a cool and off
  3655. 2:19:26period arrange a separate conflict
  3656. 2:19:28resolution session with a neutral
  3657. 2:19:30facilitator to assist parties now your
  3658. 2:19:34exam wants you to take a direct approach
  3659. 2:19:37want you to fix that problem right away
  3660. 2:19:40so what are you going to do right you
  3661. 2:19:42want to take a confronting approach so
  3662. 2:19:44the best one here that's a confront and
  3663. 2:19:45approach is going to be B that's right
  3664. 2:19:49you want to facilitate this meeting
  3665. 2:19:51actively you're going to have in every
  3666. 2:19:53meeting you're going to have conflict
  3667. 2:19:56it's just the nature of the game it's
  3668. 2:19:58how humans work so what you got to do is
  3669. 2:20:00you got to take an active approach
  3670. 2:20:03conflict is not bad conflict is a good
  3671. 2:20:05thing always remember that I told you
  3672. 2:20:06that a 100 times in the course conflict
  3673. 2:20:08is good managed conflict is good
  3674. 2:20:12unmanaged conflict that can lead to a
  3675. 2:20:14World War where people may physically
  3676. 2:20:16hurt each other it's probably not a good
  3677. 2:20:17idea never let it get there so B best
  3678. 2:20:23answer question 65 a project manager's
  3679. 2:20:26task would organize in risk for a new
  3680. 2:20:28infrastructure project to ensure
  3681. 2:20:31comprehensive risk management the
  3682. 2:20:33project manager decides to use a risk
  3683. 2:20:35breakdown structure however the team is
  3684. 2:20:37consider the RBS may become overly
  3685. 2:20:40complex and difficult to manage what
  3686. 2:20:42should the project manager to create an
  3687. 2:20:44effective and manageable RBS develop a
  3688. 2:20:46simple categorization scheme that only
  3689. 2:20:49includes high priority risk okay use an
  3690. 2:20:52existing RBS from a similar project and
  3691. 2:20:53adapt it to the current project needs
  3692. 2:20:55all
  3693. 2:20:56right create a detailed RBS with
  3694. 2:20:58multiple subcategories to capture all
  3695. 2:21:00potential risks all right involve key
  3696. 2:21:02stakeholders in development of the RBS
  3697. 2:21:04to ensure it's comprehensive and
  3698. 2:21:06manageable this is a good question and
  3699. 2:21:07it's a tough question so first of all
  3700. 2:21:09you have to remember what an RBS is an
  3701. 2:21:12RBS is done to do what an RBS actually
  3702. 2:21:15doesn't have risk in it that's in the
  3703. 2:21:16risk register what does the RBS do the
  3704. 2:21:19RBS is there to categorize risks
  3705. 2:21:25okay now you notice a if you set a
  3706. 2:21:30develop a simple categorization scheme
  3707. 2:21:32that's fine it only includes High prior
  3708. 2:21:34it doesn't really have risk in it it's a
  3709. 2:21:37way to categorize the risk you're going
  3710. 2:21:39to use those categories in your risk
  3711. 2:21:41register uh and only includes high level
  3712. 2:21:43risks high high priority risk no it's
  3713. 2:21:45not only for that use an existing RBS
  3714. 2:21:48template to adapt it to the current I
  3715. 2:21:50like this idea but every project is
  3716. 2:21:53unique it's best to get people involved
  3717. 2:21:55the more people involved in telling you
  3718. 2:21:57to risk for your project the more likely
  3719. 2:21:59you're going to be successful at it a
  3720. 2:22:01detail with multiple subcategories to
  3721. 2:22:04capture all potential risk although this
  3722. 2:22:06may be a good one the best thing here is
  3723. 2:22:08to get more people involved on your
  3724. 2:22:11project
  3725. 2:22:12remember the more people involved the
  3726. 2:22:14more key stakeholders this could be team
  3727. 2:22:16members for for example subject matter
  3728. 2:22:19experts or whoever they'll tell you
  3729. 2:22:21better of how to develop that particular
  3730. 2:22:24thing question
  3731. 2:22:2666 in a construction project the project
  3732. 2:22:29manager decides to implement value value
  3733. 2:22:32engineering to enhance the Project's
  3734. 2:22:34value the goal is to improve the radio
  3735. 2:22:38the ratio of function to cost by
  3736. 2:22:41analyzing and proposing cost effective
  3737. 2:22:43Solutions what should the project
  3738. 2:22:45manager do first have the team conduct a
  3739. 2:22:47brain sermon session to remove functions
  3740. 2:22:49for cost reduction all right Focus
  3741. 2:22:52solely on reducing cost even if it means
  3742. 2:22:54compromise and a functionality engage
  3743. 2:22:56with stakeholder to understand the
  3744. 2:22:58critical
  3745. 2:22:59functions Implement all proposed changes
  3746. 2:23:02immediately to maximize cost now this
  3747. 2:23:05one here it does say value engineering
  3748. 2:23:07but it's really a mindset question you
  3749. 2:23:09notice once again it's this first like
  3750. 2:23:11what are we going to do first value
  3751. 2:23:13engineering is about how we make things
  3752. 2:23:16cheaper it's how we make things more
  3753. 2:23:17cost effective while delivering the same
  3754. 2:23:19amount of function
  3755. 2:23:21so one of the things we never want to do
  3756. 2:23:23is to remove functions just to reduce
  3757. 2:23:25cost it's about keeping the functions
  3758. 2:23:27the same so I'm going to eliminate this
  3759. 2:23:29right off the bat that should have been
  3760. 2:23:30one of the throwout answers and
  3761. 2:23:32Implement all proposed
  3762. 2:23:35changes uh we're going to get rid of
  3763. 2:23:37that because you just don't Implement
  3764. 2:23:38all the changes uh that's probably not
  3765. 2:23:41going to maximize function the best
  3766. 2:23:43answer here by the way is going to be C
  3767. 2:23:46engage with stakeholders you want to
  3768. 2:23:48understand what the functions are notice
  3769. 2:23:51before you start to optimize the project
  3770. 2:23:53before you start
  3771. 2:23:55to maybe reduce some functions maybe
  3772. 2:23:58find alternative to those functions
  3773. 2:24:00something a little cheaper that gives
  3774. 2:24:02them the same function understand what
  3775. 2:24:04the functions are never compromise on
  3776. 2:24:06functionality best answer to there guys
  3777. 2:24:08was
  3778. 2:24:10C
  3779. 2:24:1267 a project manager is conducting a
  3780. 2:24:14value engineering Workshop to identify
  3781. 2:24:17ways to improve a Project's value during
  3782. 2:24:19the session a team member just replacing
  3783. 2:24:20a component with a cheaper alternative
  3784. 2:24:23that slightly reduces performance but
  3785. 2:24:25saves a significant amount of money what
  3786. 2:24:27are the project manager do to determine
  3787. 2:24:29if this solutions aligns with value
  3788. 2:24:31engineer approv the change as it reduces
  3789. 2:24:34overall project
  3790. 2:24:36value uh project cost reject the change
  3791. 2:24:40as it reduces performance evaluate the
  3792. 2:24:42reduction and reduction and performance
  3793. 2:24:45impacts the project functionality
  3794. 2:24:47implement the change if it does not
  3795. 2:24:49require additional stakeholder approval
  3796. 2:24:51same thing here use the mindset
  3797. 2:24:53somebody's asking you for a change what
  3798. 2:24:55are you going to be doing the best thing
  3799. 2:24:57here guys is of course to evaluate that
  3800. 2:24:59change never approve reject or implement
  3801. 2:25:03the change just without evaluating the
  3802. 2:25:06change that's part of being a project
  3803. 2:25:10manager 68 a project manager is working
  3804. 2:25:14on a large infrastructure project that
  3805. 2:25:16is facing scheduled delays the project
  3806. 2:25:18manager wants to use advanc forecast and
  3807. 2:25:21technique to predict the future status
  3808. 2:25:24and progress of the
  3809. 2:25:26project the project team has been use an
  3810. 2:25:28evm to track progress what should the
  3811. 2:25:31project manager do to forecast the
  3812. 2:25:33project completion data accurately so
  3813. 2:25:36this one here is you notice they're
  3814. 2:25:38using
  3815. 2:25:39evm and they're want they they want to
  3816. 2:25:42use Advanced technique now this of
  3817. 2:25:43course is going to be with evm so what
  3818. 2:25:45are you going to do well apply the SPI
  3819. 2:25:48to the remaining work and calculate an
  3820. 2:25:50AC okay conduct a Monte Carlo simulation
  3821. 2:25:53to account for potential variations in
  3822. 2:25:55the schedule all right use CPM to
  3823. 2:25:58reevaluate the timeline Implement
  3824. 2:26:01rolling wave planning to adjust future
  3825. 2:26:04work plans best answer here guys is
  3826. 2:26:06going to be now this by the way is
  3827. 2:26:07really definition if you really
  3828. 2:26:09understood what evm means earn value
  3829. 2:26:11management then you know some of the
  3830. 2:26:12formulas included the SPI the schedule
  3831. 2:26:15performance index you can actually take
  3832. 2:26:17and use the schedule performance index
  3833. 2:26:19with the EAC to to forecast a schedule
  3834. 2:26:22making this the best answer Monte Carlo
  3835. 2:26:24simulations looks at things multiple
  3836. 2:26:27simulations that can affect the schedule
  3837. 2:26:30helps to build the schedule more than
  3838. 2:26:31predict the
  3839. 2:26:33schedule this is to build the timeline
  3840. 2:26:35your critical path method helps you to
  3841. 2:26:37develop a schedule not necessarily to
  3842. 2:26:40predict it Rolland wave planning is just
  3843. 2:26:43planning to replan here this is not
  3844. 2:26:46related really to it doesn't really have
  3845. 2:26:47much to do with evm because this is
  3846. 2:26:50planning and evm isn't
  3847. 2:26:53executed 69 a software development
  3848. 2:26:57project is Midway through its timeline
  3849. 2:26:58and the project manager notices that the
  3850. 2:27:00actual progress is lacking behind the
  3851. 2:27:03schedule the plan
  3852. 2:27:04schedule the sponsor is concerned about
  3853. 2:27:07meeting the upcoming Milestone what
  3854. 2:27:10technique should the project manager use
  3855. 2:27:12to address the sponsor's concern about
  3856. 2:27:16uh sponsors concern and predict the
  3857. 2:27:18project completion date create a trend
  3858. 2:27:21analysis using historical performance
  3859. 2:27:23data okay apply evm to calculate the
  3860. 2:27:25time variance use a three-point
  3861. 2:27:27estimation to forecast future tasks
  3862. 2:27:30perform a resource level analysis to
  3863. 2:27:32optimize resource allocation this one is
  3864. 2:27:35really a definition question also notice
  3865. 2:27:38notice is the project is lacking behind
  3866. 2:27:41the schedule you're concerned about
  3867. 2:27:42meeting it what technique basically
  3868. 2:27:45you're going to use and predict the
  3869. 2:27:47Project's completion date which one you
  3870. 2:27:49have which one is going to help us do
  3871. 2:27:50that the best answer is going to be evm
  3872. 2:27:53correct it's similar to this question
  3873. 2:27:55that we had
  3874. 2:27:56here evm the EAC in particular the
  3875. 2:28:00estimate at completion is a Formula that
  3876. 2:28:02can predict budget and it can also
  3877. 2:28:04predict schedule Trend analysis using
  3878. 2:28:08historical information while this is
  3879. 2:28:10good evm will be more accurate because
  3880. 2:28:12it's not just based on historical it's
  3881. 2:28:14based on what's happening right now uh
  3882. 2:28:17threo estimation it tells you the door
  3883. 2:28:20duration of something it doesn't really
  3884. 2:28:21predict anything resource leveling I'm
  3885. 2:28:24not sure how that predicts anything
  3886. 2:28:25resource leveling ensures no one really
  3887. 2:28:27works over
  3888. 2:28:29time question 70 a construction project
  3889. 2:28:32is experienced significant delays due to
  3890. 2:28:35many unforeseen weather conditions
  3891. 2:28:38causing concerns about meeting the final
  3892. 2:28:41deadline the project manager needs to
  3893. 2:28:43predict the potential impact on the
  3894. 2:28:45project completion dates and communicate
  3895. 2:28:48this what approach should you take
  3896. 2:28:51update the Gan chart with the new
  3897. 2:28:52weather delay information and manually
  3898. 2:28:54adjust the timeline all right use a
  3899. 2:28:56Monte Carlo anal simulation to predict
  3900. 2:28:58the probability of various completion
  3901. 2:28:59dates all right apply CPM analysis to
  3902. 2:29:03identify which activities can be
  3903. 2:29:04fast-tracked okay perform a cost benefit
  3904. 2:29:07analysis to decide whether to hire
  3905. 2:29:09additional resources to mitigate the
  3906. 2:29:11delays now the best answer here is going
  3907. 2:29:14to be a Monti card simulation now I want
  3908. 2:29:16to point out
  3909. 2:29:18something get notice
  3910. 2:29:20many unforeseen conditions this means
  3911. 2:29:24many simulations if you're looking for
  3912. 2:29:27something that goes through many many
  3913. 2:29:29different simulations or quote unquote
  3914. 2:29:31scenarios that's the definition of a
  3915. 2:29:34Monte Carlo again chared is used to make
  3916. 2:29:36the actual schedule CPM is used to make
  3917. 2:29:40the um the the schedule it's not going
  3918. 2:29:43to be used to to predict or to give you
  3919. 2:29:46the results of multiple scenarios or
  3920. 2:29:49simulations
  3921. 2:29:50cost benefit analysis not yet this is
  3922. 2:29:54still this here is right now they have
  3923. 2:29:57to figure out how they're going to
  3924. 2:29:59manage that weather conditions then they
  3925. 2:30:01can determine if they want to hire more
  3926. 2:30:02resources so if you're doing this the
  3927. 2:30:04best answer is the Monty Carlo
  3928. 2:30:06simulation let's get started project
  3929. 2:30:08manager is preparing for a quality audit
  3930. 2:30:11of a new software development project
  3931. 2:30:13the audit team needs to ensure the
  3932. 2:30:15Project's quality management system
  3933. 2:30:17aligns with the organizational standards
  3934. 2:30:20and identify areas for improvement what
  3935. 2:30:22is the most cost- effective course of
  3936. 2:30:24action for the project manager to take
  3937. 2:30:26after the quality audit so after the
  3938. 2:30:28audit's
  3939. 2:30:29done provide the team with all documents
  3940. 2:30:32and requests through a review okay
  3941. 2:30:34prepare the team to answer any questions
  3942. 2:30:36from the audit collaborate with the team
  3943. 2:30:38to understand their findings and develop
  3944. 2:30:40corrective actions focus on uh
  3945. 2:30:43presenting the success of the project to
  3946. 2:30:45highlight the team's performance now you
  3947. 2:30:47have to read this question carefully to
  3948. 2:30:49ensure it's says after the audit best
  3949. 2:30:52answer here is going to be C first of
  3950. 2:30:55all providing the team with all project
  3951. 2:30:58documents is something you probably do
  3952. 2:30:59during the audit preparing the team to
  3953. 2:31:01answer any question is something you
  3954. 2:31:02should do before the
  3955. 2:31:05audit collaborate with the team and
  3956. 2:31:08understand that their findings yes this
  3957. 2:31:10is something you're going to do after
  3958. 2:31:13the audit focus on presenting the
  3959. 2:31:15success uh of the project to highlight
  3960. 2:31:18the teams perform this is something you
  3961. 2:31:19can probably do after after the project
  3962. 2:31:20is done um not during the audit so read
  3963. 2:31:24this one carefully if you didn't get it
  3964. 2:31:28correct 72 during the execution phase of
  3965. 2:31:32a manufacturing project an internal
  3966. 2:31:34audit team reveal several
  3967. 2:31:37non-conformances in the production
  3968. 2:31:40process the audit team has identified
  3969. 2:31:42these issues as potential risk to the
  3970. 2:31:44success what should the project manager
  3971. 2:31:46do to these
  3972. 2:31:48non-confirmed immediately the production
  3973. 2:31:50process until all confirmes are resolved
  3974. 2:31:53okay develop and Implement corrective
  3975. 2:31:56actions to address these confirmes
  3976. 2:31:57identified by the
  3977. 2:31:59team okay dismiss the non-conformist
  3978. 2:32:02minor issues and continue okay informed
  3979. 2:32:05the sponsor by these confirmed request
  3980. 2:32:07additional resources now this here is
  3981. 2:32:10not asking you what to do first this is
  3982. 2:32:12telling you to solve the problem if you
  3983. 2:32:14get that part of not is not what should
  3984. 2:32:16you do next or what should you do first
  3985. 2:32:18it's literally asking you how are you
  3986. 2:32:19going to fix this there's a couple
  3987. 2:32:20things you shouldn't be doing best
  3988. 2:32:22answer here is going to be to fix the
  3989. 2:32:25problem right develop and come up with
  3990. 2:32:27corrective actions to fix these
  3991. 2:32:33non-confirmed project like that
  3992. 2:32:35especially for something that is going
  3993. 2:32:38to
  3994. 2:32:39be as potential
  3995. 2:32:42risks right you want to evaluate it you
  3996. 2:32:44want to come up with responses to it
  3997. 2:32:46just don't halt a project like that the
  3998. 2:32:48only time you may halt a project is is
  3999. 2:32:50when safety issues for example somebody
  4000. 2:32:52might die or get injured you're breaking
  4001. 2:32:54some kind of law those are reasons to
  4002. 2:32:56Halt a project but not here this is not
  4003. 2:32:59what this is never dismiss never kick
  4004. 2:33:02the can down the road or just never do
  4005. 2:33:04nothing that's what this is that means
  4006. 2:33:07you're just going to continue doing what
  4007. 2:33:08you're doing and ignore them never
  4008. 2:33:09ignore anyone never go to your sponsor
  4009. 2:33:12for help your sponsor shouldn't be the
  4010. 2:33:13one that's helping you solve problems
  4011. 2:33:15they hired you to solve the problem not
  4012. 2:33:18them 70
  4013. 2:33:20three in the middle of a large
  4014. 2:33:21infrastructure project the project
  4015. 2:33:23manager receives an
  4016. 2:33:25external uh quality auditor highlighting
  4017. 2:33:28several significant non-confirming these
  4018. 2:33:30issues if not addressed could impact the
  4019. 2:33:32timeline of budget what should you do to
  4020. 2:33:34address these non-confirmed
  4021. 2:33:37effectively continue the plan and
  4022. 2:33:39monitor these non-confirmed escalate all
  4023. 2:33:41right request sponsor to review the
  4024. 2:33:43auditor report all right adjust the
  4025. 2:33:45scope to account for identified
  4026. 2:33:47non-confirmed integrate the recommend
  4027. 2:33:50corrective actions from the audit
  4028. 2:33:52reports into the plan all right what is
  4029. 2:33:55the best answer now this question when
  4030. 2:33:58we wrote it we notice it's not all of
  4031. 2:34:00these are going to be great choices but
  4032. 2:34:02you got to choose the best of the four
  4033. 2:34:04what did you guys
  4034. 2:34:05get some of these didn't make sense at
  4035. 2:34:07all for example don't do nothing
  4036. 2:34:10continue with the current plan and
  4037. 2:34:11monitor this is literally doing nothing
  4038. 2:34:14request is never go to your sponsor
  4039. 2:34:16right never go to the sponsor the only
  4040. 2:34:18time you go to your sponsor is for an
  4041. 2:34:20approval or disapproval you shouldn't go
  4042. 2:34:22to your sponsor for guidance on how to
  4043. 2:34:24manage a project remember they hired you
  4044. 2:34:26for that not them never adjust the scope
  4045. 2:34:30like that the scope is probably going to
  4046. 2:34:32require some kind of uh change request
  4047. 2:34:35if it's a traditional or only the
  4048. 2:34:38product owner can add to the product
  4049. 2:34:40backlog if you're changing agile scope
  4050. 2:34:42definitely not that integrate these yes
  4051. 2:34:46you
  4052. 2:34:47notice uh you re receive a report that
  4053. 2:34:51highlight non-confirmed these are not
  4054. 2:34:53address good impact the best answer here
  4055. 2:34:55is D of these four now I want I left
  4056. 2:34:57this like this because I want you guys
  4057. 2:34:59to point out I want to point out
  4058. 2:35:00something critical this isn't a test of
  4059. 2:35:03choose the correct answer it's choose
  4060. 2:35:05the best of the four now I'm going to
  4061. 2:35:07tell you I don't like d d kind of suck
  4062. 2:35:10yeah but it's the least of the suckiest
  4063. 2:35:13answer remember it's a game of four
  4064. 2:35:15choices it's a game
  4065. 2:35:17of what is the best of the
  4066. 2:35:21four none of them have to be correct
  4067. 2:35:23it's just that one has to be more
  4068. 2:35:25correct than the other three one has to
  4069. 2:35:27be the least of the suckiest answer if
  4070. 2:35:30you know what I mean the other three a b
  4071. 2:35:32and c you would probably never do but
  4072. 2:35:35you're probably saying hey Andrew it
  4073. 2:35:36doesn't say in the question that it
  4074. 2:35:38doesn't include the corrective actions
  4075. 2:35:40in a report you're absolutely right but
  4076. 2:35:42that's still D is still better than ab
  4077. 2:35:43and C if you know what I mean question
  4078. 2:35:4674 project manager is preparing to over
  4079. 2:35:49oversee the development of a new mobile
  4080. 2:35:51application during a stakeholder meeting
  4081. 2:35:54a senior executive expresses concern
  4082. 2:35:56that the project may not align with the
  4083. 2:35:58Strategic goals of the organization the
  4084. 2:36:01project manager needs to address this
  4085. 2:36:03concern to ensure continued support and
  4086. 2:36:06Alignment what should you do next
  4087. 2:36:09reassure the executive that the team is
  4088. 2:36:11capable of delivering the project on
  4089. 2:36:13time and within budget review the
  4090. 2:36:16project alignment with the Strategic
  4091. 2:36:18goals conduct a schedule a follow-up
  4092. 2:36:22meeting with the executive to discuss
  4093. 2:36:24project benefits in more detail per
  4094. 2:36:27conduct a performance review of the
  4095. 2:36:29project team to identify any areas for
  4096. 2:36:31improvement now let's take a look at
  4097. 2:36:34this you notice this stakeholder is
  4098. 2:36:36saying hey this project is not aligned
  4099. 2:36:39with our goals so what should you do
  4100. 2:36:41next well here's what you do next maybe
  4101. 2:36:44you should analyze to see if it is
  4102. 2:36:47aligned with the Strategic goal before
  4103. 2:36:48taking any
  4104. 2:36:50action a is something you don't want to
  4105. 2:36:53do this is your saying yes it is it's
  4106. 2:36:56already aine don't worry about it this
  4107. 2:36:58is doing nothing never do nothing
  4108. 2:37:01schedule a follow-up meeting you know
  4109. 2:37:03what I would probably do B then I would
  4110. 2:37:06do c understand does it really meet it
  4111. 2:37:08maybe it's something you should review
  4112. 2:37:10and notice your preparing it's like
  4113. 2:37:12you're in the beginning of this thing
  4114. 2:37:14conduct the performance review of the
  4115. 2:37:15team you haven't really basically
  4116. 2:37:17started this project yet so I'm not sure
  4117. 2:37:19why you're doing that that best answer
  4118. 2:37:20is
  4119. 2:37:22B 75 a project manager is working on a
  4120. 2:37:26government infrastructure project that
  4121. 2:37:29requires strict compliance with company
  4122. 2:37:32standards during a routine review the
  4123. 2:37:35project manager discovers that some
  4124. 2:37:37activities may may not meet the required
  4125. 2:37:40standards what should you
  4126. 2:37:41do halt all activities until a full
  4127. 2:37:44compliance review is conducted okay
  4128. 2:37:47update the project plan to include
  4129. 2:37:49additional quality checks all right
  4130. 2:37:51notify regulatory t with non-compliance
  4131. 2:37:53activities conduct the root CA to
  4132. 2:37:54identify the reasons for non-compliance
  4133. 2:37:56and Implement corrective actions if
  4134. 2:37:58you've been following along this video
  4135. 2:37:59this one should be pretty easy you
  4136. 2:38:02notice that first of all it's not that
  4137. 2:38:04the project is not meeting the
  4138. 2:38:06compliance it's not like it's 100% doing
  4139. 2:38:09that it does say me so watch the key
  4140. 2:38:11words and that brings the answer to
  4141. 2:38:13identif before you if it wasn't needing
  4142. 2:38:15the compliance and you're doing
  4143. 2:38:16something against the law I would have
  4144. 2:38:18probably said maybe is best but you
  4145. 2:38:22should never work against the law by the
  4146. 2:38:24way if a project is doing something and
  4147. 2:38:26it's against the law people may get hurt
  4148. 2:38:28or somebody might go to jail you should
  4149. 2:38:30probably stop it but if something might
  4150. 2:38:32be happening just don't pull the project
  4151. 2:38:34like that analyze it to see what's going
  4152. 2:38:37on and then if you find it maybe then
  4153. 2:38:39you do that update the plan not yet
  4154. 2:38:42analyze it to see what the corrective
  4155. 2:38:44actions are don't go notify of potential
  4156. 2:38:47non-compliance if you go to the
  4157. 2:38:49regulator ERS and you said hey there's
  4158. 2:38:50some potential things they're going to
  4159. 2:38:51say can you make sure before you let us
  4160. 2:38:55know 76 during the construction of a new
  4161. 2:38:58building the project manager lawence
  4162. 2:39:00that unforeseen geological issues will
  4163. 2:39:05significantly increase the cost beyond
  4164. 2:39:07the budget what should you do next
  4165. 2:39:09adjust the timeline to reduce labor cost
  4166. 2:39:12okay consult with a geological
  4167. 2:39:14technician for remote cost effective
  4168. 2:39:16solution implement the phase
  4169. 2:39:18Construction analyze the situation
  4170. 2:39:20consider all possible follow the mindset
  4171. 2:39:22on this one this one does have two good
  4172. 2:39:24answers the best answer here is to
  4173. 2:39:26analyze the situation hey use the
  4174. 2:39:28mindset on this one never adjust a
  4175. 2:39:30timeline like that probably requires a
  4176. 2:39:32change request Implement a phase
  4177. 2:39:34approach I'm not sure how that's going
  4178. 2:39:36to save money uh consult with a G Alo I
  4179. 2:39:41think D and B were good answers it's
  4180. 2:39:44just that this here is a more
  4181. 2:39:45incompressible answer it has more it it
  4182. 2:39:47it pulls more into it then B
  4183. 2:39:51does
  4184. 2:39:5377 as a project manager overseeing the
  4185. 2:39:55roll out of a new it systems it's
  4186. 2:39:58discovered halfway through the fiscal
  4187. 2:40:00year that several critical software
  4188. 2:40:02enhancement funded by this year budget
  4189. 2:40:04will not be completed on
  4190. 2:40:07schedule these enhancements were
  4191. 2:40:09initiated based on midyear changes and
  4192. 2:40:11are critical for the success what you
  4193. 2:40:13you do first initiate a review of the
  4194. 2:40:15scope to identify areas for schedule
  4195. 2:40:18acceleration okay
  4196. 2:40:20collaborative team to assess the project
  4197. 2:40:21deliverable and focus on critical
  4198. 2:40:23enhancements okay Engage The spons with
  4199. 2:40:26sponsor to adjust expectations and
  4200. 2:40:28secure support for external timelines
  4201. 2:40:30communicate the progress and adjust the
  4202. 2:40:32timelines for these enhancements to the
  4203. 2:40:34finance department now this one has two
  4204. 2:40:36good answers also best answer here don't
  4205. 2:40:39forget what are you going to do first
  4206. 2:40:42best answer here is going to be work
  4207. 2:40:44with your team now initiate a review of
  4208. 2:40:47the scope to identify areas for schedule
  4209. 2:40:49acceleration that's not something you're
  4210. 2:40:51going to be able to do by yourself the
  4211. 2:40:53team is going to have to help you do
  4212. 2:40:54that engage adjust their expectations
  4213. 2:40:58although that sounds okay this is the
  4214. 2:41:02second best answer that sounds okay and
  4215. 2:41:05secure supporting of the extended
  4216. 2:41:07deadlines that may not be okay to them
  4217. 2:41:09they don't want it to be
  4218. 2:41:11extended you don't want to just work
  4219. 2:41:13with the finance department you got to
  4220. 2:41:14work with your customers on this making
  4221. 2:41:15this the best answer who is the best
  4222. 2:41:18people to tell you how to implement a
  4223. 2:41:20change the team who's the best people to
  4224. 2:41:23tell you how to fix something the team
  4225. 2:41:26who's the best person to give you
  4226. 2:41:28problems to your solution the team they
  4227. 2:41:31can be the best
  4228. 2:41:33answer 78 in the midst of a major
  4229. 2:41:36software development project the project
  4230. 2:41:38manager is preparing for an upcoming
  4231. 2:41:40executive in-depth review the project
  4232. 2:41:44manager must present how the Project's
  4233. 2:41:46progress is being tracked and measured
  4234. 2:41:49to the executive team who are Keen to
  4235. 2:41:52understand how effectively the project
  4236. 2:41:54is being
  4237. 2:41:55managed so they want to know how it's
  4238. 2:41:57being tracked and
  4239. 2:41:58measured what should the project manager
  4240. 2:42:00focus on in their presentation uh focus
  4241. 2:42:03on in their presentation for the
  4242. 2:42:04Executive review provide a detailed rep
  4243. 2:42:07report on team productivity and
  4244. 2:42:09individual
  4245. 2:42:10contributions compile Eva metrics
  4246. 2:42:12including the SV CV for comprehensive
  4247. 2:42:15review Jing discussed the implementation
  4248. 2:42:18of the new project manager
  4249. 2:42:19tool and its impact on Project
  4250. 2:42:22efficiency outline the risk encountered
  4251. 2:42:25so far in the mitigation strategies this
  4252. 2:42:27one I thought was pretty straightforward
  4253. 2:42:29if you know evm if you know what SV and
  4254. 2:42:31CV stood for it was a pretty easy
  4255. 2:42:33question because if you
  4256. 2:42:35notice EV or evm allows you to measure
  4257. 2:42:40the performance of your project if you
  4258. 2:42:42notice these questions you really don't
  4259. 2:42:44need to know the formulas but you need
  4260. 2:42:45to understand what they are
  4261. 2:42:49productivity and individual contribution
  4262. 2:42:51wouldn't tell you how to how the project
  4263. 2:42:53is being measured measured generally
  4264. 2:42:55means you're measuring time and cost is
  4265. 2:42:57generally what you measure the
  4266. 2:42:58most uh I'm not sure what this
  4267. 2:43:00implementation tool is going to help us
  4268. 2:43:02measure and track so is risk the best
  4269. 2:43:05thing here what do we measure on a
  4270. 2:43:07project guys time and
  4271. 2:43:10money 79 leading a new uh new agile
  4272. 2:43:15Global Environmental Conservation
  4273. 2:43:17project the project manager overseas a
  4274. 2:43:20diverse team distributed across several
  4275. 2:43:23continents recognizing the dver the
  4276. 2:43:25diverse cultural cultural backgrounds
  4277. 2:43:28within the team the project manager aims
  4278. 2:43:30to Foster unity and effective
  4279. 2:43:32collaboration what is the most effective
  4280. 2:43:34action for the project manager to
  4281. 2:43:36enhance team
  4282. 2:43:38integration organized a series of cross
  4283. 2:43:40functional training for all teams to
  4284. 2:43:43educate them about cultural differences
  4285. 2:43:46okay set up a digital collaboration
  4286. 2:43:48space for team remember to share
  4287. 2:43:49personal and professional updates all
  4288. 2:43:51right our in monthly face Toof face
  4289. 2:43:53Retreats all right engage uh encourage
  4290. 2:43:56open communication and demonstrate
  4291. 2:43:58confident team ability and their
  4292. 2:44:00contributions two good answers on this
  4293. 2:44:02one right I know you're stuck between
  4294. 2:44:04two I didn't make this question my team
  4295. 2:44:06member did and I was kind of stuck
  4296. 2:44:08between two myself what two were you
  4297. 2:44:10stuck between was it A and D because
  4298. 2:44:12that's what I was all right I'm going to
  4299. 2:44:14eliminate the bad ones okay this is a
  4300. 2:44:16monthly face to face is probably not um
  4301. 2:44:20doable it is not a project where you
  4302. 2:44:22just have a few it notice it's a global
  4303. 2:44:25conservation project and it's team
  4304. 2:44:28distributed across the globe maybe not
  4305. 2:44:30feasible a digital collaboration space
  4306. 2:44:32is not just for people to share this is
  4307. 2:44:34given a way to work to
  4308. 2:44:35them I liked a series of crosss for all
  4309. 2:44:39teamers educate them about cultural
  4310. 2:44:41differences you could do that or you can
  4311. 2:44:44encourage open communication and let the
  4312. 2:44:47team work together you know if you're
  4313. 2:44:51the key the key here if you're
  4314. 2:44:54wondering why is it a because there's a
  4315. 2:44:57key word in the question agile remember
  4316. 2:45:01something on an agile project you're a
  4317. 2:45:03servant leader the team is a
  4318. 2:45:06self-directing
  4319. 2:45:08self-managing team and what you need to
  4320. 2:45:11do sometimes as a servant leader you
  4321. 2:45:12need to step back and let the
  4322. 2:45:15team figure out ways you don't want it
  4323. 2:45:18to get out of hands maybe if it gets out
  4324. 2:45:20of hand maybe then you would do a but
  4325. 2:45:23them have confidence in the team ability
  4326. 2:45:27to keep on progressing and encourage
  4327. 2:45:29that open line of communication that
  4328. 2:45:30would be best versus you coming up with
  4329. 2:45:33a solution see the difference in this in
  4330. 2:45:35D you're letting the team figure it out
  4331. 2:45:37complete solution and a you're giving
  4332. 2:45:39them the solution trick question by the
  4333. 2:45:42way 80 at the onset of a healthcare
  4334. 2:45:45software upgrade project the client
  4335. 2:45:47emphasizes that the the the enhancements
  4336. 2:45:50are critical to improving patient care
  4337. 2:45:52and operational efficiency potentially
  4338. 2:45:56affecting the healthcare providers
  4339. 2:45:57reputation and financial performance the
  4340. 2:46:00client is eager to
  4341. 2:46:01see improvements implemented in the
  4342. 2:46:04shortest time
  4343. 2:46:06frame what should the project manager do
  4344. 2:46:09utilize agile methodologies to ensure
  4345. 2:46:11rapid delivery of high priority features
  4346. 2:46:13all right Implement a waterfall method
  4347. 2:46:15to automate testing okay establish a
  4348. 2:46:18dedicated time task force focus on
  4349. 2:46:20critical system upgrades first all
  4350. 2:46:23right conduct a series of stakeholder
  4351. 2:46:25Workshop to prioritize software
  4352. 2:46:26enhancement based on impact the best
  4353. 2:46:28answer here guys uh notice this project
  4354. 2:46:31has just
  4355. 2:46:32started and it's a software development
  4356. 2:46:34project this project is riped ripe for
  4357. 2:46:39agile why because you notice um there
  4358. 2:46:43are things that they want first they
  4359. 2:46:45want to see the Improvement implemented
  4360. 2:46:47the good thing about agile especially SC
  4361. 2:46:48prom is that you get the most important
  4362. 2:46:50features first waterfall is not going to
  4363. 2:46:53be something that's going to be done in
  4364. 2:46:55the shortest time frame that takes the
  4365. 2:46:57longest a dedicated task focus on
  4366. 2:46:59critical the the only person that can
  4367. 2:47:01tell you the critical is the customers
  4368. 2:47:03themselves product owner conduct a
  4369. 2:47:06series of state to prioritize software
  4370. 2:47:07based this is going to be done by the
  4371. 2:47:09product owner making a the best answer
  4372. 2:47:12practice question
  4373. 2:47:1381 in the middle of an urban Pro
  4374. 2:47:16development project the project manager
  4375. 2:47:19faces a setback as a key engineer and an
  4376. 2:47:22urban planner announced their immin
  4377. 2:47:25imminent departure from the team the
  4378. 2:47:28project is already on a strict timeline
  4379. 2:47:30with critical mindset with critical
  4380. 2:47:33Milestones approaching the remaining
  4381. 2:47:35team members are concerned about the
  4382. 2:47:37increased workload and the potential
  4383. 2:47:39impact on the project schedule what
  4384. 2:47:42should the project manager
  4385. 2:47:43do increase the workload on incre on
  4386. 2:47:46team members to cover the task of The
  4387. 2:47:48Departed
  4388. 2:47:49individuals out Outsource specific
  4389. 2:47:52critical tasks to specialize firm to
  4390. 2:47:55keep the project on schedule work with
  4391. 2:47:57the remaining team members to recruit
  4392. 2:47:58new members to complete the workload and
  4393. 2:48:01apply for a project timeline extension
  4394. 2:48:04due to unforeseen staff and challenges
  4395. 2:48:07now in this particular
  4396. 2:48:09question which is something that you're
  4397. 2:48:11going to see common on your exam is that
  4398. 2:48:15somebody
  4399. 2:48:16left some team members left what do you
  4400. 2:48:19do well there's a couple things you
  4401. 2:48:21don't do and there's a couple things you
  4402. 2:48:22should be doing for example one of the
  4403. 2:48:26things here that we shouldn't be doing
  4404. 2:48:29ever on any test question is never work
  4405. 2:48:32people over over time never overwork
  4406. 2:48:36anyone part of the mindset tells us that
  4407. 2:48:40when you are managing a team never
  4408. 2:48:43overwork them in any scenario now in
  4409. 2:48:46real life it may be acceptable but for
  4410. 2:48:49your exam if that choice seems you're
  4411. 2:48:53reading it you're like Hey we're going
  4412. 2:48:55to be working this guy overtime we're
  4413. 2:48:56going to be overworking the employees
  4414. 2:49:00never an answer get rid of
  4415. 2:49:02that
  4416. 2:49:03Outsourcing not something you can do
  4417. 2:49:05right away all right although they may
  4418. 2:49:08solve the problem it's not something you
  4419. 2:49:10can do right away you have to go to a
  4420. 2:49:12whole procurement
  4421. 2:49:13process apply for this is going to
  4422. 2:49:16require some form of a change request
  4423. 2:49:18you just can't apply for that the best
  4424. 2:49:20thing here you can do is to work with
  4425. 2:49:22the mindset and make sure that you
  4426. 2:49:24involve your team members to help you
  4427. 2:49:27remember let the team help you let the
  4428. 2:49:29team figure things out not just you
  4429. 2:49:31figuring it out and in this scenario the
  4430. 2:49:34best choice here is to work with the
  4431. 2:49:36team to help them Recruit new members in
  4432. 2:49:40other words you're bringing you're
  4433. 2:49:41making them involv you're bringing them
  4434. 2:49:43on the project or I should say on the
  4435. 2:49:47issue 82
  4436. 2:49:50a firm planed to transition from lean a
  4437. 2:49:53transition to planed to transition to
  4438. 2:49:56lean development techniques the project
  4439. 2:49:58manager encounters resistance from
  4440. 2:50:00several worldwide uh stakeholders weary
  4441. 2:50:03of the new processes the project manager
  4442. 2:50:06needs to build confidence in lean
  4443. 2:50:09methodologies amongst the stakeholders
  4444. 2:50:11what uh what should the project manager
  4445. 2:50:14propose schedule meetings with the
  4446. 2:50:16stakeholder to address concerns all
  4447. 2:50:18right introduce a reward systems for
  4448. 2:50:20early adapters of lean techniques okay
  4449. 2:50:24adapt the lean development uh accept
  4450. 2:50:26that accept that lean development will
  4451. 2:50:28not work in all companies organize a
  4452. 2:50:31companywide seminar the history and
  4453. 2:50:32principles of lean now this one here
  4454. 2:50:35although I said this was Ultra hard this
  4455. 2:50:36one should be pretty easy couple things
  4456. 2:50:39here that you don't want to do is if you
  4457. 2:50:42ever read a question and it seems that
  4458. 2:50:45one of the choices is to do nothing it's
  4459. 2:50:48not the end answer never do nothing all
  4460. 2:50:51right always remember that so in that
  4461. 2:50:53one I'm going to eliminate C right off
  4462. 2:50:56the bat right off the bat and the reason
  4463. 2:50:58is
  4464. 2:50:59because in this one you're just saying
  4465. 2:51:01okay I guess lean development doesn't
  4466. 2:51:03work and you just move on if the choice
  4467. 2:51:05is to do nothing that's not the answer
  4468. 2:51:07introduce your reward systems for early
  4469. 2:51:09adap well they already don't want it but
  4470. 2:51:12you putting that in place they already
  4471. 2:51:13don't want it so you telling people
  4472. 2:51:16there going to be some kind of reward
  4473. 2:51:17you have to figure out what their
  4474. 2:51:19concern is a company wi this is the
  4475. 2:51:21history and principles of the it's not
  4476. 2:51:23addressing their concern the best thing
  4477. 2:51:25here you can do is to meet with them see
  4478. 2:51:28what what exactly like they don't like
  4479. 2:51:32and then you can explain the benefits to
  4480. 2:51:33them making death the best
  4481. 2:51:36answer 83 leading a significant
  4482. 2:51:41initiative to overhaul a corporation's
  4483. 2:51:43it infrastructure the project manager
  4484. 2:51:45has already navigated through several
  4485. 2:51:47phases success y with the CTO overseeing
  4486. 2:51:51the initiatives departs unexpectedly oh
  4487. 2:51:54when the CTO departs unexpectedly okay
  4488. 2:51:57so a major person is
  4489. 2:51:59leaving the incoming CTO then pauses the
  4490. 2:52:02initiative pinned in a comprehens review
  4491. 2:52:05of the project alignment with the
  4492. 2:52:07company's revised technological
  4493. 2:52:11Direction what is the most effective
  4494. 2:52:14first step for the project manager so
  4495. 2:52:16basically what should you do first so in
  4496. 2:52:18this question we have a key stakeholder
  4497. 2:52:21is leaving new stakeholder or should say
  4498. 2:52:24left new stakeholder comes in basically
  4499. 2:52:27what you the first arrange a meeting
  4500. 2:52:29with the new CTO to outline the project
  4501. 2:52:32benefits and strategic alignment prepare
  4502. 2:52:35a detailed report comparing the current
  4503. 2:52:39project status with industry standards
  4504. 2:52:41and
  4505. 2:52:42Trends initiate a project audit to
  4506. 2:52:45demonstrate compliance with best
  4507. 2:52:47practices and regulatory
  4508. 2:52:50requirements develop a contingency plan
  4509. 2:52:53addressing political uh potential
  4510. 2:52:55changes requested by the new
  4511. 2:52:58CTO okay let me say this first common
  4512. 2:53:02question on the exam you're going to
  4513. 2:53:03find somebody left a major stakeholders
  4514. 2:53:06left what do you do well there's a
  4515. 2:53:08couple things you don't do like just
  4516. 2:53:10don't change anything around the best
  4517. 2:53:11thing here to do when somebody leaves
  4518. 2:53:13and somebody new comes in is to meet
  4519. 2:53:15with that person understand what that
  4520. 2:53:18person is explain understand what that
  4521. 2:53:20person wants explain what this project
  4522. 2:53:22is about this is definitely the best
  4523. 2:53:24answer prepare a detail report compared
  4524. 2:53:28you probably want to do this after you
  4525. 2:53:31meet with the
  4526. 2:53:34person uh initiate a project audit to
  4527. 2:53:36demonstrate compliance not yet meet with
  4528. 2:53:39this person let outline what the
  4529. 2:53:41Project's benefits are outline remember
  4530. 2:53:44this person is saying well is this
  4531. 2:53:46project align yes what you want to do is
  4532. 2:53:48you want want to go and meet with the
  4533. 2:53:49person and show them before doing this
  4534. 2:53:51so I would do a maybe then B then C
  4535. 2:53:54develop a contingency plan addressing
  4536. 2:53:56polit uh potential Changers request not
  4537. 2:53:59yet meet with the person first now I
  4538. 2:54:02want to point out something about this
  4539. 2:54:03question you see those three choices are
  4540. 2:54:06not
  4541. 2:54:08incorrect but they're asking what to do
  4542. 2:54:10first maybe at some point we are going
  4543. 2:54:14to develop a contingency plan to address
  4544. 2:54:18potential changes maybe at some point
  4545. 2:54:20we're going to audit it maybe at some
  4546. 2:54:22point we're going to prepare detail uh
  4547. 2:54:25report showing how a detailed report
  4548. 2:54:28comparing the status of Industry
  4549. 2:54:30standards maybe we're going to do those
  4550. 2:54:32things but the first thing you want to
  4551. 2:54:33do is to meet with them discuss see what
  4552. 2:54:36this person is about see what exactly
  4553. 2:54:38they're looking for making a the best
  4554. 2:54:42answer
  4555. 2:54:4484 in the midst of estimated task for a
  4556. 2:54:47major upgrade to an ex an application a
  4557. 2:54:49project manager finds that the
  4558. 2:54:51development team has different views on
  4559. 2:54:54the effort required for a particularly
  4560. 2:54:56challenging
  4561. 2:54:57feature what should the project manager
  4562. 2:55:00do to synchronize these variant
  4563. 2:55:01estimates okay simple question you have
  4564. 2:55:05team members with different views on
  4565. 2:55:07what an estimate should be what do you
  4566. 2:55:10do suggest implementing a quick
  4567. 2:55:13prototype to better gauge the necessary
  4568. 2:55:16effort allow the team additional time to
  4569. 2:55:19research and independently reassess
  4570. 2:55:21their
  4571. 2:55:22estimates okay request each team member
  4572. 2:55:25to detail their estimation process and
  4573. 2:55:28Foster a group
  4574. 2:55:30consensus all right assign the task
  4575. 2:55:33estimation to the most experienced
  4576. 2:55:35developer to set a
  4577. 2:55:38standard okay let's see the best answer
  4578. 2:55:41here you got two you got team members
  4579. 2:55:44can't agree on an estimate what do we do
  4580. 2:55:46best answer here is to bring
  4581. 2:55:48together so in this one here let them
  4582. 2:55:52detail their estimation
  4583. 2:55:53process together we want to and Foster
  4584. 2:55:56group consensus maybe they don't
  4585. 2:55:59understand how they're coming up with
  4586. 2:56:01their estimates maybe Bob doesn't
  4587. 2:56:03understand how Tom is getting his
  4588. 2:56:05estimat maybe Jane doesn't understand
  4589. 2:56:06how Bob is doing his estimates either
  4590. 2:56:09this would be the best answer
  4591. 2:56:10here now suggest a quick
  4592. 2:56:13prototype I'm not sure if I think a
  4593. 2:56:15prototype is going a little far before
  4594. 2:56:17we do that the best thing here is to
  4595. 2:56:19bring let the team work
  4596. 2:56:21together allow the team additional time
  4597. 2:56:24to research and independently the best
  4598. 2:56:25thing here be we don't want them to do
  4599. 2:56:27it independently we want them to do it
  4600. 2:56:29together Foster group consensus let the
  4601. 2:56:32team work together C is definitely
  4602. 2:56:35better than b assign the task
  4603. 2:56:38exclamation to the most experienced
  4604. 2:56:39never give away to work just don't say
  4605. 2:56:41okay you do it all and let the team in
  4606. 2:56:42this way this is kind of like a
  4607. 2:56:45forcein conflict solution in this one
  4608. 2:56:48you're saying okay you do it all and the
  4609. 2:56:50rest of you guys just depend on that
  4610. 2:56:51person in other words you're eliminating
  4611. 2:56:54the rest of the
  4612. 2:56:57team
  4613. 2:56:5985 during the roll out of a new
  4614. 2:57:01e-commerce platform an agile project
  4615. 2:57:03manager observes a trend of customers
  4616. 2:57:07gravitating towards a competitor site
  4617. 2:57:10which recently introduced a high highly
  4618. 2:57:13user friendly checkout process what is
  4619. 2:57:16the first action the project manag ERS
  4620. 2:57:18should do engag in a detailed discussion
  4621. 2:57:22with the product owner about any recent
  4622. 2:57:24customer feedback or shifts in Market
  4623. 2:57:28Trend intensify the development effort
  4624. 2:57:32on uh refining the existing features to
  4625. 2:57:35make them more competitive all right
  4626. 2:57:38pause the introduction additional
  4627. 2:57:39features to prioritize a complete
  4628. 2:57:42overhaul add a new userfriendly checkout
  4629. 2:57:44process this one here work with the
  4630. 2:57:47mindset all right if you are working on
  4631. 2:57:50a project especially as the question
  4632. 2:57:53points out an agile project and you see
  4633. 2:57:56something that should be added to the
  4634. 2:57:59application what do you do well go to
  4635. 2:58:03the product owner work with the product
  4636. 2:58:05owner let them know about customer
  4637. 2:58:08feedback you know um saying that hey
  4638. 2:58:12there some checkout maybe the product
  4639. 2:58:14owner already knows and only the product
  4640. 2:58:16owner can put it into the product
  4641. 2:58:17backlog you should never add something
  4642. 2:58:20to an ad job project unless you're the
  4643. 2:58:22product
  4644. 2:58:23owner never just pause either never stop
  4645. 2:58:26a project just like that unless you're
  4646. 2:58:28going to kill someone unless you're
  4647. 2:58:30breaking the law unless it's against a
  4648. 2:58:32regulation intensify uh the development
  4649. 2:58:35efforts and refining the existing
  4650. 2:58:37feature to make it more competitive
  4651. 2:58:40that's not something you can do that
  4652. 2:58:41goes back to the product order once
  4653. 2:58:44again 86 in the process of initiating an
  4654. 2:58:49Advanced Analytical platform to enhance
  4655. 2:58:52datadriven decision- making across its
  4656. 2:58:54various functions an organization is
  4657. 2:58:57integrating a solution that is new to
  4658. 2:58:59its technological
  4659. 2:59:01landscape what should the project
  4660. 2:59:03manager
  4661. 2:59:04emphasize evaluation of the platform's
  4662. 2:59:06capability with Legacy Data Systems and
  4663. 2:59:10user adaptability
  4664. 2:59:12okay precise needs analysis within the
  4665. 2:59:16key business sectors to Ure the platform
  4666. 2:59:18meet specific objectives okay broad
  4667. 2:59:22consultation on future proofing the
  4668. 2:59:24platform against evolving data
  4669. 2:59:26analytical analysis Technologies all
  4670. 2:59:29right streamlining cross functional
  4671. 2:59:32workflows to minimize disruption during
  4672. 2:59:34the platform now this
  4673. 2:59:37question uh my team made it and the
  4674. 2:59:40Worden is complex like I read it I had
  4675. 2:59:43to read it two times to see what it was
  4676. 2:59:45if you read
  4677. 2:59:47it carefully it's actually pretty easy
  4678. 2:59:51all right I found this question after
  4679. 2:59:53reading it three times I'm like ah
  4680. 2:59:55obviously that's the answer but the word
  4681. 2:59:58in the big word in it just gets you just
  4682. 3:00:01got to read it a few times you maybe you
  4683. 3:00:02did that too but let me show you the
  4684. 3:00:04answer and I'll show you why it's an
  4685. 3:00:05easy question so first of all it's in
  4686. 3:00:08initiating the project is is getting
  4687. 3:00:11started what is something you're going
  4688. 3:00:13to emphasize and initiate it's
  4689. 3:00:15collecting those requirements it's
  4690. 3:00:16making sure that the project meets its
  4691. 3:00:18objectiv making sure that the scope is
  4692. 3:00:21actually something that should get done
  4693. 3:00:24in this industry remember in the process
  4694. 3:00:26of initiating you're proving you're
  4695. 3:00:28doing the business case that's one of
  4696. 3:00:30the inputs to the project Charter so
  4697. 3:00:33that's what this is
  4698. 3:00:35notice this one here precise needs
  4699. 3:00:38analysis this is important what you're
  4700. 3:00:40doing with precise needs analysis is you
  4701. 3:00:43are making sure that hey this project
  4702. 3:00:47will meet the sector that it's been
  4703. 3:00:49built for now here's where the other
  4704. 3:00:52ones are
  4705. 3:00:53wrong streamlining cross functional
  4706. 3:00:55workflows I like that but I'm going to
  4707. 3:00:57put an x on it for a reason broadcast
  4708. 3:00:59future proofing I like that I'm going to
  4709. 3:01:01put an x on it evaluation of the
  4710. 3:01:03platform I like that but I'm going to
  4711. 3:01:05put an x on it all of these are good to
  4712. 3:01:07do during initiating but B actually
  4713. 3:01:10includes AC C and D when you're
  4714. 3:01:12basically doing B you're basically doing
  4715. 3:01:14everything else one of the things you
  4716. 3:01:16want to do on this exam is if you come
  4717. 3:01:19to a question
  4718. 3:01:22and it looks like the answers are very
  4719. 3:01:25specific very very specific and you you
  4720. 3:01:27can't determine that a c and d are
  4721. 3:01:31specific to that platform or analytical
  4722. 3:01:35thing that they're doing go with a
  4723. 3:01:37broader answer remember a broad a broad
  4724. 3:01:39question should get a broad answer a
  4725. 3:01:41specific question gets a specific
  4726. 3:01:45answer 87 during the second Sprint of a
  4727. 3:01:48software development project it's
  4728. 3:01:50observed that one team member frequently
  4729. 3:01:54dictates scrum meetings leading to
  4730. 3:01:56diminish input from other team members
  4731. 3:01:59and hinder progress on task the Team
  4732. 3:02:02memb Dynamics are affected and there's a
  4733. 3:02:05growing concern over the Project's
  4734. 3:02:07collaborative environment what should
  4735. 3:02:09you do Implement Anonymous feedback
  4736. 3:02:12system to collect opinions okay reassign
  4737. 3:02:16the dominating team member to task that
  4738. 3:02:18requires less collaboration all right
  4739. 3:02:21shift to written daily updates to reduce
  4740. 3:02:24the opportunity for any single person to
  4741. 3:02:27dominate
  4742. 3:02:28discussions okay arrange a private
  4743. 3:02:31conversation with the dominating team
  4744. 3:02:33member to discuss their uh conduct's
  4745. 3:02:36impact on the Team Dynamics all right
  4746. 3:02:38this here it's a complex one if you
  4747. 3:02:41don't know the mindset if you do it's
  4748. 3:02:43not that difficult expect a question on
  4749. 3:02:46the exam
  4750. 3:02:47like this where you're going to get
  4751. 3:02:51somebody is doing something bad on a
  4752. 3:02:52project generally it's an individual
  4753. 3:02:55problem and when there's an individual
  4754. 3:02:57problem on a project your best thing to
  4755. 3:02:59do is to deal with that individual
  4756. 3:03:04individually couple things you shouldn't
  4757. 3:03:05do don't fire them don't remove them the
  4758. 3:03:09reason is because this person may not
  4759. 3:03:12know they may feel like they're doing
  4760. 3:03:14something great listen I've been in
  4761. 3:03:16meetings when I Domin ated it to him and
  4762. 3:03:19I thought I was really helping them and
  4763. 3:03:22then the boss came to me later and says
  4764. 3:03:23Andrew don't ever do that again because
  4765. 3:03:25you were making people upset you weren't
  4766. 3:03:28giving people the time to talk and I
  4767. 3:03:30didn't realize it because I was I was
  4768. 3:03:32excited you know you get excited you
  4769. 3:03:34really want to put out your opinion
  4770. 3:03:36there uh so meet with that person the
  4771. 3:03:39person may not be a bad person they just
  4772. 3:03:41may not realize that so let's meet with
  4773. 3:03:44them one
  4774. 3:03:45one we are we don't need the feedback
  4775. 3:03:48you can already see it so that's not
  4776. 3:03:50going to help shift to written don't
  4777. 3:03:52move away don't anytime you have an
  4778. 3:03:55issue don't go around the issue in this
  4779. 3:03:59one you're just saying okay so what are
  4780. 3:04:00you going to do never have meetings
  4781. 3:04:01again don't go around the issue go
  4782. 3:04:05straight to the issue solve the issue
  4783. 3:04:07remember this on your exam does this
  4784. 3:04:10Choice hit the issue or is it going
  4785. 3:04:13around the issue and see we're going
  4786. 3:04:16around that issue
  4787. 3:04:19by the way if you're enjoying this video
  4788. 3:04:21and you're learning a lot give the video
  4789. 3:04:22a like subscribe to the channel for more
  4790. 3:04:24content just like this I know it I hate
  4791. 3:04:27asking all the time but it just helps us
  4792. 3:04:30out a lot YouTube does not prioritize
  4793. 3:04:31our video if if you guys don't click
  4794. 3:04:34that like button so please click that
  4795. 3:04:36like
  4796. 3:04:37button during a critical phase of a
  4797. 3:04:40technology implementation project
  4798. 3:04:43extensive and unforeseen changes to the
  4799. 3:04:46scope have led
  4800. 3:04:48to significant delays all right these
  4801. 3:04:50potential changes alterations were
  4802. 3:04:52flagged in the initial risk assessment
  4803. 3:04:55okay concerned about the uh impli
  4804. 3:04:58implications of the Project's
  4805. 3:05:01progress the team proposes request an
  4806. 3:05:05extension from stakeholders all right
  4807. 3:05:07reasonable to ask what should you do
  4808. 3:05:10next key word conduct a toar
  4809. 3:05:13reevaluation of the timeline with input
  4810. 3:05:15from all stakeholders okay
  4811. 3:05:18ensure every scope change has been
  4812. 3:05:19properly logged and it's impact assess
  4813. 3:05:22okay finish the project schedule as
  4814. 3:05:26extend the project schedule as needed to
  4815. 3:05:28finish the scope engage directly with
  4816. 3:05:31key stakeholders to renegotiate project
  4817. 3:05:34deliverables and timeline this is a
  4818. 3:05:36tricky question all right I'm giving you
  4819. 3:05:39guys that heads up tricky tricky you
  4820. 3:05:42have to read it very carefully what
  4821. 3:05:45answer did you guys get answer answer is
  4822. 3:05:48B not
  4823. 3:05:50a so first of all let's eliminate the
  4824. 3:05:53bad ones the bad one is you just can't
  4825. 3:05:56extend the schedule like that right you
  4826. 3:05:58just you would need to go through a
  4827. 3:05:59whole change request
  4828. 3:06:02process uh engage director is to
  4829. 3:06:04renegotiate the deliverables they don't
  4830. 3:06:06want to renegotiate the best thing here
  4831. 3:06:08is to face the problem not not just get
  4832. 3:06:10rid of the problem redo it
  4833. 3:06:13all now Comes A and B this was a tricky
  4834. 3:06:18question so my team member wrote this
  4835. 3:06:21one and I almost got it wrong because I
  4836. 3:06:23wasn't reading fast enough the mindset
  4837. 3:06:26tells us if somebody wants a change
  4838. 3:06:28assess the thing before making a change
  4839. 3:06:30which is what B is but it says what to
  4840. 3:06:33do first what to do
  4841. 3:06:35next before you do that before you
  4842. 3:06:39assess the timeline you better make sure
  4843. 3:06:43that all those changes were logged that
  4844. 3:06:47all the scope changes are there because
  4845. 3:06:49imagine you go and you do a and you
  4846. 3:06:51forgot to log one of the changes that
  4847. 3:06:53was there now if you're wondering where
  4848. 3:06:55do we put this it should have been in
  4849. 3:06:57some kind of change log or issue log or
  4850. 3:06:59something so before you do a do be this
  4851. 3:07:05is a common thing on this this
  4852. 3:07:07exam when you work on this when you do
  4853. 3:07:10this test you got to be careful anytime
  4854. 3:07:13you see what to do first what you do
  4855. 3:07:15next remember put this in order say this
  4856. 3:07:18to yourself before you move
  4857. 3:07:20on out of those four choices am I doing
  4858. 3:07:23that first or that first should you and
  4859. 3:07:26that's what we're doing
  4860. 3:07:27here do you review all the all the
  4861. 3:07:31changes to the scope are are documented
  4862. 3:07:34and then assess the the the the impact
  4863. 3:07:37on the timeline or do you just assess
  4864. 3:07:39the impact on the
  4865. 3:07:40timeline without checking without
  4866. 3:07:43checking if all the Scopes changes has
  4867. 3:07:45been documented that's how you look at
  4868. 3:07:47this
  4869. 3:07:5089 as a project manager overseeing a
  4870. 3:07:54pivotal update to a client Software
  4871. 3:07:56System you notice a significant lack of
  4872. 3:07:58Engagement from the client side during
  4873. 3:08:01critical Sprint review sessions despite
  4874. 3:08:03this your team has successfully
  4875. 3:08:05developed a a working prototype that's
  4876. 3:08:08ready for
  4877. 3:08:09evaluation what is the first thing the
  4878. 3:08:12project manager should do send a detail
  4879. 3:08:15Pro uh send a detailed progress report
  4880. 3:08:17email to the client highlighting the
  4881. 3:08:20prototype's completion and next steps
  4882. 3:08:24deploy the prototype to the client to
  4883. 3:08:26gather their feedback
  4884. 3:08:29okay schedule a comprehensive review
  4885. 3:08:31session with the Project's technical
  4886. 3:08:34lead to refine the Prototype before
  4887. 3:08:37client's
  4888. 3:08:39presentation organize a Sprint review to
  4889. 3:08:43actively review the Prototype
  4890. 3:08:44encouraging their inputs and and
  4891. 3:08:46adjustments
  4892. 3:08:49now this this question not too difficult
  4893. 3:08:53so the it seems like there's kind of
  4894. 3:08:55like a lack of Engagement maybe what the
  4895. 3:08:58client is seeing is not what they want
  4896. 3:09:00the best thing here to do is to do a
  4897. 3:09:02Sprint review the only time I don't want
  4898. 3:09:05to say the only time but the main time
  4899. 3:09:08that a client comes in and gives us
  4900. 3:09:09feedback on the product is during those
  4901. 3:09:12Sprint
  4902. 3:09:14reviews you don't want to just send out
  4903. 3:09:16an email it's not just about an email
  4904. 3:09:19about what we did we need their input
  4905. 3:09:21the point of prototypes is to get input
  4906. 3:09:24just you just can't deploy the Prototype
  4907. 3:09:26and wait for their feedback they might
  4908. 3:09:28not know it's exist or they might not
  4909. 3:09:30use it the best thing to do is to
  4910. 3:09:31demonstrate that now this one here
  4911. 3:09:35comprehensive review notice the
  4912. 3:09:36Project's technical lead you don't
  4913. 3:09:39prototypes are meant to be given to
  4914. 3:09:41customers not just to the technical
  4915. 3:09:43leads you want to get prototypes into
  4916. 3:09:45the hand of the customers demonst ation
  4917. 3:09:48product usage making D the best
  4918. 3:09:51answer and the last question I know I
  4919. 3:09:54hate to ask again but can you click that
  4920. 3:09:56like button subscribe to the channel I
  4921. 3:09:57know I know it's
  4922. 3:09:59annoying in the midst of a Project's
  4923. 3:10:01life cycle a project manager identifies
  4924. 3:10:04that essential feedback from a vital
  4925. 3:10:07operational division has been
  4926. 3:10:08consistently omitted in the planet and
  4927. 3:10:10execution phases this negligence has led
  4928. 3:10:14to widespread dissatisfaction con conc
  4929. 3:10:17erning how project outcomes align with
  4930. 3:10:19operational workflow of this
  4931. 3:10:22division what should the project manager
  4932. 3:10:24do first now we just did a question like
  4933. 3:10:27this where we talked about what you do
  4934. 3:10:31first so let's take a look at this
  4935. 3:10:34change the scope to include the
  4936. 3:10:35overlooked operational
  4937. 3:10:37Insight conduct a comprehensive review
  4938. 3:10:40of the projects adhes to the
  4939. 3:10:44organizational policies adherence to the
  4940. 3:10:47organizational policies review the
  4941. 3:10:49communication management plan to
  4942. 3:10:51understand the current Communication
  4943. 3:10:53channel craft a refect a reactive plan
  4944. 3:10:56to integrate unforeseen operational
  4945. 3:10:58needs into the Project's trajectory this
  4946. 3:11:01is not an easy question it sounds like
  4947. 3:11:04an easy question now before I give you
  4948. 3:11:05the answer I want to point out something
  4949. 3:11:07you notice that essential feedback from
  4950. 3:11:10has been consistently
  4951. 3:11:13omitted H there's a problem there
  4952. 3:11:16there's negligence in the flow of some
  4953. 3:11:20kind of communications right there this
  4954. 3:11:24has led to problems what should you do
  4955. 3:11:26first well the first thing you want to
  4956. 3:11:29do is to understand why that problem
  4957. 3:11:32exists first of all couple things here
  4958. 3:11:35we can
  4959. 3:11:36eliminate you can't just change a scope
  4960. 3:11:39like that it's not you if it's agile the
  4961. 3:11:42scope belongs to the product owner if
  4962. 3:11:45it's traditional it needs to go to a
  4963. 3:11:47change request so let's get rid of
  4964. 3:11:50it a reactive plan don't fix a problem
  4965. 3:11:54yet understand the problem before fixing
  4966. 3:11:57the
  4967. 3:11:57problem get ready d c a comprehensive
  4968. 3:12:02review of the product this is the
  4969. 3:12:03organizational policies the real problem
  4970. 3:12:06here is that the feedback was omitted
  4971. 3:12:09get to the root cause of the
  4972. 3:12:11problem okay so it's not just the
  4973. 3:12:14organizational policy is that there's
  4974. 3:12:16something wrong in the way
  4975. 3:12:17Communications is getting done the best
  4976. 3:12:20thing here we can do is to review that
  4977. 3:12:21communication management plan review
  4978. 3:12:24that plan see what's going on why was
  4979. 3:12:26there a disconnect on the plan itself we
  4980. 3:12:29can see the correct all right question
  4981. 3:12:3391 in the midst of deploying a major it
  4982. 3:12:36infrastructure update a project manager
  4983. 3:12:39identifies a significant knowledge Gap
  4984. 3:12:42within the
  4985. 3:12:44team primary amounts uh amount
  4986. 3:12:47recently onboarded staff with the
  4987. 3:12:49Project's tight deadline and budget
  4988. 3:12:52fully allocated external training
  4989. 3:12:54options are not feasible what two action
  4990. 3:12:56should the project manager take next now
  4991. 3:12:59you notice this is a choose two and I
  4992. 3:13:02want to point out to you that on your
  4993. 3:13:04exam you're going to have these
  4994. 3:13:06multi-choice questions where you have to
  4995. 3:13:07select two or three of those choices so
  4996. 3:13:10keep that in mind I think this is the
  4997. 3:13:12first one I'm giving you in this series
  4998. 3:13:13but keep that in mind you will see four
  4999. 3:13:16or five of these types of questions on
  5000. 3:13:17your full test all right so let's go
  5001. 3:13:19through the choices here assess specific
  5002. 3:13:22areas uh where the new staff members
  5003. 3:13:24lack
  5004. 3:13:26expertise consider reallocating critical
  5005. 3:13:29task to more experienced team members
  5006. 3:13:31until further notice propose a beef a
  5007. 3:13:34brief project pause to reallocate budget
  5008. 3:13:37funds towards emergency training
  5009. 3:13:40establish a mentorship paring between
  5010. 3:13:42the new staff and seasoned Professionals
  5011. 3:13:44for on the job training suggest that new
  5012. 3:13:46staff in dependently seek out online
  5013. 3:13:48resources to bridge their knowledge gaps
  5014. 3:13:51at their own cost now if you appli in
  5015. 3:13:54the mindset this question is not too
  5016. 3:13:56difficult notice that you have this take
  5017. 3:13:59next right so what are you going to be
  5018. 3:14:00doing next well the next thing you
  5019. 3:14:02should really be doing is knowing okay
  5020. 3:14:05in what specific areas are they lacking
  5021. 3:14:09any kind of training like what specific
  5022. 3:14:11areas that they lacking knowledge in you
  5023. 3:14:13shouldn't just go and start doing
  5024. 3:14:15training until you understand understand
  5025. 3:14:17that so hopefully you guys got that um
  5026. 3:14:19the next good answer here was let's put
  5027. 3:14:22a some kind of mentorship and you got
  5028. 3:14:24initiate this you have to be proactive
  5029. 3:14:27you should not tell the team that they
  5030. 3:14:30should just go and figure it out
  5031. 3:14:31themselves that's what e does that's why
  5032. 3:14:34that's wrong you shouldn't say okay you
  5033. 3:14:36guys go and find your own thing and
  5034. 3:14:38especially at their own cost on this
  5035. 3:14:41exam don't be negative if a choice seems
  5036. 3:14:44negative it's probably not the right
  5037. 3:14:46answer
  5038. 3:14:48uh consider reallocating critical task
  5039. 3:14:51what you're doing here is you're
  5040. 3:14:52overworking people if you have a choice
  5041. 3:14:55that seems like you're overworking
  5042. 3:14:56people probably not the right answer
  5043. 3:14:58never pause your project the only time
  5044. 3:15:01you should ever shut a project down is
  5045. 3:15:03if you're doing something that's against
  5046. 3:15:04the law or or unethical for example
  5047. 3:15:07you're breaking some kind of regulations
  5048. 3:15:09then it's a good time to stop the
  5049. 3:15:10project maybe there's a safety
  5050. 3:15:12regulations that you're not meeting then
  5051. 3:15:14it's a good time to stop the project but
  5052. 3:15:16when when it comes to things like this
  5053. 3:15:18you probably don't stop the project
  5054. 3:15:19making a and d the best
  5055. 3:15:23answers question
  5056. 3:15:2592 while working on an Innovative web
  5057. 3:15:28plat web platform a project manager
  5058. 3:15:32receives a request from a critical
  5059. 3:15:33stakeholder for the inclusion of several
  5060. 3:15:36unforeseen functionalities within the
  5061. 3:15:38current Agile development cycle what
  5062. 3:15:41should the project manager do advise the
  5063. 3:15:43stakeholder to present their suggestion
  5064. 3:15:45following the review of the
  5065. 3:15:47uh present cycle recommend assessing the
  5066. 3:15:51viability of these functions these
  5067. 3:15:53functionalities add the sub subsequent
  5068. 3:15:56team plan and meeting swiftly revise the
  5069. 3:15:59Project's development agenda to Inc
  5070. 3:16:02compress the requested functionalities
  5071. 3:16:04have the product owner to engage with
  5072. 3:16:06stakeholders concerning the
  5073. 3:16:08incorporation of their request into the
  5074. 3:16:10ongoing project now I know I said these
  5075. 3:16:13are going to be complex questions but if
  5076. 3:16:14you understand agile practices it's
  5077. 3:16:16rather really easily if you don't this
  5078. 3:16:19is a pretty complex question so what
  5079. 3:16:21happens when somebody requests some kind
  5080. 3:16:23of function on an agile project what do
  5081. 3:16:25you do well the best thing here you do
  5082. 3:16:28is to have them meet with the product
  5083. 3:16:30owner remember something only the
  5084. 3:16:31product owner can add functions to a
  5085. 3:16:35project not a project manager you don't
  5086. 3:16:37have that capability that's the role of
  5087. 3:16:39the product owner not the team the
  5088. 3:16:40product
  5089. 3:16:42owner never just say uh advise the Stak
  5090. 3:16:45present to the next cycle have them meet
  5091. 3:16:47with the product owner look at this
  5092. 3:16:50recommend assessing the vi function in
  5093. 3:16:51the next team plan meeting the team
  5094. 3:16:53doesn't determine functionalities the
  5095. 3:16:55product owner does you should not
  5096. 3:16:57swiftly incorporate it that is not your
  5097. 3:17:01job 93 as the deadline for critical
  5098. 3:17:04project approaches the project manager
  5099. 3:17:06notices a decrease in team enthusiasm
  5100. 3:17:10with several members consistently arri
  5101. 3:17:12and late to the office the project
  5102. 3:17:14manager notes the team is not focused
  5103. 3:17:16and D at what should you
  5104. 3:17:18do coordinate with human resources to
  5105. 3:17:22dismiss potential postp part uh to
  5106. 3:17:26discuss potential post project
  5107. 3:17:28opportunities for team members okay
  5108. 3:17:31maybe that'll motivate them conduct
  5109. 3:17:33motivational Workshop to re re-energize
  5110. 3:17:35the team and reinforce the importance of
  5111. 3:17:37their contributions all right sounds
  5112. 3:17:39good too initiate a peer recognition
  5113. 3:17:41program to highlight individual
  5114. 3:17:43contributions and Foster team Spirits
  5115. 3:17:45all right that's that's good good too in
  5116. 3:17:47for is strict attendance policy to curb
  5117. 3:17:49latencies and improve discipline within
  5118. 3:17:52the team I'm going to eliminate this one
  5119. 3:17:53right off the
  5120. 3:17:54bat the reason is because again on this
  5121. 3:17:58the mindset is going to tell us never be
  5122. 3:18:01negative if you're coming out so if
  5123. 3:18:02you're coming after someone and yelling
  5124. 3:18:04at them and disciplining them and
  5125. 3:18:05Reporting them and firing them it's
  5126. 3:18:07never the answer unless the question
  5127. 3:18:09says what not to do well in this one
  5128. 3:18:12here what are we going to do so we got
  5129. 3:18:15three good answers we we could see we
  5130. 3:18:17could try to motivate him by discussing
  5131. 3:18:21some kind of uh meeting with the pmo or
  5132. 3:18:25the HR to make sure they have more
  5133. 3:18:26opportunities afterwards maybe that
  5134. 3:18:27motivate them maybe we should try
  5135. 3:18:29motivating them or a peer recognition
  5136. 3:18:31what did you guys get best answer here
  5137. 3:18:34is what you should do as a project
  5138. 3:18:35manager is you should be keeping your
  5139. 3:18:37team motivated
  5140. 3:18:39correct you should keep your team
  5141. 3:18:42motivated don't just tell the team you
  5142. 3:18:44see what you're doing here in a is that
  5143. 3:18:46you're giving away the motivation to the
  5144. 3:18:49HR department C you're having them
  5145. 3:18:52individually try to motivate each other
  5146. 3:18:54by a peer recognition program the best
  5147. 3:18:56thing here you should do is try to do B
  5148. 3:18:59first I would do see if this works meet
  5149. 3:19:02with your team why are they feeling bad
  5150. 3:19:04what can I do what's going on guys
  5151. 3:19:07remember confront the problem is the key
  5152. 3:19:09on this
  5153. 3:19:10exam all right I know I said hard
  5154. 3:19:13questions this one is actually easy
  5155. 3:19:15during the development of a new
  5156. 3:19:16Healthcare System the project manager
  5157. 3:19:18requests that the product owner
  5158. 3:19:20prioritize features that will
  5159. 3:19:22significantly enhance patient data
  5160. 3:19:24processing efficiently what tool should
  5161. 3:19:27a product owner use scope statement
  5162. 3:19:29Sprint backlog product backlog WBS best
  5163. 3:19:31answer here is the product backlog the
  5164. 3:19:33product backlog stores all of the
  5165. 3:19:36features for an agile um for an Agile
  5166. 3:19:39development project how did I know that
  5167. 3:19:42this was an agile project even if it
  5168. 3:19:44didn't say it notice it says the product
  5169. 3:19:47owner the WBS and the scope statements
  5170. 3:19:50are used in traditional projects for a
  5171. 3:19:53full project management plan the Sprint
  5172. 3:19:55backlog contains things that will get
  5173. 3:19:57done in the next Sprint it doesn't have
  5174. 3:19:59all the features that that's going to be
  5175. 3:20:01on the agile project and the product
  5176. 3:20:03owner doesn't add to the Sprint backlog
  5177. 3:20:05only the team does now on your exam
  5178. 3:20:09expect where you're going to get some
  5179. 3:20:11similar questions like this where a few
  5180. 3:20:13of them are super easy you read it you
  5181. 3:20:15just pass it right away but then of
  5182. 3:20:17course you're going to get hard
  5183. 3:20:20questions like this one during the final
  5184. 3:20:23stages of a significant infrastructure
  5185. 3:20:26project it was discovered that
  5186. 3:20:28comprehensive reports on critical
  5187. 3:20:30structural
  5188. 3:20:31assessments performed by a key engineer
  5189. 3:20:34who has since Departed the company were
  5190. 3:20:36not documented or shared with the team
  5191. 3:20:40to mitigate such risk in the future what
  5192. 3:20:43should have been implemented by the
  5193. 3:20:45project manager during the project
  5194. 3:20:46Project Life Cycle all right so now
  5195. 3:20:48we're looking back all right and this
  5196. 3:20:50question I'm telling you guys is not
  5197. 3:20:51easy have the team initiate a cross
  5198. 3:20:54trainining program enabling team members
  5199. 3:20:56to understand and perform each other's
  5200. 3:20:58roles during absence okay organize
  5201. 3:21:02monthly knowledge exchange sessions
  5202. 3:21:05where engineer could discuss challenges
  5203. 3:21:07and solutions ensuring Collective
  5204. 3:21:09awareness of project
  5205. 3:21:11details okay uh engage external
  5206. 3:21:15Consultants to oversee all critical
  5207. 3:21:17testing phases ensuring an unbiased
  5208. 3:21:20review on documentation of
  5209. 3:21:22finding all right establish an
  5210. 3:21:26integrated project management
  5211. 3:21:27information system to share
  5212. 3:21:29information this question is not easy
  5213. 3:21:32most people when I did this with my um
  5214. 3:21:35with my classes got this one wrong so
  5215. 3:21:37let's see what you guys got now this
  5216. 3:21:40type of question you have to think
  5217. 3:21:41longterm like but longterm from the
  5218. 3:21:44beginning not something you could have
  5219. 3:21:46fix it they're not asking you to fix the
  5220. 3:21:48problem they're saying what should have
  5221. 3:21:51what what could you do now to prevent
  5222. 3:21:53this in the future all right that's what
  5223. 3:21:56they're trying to
  5224. 3:21:57do so the best answer here is going to
  5225. 3:22:01be D correct I'm not sure if you guys
  5226. 3:22:04got that but that's the answer here's
  5227. 3:22:06why there's a few of these we're going
  5228. 3:22:09to eliminate right off the bat first of
  5229. 3:22:10all let's get rid of B monthly knowledge
  5230. 3:22:14sessions a month may be too long try
  5231. 3:22:16have to put a timeline on something that
  5232. 3:22:18means if somebody quit halfway through
  5233. 3:22:20the month all the knowledge between day
  5234. 3:22:221 to day 15 is gone what if they quit on
  5235. 3:22:24day 29 and you do the knowledge sessions
  5236. 3:22:26every 30 days um you kind of lost 29
  5237. 3:22:29days wor of knowledge not a good
  5238. 3:22:32idea we don't want to engage you don't
  5239. 3:22:34need to bring people in to start to put
  5240. 3:22:38all kinds of of additional pressure on
  5241. 3:22:41the team or additional team members not
  5242. 3:22:43a good idea let's get rid of those two
  5243. 3:22:45choices now I really liked it A and
  5244. 3:22:48D in a you have Team initiate cross
  5245. 3:22:52training program that way everybody
  5246. 3:22:54seems to be doing everybody's work
  5247. 3:22:56enabling team members to understand and
  5248. 3:22:57perform each other's role but what if
  5249. 3:23:00what if I know cross training is good
  5250. 3:23:03but what if it's an engineering job what
  5251. 3:23:05if Engineers need certain kind of
  5252. 3:23:06licenses there's a reason we put
  5253. 3:23:08engineers in
  5254. 3:23:10there that's may not work at all but you
  5255. 3:23:14know what's going to definitely work d
  5256. 3:23:17if you have an information system that
  5257. 3:23:18shares information something that's done
  5258. 3:23:21throughout the project then this if you
  5259. 3:23:23notice if we have a system that was
  5260. 3:23:25consistently sharing information this
  5261. 3:23:28would have solved the problem of this
  5262. 3:23:32guy leaving and anybody can leave at any
  5263. 3:23:33point because the information is all
  5264. 3:23:36there making D better than
  5265. 3:23:41a 96 as a project manager initiates a
  5266. 3:23:44project with a fully remote team
  5267. 3:23:46ensuring effective communication becomes
  5268. 3:23:48a challenge what is the best approach
  5269. 3:23:50for the project manager to maintain
  5270. 3:23:53consistent information flow within the
  5271. 3:23:55team suggest the creation of a monthly
  5272. 3:23:58detailed project updates for
  5273. 3:24:00comprehensive overview all right
  5274. 3:24:03establish structured online
  5275. 3:24:04communication platform for frequent and
  5276. 3:24:07organized team interactions all
  5277. 3:24:10right recommend open form for team
  5278. 3:24:12members to post daily updates okay
  5279. 3:24:15organize bi-weekly email blast to
  5280. 3:24:17summarize project progress and incoming
  5281. 3:24:19tasks I like this question this question
  5282. 3:24:22has a very important lesson to learn the
  5283. 3:24:25best answer here is going to be B now I
  5284. 3:24:27want to point out
  5285. 3:24:29something when you get a vague question
  5286. 3:24:32you can't generally answer it with a
  5287. 3:24:34very specific answer for example if I
  5288. 3:24:37say what's the best color shirt to wear
  5289. 3:24:40and your answer is you should wear blue
  5290. 3:24:41well that's my answer too let's all wear
  5291. 3:24:43blue I wear blue every day
  5292. 3:24:46but not everybody likes blue the best
  5293. 3:24:48color shirt to wear is whatever makes
  5294. 3:24:50the stakeholder happy and
  5295. 3:24:52successful notice it's a vague question
  5296. 3:24:55with a vague answer notice this
  5297. 3:24:58particular question is like well what
  5298. 3:25:00can we do to ensure effective
  5299. 3:25:03communication is it an email is it an
  5300. 3:25:06open form or is it some monthly detail
  5301. 3:25:09reports notice how a c and d are very
  5302. 3:25:14particular things versus B it's well
  5303. 3:25:18obviously they're online let's get some
  5304. 3:25:21kind of platform for they're not we're
  5305. 3:25:24not doing a monthly we're not doing a
  5306. 3:25:27daily we're not doing a weekly we're
  5307. 3:25:29just saying frequent this is more
  5308. 3:25:32generic than the
  5309. 3:25:34others that's what we want remember a
  5310. 3:25:37generic question should get a pretty
  5311. 3:25:39generic answer you can't just give a
  5312. 3:25:42specific question if you don't have all
  5313. 3:25:44the details this question doesn't give
  5314. 3:25:46much detailed it's a very open-ended
  5315. 3:25:48question should get an open-ended answer
  5316. 3:25:50got it hopefully that makes sense so
  5317. 3:25:54this question I don't think was
  5318. 3:25:55difficult but it taught a very important
  5319. 3:25:57lesson that when you go through your
  5320. 3:25:58exam keep this taught in mind as you go
  5321. 3:26:01through it by the way if you find this
  5322. 3:26:03tip help helpful and it's going to help
  5323. 3:26:04you on your test give the video a like
  5324. 3:26:05subscribe to the
  5325. 3:26:08channel 97 as a complex project draws to
  5326. 3:26:12a close the project manager realizes
  5327. 3:26:15that several risks
  5328. 3:26:16initially assess as slow probability and
  5329. 3:26:19impact evolved into significant issues
  5330. 3:26:22catching the project team off guard all
  5331. 3:26:24right this is a common thing by the way
  5332. 3:26:26in real life what proactive step notice
  5333. 3:26:30proactive should the project manager
  5334. 3:26:32have taken Implement a weekly risk
  5335. 3:26:34review session with the Project's coure
  5336. 3:26:36team to identify any changes in the risk
  5337. 3:26:39landscape all right Institute a monthly
  5338. 3:26:42risk tracking system to monitors the
  5339. 3:26:45project risk stat is continuously okay
  5340. 3:26:48mandated is zero policy of tolerance for
  5341. 3:26:50all risks ensuring every potential risk
  5342. 3:26:52was addressed immediately upon
  5343. 3:26:54identification H I don't know what that
  5344. 3:26:56one zero uh tolerance that that might be
  5345. 3:27:00tough under taken continuous assessment
  5346. 3:27:04and prioritization of risk throughout
  5347. 3:27:05the Project Life Cycle so we just did
  5348. 3:27:09that question generic type of question
  5349. 3:27:12where you got this generic uh question
  5350. 3:27:15and the best answer was generic answer
  5351. 3:27:16what do you think this one is well it's
  5352. 3:27:19the same type of question I put here
  5353. 3:27:21because if there's one thing we got to
  5354. 3:27:23learn is in the course I taught you guys
  5355. 3:27:26risk is something that's continuous it's
  5356. 3:27:28something you do all the time not
  5357. 3:27:30something you do some of the time risk
  5358. 3:27:32you consistently assess risk remember
  5359. 3:27:36risk changes
  5360. 3:27:38365 247
  5361. 3:27:40365 all right risk changes all the time
  5362. 3:27:43every day is there's a new risk every
  5363. 3:27:45day certain risk Chang so you should be
  5364. 3:27:47assessing risk on a continuous basis not
  5365. 3:27:50necessarily on a weekly or monthly basis
  5366. 3:27:53maybe you should be doing it on an
  5367. 3:27:55hourly basis maybe every minute you
  5368. 3:27:56should be doing it but we don't have a
  5369. 3:27:58choice like that or do we well
  5370. 3:28:00continuous assessment this ensures that
  5371. 3:28:03the project determines what's best for
  5372. 3:28:05them every project May assess risk at
  5373. 3:28:07different times so we don't want to just
  5374. 3:28:09go in there and choose something so
  5375. 3:28:12specific a zero policy probably will not
  5376. 3:28:15be implemented but when it comes to risk
  5377. 3:28:17assessment you should make sure that you
  5378. 3:28:19consistently assess risk because when
  5379. 3:28:22you start a project a risk that seems ah
  5380. 3:28:25it's not that important or risk that
  5381. 3:28:27seems that it's not going to really
  5382. 3:28:28impact you can change over time let's
  5383. 3:28:30keep that in
  5384. 3:28:31mind
  5385. 3:28:3398 in a project in a project uh
  5386. 3:28:37designated to deploy new technologies
  5387. 3:28:39across several departments a project
  5388. 3:28:41manager notices a shift in stakeholder
  5389. 3:28:44satisfaction levels
  5390. 3:28:46despite the project ading to its
  5391. 3:28:48timeline and deliverables being met
  5392. 3:28:51feedback indicates a perception of
  5393. 3:28:53diminish and returns in terms of value
  5394. 3:28:56from the recent project increments so
  5395. 3:28:58this is a long question as you can see
  5396. 3:29:01notice they're pushing things out
  5397. 3:29:03they're on time but the perception is
  5398. 3:29:06hey not great stakeholders are just not
  5399. 3:29:08seeing the value much anymore what
  5400. 3:29:11approach should the project manager take
  5401. 3:29:12to address these concerns clarify to the
  5402. 3:29:15state call is that the timeline needs
  5403. 3:29:17and and completed deliverables are the
  5404. 3:29:19primary indicators of success assuring
  5405. 3:29:22them that the project is right on track
  5406. 3:29:25all right highlight to the stakeholders
  5407. 3:29:27the inherent fluctuations in value
  5408. 3:29:29perception due to the variant nature of
  5409. 3:29:32resources and expected benefits at
  5410. 3:29:35different project stages all
  5411. 3:29:37right communicate to stakehold is a
  5412. 3:29:39common practice to tackle the most value
  5413. 3:29:42adding elements first result in a
  5414. 3:29:44perceived decrease in value as the
  5415. 3:29:46project progresses okay that's actually
  5416. 3:29:49true by the way in in an agile project
  5417. 3:29:52as time moves on you get less valuable
  5418. 3:29:54things analyze the trend and value with
  5419. 3:29:56the team to identify new online issues
  5420. 3:29:58device strategies for consistent value
  5421. 3:30:01and transparently relay those plans to
  5422. 3:30:03stakeholders good what is the best
  5423. 3:30:06answer here so notice we want to address
  5424. 3:30:10the
  5425. 3:30:11concern there are two good choices here
  5426. 3:30:14and that's going to be either C or D
  5427. 3:30:17making D the best answer now why is it
  5428. 3:30:19not a well you meet in your timeline and
  5429. 3:30:22you go into them is basically you're
  5430. 3:30:24forcing it upon them you're not really
  5431. 3:30:26doing anything to address the concern in
  5432. 3:30:28a you're basically saying hey we're on
  5433. 3:30:32time and you should like that that's
  5434. 3:30:34just being on time being deliverables
  5435. 3:30:36means you guys should be happy B let
  5436. 3:30:39them know okay it's okay for you guys to
  5437. 3:30:41be unhappy now I know it's going to go
  5438. 3:30:43up and down basically you're not really
  5439. 3:30:44addressing their concern and so is C
  5440. 3:30:47actually because in C you're basically
  5441. 3:30:49telling them well you know in agile
  5442. 3:30:51projects the first thing you get first
  5443. 3:30:52is going to be and everything else is
  5444. 3:30:53going to be bad after that that's really
  5445. 3:30:56but you're not addressing the core
  5446. 3:30:57concern maybe there's more to this I'll
  5447. 3:31:00tell you guys something on this test
  5448. 3:31:02confront the problem solve the problem
  5449. 3:31:04never kick the can down the road never
  5450. 3:31:06push away the problem and never say it's
  5451. 3:31:08not a problem the question it's telling
  5452. 3:31:10you it's a problem come up with
  5453. 3:31:12something to solve that problem I know C
  5454. 3:31:15is correct
  5455. 3:31:17but it doesn't mean you shouldn't on you
  5456. 3:31:18shouldn't identify what the underlying
  5457. 3:31:21issue is notice that's what the is
  5458. 3:31:23saying see what's going on here and see
  5459. 3:31:25what if there isn't on the line
  5460. 3:31:28isue 99 in the initial stages of
  5461. 3:31:32launching a Pioneer and software tool
  5462. 3:31:34aimed at small businesses the project
  5463. 3:31:36manager is focused on ensuring the
  5464. 3:31:38Project's quality resonates with its
  5465. 3:31:40target
  5466. 3:31:41audience what approach should the
  5467. 3:31:43project manager employ to ascend this
  5468. 3:31:45offer tool embodies the highest quality
  5469. 3:31:48standards engage a reputable software
  5470. 3:31:51development firm to ensure the tool
  5471. 3:31:53aligns with industry standards okay
  5472. 3:31:56recruit a chief quality officer to
  5473. 3:31:58oversee quality control throughout the
  5474. 3:32:01throughout the development establish
  5475. 3:32:03specific benchmarks quality benchmarks
  5476. 3:32:05for the software tool and continuously
  5477. 3:32:07seek ways to enhance them all right
  5478. 3:32:09instruct the lead developer to
  5479. 3:32:11prioritize refine and the software
  5480. 3:32:13platform and user experience now in this
  5481. 3:32:16one here the best answer is going to be
  5482. 3:32:19C there's a couple things so you're
  5483. 3:32:21building a software that you want to
  5484. 3:32:23have good quality a couple things we
  5485. 3:32:27don't know what a is about engage a
  5486. 3:32:30reputable software firm I'm not not
  5487. 3:32:32because a s a firm is reputable doesn't
  5488. 3:32:35mean that it actually is going to
  5489. 3:32:37produce quality software right some big
  5490. 3:32:40software firms produce pretty crappy
  5491. 3:32:42software think of Microsoft uh to ensure
  5492. 3:32:45it aligns with industry standards the
  5493. 3:32:46best way to know industry
  5494. 3:32:48standards is to do benchmarks
  5495. 3:32:52benchmarking is a tool we use in ad as
  5496. 3:32:54tool we use in traditional projects to
  5497. 3:32:56understand what our industry standards
  5498. 3:32:58and how to meet them if you meet a
  5499. 3:33:00benchmark generally you're going to
  5500. 3:33:01produce good quality
  5501. 3:33:02products you should not be hiring a
  5502. 3:33:05quality officer that is your job the
  5503. 3:33:08lead to to prioritize this is something
  5504. 3:33:11that the product owner should do or
  5505. 3:33:13something that more the project manager
  5506. 3:33:15the project sponsor is going to
  5507. 3:33:17do last question guys question 100 in
  5508. 3:33:21the in the progression of an extensive
  5509. 3:33:23software development project a pivotal
  5510. 3:33:25client proposes the introduction of a
  5511. 3:33:27new cloud-based technology mid project
  5512. 3:33:30significantly deviating from the initial
  5513. 3:33:33technology stacked outline the
  5514. 3:33:36suggestion aligns with the client's
  5515. 3:33:38ongoing digital transformation e uh
  5516. 3:33:41efforts what should the project manager
  5517. 3:33:43do
  5518. 3:33:43next analyze the proposed change for
  5519. 3:33:46strategic alignment and potential impact
  5520. 3:33:48on business outcome okay notify the
  5521. 3:33:51projects that did about The Client shift
  5522. 3:33:53towards digital transformation all right
  5523. 3:33:55implement the change to the timeline of
  5524. 3:33:57budget integrating new technology
  5525. 3:33:59okay evaluate the team's current
  5526. 3:34:01capabilities against the demand
  5527. 3:34:03introduced by the new technology the
  5528. 3:34:05best thing here you're going to do if a
  5529. 3:34:07stakeholder comes to you with a change
  5530. 3:34:09any kind of change on this project now
  5531. 3:34:12we're not saying that this is some kind
  5532. 3:34:13of agile project here so we're not sure
  5533. 3:34:16if it is but if they come to you with
  5534. 3:34:18some kind of a change the best thing you
  5535. 3:34:20can do is to assess that change just
  5536. 3:34:23don't go and implement the change don't
  5537. 3:34:26go to the steering committee if you
  5538. 3:34:27don't understand the chain the changes
  5539. 3:34:30and that brought to two good answer
  5540. 3:34:32either was a or D if you got one of
  5541. 3:34:34those two don't feel bad if you got D
  5542. 3:34:36but you know what here's why you should
  5543. 3:34:38have gone with a
  5544. 3:34:40before you assess the team capabilities
  5545. 3:34:44against the change see if the change
  5546. 3:34:46really is the stakeholder comes and says
  5547. 3:34:48hey this is notice the suggestion aligns
  5548. 3:34:52with their digital well does it maybe
  5549. 3:34:54you want to do that assessment first see
  5550. 3:34:57how it's going to affect the project see
  5551. 3:34:59how it's going to affect the outcome of
  5552. 3:35:00the project and if you feel you know
  5553. 3:35:03what maybe maybe this is good maybe this
  5554. 3:35:05a line then maybe you do D so let's do a
  5555. 3:35:08then we do D making a the best answer
  5556. 3:35:12all right questions
  5557. 3:35:13101 Jan the initiation the initiation
  5558. 3:35:17phase of an Environmental Conservation
  5559. 3:35:20project the project manager laws that a
  5560. 3:35:22key funding agency requires a
  5561. 3:35:24preliminary environmental impact
  5562. 3:35:26assessment before releasing additional
  5563. 3:35:29funds despite the agency history of
  5564. 3:35:32increase in additional funds following
  5565. 3:35:35initial assessments a senior team member
  5566. 3:35:38suggest full project planning should
  5567. 3:35:40commence immediately to expedite the
  5568. 3:35:43process what should the project manager
  5569. 3:35:45do keyword
  5570. 3:35:48next direct the team's efforts
  5571. 3:35:51exclusively towards completing the
  5572. 3:35:53required
  5573. 3:35:54assessment consult the organization Pro
  5574. 3:35:58the projects organization
  5575. 3:36:01guidelines proceed with drafting a
  5576. 3:36:04comprehensive project plan to cover all
  5577. 3:36:06phases including post assessment
  5578. 3:36:09activities aligned with the senior
  5579. 3:36:11members suggestion and initiate detailed
  5580. 3:36:13planning for subsequent pro project
  5581. 3:36:17stages now this question I found
  5582. 3:36:20difficult this was a pretty difficult
  5583. 3:36:22question but remember what you're doing
  5584. 3:36:24next is not just taking an action but is
  5585. 3:36:26assessing looking around reviewing
  5586. 3:36:28something making sure that the next
  5587. 3:36:31action you take is a good action so
  5588. 3:36:34assess review see what's right to take
  5589. 3:36:36and then take an actual
  5590. 3:36:38action answer here is going to be
  5591. 3:36:41understanding what the organization
  5592. 3:36:43wants this is a complex thing because
  5593. 3:36:45the team member is telling you hey we
  5594. 3:36:48should start planning right away and
  5595. 3:36:50really don't wait for the assessment to
  5596. 3:36:52come back but is that what the company
  5597. 3:36:54actually wants so it's not a question
  5598. 3:36:57you can answer right off the bat the
  5599. 3:36:59best thing to do is to make sure that
  5600. 3:37:01you have the right guidance from the
  5601. 3:37:04company now couple things never shut
  5602. 3:37:08people down in this one here you're
  5603. 3:37:09telling them hey I don't care what
  5604. 3:37:11you're saying do that if a choice seems
  5605. 3:37:13negative it's probably not the answer in
  5606. 3:37:16this one it's like you're disregarding
  5607. 3:37:18what they said and you're just pointing
  5608. 3:37:19the direction if a team member gives you
  5609. 3:37:21some advice try to follow up on that
  5610. 3:37:23advice I'm not saying to follow it I'm
  5611. 3:37:25saying to follow up on it in other words
  5612. 3:37:27see if that's the right
  5613. 3:37:29advice draft a uh comprehensive plan no
  5614. 3:37:33wait see what the guidelines are then do
  5615. 3:37:36that and definitely don't just Implement
  5616. 3:37:38what the team member wants without
  5617. 3:37:40seeing if the guidelines or if that's
  5618. 3:37:41how the company should be doing it
  5619. 3:37:45102 towards the end of a large scale
  5620. 3:37:48infrastructure development project the
  5621. 3:37:50project manager detects a Slowdown in
  5622. 3:37:52progress with significant number of
  5623. 3:37:54tasks pendant in the Project's quality
  5624. 3:37:56assurance stage the project is managed
  5625. 3:37:58using a combination of traditional and
  5626. 3:38:00agile methodologies what should you do
  5627. 3:38:03next initiate an intensive quality
  5628. 3:38:06assurance session for the team project
  5629. 3:38:08Team all right bring in an external
  5630. 3:38:10consultant with expertise in in quality
  5631. 3:38:13assurance all right facilitate a problem
  5632. 3:38:16solving session to tackle the quality
  5633. 3:38:18assurance bottleneck with the team
  5634. 3:38:21allocate additional time specifically
  5635. 3:38:22for quality insurance task in the
  5636. 3:38:24project schedule all right best answer
  5637. 3:38:27here if you if you went through the
  5638. 3:38:29mindset you know this one is not too
  5639. 3:38:32difficult because the answer here is
  5640. 3:38:34going to be hey work with the team
  5641. 3:38:37anytime you face a problem on a project
  5642. 3:38:40go to The Experts to help you in this
  5643. 3:38:42particular one there is some kind of
  5644. 3:38:45issue going on here you detect a
  5645. 3:38:46Slowdown and progress you got to
  5646. 3:38:48understand what's causing that there's a
  5647. 3:38:50big number of tasks pending in the
  5648. 3:38:52quality assurance stage the best thing
  5649. 3:38:54here to do is to have the team help you
  5650. 3:38:56to solve this problem
  5651. 3:38:59notice a is not correct at all because
  5652. 3:39:01it's intensive quality assurance
  5653. 3:39:04training session um before we do that
  5654. 3:39:07let's come up with a let's meet with the
  5655. 3:39:09team to see what's actually going on so
  5656. 3:39:11let's do this maybe we can do c maybe if
  5657. 3:39:14needed we way you don't need to bring in
  5658. 3:39:16a consultant meet with the team see if
  5659. 3:39:18the team can solve it first maybe then
  5660. 3:39:20you do we no don't allocate additional
  5661. 3:39:23time meet with the team and see if they
  5662. 3:39:24can fix it before doing that so remember
  5663. 3:39:27what are you doing next anytime you get
  5664. 3:39:29questions of what you should do next
  5665. 3:39:30remember it's basically putting them in
  5666. 3:39:31order like we do we should do this then
  5667. 3:39:33do this meet with the team first and
  5668. 3:39:34then see what actions it's best to take
  5669. 3:39:39next number three Jan ongoing Urban
  5670. 3:39:44Development traditional project the
  5671. 3:39:46project manager is informed that a
  5672. 3:39:49stakeholder directly approached a team
  5673. 3:39:51member with with a request for
  5674. 3:39:54additional
  5675. 3:39:55feature which led to the team member
  5676. 3:39:57being distracted from their primary task
  5677. 3:40:00affecting the Project's progress what
  5678. 3:40:02should the project manager do now I want
  5679. 3:40:04to point out that they particularly
  5680. 3:40:06stated that this is a traditional
  5681. 3:40:08project all right so you got to
  5682. 3:40:10understand how to handle scope changes
  5683. 3:40:12or feature changes on a project
  5684. 3:40:16address the stakeholders requests and
  5685. 3:40:18its impacts on the team productivity in
  5686. 3:40:20the next project status meeting B report
  5687. 3:40:24the issue to Senior Management
  5688. 3:40:26highlighting the stakeholders bypass of
  5689. 3:40:28formal request channels and its effect
  5690. 3:40:31instruct C instruct the team members uh
  5691. 3:40:34the team member to direct the
  5692. 3:40:35stakeholder to submit all future
  5693. 3:40:38requests through the state TR the
  5694. 3:40:40project manager for proper evaluation
  5695. 3:40:43and documentation all right in encourage
  5696. 3:40:45a stakeholder to participate in the
  5697. 3:40:47project schedule review sessions to
  5698. 3:40:49ensure their input is captured in a
  5699. 3:40:51structured manner best answer here
  5700. 3:40:53remember it's a traditional
  5701. 3:40:55project is going to be tell them hey
  5702. 3:40:59send a stakeholder to me when you're
  5703. 3:41:01managing a traditional project it is
  5704. 3:41:04important to follow the change
  5705. 3:41:06management process which generally means
  5706. 3:41:08people bring their changes to the
  5707. 3:41:09project manager and the project manager
  5708. 3:41:11will assess the change and see if the
  5709. 3:41:12change is approve or not that's the best
  5710. 3:41:15thing you can do so you can go to the
  5711. 3:41:16team member and instruct them hey if a
  5712. 3:41:17stakeholder is doing this tell them to
  5713. 3:41:19come to me not to
  5714. 3:41:22you uh notice a which at the beginning
  5715. 3:41:25sounds good and then it's impact on the
  5716. 3:41:28team no what you need to do is you need
  5717. 3:41:30to uh and it shouldn't be the next
  5718. 3:41:33status meeting because God knows how
  5719. 3:41:35long ago that is how when that's going
  5720. 3:41:37to be from
  5721. 3:41:39now so the best thing here to do is to
  5722. 3:41:42let them know you know tell the
  5723. 3:41:44stakeholders come to to me that way it
  5724. 3:41:45doesn't affect the team productivity
  5725. 3:41:47never report anyone on this test you're
  5726. 3:41:50probably going to get choices quite a
  5727. 3:41:52few questions going to have choices
  5728. 3:41:54report this guy to Senior Management
  5729. 3:41:56report this guy to the sponsor report
  5730. 3:41:58this guy to the project management
  5731. 3:41:59office those are never the answer never
  5732. 3:42:01report anyone never try to get people in
  5733. 3:42:03trouble never try to get anyone
  5734. 3:42:06fired encourage to participate in the
  5735. 3:42:09project schedule this is not anything to
  5736. 3:42:11do with the schedule this is a scope
  5737. 3:42:13change notice they're added a feature
  5738. 3:42:18question
  5739. 3:42:19104 in the early planning stages of a
  5740. 3:42:23green building project the project
  5741. 3:42:25manager faces challenges with limited
  5742. 3:42:28data available for defining specific
  5743. 3:42:31activities and estimating their
  5744. 3:42:32durations accurately what strategy
  5745. 3:42:35should the project manager employ
  5746. 3:42:37Implement a detailed timeline with key
  5747. 3:42:40milestones and delivery dates okay
  5748. 3:42:42utilize Progressive elaboration and
  5749. 3:42:44flexible plan plan
  5750. 3:42:46techniques adapt iterative planning with
  5751. 3:42:49regular evaluations and adjustments use
  5752. 3:42:52detail estimation method derived from a
  5753. 3:42:54comprehensive work breakdown structure
  5754. 3:42:56best answer here guys now remember to
  5755. 3:42:58choose two best answer here is going to
  5756. 3:43:00be B and C correct here's why because
  5757. 3:43:04notice so you can do the estimation
  5758. 3:43:06because you have limited data
  5759. 3:43:09um for defining specific act limited
  5760. 3:43:12data for Define an activity means you
  5761. 3:43:14don't really have a comprehensive
  5762. 3:43:17WBS and you can't do a detail timeline
  5763. 3:43:20because you're having difficulties
  5764. 3:43:22estimating things the best thing here
  5765. 3:43:24you can do is when you're doing projects
  5766. 3:43:27that are complex is plan to replan
  5767. 3:43:30that's the whole concept of progressive
  5768. 3:43:32elaboration in which case as time is
  5769. 3:43:34progressing Things become more detailed
  5770. 3:43:36for example if I say let's do a 5-year
  5771. 3:43:39project can we really plan the specific
  5772. 3:43:42duration of an activity that's going to
  5773. 3:43:44happen in year five right now the whole
  5774. 3:43:47world can change in year five so what we
  5775. 3:43:49do is we say you know what leave that
  5776. 3:43:51duration plan in until we get closer to
  5777. 3:43:54year five maybe in year four we'll do
  5778. 3:43:56that that's a concept of progressive
  5779. 3:43:58elaboration and then iterative plan it
  5780. 3:44:00means we're plan to replan we're going
  5781. 3:44:01to say you know what we're going to plan
  5782. 3:44:04we're making a plan right now to replan
  5783. 3:44:05in four years for activities in year
  5784. 3:44:08five we did cover this in the course
  5785. 3:44:10hopefully you got this one right
  5786. 3:44:13question 105 as a project manager
  5787. 3:44:16overseeing the development of a new line
  5788. 3:44:18of echo-friendly packaging material you
  5789. 3:44:20encounter push back from certain
  5790. 3:44:22stakeholders who who question who
  5791. 3:44:25questions the Project's viability due to
  5792. 3:44:29environmental regulations and Market
  5793. 3:44:30demands
  5794. 3:44:32uncertainty what action should the
  5795. 3:44:34project manager
  5796. 3:44:36take request a meeting with key
  5797. 3:44:38stakeholders to directly address their
  5798. 3:44:40concerns and provide detailed
  5799. 3:44:42explanations okay continuously evaluate
  5800. 3:44:46and adjust projects f f foundational
  5801. 3:44:49documents to ensure they reflect current
  5802. 3:44:51conditions and insights craft a
  5803. 3:44:54comprehensive risk management strategy
  5804. 3:44:56to identify and mitigate potential
  5805. 3:44:58issues related to regulations and Market
  5806. 3:45:01response align project objectives and
  5807. 3:45:04broader environmental sustainability
  5808. 3:45:05goals to ensure comprehensive
  5809. 3:45:07organizational coherence now you're
  5810. 3:45:10having a problem with the stakeholders
  5811. 3:45:12they're questioning hey can we do this
  5812. 3:45:15project is there
  5813. 3:45:16Market is there some kind of
  5814. 3:45:18environmental regulations anytime you
  5815. 3:45:20have a problem on a project the best
  5816. 3:45:22thing here to do guys is to address it
  5817. 3:45:25with those stakeholders meet with the
  5818. 3:45:27stakeholders understand their main
  5819. 3:45:29concern directly address that concern
  5820. 3:45:32and solve that problem
  5821. 3:45:34now continuously evaluate and adjust I'm
  5822. 3:45:37not sure what the foundational document
  5823. 3:45:39here is we're not even too sure what is
  5824. 3:45:42it that the stakeholders are so
  5825. 3:45:43concerned about find that out
  5826. 3:45:45then maybe come up with a risk
  5827. 3:45:47management plan or some kind of risk
  5828. 3:45:49strategy um and depending on what the
  5829. 3:45:52strategy is maybe you do d right realign
  5830. 3:45:56the objectives maybe if that's needed
  5831. 3:45:57depending on what their concern is but
  5832. 3:45:59if you have a stakeholder with issues if
  5833. 3:46:01you have stakeholders that has a problem
  5834. 3:46:03with the way the project is done the
  5835. 3:46:05best thing here to do is address those
  5836. 3:46:06issues with the stakeholder thems
  5837. 3:46:09themselves 106 in leading a complex
  5838. 3:46:13software development project with te
  5839. 3:46:14team members spread across diverse
  5840. 3:46:17geographical
  5841. 3:46:18locations the project manager seeks
  5842. 3:46:21strategies to enhance cohesion and
  5843. 3:46:24ensure project Effectiveness oh boy
  5844. 3:46:27sorry about that uh forgot to put that
  5845. 3:46:29on there all right pause I'm I don't
  5846. 3:46:31want to redo this video just pause the
  5847. 3:46:33video right now good you did that all
  5848. 3:46:35right now you're now you're caught up
  5849. 3:46:37ensure project Effectiveness what action
  5850. 3:46:39should the project manager take organize
  5851. 3:46:42intermediate gathering for collab
  5852. 3:46:45problem solving and team integration
  5853. 3:46:47exercises have members meet in one time
  5854. 3:46:49zone to ensure everyone can
  5855. 3:46:51attend initiate a buddy system parent uh
  5856. 3:46:55remote team members to Foster cross
  5857. 3:46:59Regional collaboration and knowledge
  5858. 3:47:01sharing utilize a flexible work schedule
  5859. 3:47:04allowing team members to choose their
  5860. 3:47:07work hours all right what is the best
  5861. 3:47:10answer here so let's take a look at this
  5862. 3:47:14all right you got a
  5863. 3:47:16team across diverse geographical
  5864. 3:47:20locations the best answer with that in
  5865. 3:47:23mind best answer is going to be a now
  5866. 3:47:26some of these answers are just plain raw
  5867. 3:47:28notice have members Mee in one time zone
  5868. 3:47:31well that means not everyone can attend
  5869. 3:47:33because they don't work in the same time
  5870. 3:47:34zone it's cross geographical
  5871. 3:47:36locations a buddy appearance system
  5872. 3:47:38means that only those two people are
  5873. 3:47:40going to work
  5874. 3:47:41together flexible work schedule if you
  5875. 3:47:44allow them to choose choose their own
  5876. 3:47:45work schedule they might be working more
  5877. 3:47:47apart than together so a is not I don't
  5878. 3:47:50think a is a great answer but it is the
  5879. 3:47:52best of the for answer and this brings
  5880. 3:47:54me to a point remember what this exam is
  5881. 3:47:56this exam is not about choosing the
  5882. 3:48:00correct answer it's choosing the best of
  5883. 3:48:03the four so sometimes you got to choose
  5884. 3:48:04the least of the suckiest answer because
  5885. 3:48:07maybe they all suck but one of them is
  5886. 3:48:09going to be the least of those the least
  5887. 3:48:12worst answer and that's the one you go
  5888. 3:48:14with
  5889. 3:48:18107 as a project manager of a new
  5890. 3:48:21healthcare software implementation
  5891. 3:48:22project you're leading a team that's
  5892. 3:48:25decided to embrace a hybrid approach
  5893. 3:48:28combining elements of both agile and
  5894. 3:48:31waterfall methodologies the project
  5895. 3:48:33success hinges on your ability to unify
  5896. 3:48:37the team towards a common goal aim the
  5897. 3:48:40complexities of the healthcare sector
  5898. 3:48:42what steps should you take to ensure the
  5899. 3:48:44team
  5900. 3:48:45functions effectively as a cohesive
  5901. 3:48:48unit okay so this is a common thing in
  5902. 3:48:51real life all right very common thing in
  5903. 3:48:52real life that you have teams that are
  5904. 3:48:55combined and they're trying to do a
  5905. 3:48:56hybrid
  5906. 3:48:57approach uh you got to make sure you
  5907. 3:48:59unify them all right what are we going
  5908. 3:49:01to do schedule a regular one-on-one
  5909. 3:49:03meeting with team members to tailor
  5910. 3:49:05communication and task management to the
  5911. 3:49:07individual
  5912. 3:49:09preference create a conflict resolution
  5913. 3:49:11protocol that emphasizes empathy your
  5914. 3:49:14understanding to address disagreements
  5915. 3:49:17quickly designate clear roles and
  5916. 3:49:19responsibility to each team member to
  5917. 3:49:21streamline project execution and
  5918. 3:49:23accountability Foster a culture of open
  5919. 3:49:25communication and establish your Norms
  5920. 3:49:28to guide effective to guide
  5921. 3:49:30collaborative efforts now this question
  5922. 3:49:32is not that uh easy I thought this one
  5923. 3:49:36was pretty difficult because they all
  5924. 3:49:37sound great and it's not uncommon on
  5925. 3:49:41your
  5926. 3:49:42exam to have all four choices s right
  5927. 3:49:45you got to go with the best one the
  5928. 3:49:46easiest way to do this is find a choice
  5929. 3:49:48that includes them all find a choice
  5930. 3:49:51that really that can apply to the entire
  5931. 3:49:53thing and that brings me to this choice
  5932. 3:49:56of
  5933. 3:49:57D you see open
  5934. 3:50:00communication shared Norms this here is
  5935. 3:50:03going to form that collaborative effort
  5936. 3:50:06because with open Communications this
  5937. 3:50:08allows everyone to work together now
  5938. 3:50:11there's a couple things here why the
  5939. 3:50:12others are not wrong notice regular
  5940. 3:50:14one-on-one meetings with team members to
  5941. 3:50:16tailor
  5942. 3:50:17Communications and to the if you do this
  5943. 3:50:20with every single one it might be very
  5944. 3:50:22difficult especially on a hybrid project
  5945. 3:50:25because individual and the way
  5946. 3:50:27Communications are done is vastly
  5947. 3:50:28different between agile and
  5948. 3:50:32traditional protocol emphasizes I do
  5949. 3:50:35like this one but you know what open
  5950. 3:50:37Communications established Norms will
  5951. 3:50:40include B designate clear roles to each
  5952. 3:50:43member that's also is going to be be in
  5953. 3:50:45open Communications they caned the best
  5954. 3:50:48answer if you have multiple answers that
  5955. 3:50:50sounds great try to find the one that
  5956. 3:50:52includes the others if one includes all
  5957. 3:50:54those good answers that means probably
  5958. 3:50:56the right
  5959. 3:50:59answer 108 as a as a project manager
  5960. 3:51:03over seeing a large scale renewable
  5961. 3:51:06energy project you're confronted with a
  5962. 3:51:08sudden need to transition your
  5963. 3:51:10traditionally onsite team to work to
  5964. 3:51:13remote work due to environmental
  5965. 3:51:15regulations and affect and
  5966. 3:51:18affecting access to the project site
  5967. 3:51:21several members expressed concern about
  5968. 3:51:23their inexperience with with and the
  5969. 3:51:26potential challenges of maintaining
  5970. 3:51:29their usual level of productivity and
  5971. 3:51:31communication in a remote
  5972. 3:51:33environment what what step should the
  5973. 3:51:36project manager take to ensure the team
  5974. 3:51:38remains productive and cohesive while
  5975. 3:51:42working remotely
  5976. 3:51:45he arrange for economic home office
  5977. 3:51:47setups for all members to enhance their
  5978. 3:51:50work from their home working environment
  5979. 3:51:52all right I like that you should make
  5980. 3:51:54them comfortable partner with it to
  5981. 3:51:57provide customized Tech solutions for
  5982. 3:51:59each team member based on a specific
  5983. 3:52:01remote home okay probably should do that
  5984. 3:52:04too arrange for a comprehensive training
  5985. 3:52:06on remote uh Communications and project
  5986. 3:52:09manag to improve team adaptability okay
  5987. 3:52:12Implement a more flexible project
  5988. 3:52:14timeline to account for learning curve
  5989. 3:52:16associated with adapting to remote work
  5990. 3:52:19difficult
  5991. 3:52:20question I think each one of these has
  5992. 3:52:23their has their correct answer but one
  5993. 3:52:25of them really deals with the problem
  5994. 3:52:29head on and the problem that they're
  5995. 3:52:31really dealing with is their
  5996. 3:52:35productivity which one here is you see
  5997. 3:52:39the potential challenges of maintaining
  5998. 3:52:41the key thing here is productivity and
  5999. 3:52:43communication
  6000. 3:52:45it's not about their
  6001. 3:52:47ergonomics or their IT
  6002. 3:52:51issues uh or their time all right it's
  6003. 3:52:55how are they going to communicate so
  6004. 3:52:56come up with a good training system to
  6005. 3:52:58manage their
  6006. 3:53:00Communication in in these questions you
  6007. 3:53:02have to read carefully a few words can
  6008. 3:53:05change an entire question in fact one
  6009. 3:53:07word can change an entire question keep
  6010. 3:53:09that in mind so read
  6011. 3:53:12carefully 109
  6012. 3:53:15facing the challenge facing the
  6013. 3:53:17challenge of rolling out a critical
  6014. 3:53:19Disaster Response application a project
  6015. 3:53:22manager leads a multi-disciplinary team
  6016. 3:53:25under tight deadlines the application
  6017. 3:53:27needs to be operational in a third of
  6018. 3:53:30the standard timeline to effectively
  6019. 3:53:32respond to an ongoing crisis what action
  6020. 3:53:35should the project manager take to
  6021. 3:53:36ensure timely delivery while maintaining
  6022. 3:53:39essential functions essential
  6023. 3:53:41functionality accelerate All Phases of
  6024. 3:53:43the timeline
  6025. 3:53:45streamline Communication channel to
  6026. 3:53:47enhance team efficiency focus on team
  6027. 3:53:49deliver and MVP increase uh working
  6028. 3:53:52hours to cover more tasks and less time
  6029. 3:53:55if you understand the way agile works
  6030. 3:53:58the best thing here you can do is going
  6031. 3:54:01to
  6032. 3:54:02be correct we want an MVP or a minimum
  6033. 3:54:07viable product this is going to allow us
  6034. 3:54:08to push something to the market very
  6035. 3:54:10quickly notice needs to be operational
  6036. 3:54:13in a third
  6037. 3:54:15thir of the standard timeline by
  6038. 3:54:18utilizing an MVP we an MVP a minimum
  6039. 3:54:21viral product allows you to release
  6040. 3:54:23something to your users very very
  6041. 3:54:25quickly now it's probably not going to
  6042. 3:54:27have every single feature but it's going
  6043. 3:54:29to have the most used features or the
  6044. 3:54:31most requested because remember how if
  6045. 3:54:33you follow agile you build the most
  6046. 3:54:35valuable features first so this is going
  6047. 3:54:37to give them access to
  6048. 3:54:39it accelerating All Phases may not be
  6049. 3:54:43doable for example you can't accelerate
  6050. 3:54:45coding and testing because if you
  6051. 3:54:47haven't coded anything there's under to
  6052. 3:54:48test streamline communication although
  6053. 3:54:51this will increase efficiency the best
  6054. 3:54:52thing is to go with that mvp increase
  6055. 3:54:55never work people overtime all right if
  6056. 3:54:58you ever have a choice on your exam to
  6057. 3:54:59overwork your employees that sounds
  6058. 3:55:01negative don't do
  6059. 3:55:03it last question during the execution
  6060. 3:55:06phase of a large scale environmental
  6061. 3:55:09restoration project the project manager
  6062. 3:55:11encounters a debate among team members
  6063. 3:55:14regarding a necessary extension of
  6064. 3:55:16timeline due to unforeseen regulatory
  6065. 3:55:18changes how should the project manager
  6066. 3:55:20proceed stick to the stakeholder
  6067. 3:55:22Communications plan for systematic
  6068. 3:55:25engagement decision- making analyze the
  6069. 3:55:27impact of the timeline expand on the
  6070. 3:55:29project then consult with the team for
  6071. 3:55:31guidance organize an urgent team meeting
  6072. 3:55:34to vote on the timeline extension aiming
  6073. 3:55:36for a democratic uh uh decision directly
  6074. 3:55:41implement the timeline extension
  6075. 3:55:43prioritizing regulatory compliance all
  6076. 3:55:45right what is the best answer
  6077. 3:55:47so follow your mindset on this one I
  6078. 3:55:50taught this one here not too difficult
  6079. 3:55:53all right you have a debate am team
  6080. 3:55:55members regarding the extension assess
  6081. 3:55:57it but remember just don't assess it by
  6082. 3:55:59yourself make sure to consult with the
  6083. 3:56:01team let the team help you assess this
  6084. 3:56:03work with the entire
  6085. 3:56:05team uh just just don't tell them to
  6086. 3:56:08stick to this in decision making address
  6087. 3:56:10the problems organize an urgent meeting
  6088. 3:56:12to vote on it well before you vote on
  6089. 3:56:14the extension assess it before you do
  6090. 3:56:16that directly do don't do that assess it
  6091. 3:56:19to see how it affects the project and
  6092. 3:56:21have the team help you question 111
  6093. 3:56:25halfway through a software development
  6094. 3:56:26project the project manager identifies
  6095. 3:56:29that an important security feature was
  6096. 3:56:31omitted this feature is essential for
  6097. 3:56:33the software to me industry security
  6098. 3:56:35guidelines the project manager stands
  6099. 3:56:37that integrating this feature promptly
  6100. 3:56:39is critical to prevent potential
  6101. 3:56:41security breaches what is the most
  6102. 3:56:43effective course of action the project
  6103. 3:56:44manager should take
  6104. 3:56:47next schedule an urgent meeting with
  6105. 3:56:49stakeholders to discuss the Implement of
  6106. 3:56:51the implications of incorporating the
  6107. 3:56:53security feature conduct an impact to
  6108. 3:56:56understand the impact of adding this
  6109. 3:56:58feature at this stage of the project
  6110. 3:57:00prioritize the security features in a
  6111. 3:57:01project backlog ensuring that IT
  6112. 3:57:03addresses the next phase seek additional
  6113. 3:57:06resources to include the security
  6114. 3:57:08features without alterating alter the
  6115. 3:57:11current project Milestones remember
  6116. 3:57:13you're doing this here it says what
  6117. 3:57:15should you take next so you missed the
  6118. 3:57:17feature the best thing you're going to
  6119. 3:57:18be doing next is to see how adding this
  6120. 3:57:22in is going to affect the current
  6121. 3:57:23project because we know we got to add it
  6122. 3:57:24in but we got to see okay how is this
  6123. 3:57:27going to affect the project how much is
  6124. 3:57:28it going to drive the budget how much is
  6125. 3:57:30going to drive up the schedule before we
  6126. 3:57:32do anything else now there's a couple uh
  6127. 3:57:36reasons why the rest of these are wrong
  6128. 3:57:38first of all you should have eliminated
  6129. 3:57:39C the project manager cannot add to the
  6130. 3:57:42project backlog and not prioritize the
  6131. 3:57:45project backlog urgent to discuss the
  6132. 3:57:48but we already know that if we don't
  6133. 3:57:51incorporate it you don't need a because
  6134. 3:57:53you already know that there's going to
  6135. 3:57:54be security breaches there's no need for
  6136. 3:57:56a seek additional resource assess it
  6137. 3:57:59before seeking additional resources
  6138. 3:58:02making B the best
  6139. 3:58:05answer 112 during a healthcare facility
  6140. 3:58:08upgrade project a project manager is
  6141. 3:58:11informed by a key stakeholder that
  6142. 3:58:13certain Advanced technological features
  6143. 3:58:16expected by the stakeholders are not
  6144. 3:58:19visible in the preliminary designs what
  6145. 3:58:22should the project manager do to address
  6146. 3:58:24the stakeholders concerns review the
  6147. 3:58:26project plan and update the
  6148. 3:58:29stakeholders okay confirm with the
  6149. 3:58:32stakeholders that their expectations
  6150. 3:58:33will be integrated in the design
  6151. 3:58:36provision process organize a detailed
  6152. 3:58:38presentation on the current project
  6153. 3:58:40status and future Milestones have the
  6154. 3:58:42team include the design and the project
  6155. 3:58:44scope what are we going to be doing how
  6156. 3:58:47do we how are we going to address this
  6157. 3:58:48person's concern best answer here guys
  6158. 3:58:51is to review the plan and update the
  6159. 3:58:53stakeholders that is correct so first of
  6160. 3:58:56all notice a key stake certain
  6161. 3:59:00technological expected are not visible
  6162. 3:59:03so it's not visible to them is it in the
  6163. 3:59:06plan well that part I'm not sure about
  6164. 3:59:08so go and find out you're a project
  6165. 3:59:10manager hey stakeholder comes to you and
  6166. 3:59:13says hey it's not in the plan but are
  6167. 3:59:15you sure it's not in the plan do you
  6168. 3:59:17know that your next step how do how are
  6169. 3:59:19you going to address this your best step
  6170. 3:59:20here is to review the plan to see if it
  6171. 3:59:22is or it's
  6172. 3:59:23not you can't confirm with them that
  6173. 3:59:26it'll be integrated unless you check
  6174. 3:59:27that plan you shouldn't organize a
  6175. 3:59:30detail and future Milestone the
  6176. 3:59:31stakeholders check the plan first just
  6177. 3:59:34the team can't include things like that
  6178. 3:59:35in a scope it has to go to a full change
  6179. 3:59:38process and if it's if it's a
  6180. 3:59:40traditional project it'll go to a change
  6181. 3:59:42process if it's an adile project to
  6182. 3:59:44product owner can add
  6183. 3:59:45it 113 following a corporate
  6184. 3:59:48restructuring the project manager
  6185. 3:59:51notices that the newly assembled team is
  6186. 3:59:54having difficulty adapting to their
  6187. 3:59:56Collective
  6188. 3:59:57role with members often prepare
  6189. 4:00:00prefering to work in isolation rather
  6190. 4:00:02than as a unified team this behavior is
  6191. 4:00:05affecting the Synergy and effect and
  6192. 4:00:07efficiency of project work what should
  6193. 4:00:09the project manager do to enhance Team
  6194. 4:00:12Dynamics are organize a workshop to
  6195. 4:00:15focus on team integration and
  6196. 4:00:17collaborative problem solving Implement
  6197. 4:00:19a flexible work policy to accommodate
  6198. 4:00:21individual work preference establish a
  6199. 4:00:23regular oneon-one check-in to address
  6200. 4:00:25any personal concerns affecting teamwork
  6201. 4:00:28initiate a competitive Initiative
  6202. 4:00:30Program to encourage collaboration
  6203. 4:00:33there's really only two good answers
  6204. 4:00:34here you got they working in Silo
  6205. 4:00:37activities basically they're in
  6206. 4:00:38isolation the two good answers here was
  6207. 4:00:41either a or D first of all B was never a
  6208. 4:00:45good answer because of flexible work if
  6209. 4:00:47they're now they're not together at all
  6210. 4:00:50some may work sometime or not you're
  6211. 4:00:51separating them even more a one-on-one
  6212. 4:00:54checkin doesn't address them working
  6213. 4:00:56together now you're just addressing them
  6214. 4:00:58it's like you're promoting the
  6215. 4:00:59one-on-one initiate a comp uh
  6216. 4:01:02competitive Initiative Program this here
  6217. 4:01:05is going to make them more competitive
  6218. 4:01:06may not put them the best thing here to
  6219. 4:01:08do is to bring them together put them in
  6220. 4:01:11workshops and let them start working
  6221. 4:01:13together
  6222. 4:01:14let them come up with ways to solve
  6223. 4:01:17problems
  6224. 4:01:20114 in an initiative to manage a
  6225. 4:01:22software development team spread across
  6226. 4:01:24multiple continent a project manager
  6227. 4:01:27seeks to enhance collaboration and
  6228. 4:01:29ensure synchronous work Dynamics the
  6229. 4:01:31team diversity in culture and geography
  6230. 4:01:34presents a unique challenge in
  6231. 4:01:36maintaining effective Communications and
  6232. 4:01:40collaboration what initiative should the
  6233. 4:01:42project manager prior prti to ensure
  6234. 4:01:45effective team
  6235. 4:01:47collaboration okay so once again you're
  6236. 4:01:49trying to make this team work together
  6237. 4:01:51but now you have them spread across
  6238. 4:01:54continents a introduce a dynamic
  6239. 4:01:56platform for real-time video conference
  6240. 4:01:57and interactive sessions all right
  6241. 4:02:00Implement an asynchronous communication
  6242. 4:02:02tool for delayed but comprehensive
  6243. 4:02:04exchange all right see arrange for
  6244. 4:02:06physical uh annual physical meetups to
  6245. 4:02:09Foster personal connections D develop an
  6246. 4:02:12internal email newsletter for weekly
  6247. 4:02:15updates on Project progress so we want
  6248. 4:02:18the team to work together you have them
  6249. 4:02:19in a diverse you have them across the
  6250. 4:02:21continent um they're having a problem
  6251. 4:02:24with effective Communications so how can
  6252. 4:02:27we increase and make their
  6253. 4:02:29Communications better the best answer
  6254. 4:02:31here guys is going to be a if you got a
  6255. 4:02:34that is correct and the reason is
  6256. 4:02:35because a real time video conference in
  6257. 4:02:38like Zoom will help them to communicate
  6258. 4:02:40a lot better a physical Meetup is not
  6259. 4:02:42going to solve this because that's just
  6260. 4:02:43just once a year and email is more of a
  6261. 4:02:47push type communication it's not an
  6262. 4:02:49interactive
  6263. 4:02:51communication asynchronous is offline so
  6264. 4:02:54it's not interactive you want them
  6265. 4:02:56effective Communications and especially
  6266. 4:02:58collaboration when you think
  6267. 4:03:00collaboration always think of
  6268. 4:03:04interactive you can't be collaborative
  6269. 4:03:06if I me and you are not collaborating if
  6270. 4:03:08I'm just giving you information this
  6271. 4:03:10video is not is not a collabor ation
  6272. 4:03:14between me and you I'm not taking from
  6273. 4:03:16you you're not taking from me I'm just
  6274. 4:03:17giving you
  6275. 4:03:18information so you don't want something
  6276. 4:03:21that's asynchronous you want something
  6277. 4:03:22that's more synchronous make an a the
  6278. 4:03:24best
  6279. 4:03:25answer
  6280. 4:03:27115 in the critical validation stage of
  6281. 4:03:31a software development project a
  6282. 4:03:33thirdparty component fails to meet the
  6283. 4:03:35expected performance Benchmark this
  6284. 4:03:37discrepancy leads to significant
  6285. 4:03:39concerns about meeting the project
  6286. 4:03:42timeline the man identifies that the
  6287. 4:03:44failure is due to the component being
  6288. 4:03:46developed based on outdated
  6289. 4:03:49specifications what could have been done
  6290. 4:03:51to prevent this from happening now
  6291. 4:03:53you're going to get these questions
  6292. 4:03:54where you see something that says
  6293. 4:03:55prevent from happening that means don't
  6294. 4:03:58fix the problem right now it means to
  6295. 4:04:03fix the problem before it can happen
  6296. 4:04:05right it means to prevent the problem
  6297. 4:04:07from happening so be careful when you
  6298. 4:04:09read the
  6299. 4:04:10answers conduct a comprehensive review
  6300. 4:04:12of the project requirement and
  6301. 4:04:14management processes with stakeholders
  6302. 4:04:16to align expectations and specifications
  6303. 4:04:18all right initiate a cost benefit
  6304. 4:04:20analysis determine if redesign of the
  6305. 4:04:22components is financially viable
  6306. 4:04:24compared to potential project delays all
  6307. 4:04:26right schedule urgent me with supplier
  6308. 4:04:28to negotiate expertise delivery terms
  6309. 4:04:30all right assign a team assign a team to
  6310. 4:04:34develop a work around for the fail
  6311. 4:04:36component the best answer here is going
  6312. 4:04:38to be a you notice so read the question
  6313. 4:04:42carefully the failure is due to a
  6314. 4:04:44component being developed based on
  6315. 4:04:45outdated
  6316. 4:04:47specification now that means the
  6317. 4:04:49specifications were
  6318. 4:04:52incorrect B to determine if redesign and
  6319. 4:04:56this is going to fix the current problem
  6320. 4:04:58we don't want that we want to prevent
  6321. 4:04:59the current problem schedule an urgent
  6322. 4:05:02meeting with the supply to negotiate exp
  6323. 4:05:04this here might fix the current problem
  6324. 4:05:06assign a team to you don't want to work
  6325. 4:05:08around work around means you you a work
  6326. 4:05:10around means something failed and then
  6327. 4:05:11you're going around that trying to fix
  6328. 4:05:13it that all of these doesn't line up
  6329. 4:05:16with the keyword of prevent this problem
  6330. 4:05:19maybe if the question was like how do
  6331. 4:05:20you fix this problem you know maybe B
  6332. 4:05:22and maybe b and a would have probably B
  6333. 4:05:25and D would have been a good answer but
  6334. 4:05:27they're asking to prevent the problem so
  6335. 4:05:29read carefully 116 a project manager is
  6336. 4:05:34overseeing a project designed to deliver
  6337. 4:05:38iterative enhancement to an existing
  6338. 4:05:40service and has an established
  6339. 4:05:43prioritize product backlog from the
  6340. 4:05:44product owner good despite this the
  6341. 4:05:47product owner later voices concern to
  6342. 4:05:49Senior Management about the Project's
  6343. 4:05:51Direction not aligning with the
  6344. 4:05:52expectations with
  6345. 4:05:54expectations what initiative should a
  6346. 4:05:56project manager have undertaken all
  6347. 4:05:58right so we got a project the product
  6348. 4:06:01owner prioritize the product backlog but
  6349. 4:06:03they just don't like the direction that
  6350. 4:06:04they're going in what should we do
  6351. 4:06:07Institute a comprehensive stakeholder
  6352. 4:06:08engagement plan to ensure all voices are
  6353. 4:06:10heard and integrated into project
  6354. 4:06:12planning okay adapt a more flexible
  6355. 4:06:15approach to project management
  6356. 4:06:16methodologies to accommodate changing
  6357. 4:06:18stakeholders expectations all right
  6358. 4:06:20enhance team training on the Project's
  6359. 4:06:22Technical and business aspect to ensure
  6360. 4:06:24a deeper understand of project goals all
  6361. 4:06:26right organize regular Sprint review
  6362. 4:06:28meetings with the product owner and
  6363. 4:06:30conduct team retrospective to close the
  6364. 4:06:32feedback loop now you right off the bat
  6365. 4:06:35you can tell that this is going to be an
  6366. 4:06:37agile project you got the product owner
  6367. 4:06:39you got the product
  6368. 4:06:41backlog uh keep in mind here that the
  6369. 4:06:44product owner is not sure like they're
  6370. 4:06:45not something is not aligning to ensure
  6371. 4:06:48that an ad job project stays aligned you
  6372. 4:06:50should be doing your Sprint review
  6373. 4:06:53meetings the Sprint review meetings is
  6374. 4:06:55when the product owner the customer
  6375. 4:06:56comes in and sees what happening then
  6376. 4:06:58they can give feedback basically at the
  6377. 4:07:01end of every Sprint which is basically
  6378. 4:07:03every month or or every few weeks to
  6379. 4:07:06tell you if it's a line or it's not a
  6380. 4:07:09line now why is the rest not wrong well
  6381. 4:07:12it's not it's not really into there's
  6382. 4:07:15nothing in the question that states that
  6383. 4:07:16there's a problem with the team's
  6384. 4:07:19technical understanding of this so
  6385. 4:07:21that's wrong a more flexible approach to
  6386. 4:07:23the method there's nothing wrong with
  6387. 4:07:24the methodology maybe the methodology is
  6388. 4:07:26not used right Institute a comprehensive
  6389. 4:07:29and to ensure all voices heard you may
  6390. 4:07:32never hear all voices on all projects so
  6391. 4:07:34the best answer here is to make sure you
  6392. 4:07:36do the Sprint review
  6393. 4:07:39meetings by the way if you guys are
  6394. 4:07:40enjoying this video give the video a
  6395. 4:07:42like make sure to
  6396. 4:07:44subscribe 117 after project Milestone a
  6397. 4:07:47team member voices concerns over the
  6398. 4:07:50lack of detailed feedback regarding
  6399. 4:07:52their project contributions the
  6400. 4:07:53individual feels that without specific
  6401. 4:07:56Insight their ability to improve and
  6402. 4:07:58impact the project positively is limited
  6403. 4:08:01what should the project manager consider
  6404. 4:08:03first schedule on All
  6405. 4:08:06Hands meeting to discuss project
  6406. 4:08:08performance and individual contributions
  6407. 4:08:10openly establish an online form for the
  6408. 4:08:13project team to post accomplishments and
  6409. 4:08:16receive peer
  6410. 4:08:17feedback uh introduce a quarter review
  6411. 4:08:19system that focuses on Project Specific
  6412. 4:08:21achievements and growth areas enhance
  6413. 4:08:24documentation of individual performance
  6414. 4:08:27metrics and provide regular personalized
  6415. 4:08:29feedback session all right best answer
  6416. 4:08:31here guys remember it's one
  6417. 4:08:34stakeholder it's one team member so what
  6418. 4:08:37are we going to be doing is we should
  6419. 4:08:39personalize feedback first of all you
  6420. 4:08:42don't want to do individual ual
  6421. 4:08:43contributions and and say openly how
  6422. 4:08:47someone is doing great or not doing
  6423. 4:08:49great uh or this one because then it may
  6424. 4:08:52seem like some people are doing more
  6425. 4:08:53than others and may not necessarily be
  6426. 4:08:55true you don't want just an online form
  6427. 4:08:58you want to address this directly with
  6428. 4:08:59the team quarterly system maybe too long
  6429. 4:09:03or Too Short depending on the project
  6430. 4:09:05the best thing here let people know what
  6431. 4:09:07those individual metrics are so they
  6432. 4:09:09know if they're meeting them and you
  6433. 4:09:10want regular personalized feedback on
  6434. 4:09:12this making D the best
  6435. 4:09:16answer 118 during a project review the
  6436. 4:09:20client identifies a critical feature in
  6437. 4:09:22the new software application that was
  6438. 4:09:24not that was discussed but not
  6439. 4:09:27implemented so they knew about it but we
  6440. 4:09:29didn't put it in the project manager
  6441. 4:09:30verifies that this in this feature was
  6442. 4:09:33indeed documented as part of the scope
  6443. 4:09:36what should the project manager on take
  6444. 4:09:38as a preliminary
  6445. 4:09:40action initiate a brainstorming session
  6446. 4:09:43with the stakeholder to identify
  6447. 4:09:44alternative for the missing feature
  6448. 4:09:46arrange a detailed discussion with the
  6449. 4:09:48team to understand the oversight and
  6450. 4:09:50develop corrective action commission an
  6451. 4:09:52external audit to evaluate the project
  6452. 4:09:55management processes and identify gaps
  6453. 4:09:58recommend the suspension the project
  6454. 4:10:00delivery timeline to reevaluate all
  6455. 4:10:02project components comprehensively now
  6456. 4:10:05this you're going to follow the mindset
  6457. 4:10:07so we miss something if you miss a
  6458. 4:10:09feature that's critical that should have
  6459. 4:10:11been there they knew they should have
  6460. 4:10:12gotten it done but we just didn't get it
  6461. 4:10:14done find out why what happened meet
  6462. 4:10:17with the team and then come up with a
  6463. 4:10:19way to solve it that's the best thing we
  6464. 4:10:21can do brainstorming you don't want to
  6465. 4:10:23come up with alternative Solutions until
  6466. 4:10:25meeting with the team maybe the team
  6467. 4:10:26maybe this is something the team can
  6468. 4:10:28Implement right away you don't need an
  6469. 4:10:30external audit um to identify any gaps
  6470. 4:10:35in the project this should have been a
  6471. 4:10:36throughout answer before you do any of
  6472. 4:10:38that remember it's a prelim you know
  6473. 4:10:40it's a primary action one of the things
  6474. 4:10:42you want to do as a primary action is to
  6475. 4:10:43meet with the team have the team help
  6476. 4:10:45you solve this recommend the suspension
  6477. 4:10:48never stop your project the only time
  6478. 4:10:50You' ever probably stop a project is if
  6479. 4:10:52you're breaking the law or someone may
  6480. 4:10:54may die or some kind of safety
  6481. 4:10:56issue but never stop a project like
  6482. 4:10:59that 119 upon discovering a significant
  6483. 4:11:03quality issue with a key suppliers
  6484. 4:11:06deliverables the project manager needs
  6485. 4:11:08to address the problem to maintain
  6486. 4:11:10project standards what should the
  6487. 4:11:12project man what should be the project
  6488. 4:11:13manager's initial action schedule an
  6489. 4:11:16urgent project team meeting to
  6490. 4:11:18brainstorm potential solutions to the
  6491. 4:11:20Quality
  6492. 4:11:21Issue request and immediate
  6493. 4:11:24comprehensive quality audits on all
  6494. 4:11:25supplier deliverables to identify the
  6495. 4:11:28scope of the problem all right refer to
  6496. 4:11:30the Project's risk register for pre
  6497. 4:11:33predetermined mitigation actions D draft
  6498. 4:11:37and Urgent communication to the supplier
  6499. 4:11:38demanded and explanation of proposed
  6500. 4:11:41rectification plan okay so what is going
  6501. 4:11:43to be your initial action which is
  6502. 4:11:44basically going to be what's your first
  6503. 4:11:46action and this question was tricky
  6504. 4:11:49because the answer here is actually c
  6505. 4:11:51not sure if you got this one so what
  6506. 4:11:54this is doing is this is testing your
  6507. 4:11:56ability to understand okay so we have an
  6508. 4:11:58issue now but before something becomes
  6509. 4:11:59an issue it should have been a risk so
  6510. 4:12:02when you were identifying your risk in
  6511. 4:12:05in the plan and process you should have
  6512. 4:12:06had a risk that says uh deliverable or
  6513. 4:12:10product not meeting quality from quality
  6514. 4:12:13requirements from
  6515. 4:12:15suppliers now the actions you take
  6516. 4:12:18should have been stored in the risk
  6517. 4:12:19register which is what this is so you
  6518. 4:12:21should have had this thing down as a
  6519. 4:12:23risk and if the risk does materialize
  6520. 4:12:25then you should have looked at the risk
  6521. 4:12:27register to tell you the mitigation
  6522. 4:12:29strategy for it that's why this is the
  6523. 4:12:31best answer
  6524. 4:12:33here uh an urgent team meeting although
  6525. 4:12:36I like a I like B uh first of all d is
  6526. 4:12:43never never do anything like demanding
  6527. 4:12:46an
  6528. 4:12:46explanation you never want to be
  6529. 4:12:48negative so I would eliminated that you
  6530. 4:12:50A and B are good actions but you want to
  6531. 4:12:52do c first then maybe do a and b so if
  6532. 4:12:58you got a and b keep in mind that c
  6533. 4:13:00should have just came first it's that
  6534. 4:13:02initial
  6535. 4:13:04action last question guys 120 after an
  6536. 4:13:09unscheduled discussion a project team
  6537. 4:13:11member advises the client about
  6538. 4:13:13potential project delays due to frequent
  6539. 4:13:16changes and requirements what proactive
  6540. 4:13:18steps should the project manager take to
  6541. 4:13:20manage project Communications more
  6542. 4:13:22effectively emphasize to the project
  6543. 4:13:24team the importance of routing all
  6544. 4:13:27Communications to the project manager to
  6545. 4:13:28ensure consistency and accuracy conduct
  6546. 4:13:31a workshop with the team to underscore
  6547. 4:13:33the significance of adherent to the
  6548. 4:13:35Project's communication guidelin
  6549. 4:13:38schedule a meeting with the client to
  6550. 4:13:39directly address their concern and
  6551. 4:13:41clarifying any misunderstanding about
  6552. 4:13:42the the project timeline require all
  6553. 4:13:45significant project updates and
  6554. 4:13:46communication convey through formal
  6555. 4:13:48channels to maintain documentation and
  6556. 4:13:50Clarity I thought this question was very
  6557. 4:13:53very difficult the answer here guys is
  6558. 4:13:55going to be
  6559. 4:13:57the um this is there's nothing here that
  6560. 4:14:00says it's an agile project unscheduled
  6561. 4:14:03discussions is probably not something
  6562. 4:14:05you want to do especially on those
  6563. 4:14:06traditional projects you want to make
  6564. 4:14:08sure that you have formal channels all
  6565. 4:14:11communication should be documented
  6566. 4:14:12should be maintain and should go through
  6567. 4:14:15the project communication channels
  6568. 4:14:17follow your communication management
  6569. 4:14:18plan in other words emphasize to the
  6570. 4:14:20team the importance about you shouldn't
  6571. 4:14:22not all communication be careful of this
  6572. 4:14:24word all and let me see that in a choice
  6573. 4:14:27it means everything goes through the PM
  6574. 4:14:29no a workshop you never underscore
  6575. 4:14:31anyone schedule a meeting with the
  6576. 4:14:33client to address well this is just this
  6577. 4:14:36one time you know what solution can you
  6578. 4:14:39take to ensure this never happens again
  6579. 4:14:40make indeed the best answer practice
  6580. 4:14:43question 121 during the execution phase
  6581. 4:14:46conflicts have Arisen between two team
  6582. 4:14:48members negatively impacting their work
  6583. 4:14:51output despite the project manager's
  6584. 4:14:53effort to encourage open communic open
  6585. 4:14:55communication to resolve the
  6586. 4:14:56disagreements there has been no
  6587. 4:14:58improvement by the way this is a common
  6588. 4:15:00thing in real life what action should
  6589. 4:15:02the PM consider as the next step to
  6590. 4:15:04resolve the conflict implement the
  6591. 4:15:06strategy to delegate separate tasks to
  6592. 4:15:08team members reduce in direct
  6593. 4:15:09interaction arrange for a third- party
  6594. 4:15:11mediator to facilitate a solution
  6595. 4:15:13between the two members have the team
  6596. 4:15:15members keep working on the issues to
  6597. 4:15:16solve the problem address the conflict
  6598. 4:15:18by making a decision that best serves a
  6599. 4:15:20project objectives even if it's
  6600. 4:15:22unilateral now this kind of question is
  6601. 4:15:25common on the exam and this is a tough
  6602. 4:15:27question because there's really two good
  6603. 4:15:28answers let's see what you got the best
  6604. 4:15:31answer here is going to be D now let's
  6605. 4:15:35go through this because there's really
  6606. 4:15:36two good answers let's eliminate the of
  6607. 4:15:38the guarantee where's that mouse let's
  6608. 4:15:41eliminate the guarantee back ones all
  6609. 4:15:44right my pad isn't working in this
  6610. 4:15:46video so let's take a look at this which
  6611. 4:15:50one here is the bad one well first of
  6612. 4:15:52all C get rid of C because in C in that
  6613. 4:15:57one you're doing nothing in other words
  6614. 4:15:59if the question is basically take no
  6615. 4:16:01action in other words let them figure it
  6616. 4:16:03out themselves it's never an it's never
  6617. 4:16:05an answer on the question says what not
  6618. 4:16:07to do as a project manager be proactive
  6619. 4:16:09help things just don't do nothing the
  6620. 4:16:12next one here you're going to elate just
  6621. 4:16:13Implement don't separate them separating
  6622. 4:16:16the task is kind of like pushing the
  6623. 4:16:17conflict aside this is it's it's a way
  6624. 4:16:21of like smoothing out the conflicts
  6625. 4:16:22where you're saying hey don't worry
  6626. 4:16:24about it in other words you're
  6627. 4:16:25separating them but you're not
  6628. 4:16:26addressing the conflict now comes two
  6629. 4:16:29that actually may solve the conflict
  6630. 4:16:31arrange for a third- party mediator or
  6631. 4:16:33address the conflict now the best answer
  6632. 4:16:37here when when there is a big Conflict
  6633. 4:16:39Management happening on the project that
  6634. 4:16:42team members cannot resolve sometimes
  6635. 4:16:44it's best for the project manager to
  6636. 4:16:47make a step and take the options that's
  6637. 4:16:49best for the project objectives you guys
  6638. 4:16:51got to remember something it's important
  6639. 4:16:53to solve problems to the benefit of the
  6640. 4:16:56project objectives not just to the
  6641. 4:16:58benefit of Bob or Mary it's all about
  6642. 4:17:01satisfying the objectives of the project
  6643. 4:17:03to meet stakeholder needs now the other
  6644. 4:17:05one here is just to get a third party to
  6645. 4:17:07resolve the third party mediator in this
  6646. 4:17:09one you are taking a proactive step to
  6647. 4:17:11solve the problem
  6648. 4:17:14122 A team member has been reporting no
  6649. 4:17:17progress on a critical task for several
  6650. 4:17:20days during the daily standup meetings
  6651. 4:17:22causing a potential delay in the project
  6652. 4:17:24timeline this task is critical for the
  6653. 4:17:26next phase of the project what should
  6654. 4:17:28the PM do to facilitate progress
  6655. 4:17:30organize a brainstorming session with
  6656. 4:17:32the team to find alternative solution to
  6657. 4:17:34complete the
  6658. 4:17:35task initiate a risk assessment meeting
  6659. 4:17:38to evaluate the impact of the delay
  6660. 4:17:40schedule a 101 meeting with a team
  6661. 4:17:42member to identify any obstacles
  6662. 4:17:44encourage a team member to provide
  6663. 4:17:46detailed reports okay I do want to point
  6664. 4:17:48out here that this is a problem with a
  6665. 4:17:50particular team member and if you have a
  6666. 4:17:51problem with a member the best thing
  6667. 4:17:53here to do is to meet with that person
  6668. 4:17:56it's not the entire team so you don't
  6669. 4:17:57need to involve the entire
  6670. 4:18:00team uh this thing here if it's one
  6671. 4:18:03person you don't want to uh you don't
  6672. 4:18:06want to bring the whole team in meet
  6673. 4:18:08with that person talk to that person now
  6674. 4:18:10D does say encourage the team member to
  6675. 4:18:12provide but before you do that what you
  6676. 4:18:15want to do is you want to schedule a
  6677. 4:18:16meeting and see what's going on why is
  6678. 4:18:19before you say hey go do this see what's
  6679. 4:18:21going on so you would want to do c
  6680. 4:18:25first
  6681. 4:18:27123 For an upcoming critical initiative
  6682. 4:18:30a project manager must engage a vendor
  6683. 4:18:32notorious for not meeting deadlines yet
  6684. 4:18:35uniquely skilled for the project
  6685. 4:18:37requirements what approach should the
  6686. 4:18:39project manager consider during project
  6687. 4:18:41planning initi iate a collaborative
  6688. 4:18:43effort with the vendor to streamline
  6689. 4:18:45workflow and reduce potential delays
  6690. 4:18:48develop a contingency plan that involves
  6691. 4:18:50parallel work streams with similar
  6692. 4:18:52expertise set penalty clause for delays
  6693. 4:18:54in the vendor agreement propose a
  6694. 4:18:56performance-based payment schedule to
  6695. 4:18:58motivate timely deliveries without extra
  6696. 4:19:01costs all right what should we do now
  6697. 4:19:04this one actually has a few good answers
  6698. 4:19:06there's a few of them that are bad but
  6699. 4:19:09there's a few good answers here best
  6700. 4:19:10answer here guys is going to be a that
  6701. 4:19:13is correct if you got it now one of them
  6702. 4:19:15that you want to you don't want to just
  6703. 4:19:16penalize people like that although
  6704. 4:19:18penalty Clauses are set in contracts you
  6705. 4:19:20don't want to just do that without
  6706. 4:19:22seeing unless there was no other option
  6707. 4:19:24so let's eliminate that develop a
  6708. 4:19:27contingency plan that involves parallel
  6709. 4:19:29work before you do that work with the
  6710. 4:19:31vendor all right you want to work with
  6711. 4:19:33the vendor to see why are they notorious
  6712. 4:19:35late how are they going to solve this
  6713. 4:19:37and what can we do to reduce potential
  6714. 4:19:38delay just don't come up with other work
  6715. 4:19:40that we can do although I like D I think
  6716. 4:19:44there was one one bad answer was C you
  6717. 4:19:47should have Tor that out two good
  6718. 4:19:48answers Was A and D so D was this
  6719. 4:19:51proposed performance payment this has
  6720. 4:19:53given them an incentive before you do
  6721. 4:19:56that though work with the vendor and
  6722. 4:19:58then maybe D would have been an option
  6723. 4:20:01so let's go a then
  6724. 4:20:04D
  6725. 4:20:06124 upon discovering a critical design
  6726. 4:20:08issue in a software develop software
  6727. 4:20:10project stakeholders are un certain
  6728. 4:20:13about proceeding with the with the
  6729. 4:20:15implementation is plan what is the most
  6730. 4:20:17effective step for project manager for
  6731. 4:20:19the project manager to take to address
  6732. 4:20:20the concerns recommend a comprehensive
  6733. 4:20:22overhaul of the design update the
  6734. 4:20:24project quality assurance procedures to
  6735. 4:20:27Inc compress this new discovery initiate
  6736. 4:20:30a thorough risk evaluation to ascend
  6737. 4:20:31certain to ascend the flaws potential
  6738. 4:20:35impacts on the project deliverables
  6739. 4:20:37propose the introduction of additional
  6740. 4:20:39project phases to rectify the the
  6741. 4:20:41identified design issue now I want to
  6742. 4:20:43point out this is something that's
  6743. 4:20:45common they're not certain they're not
  6744. 4:20:49uh with the implementation but what are
  6745. 4:20:50you going to do well they said they're
  6746. 4:20:52not certain before you do anything else
  6747. 4:20:54what we what we should do is go in and
  6748. 4:20:56do an assessment right thorough risk
  6749. 4:20:59evaluation about any potential flaws
  6750. 4:21:03that are out there you shouldn't
  6751. 4:21:05recommend the overhaul you shouldn't do
  6752. 4:21:07this as one of the first step you
  6753. 4:21:09shouldn't recommend a comprehensive
  6754. 4:21:10overhaul of the entire design if you're
  6755. 4:21:12really you don't know what's going on
  6756. 4:21:13there you shouldn't update anything
  6757. 4:21:16unless you understand what's Happening
  6758. 4:21:18Here notice they're uncertain generally
  6759. 4:21:21when something is uncertain remember
  6760. 4:21:22something that's uncertain is a risk
  6761. 4:21:24something that has happened is an issue
  6762. 4:21:27now this one here propose additional
  6763. 4:21:29phases before you do that evaluate for
  6764. 4:21:32the potential impacts on these potential
  6765. 4:21:35risks when it comes to managing risk
  6766. 4:21:37keep in mind before you determine an
  6767. 4:21:40action to a risk identify
  6768. 4:21:42that risk and assess its impact on the
  6769. 4:21:45project then come up with the solutions
  6770. 4:21:47remember those three steps identify the
  6771. 4:21:49risk assess the risk identify potential
  6772. 4:21:51mitigation
  6773. 4:21:54strategies 125 at the onset of a new
  6774. 4:21:57phase in a complex project after a
  6775. 4:22:00successful kickoff meeting at the
  6776. 4:22:01client's site a team member request a
  6777. 4:22:05transfer to another project due to
  6778. 4:22:07discomfort with a colleague's behavior
  6779. 4:22:09during their first face-to-face
  6780. 4:22:11interaction what are the most suitable
  6781. 4:22:13actions for the project manager to
  6782. 4:22:15consider now we got five options let's
  6783. 4:22:18choose two organize AE organize a
  6784. 4:22:21conflict resolution meeting to address
  6785. 4:22:24and potentially resolve the
  6786. 4:22:25interpersonal issues between the team
  6787. 4:22:27members propose an immediate team
  6788. 4:22:30restructuring to the human resources
  6789. 4:22:32department separate the conflict
  6790. 4:22:34emphasize the Project's commitment to a
  6791. 4:22:36respectful and inclusive workplace by
  6792. 4:22:39reiterating the diversity and inclusion
  6793. 4:22:42guidelines seek guidance from the pmo to
  6794. 4:22:44determine the best course of action
  6795. 4:22:46suggest a temporary team reassignment
  6796. 4:22:48for both individual to assess the impact
  6797. 4:22:50on the Project Dynamics all right what
  6798. 4:22:53did you get this one here if you
  6799. 4:22:56understand the mindset if you know how
  6800. 4:22:58to handle people that's best for the
  6801. 4:23:01project I don't think this question was
  6802. 4:23:02very difficult although it did had a few
  6803. 4:23:04good options best answer here choose two
  6804. 4:23:07was going to be a and C why because
  6805. 4:23:10first of all we want to come up with a
  6806. 4:23:11conflict ver solution meeting this one
  6807. 4:23:13you guys should have all got if there's
  6808. 4:23:14a problem between team members bring
  6809. 4:23:16them together and let's solve the
  6810. 4:23:17problem that's confronting the problem
  6811. 4:23:20you shouldn't restructure the thing just
  6812. 4:23:22right off the bat this might affect the
  6813. 4:23:25entire Team Dynamics never go to the pmo
  6814. 4:23:29unless it's something out of your hands
  6815. 4:23:30when it comes to team conflicts that is
  6816. 4:23:32something within the control of the PM
  6817. 4:23:33that you should solve don't just fire
  6818. 4:23:36people if you ever get a question about
  6819. 4:23:38firing someone it's never the answer all
  6820. 4:23:41right if you don't don't get rid of
  6821. 4:23:42people try to manage people try to
  6822. 4:23:45understand the problem and solve the
  6823. 4:23:47problem so what we want to do bring them
  6824. 4:23:49together we want to solve that problem
  6825. 4:23:52and then we want to make sure that we
  6826. 4:23:53build a project team that's inclusive
  6827. 4:23:56and diverse and follows good
  6828. 4:23:59guidelines all right guys hopefully you
  6829. 4:24:02guys are learning if you guys are
  6830. 4:24:03enjoying this video can you give the
  6831. 4:24:04video a like subscribe to the channel
  6832. 4:24:06for more content just like
  6833. 4:24:08this practice question
  6834. 4:24:10126 and I hybrid Environ in a hybrid
  6835. 4:24:13project environment stakeholders are
  6836. 4:24:15experiencing challenging in assessing
  6837. 4:24:18the most recent version of the project
  6838. 4:24:19schedule in the Project's online
  6839. 4:24:22document management
  6840. 4:24:24system what proactive measure should the
  6841. 4:24:26project manager take Implement an
  6842. 4:24:29iterative tutorial with the document
  6843. 4:24:31management system to guide stakeholders
  6844. 4:24:32through the navigation all right B
  6845. 4:24:35ensure all stakeholders are train on how
  6846. 4:24:36to use the document management system
  6847. 4:24:38and not a location of critical documents
  6848. 4:24:40okay develop a feedback mechanism within
  6849. 4:24:44the document management for stakeholders
  6850. 4:24:46or report accessibility issues all right
  6851. 4:24:47create a detail create a dedicated hline
  6852. 4:24:50for stakeholders to call in or receive
  6853. 4:24:51guidance and access in the
  6854. 4:24:53project documents now I want to point
  6855. 4:24:56out here that this question uses a very
  6856. 4:24:58important term it's not what do you do
  6857. 4:25:01next it's what proactive measure be
  6858. 4:25:04careful with these here you see when it
  6859. 4:25:06says what to do next it means you're
  6860. 4:25:07addressing the current conflict in this
  6861. 4:25:10question we're not addressing the
  6862. 4:25:11current conf conflict we are preventing
  6863. 4:25:14the current conflict so you don't want
  6864. 4:25:17to do something right now to solve the
  6865. 4:25:19problem you want to do something to
  6866. 4:25:21prevent the problem make sure the
  6867. 4:25:22problem never happened
  6868. 4:25:24now what can we do best answer here is
  6869. 4:25:27going to be B part of the exam content
  6870. 4:25:31outline for your current PMP exam talks
  6871. 4:25:33about training your team members that's
  6872. 4:25:35what this is in sure they're all trained
  6873. 4:25:37to use it if they're all trained notice
  6874. 4:25:39they're experiencing challenges if
  6875. 4:25:41they're all trained they should have a
  6876. 4:25:43good understanding of how to access that
  6877. 4:25:45system you don't want to just put an
  6878. 4:25:47interactive tutorial although I think A
  6879. 4:25:49and B were the two best answers um this
  6880. 4:25:51one here to guide this is through the
  6881. 4:25:53navigation process all right notice we
  6882. 4:25:57want to do the whole thing not just how
  6883. 4:25:59to use it that's going to include that
  6884. 4:26:01but how to locate the documents B is
  6885. 4:26:02just a better answer than
  6886. 4:26:05a a feedback mechanism nope let them
  6887. 4:26:07learn how to use it not just when you
  6888. 4:26:10see C and D is more like you guys figure
  6889. 4:26:13it out and they call us for help that's
  6890. 4:26:15what basically D is um and C let them
  6891. 4:26:19figure it out and then tell us what if
  6892. 4:26:22there's any accessibility problems let's
  6893. 4:26:24train them ahead of time
  6894. 4:26:27127 in the midst of a software
  6895. 4:26:30development project the project manager
  6896. 4:26:31notices that the software features are
  6897. 4:26:34not aligned with the client's
  6898. 4:26:35requirements this misalignment has
  6899. 4:26:37caused the project schedule to slip
  6900. 4:26:39moving the schedule performance index or
  6901. 4:26:42SPI from 1.05 to 85 and the CPI from 1.2
  6902. 4:26:47to .95 what is the most effective course
  6903. 4:26:49of action for the project manager to
  6904. 4:26:50ensure the project meets its deadline
  6905. 4:26:53and quality requirements in the future
  6906. 4:26:56Implement a code review process to
  6907. 4:26:57identify an address defects before they
  6908. 4:27:00progress in a testing phase all right
  6909. 4:27:02enance communication with stakeholders
  6910. 4:27:03to refine project requirements and
  6911. 4:27:06expectations Implement an automated
  6912. 4:27:07testing tool to increase
  6913. 4:27:10efficiency re revisit it and adjust the
  6914. 4:27:13project schedule to better align with
  6915. 4:27:15project realities and client needs all
  6916. 4:27:19right guys what is the best answer here
  6917. 4:27:21now the best answer here guys is going
  6918. 4:27:23to be you got to read it very carefully
  6919. 4:27:26you see in this question I don't think
  6920. 4:27:28this question was difficult if you
  6921. 4:27:30didn't read if you if you read it
  6922. 4:27:31carefully it wasn't if you didn't it was
  6923. 4:27:33difficult because it tells you that
  6924. 4:27:36you're slipping so you're right now
  6925. 4:27:38you're 15% behind schedule and you're
  6926. 4:27:41about 5% over budget that's what those
  6927. 4:27:43numbers are telling us but
  6928. 4:27:47realistically it's not aligning with the
  6929. 4:27:50client requirements that's what's
  6930. 4:27:52causing all of
  6931. 4:27:53this right so the question is how can we
  6932. 4:27:56solve the alignment don't solve the
  6933. 4:28:00scheduling and the cost problem that's
  6934. 4:28:02where it throws you off things like
  6935. 4:28:04implementing a code
  6936. 4:28:07review uh all the other options A and B
  6937. 4:28:11A and in particular
  6938. 4:28:13uh really is addressing that schedule
  6939. 4:28:16and budget problem to like reduce that
  6940. 4:28:19but the problem really isn't in the
  6941. 4:28:21schedule is it it's in the expectations
  6942. 4:28:24and D is revisit you just can't go and
  6943. 4:28:26adjust the scope the best thing to do is
  6944. 4:28:30have the client come in to help you
  6945. 4:28:32adjust that
  6946. 4:28:34scope
  6947. 4:28:36128 a project manager is overseeing the
  6948. 4:28:38development of a new Urban Park during
  6949. 4:28:41the project a dispute arises between the
  6950. 4:28:44landscape designer and the environmental
  6951. 4:28:46consultant over the choice of plant
  6952. 4:28:48species with each advocating for
  6953. 4:28:51different selections based on ecological
  6954. 4:28:54impact what is the most effective course
  6955. 4:28:56of action for the project manager for
  6956. 4:28:57the projects the Project's ecological
  6957. 4:29:00and design goals are both met or
  6958. 4:29:02ecological you can pronounce it that way
  6959. 4:29:04too organize a collaborative session
  6960. 4:29:06between both parties to integrate the
  6961. 4:29:08ecological concerns with
  6962. 4:29:10design aesthetic
  6963. 4:29:14solicit input from local community to
  6964. 4:29:16determine their preference and guide
  6965. 4:29:18decision Implement a trial period for
  6966. 4:29:20both selections to evaluate their
  6967. 4:29:22performance in the Parks environment
  6968. 4:29:24rely on external research finding to
  6969. 4:29:27make decisions based on the best
  6970. 4:29:29practices all right this one here you
  6971. 4:29:31got a problem between two parties best
  6972. 4:29:33answer here bring the parties together
  6973. 4:29:36and let them work together to see what
  6974. 4:29:38is the best option for the project you
  6975. 4:29:41don't want to just push them aside or
  6976. 4:29:45Implement do your own thing cuz that's
  6977. 4:29:47what C is this is like you're saying
  6978. 4:29:49okay let's do this in a trial so you're
  6979. 4:29:50basically hearing what they say you're
  6980. 4:29:52making a decision get input well the
  6981. 4:29:55problem is not with the local community
  6982. 4:29:56so far the problem is between these two
  6983. 4:29:58folks right between the environmental
  6984. 4:30:00consultant and the
  6985. 4:30:02designer uh rely on external research
  6986. 4:30:06finding before you do that what you want
  6987. 4:30:09to do it's a problem between two teams
  6988. 4:30:12members have the two team members work
  6989. 4:30:14it out basically part of that
  6990. 4:30:18mindset
  6991. 4:30:19129 in the process of deploying a new
  6992. 4:30:21customer relation management system the
  6993. 4:30:24project manager realizes that the
  6994. 4:30:26updates provided to the sales department
  6995. 4:30:29head are perceived as lacking specifics
  6996. 4:30:31on user adaptation rates and feedback
  6997. 4:30:35what should the project manager do to
  6998. 4:30:36ensure the sales department head
  6999. 4:30:37receives the necessary information to
  7000. 4:30:39gauge project
  7001. 4:30:40success tailor the project updates to
  7002. 4:30:44include detail metrics on user
  7003. 4:30:46adaptation rates and specific feedback
  7004. 4:30:49for users all right Implement an
  7005. 4:30:51interactive dashboard that allows a
  7006. 4:30:52sales department head to access
  7007. 4:30:54real-time data organize a bi-weekly
  7008. 4:30:56review sessions to verbally communicate
  7009. 4:30:59user adaptation metrics get a feedback
  7010. 4:31:02distribute a monthly comprehensive
  7011. 4:31:04report covering all aspects of the CRM
  7012. 4:31:06deployment including user adaptation
  7013. 4:31:08this this question really goes to the
  7014. 4:31:10Core
  7015. 4:31:12of project management it goes to the
  7016. 4:31:14core of studying project management and
  7017. 4:31:17knowing what you should be doing as a
  7018. 4:31:18project manager because if you study
  7019. 4:31:20well you're going to come to understand
  7020. 4:31:22that tailor the communication one of the
  7021. 4:31:26things is in that you're going to learn
  7022. 4:31:28in the course you've learned already is
  7023. 4:31:30there's this process called identify
  7024. 4:31:32stakeholders in that you're not just
  7025. 4:31:33knowing who your stakeholders are but
  7026. 4:31:35you're understanding what their
  7027. 4:31:36communication preference are is from the
  7028. 4:31:39output stakeholder register that you
  7029. 4:31:41create communication management plan and
  7030. 4:31:43your stakeholder engagement plan which
  7031. 4:31:45means meet with the stakeholder and
  7032. 4:31:47tailor the communication to the
  7033. 4:31:48stakeholder on a project not all
  7034. 4:31:51stakeholder receives the same
  7035. 4:31:53information in fact stakeholders
  7036. 4:31:55receives vastly different information
  7037. 4:31:57the report you give to your CEO isn't a
  7038. 4:31:59report you're going to be given to team
  7039. 4:32:00members right so let's tailor that
  7040. 4:32:03communication to your
  7041. 4:32:05stakeholders every option here you are
  7042. 4:32:08choosing what's best for them let them
  7043. 4:32:11choose what's best for
  7044. 4:32:13them last question a project manager is
  7045. 4:32:16leading the development of a new public
  7046. 4:32:17park in a densely populated urban area
  7047. 4:32:20Community leaders have written concerns
  7048. 4:32:22about the Project's approach to
  7049. 4:32:23maintaining the natural habitat and
  7050. 4:32:25promoting biodiversity what should you
  7051. 4:32:27do next organize your community leaders
  7052. 4:32:29to detail their concerns about the
  7053. 4:32:31projects and its impact okay
  7054. 4:32:32Distributing information brochure
  7055. 4:32:34detailing the environmental benefit host
  7056. 4:32:36a virtual presentation with experts
  7057. 4:32:39discussing the Project's impact on local
  7058. 4:32:41wildlife launch a community feedback
  7059. 4:32:43initiative to get a suggestion of
  7060. 4:32:45further Improvement okay what should you
  7061. 4:32:47do next well if you have stakeholders
  7062. 4:32:49that
  7063. 4:32:50have uh some kind of concern get more
  7064. 4:32:54detail about that concern so we can
  7065. 4:32:56address it we want to do this first
  7066. 4:32:58right before you first of all we're not
  7067. 4:33:01sure if the project they're saying it
  7068. 4:33:03doesn't meet it so you telling them more
  7069. 4:33:05about it this is not going to help them
  7070. 4:33:06host of virtual experts discussing the
  7071. 4:33:08impact on local
  7072. 4:33:10Wildlife although this was the other
  7073. 4:33:12good answer uh discussing the projects
  7074. 4:33:15on notice with experts well we want to
  7075. 4:33:18meet with these Community leaders all
  7076. 4:33:20right launch community feedback I like
  7077. 4:33:23this option on farther but you know what
  7078. 4:33:26before we do that let's get to the core
  7079. 4:33:28of the problem what don't they like all
  7080. 4:33:30right let's get into it
  7081. 4:33:33131 by way I'm going to be reading it
  7082. 4:33:35and answering it right away please pause
  7083. 4:33:37the video you read it you answer it and
  7084. 4:33:40then see how you do to counteract the
  7085. 4:33:43issue of certain team members
  7086. 4:33:45disproportionately influencing the
  7087. 4:33:46outcome of project scope discussions the
  7088. 4:33:48project band decided to implement a
  7089. 4:33:50nominal group technique session what is
  7090. 4:33:53the significant benefit of utilizing
  7091. 4:33:55this approach enables the sequential
  7092. 4:33:57voting process to prioritize task
  7093. 4:34:00encourages equal contributions from all
  7094. 4:34:02team member prevents any single
  7095. 4:34:03viewpoints from
  7096. 4:34:04dominating stimulates Creative Solutions
  7097. 4:34:07through group server groups group
  7098. 4:34:09Synergy this is a tough question because
  7099. 4:34:11there's two answers now if you know this
  7100. 4:34:13group technique here this nominal group
  7101. 4:34:14techniques definition there's two good
  7102. 4:34:17answers uh that you could have gone with
  7103. 4:34:20and those two good answers was either B
  7104. 4:34:22or C now first of all it's not just
  7105. 4:34:25about sequential voting and uh groups
  7106. 4:34:29Synergy or Creative
  7107. 4:34:31Solutions this type
  7108. 4:34:33of uh group technique or management
  7109. 4:34:36technique here what this is going to do
  7110. 4:34:37is just ensure that everyone gets their
  7111. 4:34:39Viewpoint across and not just a few
  7112. 4:34:42people dominated but it's really not
  7113. 4:34:44about just about equal it's not equal
  7114. 4:34:46contributions but it's everybody's
  7115. 4:34:48contributions some may have more than
  7116. 4:34:49others but it prevents one or two people
  7117. 4:34:51from dominating your meat and make C the
  7118. 4:34:54best answer question 132 Jing an
  7119. 4:34:57environmental impact review of an energy
  7120. 4:34:59project the project manager discovers
  7121. 4:35:01that the environmental plan does not
  7122. 4:35:03adequately address potential impacts on
  7123. 4:35:06local Wildlife what should the PM do
  7124. 4:35:09encourage the environmental specialist
  7125. 4:35:10to assess the environmental impact on
  7126. 4:35:13Wildlife protection suggest the team
  7127. 4:35:15create a new environmental plan continue
  7128. 4:35:17with the project that's plan adjust
  7129. 4:35:19based on regulatory feedback pause the
  7130. 4:35:21project to reassess all environment
  7131. 4:35:23environmental impact aspects what should
  7132. 4:35:25you do first well before you stop the
  7133. 4:35:28project before and that's going to be
  7134. 4:35:30the before you stop the project to
  7135. 4:35:32create a new
  7136. 4:35:33plan if you feel like there's something
  7137. 4:35:35going on meet with the right specialist
  7138. 4:35:37meet with the right people on the team
  7139. 4:35:40to see okay I I think I got a hunch
  7140. 4:35:42maybe this is not going to work or this
  7141. 4:35:44can potential impact don't stop
  7142. 4:35:47something that's potential don't stop
  7143. 4:35:48the project that's potential ensure that
  7144. 4:35:50your this potential is 100% correct or
  7145. 4:35:52you have good information before making
  7146. 4:35:55that decision so the first thing you
  7147. 4:35:56should do is make that assessment and
  7148. 4:35:59never do nothing just don't continue to
  7149. 4:36:00plan and wait for some kind of
  7150. 4:36:02regulatory feedback never do nothing
  7151. 4:36:05always assess the
  7152. 4:36:07situation 133 as new software
  7153. 4:36:10development project kicks off
  7154. 4:36:12when is it most appropriate for the
  7155. 4:36:14project manager to conduct the first
  7156. 4:36:16status first project status meeting
  7157. 4:36:19shortly after the project kickoff
  7158. 4:36:21meeting to align on early objectives
  7159. 4:36:23after the two after two development
  7160. 4:36:25Sprint is completed once the first
  7161. 4:36:27version of the project is ready as soon
  7162. 4:36:29as the team demonstrates progress and
  7163. 4:36:31collaboration all right this was a tough
  7164. 4:36:33question it really had two good answers
  7165. 4:36:35and that was either a or D now you don't
  7166. 4:36:39want to wait for Sprints to be done or
  7167. 4:36:42or a product an entire first version
  7168. 4:36:44this can take a long
  7169. 4:36:46time it really comes down should you do
  7170. 4:36:48one shortly after the kickoff meeting
  7171. 4:36:49well the kickoff meeting is about
  7172. 4:36:51alignment to the project objectives you
  7173. 4:36:53don't need it right after that but the
  7174. 4:36:56moment the team starts to demonstrate
  7175. 4:36:58progress the moment the team starts to
  7176. 4:36:59work on the product now you have
  7177. 4:37:01something to report on notice this is a
  7178. 4:37:03status
  7179. 4:37:04meeting if you haven't really done
  7180. 4:37:06anything on the project you really
  7181. 4:37:07cannot report status on it right so n it
  7182. 4:37:09just demonstrate progress on there the
  7183. 4:37:13best
  7184. 4:37:14answer 134 team members lack enthusiasm
  7185. 4:37:18for participating in essential project
  7186. 4:37:21planning sessions with many arriving
  7187. 4:37:23late or not contributing uhoh this is
  7188. 4:37:25not good what strategy should the
  7189. 4:37:27project manager employ first introduce a
  7190. 4:37:31structured agenda with allocated times
  7191. 4:37:33for each speaker to ensure Focus
  7192. 4:37:35discussion all right develop a rotating
  7193. 4:37:38Leadership Model for the planning
  7194. 4:37:39session allowing different members to
  7195. 4:37:40lead okay encourage team member to
  7196. 4:37:42contribute their insights and
  7197. 4:37:44suggestions on Improvement the uh the
  7198. 4:37:46plan and process all right transition to
  7199. 4:37:48a digital collaboration platform for
  7200. 4:37:51planning sessions to provide flexibility
  7201. 4:37:54and participation this one had quite a
  7202. 4:37:56few good answers by the way tough
  7203. 4:37:58question best answer here guys is going
  7204. 4:38:00to be did you get it C is correct now
  7205. 4:38:03why is C correct notice in this one
  7206. 4:38:08here you're telling them what to do
  7207. 4:38:11you're telling them what to do you're
  7208. 4:38:13telling them what to do or you're
  7209. 4:38:14designing the whole thing this one here
  7210. 4:38:17let's meet with the team and let's
  7211. 4:38:18encourage them to do something encourage
  7212. 4:38:21them to share encourage them to bring
  7213. 4:38:23their suggestions encourage them to be
  7214. 4:38:25part of the team just don't come out and
  7215. 4:38:27says okay we're going to do this we're
  7216. 4:38:28going to do this we're going to do this
  7217. 4:38:29that's not being a good servant leader
  7218. 4:38:30that's more of a dictator type
  7219. 4:38:33leadership 135 when the project manager
  7220. 4:38:36of a software development project finds
  7221. 4:38:38the specification provided by the client
  7222. 4:38:40are ambiguous was what is the most
  7223. 4:38:42appropriate initial
  7224. 4:38:43action initiate development based on the
  7225. 4:38:46existing specifications while waiting
  7226. 4:38:48forther clarification all right and from
  7227. 4:38:51the Project's key stakeholders about the
  7228. 4:38:54potential for delays and scope
  7229. 4:38:56clarification reach out to the client
  7230. 4:38:58for clarification and Confirmation
  7231. 4:39:00adjust the timeline to accommodate
  7232. 4:39:01potential changes in the project scope
  7233. 4:39:04best answer here guys is going to be did
  7234. 4:39:07you get it C is correct why is that well
  7235. 4:39:11you should never really execute a
  7236. 4:39:13project or you should not do a project
  7237. 4:39:15if you don't understand the scope if you
  7238. 4:39:18don't know the scope of the project
  7239. 4:39:19you're setting yourself up for almost
  7240. 4:39:21guaranteed failure so you don't want
  7241. 4:39:23that so the best answer here guys is
  7242. 4:39:25going to be reach out for confirmation
  7243. 4:39:28because this can lead to delays
  7244. 4:39:30obviously pushing the project over for
  7245. 4:39:32scope delays potential time and cost
  7246. 4:39:35delays
  7247. 4:39:37so initi the other good answer is
  7248. 4:39:40initiate development based on
  7249. 4:39:41nonexistent if you do this you're
  7250. 4:39:43guaranteed to fail because you don't
  7251. 4:39:44have the right scope
  7252. 4:39:46clarification are you telling them about
  7253. 4:39:49potential for delays this was the second
  7254. 4:39:51best
  7255. 4:39:53answer before you do that let's see if
  7256. 4:39:55we can get it first then we we may want
  7257. 4:39:58to do that uh you can't just adjust
  7258. 4:40:00timeline especially on these types of
  7259. 4:40:02remember on an agile project technically
  7260. 4:40:04you have a fixed timeline on a
  7261. 4:40:06traditional project you need approval
  7262. 4:40:07for
  7263. 4:40:08that before I get to this question if
  7264. 4:40:11you're in enjoying this video give the
  7265. 4:40:12video a like subscribe to the Channel
  7266. 4:40:15136 upon noticing the primary technology
  7267. 4:40:18provider for a digital transformation
  7268. 4:40:20project will not meet the deadline for
  7269. 4:40:22delivering Essential Software component
  7270. 4:40:24a RIS previously noted to the provider
  7271. 4:40:27previously noted due to the providers
  7272. 4:40:29historical performance issue what should
  7273. 4:40:30you do next negotiate with alternative
  7274. 4:40:33technology vendors to ensure timely
  7275. 4:40:35delivery and update the financial plan
  7276. 4:40:38to reflect any changes report the
  7277. 4:40:40situation and potential impact of the
  7278. 4:40:42project steering committee for immediate
  7279. 4:40:44guidance consult the risk register with
  7280. 4:40:47the team organize a strategy session
  7281. 4:40:51with the project team to identify
  7282. 4:40:52variable Immediate Solutions all right
  7283. 4:40:55best answer here now there's two good
  7284. 4:40:57answers all right those two good answers
  7285. 4:40:59was C and D now you know this was this
  7286. 4:41:03was a risk that was previously noted so
  7287. 4:41:05where would the risk be it'll be in the
  7288. 4:41:08risk register with the actual mitigation
  7289. 4:41:10Str
  7290. 4:41:11strategy you don't want to just
  7291. 4:41:13negotiate with the vendor the moment the
  7292. 4:41:15vendor did something
  7293. 4:41:17bad right you notice will not meet so
  7294. 4:41:21this is guaranteed to happen so this is
  7295. 4:41:22going to become an issue where do you
  7296. 4:41:24find a solution to risk that has
  7297. 4:41:25previously been documented in the risk
  7298. 4:41:28register making that the best one um
  7299. 4:41:32report the situation not to the stering
  7300. 4:41:34committee you don't take things to the
  7301. 4:41:36stering committee especially project
  7302. 4:41:37problems that is under the control of
  7303. 4:41:39the PM the stering committee is more for
  7304. 4:41:42like choosing or approving a change they
  7305. 4:41:45may choose the direction of a project
  7306. 4:41:46but project issues that's your thing to
  7307. 4:41:48fix organize a session with the team you
  7308. 4:41:51don't need to do this yet the reason is
  7309. 4:41:53because you've already done it with the
  7310. 4:41:54team it should have been in your risk
  7311. 4:41:57register
  7312. 4:41:59137 discovering that one team member
  7313. 4:42:02feels their efforts are undervalued
  7314. 4:42:04compared to others leading to a decline
  7315. 4:42:06in the participation and the overall
  7316. 4:42:07team spirit what should the PM do to
  7317. 4:42:10mend the situation uplift the team
  7318. 4:42:13schedule individual performance reviews
  7319. 4:42:15to provide personal feedback and growth
  7320. 4:42:17plans all right conduct a project
  7321. 4:42:19Milestone cabor celebration to
  7322. 4:42:22acknowledge all team members
  7323. 4:42:23contribution equally highlight the
  7324. 4:42:25import the Highlight the Project's
  7325. 4:42:28Collective achievements emphasizing the
  7326. 4:42:30success is attributed to the team as a
  7327. 4:42:32whole not individual implement the peer
  7328. 4:42:35recognition program where team members
  7329. 4:42:36can acknowledge each other's
  7330. 4:42:37contribution best answer here this one
  7331. 4:42:39has a bunch of good answers by the way I
  7332. 4:42:40thought this one was pretty difficult
  7333. 4:42:43the best answer here guys is going to be
  7334. 4:42:46C now I know I know it says
  7335. 4:42:49inid it's one person right one team
  7336. 4:42:52member but notice the real question is
  7337. 4:42:55not just fixing that team member right
  7338. 4:42:57the real question
  7339. 4:43:00is uplift the team what that's the main
  7340. 4:43:04point of this question it's like okay
  7341. 4:43:07what do you want to do how can we uplift
  7342. 4:43:08the team well bring the team together
  7343. 4:43:11show them what they have done tell them
  7344. 4:43:12the success is due to all of them you
  7345. 4:43:15notice this guy feels under value
  7346. 4:43:17compared to others let them know right
  7347. 4:43:19he's why does he feel like that he feels
  7348. 4:43:21like some have done more maybe it was
  7349. 4:43:23she and she felt like some has done more
  7350. 4:43:25something like that let them know the
  7351. 4:43:27success isn't just to one person it's to
  7352. 4:43:29the entire team individual performance
  7353. 4:43:31review this was the other good answer
  7354. 4:43:33you could have gone
  7355. 4:43:34with this is feedback and growth plan
  7356. 4:43:37but it's the entire team right it notes
  7357. 4:43:40the overall team period so address the
  7358. 4:43:42team not just one
  7359. 4:43:44person conduct a milestone celebration
  7360. 4:43:46we're not sure if Milestones here is
  7361. 4:43:49what's going to help them uh a milestone
  7362. 4:43:52celebration to acknowledge all team
  7363. 4:43:53members we not not every project not
  7364. 4:43:56everyone contributes equally all right
  7365. 4:43:59some may contribute more some may do
  7366. 4:44:00more work than others it's I'm not
  7367. 4:44:03saying others are not important but some
  7368. 4:44:04people just do more work because that's
  7369. 4:44:06required of them Implement a peer
  7370. 4:44:08recognition this is given over let the
  7371. 4:44:10team members technology each other and
  7372. 4:44:11leaving you out don't do that never let
  7373. 4:44:13people solve problems by themselves work
  7374. 4:44:15with them to do
  7375. 4:44:17it
  7376. 4:44:18138 faced with a constrainted budget and
  7377. 4:44:21a tight deadline for launching a new
  7378. 4:44:23product development project the project
  7379. 4:44:25manager discovers that the current
  7380. 4:44:27Financial Resources will not suffice to
  7381. 4:44:30cover all the project all the uh project
  7382. 4:44:33activities all the projected activities
  7383. 4:44:35what should the project manager do next
  7384. 4:44:38propose a phased project approach to
  7385. 4:44:40stay holders focusing on critical
  7386. 4:44:43development phase first document the
  7387. 4:44:45financial shortfall in the project
  7388. 4:44:46status report highligh and potential
  7389. 4:44:49impacts on the timeline have the pmo
  7390. 4:44:52identify priority areas and allocate
  7391. 4:44:54budget to critical stages engage with
  7392. 4:44:56the team to explore options for re
  7393. 4:44:58reallocating budget items to cover key
  7394. 4:45:00tasks all right what are we going to be
  7395. 4:45:03doing best answer here guys is D now
  7396. 4:45:06here's what you notice you're faced with
  7397. 4:45:09a constrained budget and a deadline you
  7398. 4:45:11got to get this product out the door you
  7399. 4:45:14realize you got enough money to cover
  7400. 4:45:16each
  7401. 4:45:17activity what are we going to do here
  7402. 4:45:21well propose a phased approach to
  7403. 4:45:24stakeholders okay focus on critical
  7404. 4:45:26development I like that but you notice
  7405. 4:45:28this is something you're doing on your
  7406. 4:45:29own you're not engaging the team here
  7407. 4:45:31you're you're proposing this this option
  7408. 4:45:34you should engage your team D is just a
  7409. 4:45:37better answer than a if the team says to
  7410. 4:45:39do a maybe it's a good option but you
  7411. 4:45:41shouldn't choose that by yourself
  7412. 4:45:43document and Stat highlighting the
  7413. 4:45:45importance the the impact on it be you
  7414. 4:45:48don't know those potential impact yet
  7415. 4:45:50work with the team on this so you want
  7416. 4:45:51to do d d can lead to a or b or both
  7417. 4:45:55have the pmo don't bring the pmo work
  7418. 4:45:58with the team first before go into your
  7419. 4:46:01pmo pmo can provide guidance and
  7420. 4:46:04approvals and whatnot but with something
  7421. 4:46:06like this let your team work with you
  7422. 4:46:07always work with your team to solve
  7423. 4:46:09issues as part of the mindset
  7424. 4:46:12139 during a significant landscape
  7425. 4:46:15redesigned project the project manager
  7426. 4:46:17finds a cut ined irrigation system that
  7427. 4:46:21could that could drastically reduce
  7428. 4:46:23water usage and maintain costs
  7429. 4:46:25introducing the system would necessitate
  7430. 4:46:27a modest increase in both project budget
  7431. 4:46:29and timeline what should the project
  7432. 4:46:31manager take what should the project
  7433. 4:46:32maner take first assess the Project's
  7434. 4:46:35existing budget and
  7435. 4:46:36timeline initiate a pilot pilot project
  7436. 4:46:39with the current scope drafted detailed
  7437. 4:46:41analysis comparing the long-term savings
  7438. 4:46:44and environmental benefit of the new
  7439. 4:46:46system against the initial increase in
  7440. 4:46:48Project cost and timeline for
  7441. 4:46:50stakeholder review showcase the
  7442. 4:46:51compatibility of the new integration
  7443. 4:46:53system with the project sustainability
  7444. 4:46:54goals and Report finding to stakeholders
  7445. 4:46:57best answer here guys what are we going
  7446. 4:46:59to do now it's going to
  7447. 4:47:02be notice what should you do basically
  7448. 4:47:06basically what should you do first I
  7449. 4:47:08like this one there's two good answers Z
  7450. 4:47:10or
  7451. 4:47:11all right just don't you just don't want
  7452. 4:47:12to showcase it you have to assess its
  7453. 4:47:14impact on the project you shouldn't push
  7454. 4:47:16it out either unless you know how it's
  7455. 4:47:18going to impact the project assess the
  7456. 4:47:20the Project's existing
  7457. 4:47:22budget uh and timeline but it's not just
  7458. 4:47:25those two right you want to do a
  7459. 4:47:27detailed analysis long-term savings and
  7460. 4:47:30benefits of the new system against the
  7461. 4:47:31initial increase in cost so basically
  7462. 4:47:35assess how this thing is going to affect
  7463. 4:47:36the scope how it's going to affect the
  7464. 4:47:38increase in cost and time this one here
  7465. 4:47:41is a and C is basically saying almost
  7466. 4:47:44the same thing but C is giving you a
  7467. 4:47:46more detailed explanation making c a
  7468. 4:47:48better answer than a I know writing
  7469. 4:47:52these hard questions sometimes is
  7470. 4:47:53difficult a is not a bad answer I'm
  7471. 4:47:55telling you guys a is not a bad answer
  7472. 4:47:56just C is a better answer because in
  7473. 4:47:59this one you're looking at long-term
  7474. 4:48:00saving you're looking at environmental
  7475. 4:48:01benefits you're looking at how it's
  7476. 4:48:03going to increase cost how it's going to
  7477. 4:48:04increase time and then you're giving it
  7478. 4:48:05to the stakehold of a review versus just
  7479. 4:48:07ay it's just the budget and the timeline
  7480. 4:48:09you're really not looking at the
  7481. 4:48:10Environmental benefit is just more than
  7482. 4:48:12that right See's
  7483. 4:48:15better 140 during a critical phase of a
  7484. 4:48:19healthcare software implementation
  7485. 4:48:20project the project manager realizes
  7486. 4:48:22that the project team is struggling to
  7487. 4:48:23maintain Pace with rapid iterations and
  7488. 4:48:26frequent changes in Project requirements
  7489. 4:48:29indicating a need for better cohesion
  7490. 4:48:31and flexibility what two practices
  7491. 4:48:33should the project man Implement to
  7492. 4:48:35improve team performance and project
  7493. 4:48:37fluidity fluidity now a Foster a culture
  7494. 4:48:41of continuous dialogue and collaboration
  7495. 4:48:43amongst team memb Embrace a mindset of
  7496. 4:48:45flexibility and willingness to adapt the
  7497. 4:48:47project shift Implement regular
  7498. 4:48:49retrospectives to identify an act on
  7499. 4:48:51Improvement opportunities organize a
  7500. 4:48:53training session on agile methodologies
  7501. 4:48:54to enhance team understand schedule
  7502. 4:48:57brief daily check-ins to keep the team
  7503. 4:48:59aligned and informed love this question
  7504. 4:49:02to me this was the hardest of the 10
  7505. 4:49:04questions in this set by the way they
  7506. 4:49:07all sound great all right so we want but
  7507. 4:49:10let's focus on the thing you want better
  7508. 4:49:12cohesion and flexibility so we need the
  7509. 4:49:15keyword is flexibility and bringing them
  7510. 4:49:17together what two option does that
  7511. 4:49:20that's the answer that's the main point
  7512. 4:49:22of the question I'm not saying you
  7513. 4:49:25shouldn't do you should do c you should
  7514. 4:49:27do D probably want to do uh e also but
  7515. 4:49:32if you're looking for flexibility then
  7516. 4:49:33choose the answer that includes that let
  7517. 4:49:35them build that mindset of flexibility
  7518. 4:49:38and in order to bring people together
  7519. 4:49:39it's all about collaboration
  7520. 4:49:41so if you read the question carefully
  7521. 4:49:43the answers to the to the question was
  7522. 4:49:46literally in the
  7523. 4:49:47question um these here while they were
  7524. 4:49:50good they didn't get to the core of the
  7525. 4:49:52question retrospectives are not bad but
  7526. 4:49:55retrospectives are more of how to
  7527. 4:49:57improve the next Sprint not necessarily
  7528. 4:49:58to embrace
  7529. 4:50:00flexibility the training session that
  7530. 4:50:02may Embrace flexibility but it might not
  7531. 4:50:05do cohesion that that well daily uh
  7532. 4:50:09check-ins we do that on a day today
  7533. 4:50:11basis in agile that's really to look for
  7534. 4:50:13more issues best answers is a and b
  7535. 4:50:16let's get into our questions here all
  7536. 4:50:18right where's Mike pen here we go as a
  7537. 4:50:20project manager in charge of a new
  7538. 4:50:21sustainability initiative you have
  7539. 4:50:23introduced a groundbreaking
  7540. 4:50:25environmental monitoring system however
  7541. 4:50:27you notice that your project team is
  7542. 4:50:29hesitant to adapt this technology
  7543. 4:50:31leading to delays in the implementation
  7544. 4:50:33phase what is the most effective measure
  7545. 4:50:35to ensure team adaptation and project
  7546. 4:50:39progress we Implement a reward system
  7547. 4:50:41for early adapters of the technology
  7548. 4:50:44arrange for a series of brief
  7549. 4:50:47informative sessions on how the
  7550. 4:50:48technology contributes to project
  7551. 4:50:50goal conduct an extensive workshop with
  7552. 4:50:53the team that examines the technology
  7553. 4:50:55enlist the help of environmental expert
  7554. 4:50:57to explain the importance of the
  7555. 4:50:58technology to the team's work okay so
  7556. 4:51:01what are we going to be doing here you
  7557. 4:51:03have a team that is hesitant as you can
  7558. 4:51:07see here to adapt to the technology but
  7559. 4:51:10why are they hant maybe because they
  7560. 4:51:11just don't understand the technology so
  7561. 4:51:15one of the things you you don't want to
  7562. 4:51:16do on this exam is force something on
  7563. 4:51:19someone don't push things on the team
  7564. 4:51:21let show people why something is
  7565. 4:51:24important so first of all you don't
  7566. 4:51:27need uh a doesn't really work on this
  7567. 4:51:29question because it's the team that is
  7568. 4:51:32hesitant and you just don't want to just
  7569. 4:51:34push it on them which is kind of what a
  7570. 4:51:35is doing it's like okay it's a reward if
  7571. 4:51:38you guys do it but they're probably
  7572. 4:51:39going to be still hesitant you want to
  7573. 4:51:41you want to take the choice to remove
  7574. 4:51:45this word like how to remove them being
  7575. 4:51:47hesitant on it arrange for a series of
  7576. 4:51:50brief informed on how the technology
  7577. 4:51:51contributes to the project goal was the
  7578. 4:51:53other good
  7579. 4:51:54answer enlist the help of the
  7580. 4:51:57environment no you don't want to just go
  7581. 4:51:58outside work with the team first so it
  7582. 4:52:01was two good answers it was either B or
  7583. 4:52:03C here I was going on it now you notice
  7584. 4:52:06this one is how it contributes to the
  7585. 4:52:08project goal the best thing here we can
  7586. 4:52:10can do is have the team work with the
  7587. 4:52:11technology have them dis Discover it
  7588. 4:52:14themselves versus we telling them hey
  7589. 4:52:16this is going to align with the goal so
  7590. 4:52:18those were the two options should we let
  7591. 4:52:20them Discover it let them examine it and
  7592. 4:52:22let them find out for themselves or
  7593. 4:52:24should we just tell it to them if you're
  7594. 4:52:26saying hey it's best let them find out
  7595. 4:52:28they're going to better understand the
  7596. 4:52:29technology that's why C is going to be
  7597. 4:52:33better than
  7598. 4:52:35b 142 launching a project uh launching a
  7599. 4:52:40project to introduce a new Health Care
  7600. 4:52:42System across multiple clinics the
  7601. 4:52:44project manager realizes that there are
  7602. 4:52:46discrepancies between the project scope
  7603. 4:52:48and the latest project data protection
  7604. 4:52:52regulation while the Project's
  7605. 4:52:54leadership team advises proceeding as
  7606. 4:52:57planned anticipating that these
  7607. 4:52:58discrepancies will be dissolved in due
  7608. 4:53:01time the project manager is concerned
  7609. 4:53:02about potential compliance issues this
  7610. 4:53:04is something that's probably very
  7611. 4:53:06realistic in real life by the way what
  7612. 4:53:08is the most appropriate initial step for
  7613. 4:53:10the project manager conduct an in-depth
  7614. 4:53:12analysis of the health care of the
  7615. 4:53:14Health Data protection regulations and
  7616. 4:53:16outline a detailed compliance plan okay
  7617. 4:53:18initiate a risk assessment session to
  7618. 4:53:20evaluate the impact of potential
  7619. 4:53:22non-compliance on the project arrange a
  7620. 4:53:26consultation with a legal expert in the
  7621. 4:53:28health health data protection uh to
  7622. 4:53:31advise on compliance strategies
  7623. 4:53:34redesigned the project scope to include
  7624. 4:53:36only those elements currently in
  7625. 4:53:38compliance with existing regulations so
  7626. 4:53:40there was one answer you could have just
  7627. 4:53:42throw right out and it really came down
  7628. 4:53:44to three good answers I thought this was
  7629. 4:53:46a very difficult question here's what I
  7630. 4:53:48got let's see what you guys got now
  7631. 4:53:52first of all Which choice could you have
  7632. 4:53:54thrown out well you just can't just go
  7633. 4:53:57and just redesign a scope like that on a
  7634. 4:53:59project first of all if it's a
  7635. 4:54:00traditional project keep in mind on
  7636. 4:54:02traditional projects you need that
  7637. 4:54:04change management system you need to do
  7638. 4:54:06a change request you need to have a
  7639. 4:54:07change control board or sponsor review
  7640. 4:54:10it and on an adob project if you want to
  7641. 4:54:11change a scope you got to have the
  7642. 4:54:13product owner added to the product
  7643. 4:54:14backlog so at no point is a project
  7644. 4:54:17manager should be ever redesign it or
  7645. 4:54:18changing a scope without either the
  7646. 4:54:20sponsor or the product owner now this
  7647. 4:54:24one says arrange a consultation with
  7648. 4:54:25legal experts so you don't want to go
  7649. 4:54:27outside yet it's saying the initial step
  7650. 4:54:30right so this is the key word it's like
  7651. 4:54:32what should you be doing first so you
  7652. 4:54:34don't want to go outside yet you never
  7653. 4:54:36want to just go outside unless there's
  7654. 4:54:38really no other option try to do the
  7655. 4:54:40internally on the project now it came
  7656. 4:54:43down to two all right I really thought
  7657. 4:54:45is it going to be risk assessment
  7658. 4:54:47session to evaluate the impact or an
  7659. 4:54:50in-depth analysis of the data and come
  7660. 4:54:52up with a compliance plan well before we
  7661. 4:54:55do before you come up and you start
  7662. 4:54:58doing all your risk assessment you have
  7663. 4:54:59to conduct an in-depth plan what exactly
  7664. 4:55:02is this risk compliance so what you
  7665. 4:55:05should be doing is an in-depth analysis
  7666. 4:55:08of this particular regulation
  7667. 4:55:11that makes a better than b by the way I
  7668. 4:55:13want to point out something that by
  7669. 4:55:14doing a you're going to be doing B also
  7670. 4:55:16because when you do an in-depth analysis
  7671. 4:55:18and coming up with your compliance plan
  7672. 4:55:20you should be doing the risk assessment
  7673. 4:55:21in it making a a better
  7674. 4:55:25answer 143 at the beginning of a green
  7675. 4:55:28buildin project the project manager is
  7676. 4:55:31tasked by the lead architect to engage a
  7677. 4:55:34key supplier known for their sustainable
  7678. 4:55:36materials however the supplier is
  7679. 4:55:39reluctant to collaborate believing the
  7680. 4:55:41Project's environmental goals do not
  7681. 4:55:42align with their business model what
  7682. 4:55:45action should the project manager take
  7683. 4:55:46to encourage supplier participation
  7684. 4:55:49propose a trial period for the supplier
  7685. 4:55:50to assess the Project's commitment to
  7686. 4:55:54sustainability refer the matter to the
  7687. 4:55:56lead architect suggesting the need for
  7688. 4:55:58higher higher level negotiations
  7689. 4:56:02initiated a campaign to highlight the
  7690. 4:56:03project sustainability achievement and
  7691. 4:56:05future plans conduct a detailed
  7692. 4:56:08presentation for the supply outline and
  7693. 4:56:09the environment at impact and mutual
  7694. 4:56:11benefits okay this one here pretty
  7695. 4:56:14difficult really came down to two good
  7696. 4:56:16answers what answer did you get because
  7697. 4:56:17I got D to me is the best answer here
  7698. 4:56:21here's why now you notice this person
  7699. 4:56:24like the first question is
  7700. 4:56:26reluctant the other one in the first
  7701. 4:56:28question we had in this 141 they were
  7702. 4:56:31hesitant in this one this one they
  7703. 4:56:33they're reluctant they're like we don't
  7704. 4:56:35know why we should do this and you
  7705. 4:56:37notice it does not align with with their
  7706. 4:56:39business bus model so you have to help
  7707. 4:56:41prove that so the question is saying hey
  7708. 4:56:45this guy doesn't want to do it because
  7709. 4:56:47he doesn't feel that it aligns with
  7710. 4:56:48their business model so now you have to
  7711. 4:56:50go and prove that to them a trial period
  7712. 4:56:52is not going to prove that it aligns to
  7713. 4:56:55their business model this is them doing
  7714. 4:56:56it this is them doing it but they're not
  7715. 4:56:59really sure if they're align or not you
  7716. 4:57:01don't want to never give away your work
  7717. 4:57:02if this if there's a choice on your exam
  7718. 4:57:05that says give the work to someone it's
  7719. 4:57:07probably not the answer
  7720. 4:57:10a campaign to highlight the project
  7721. 4:57:11sustainability achievement well you know
  7722. 4:57:13what this is going to be their
  7723. 4:57:15achievement and future plans it doesn't
  7724. 4:57:17C does not really have anything to do
  7725. 4:57:20with the vendor by the way but D does
  7726. 4:57:22and D you're going to go to them you're
  7727. 4:57:23going to show them what's why this
  7728. 4:57:25particular thing is useful for the
  7729. 4:57:27project and the benefits that they're
  7730. 4:57:29going to get out of it makeing D the
  7731. 4:57:32best
  7732. 4:57:33answer 144 following a directive to
  7733. 4:57:37enhance operation efficiency within a
  7734. 4:57:41within a multinational corporation the
  7735. 4:57:43executive team has requested an update
  7736. 4:57:45on the progress and remain in TAS for
  7737. 4:57:48all ongoing ad job projects what
  7738. 4:57:51methodology should uh what methodology
  7739. 4:57:53should the project manager employ to
  7740. 4:57:55accurately convey this information time
  7741. 4:57:57tracking analysis resource allocation
  7742. 4:57:59report progress Milestone review or
  7743. 4:58:01Sprint burnup chart all right this one
  7744. 4:58:03here was actually pretty easy you notice
  7745. 4:58:06they want to see uh how much work is
  7746. 4:58:08left on remaining task and this uh the
  7747. 4:58:11burn
  7748. 4:58:12up chart does that now I do want to
  7749. 4:58:15point out that it the burn up chart is
  7750. 4:58:19use an agile because it represents the
  7751. 4:58:21work completed versus the work remaining
  7752. 4:58:24done so I want you guys to before you
  7753. 4:58:27walk into your exam room you're probably
  7754. 4:58:30going to get a questions on burn up and
  7755. 4:58:32burn down chart make sure you know the
  7756. 4:58:33difference we do cover those in the
  7757. 4:58:35class and you notice the moment we
  7758. 4:58:38saw that they were looking on agile
  7759. 4:58:40projects you should have known right
  7760. 4:58:42away burn up and burn down charts are
  7761. 4:58:44exclusive there time tracking analysis
  7762. 4:58:47is not something we use uh these are the
  7763. 4:58:49things are not something we use on adob
  7764. 4:58:51projects they're more likely used on
  7765. 4:58:53traditional
  7766. 4:58:55projects 145 during a complex software
  7767. 4:58:59development project the project manager
  7768. 4:59:00notes that several Technical and
  7769. 4:59:03operational challenges are arising due
  7770. 4:59:05to conflicting requirements from various
  7771. 4:59:07stakeholders what is the most efficient
  7772. 4:59:09strategy for the manager to facilitate
  7773. 4:59:11project advancement initiate a
  7774. 4:59:13stakeholder analysis to better
  7775. 4:59:15understand conflict interests and
  7776. 4:59:16address them systematically all
  7777. 4:59:18right assign a team assign team leaders
  7778. 4:59:21to negotiate solutions for each
  7779. 4:59:23conflicting re requirement directly with
  7780. 4:59:24the stakeholders all right update the
  7781. 4:59:26project communication plan to include
  7782. 4:59:28more frequent uh stakeholder engagement
  7783. 4:59:31sessions okay directly negotiate and
  7784. 4:59:34reconcile the conflicting requirements
  7785. 4:59:36to Streamlight project execution this is
  7786. 4:59:39a trick question don't go with the
  7787. 4:59:42answer you think you're going to go with
  7788. 4:59:44I'm telling you guys this is a trick
  7789. 4:59:46question
  7790. 4:59:48now these types of questions you have to
  7791. 4:59:50read them very carefully because if a
  7792. 4:59:52lot of you guys said a it's not right
  7793. 4:59:56here's why you see the question
  7794. 4:59:59specifically asked to fix this it's an
  7795. 5:00:03effective strategy to facilitate project
  7796. 5:00:06advancement so what strategy here is
  7797. 5:00:10going to allow the project to proceed
  7798. 5:00:13you see a is not a good answer because
  7799. 5:00:15in this one you're just trying to
  7800. 5:00:17understand their conflicts so in this
  7801. 5:00:21one you're understanding their conflicts
  7802. 5:00:23and you're trying to address them the
  7803. 5:00:24best way to address them is to negotiate
  7804. 5:00:28with them negotiate and reconcile the
  7805. 5:00:31actual differences between the project
  7806. 5:00:34making a a better answer than making d a
  7807. 5:00:36better answer than a never give away
  7808. 5:00:39anything never say okay hey you guys go
  7809. 5:00:42out and you guys do this update the
  7810. 5:00:44communication plan to include more
  7811. 5:00:46frequent stakeholder engagement it's not
  7812. 5:00:47something you can do without a change
  7813. 5:00:48request now I want to point out
  7814. 5:00:52something to you guys if this question
  7815. 5:00:53it says what should you do first what
  7816. 5:00:55should you do next then a would have
  7817. 5:00:57been a better answer than D but the
  7818. 5:00:59question isn't asking for what to do
  7819. 5:01:01first the question is literally asking
  7820. 5:01:02to fix the problem so I want you guys to
  7821. 5:01:04point out something if you're looking if
  7822. 5:01:06a question is like how do you fix this
  7823. 5:01:09you can't fix things things by examining
  7824. 5:01:10things if the question is what should
  7825. 5:01:12you do first well never fix things first
  7826. 5:01:16all right so you got to read it
  7827. 5:01:18carefully all right so let's let's let
  7828. 5:01:19let me say that again if a question says
  7829. 5:01:22what what's the next step what should
  7830. 5:01:23you do first then don't fix it right
  7831. 5:01:26away examine the situation analyze
  7832. 5:01:29what's happening around you read some
  7833. 5:01:31documents review your plans meet with
  7834. 5:01:34team members ask them what's going on
  7835. 5:01:37but if they're asking hey what which
  7836. 5:01:39which one of these choices will fix this
  7837. 5:01:41problem eliminate this problem well you
  7838. 5:01:44asking around you checking plans you
  7839. 5:01:46doing this is not going to fix or
  7840. 5:01:47eliminate the problem then you got to
  7841. 5:01:49come up with an actual concrete solution
  7842. 5:01:51to address the actual
  7843. 5:01:55problem all right 146 during the
  7844. 5:01:58integration phase of an international IT
  7845. 5:02:00project the project manager noticed
  7846. 5:02:02frequent miscommunications between the
  7847. 5:02:04on-site and offshore teams primly due to
  7848. 5:02:08cultural misunderstanding and language
  7849. 5:02:11nuisances the project manager has
  7850. 5:02:13individually spoken with members from
  7851. 5:02:15both teams and confirmed that these
  7852. 5:02:17differences are hindering project
  7853. 5:02:19progress all right this may be real life
  7854. 5:02:21for if you work on many uh International
  7855. 5:02:23projects what should the project manager
  7856. 5:02:25do to enhance understanding cooperation
  7857. 5:02:27between the teams Implement a technology
  7858. 5:02:30I'm sorry Implement a mandatory language
  7859. 5:02:33proficiency course for all team members
  7860. 5:02:35okay facilitate a workshop that allow
  7861. 5:02:37both teams to share the cultural norms
  7862. 5:02:39and communication preferences assign a
  7863. 5:02:41bilingual team liaison to translate
  7864. 5:02:43immediate communication require all
  7865. 5:02:45project communication to be
  7866. 5:02:47conducted in written form to reduce
  7867. 5:02:50misunderstanding best answer here guys
  7868. 5:02:52is of course B yeah this one wasn't too
  7869. 5:02:55difficult so if you have team members
  7870. 5:02:57that can't get along the best thing to
  7871. 5:02:59do we are we learn in the in our exam is
  7872. 5:03:02we have to make sure we train them
  7873. 5:03:04correctly uh we don't want anything
  7874. 5:03:06that's just mandatory we can't I don't
  7875. 5:03:07think people are going to learn an
  7876. 5:03:09entire language that
  7877. 5:03:11quickly require all Comm to be done in a
  7878. 5:03:14written sometimes best it's hard to do
  7879. 5:03:17written Communications if they're
  7880. 5:03:18actually communicating very
  7881. 5:03:20frequently uh you don't want to just
  7882. 5:03:23pass it on and if the liaison is not
  7883. 5:03:26there to translate might be a problem
  7884. 5:03:28the best thing here is to have them work
  7885. 5:03:30together as a project manager facilitate
  7886. 5:03:32facilitate facilitate bring people
  7887. 5:03:34together let them work together let them
  7888. 5:03:36discuss what's going on so the problem
  7889. 5:03:38is actually solved making B the best
  7890. 5:03:41answer 147 as part of a companywide
  7891. 5:03:45project to enhance it security the
  7892. 5:03:47project manager schedule a series of
  7893. 5:03:48educational webinars for employees a
  7894. 5:03:51leader from a department not yet covered
  7895. 5:03:53in the initial roll out expresses
  7896. 5:03:55interest in attending one of these early
  7897. 5:03:57sessions what should the project manager
  7898. 5:03:59do to best support the initiative's
  7899. 5:04:01goals and engage interested stakeholders
  7900. 5:04:04all right limited webinar attendance
  7901. 5:04:06only those Department schedule for early
  7902. 5:04:07phase roll up okay so suggest the
  7903. 5:04:10webinar leader wait for the tailored
  7904. 5:04:11sessions uh tailored session specific to
  7905. 5:04:14the department encourage Department to
  7906. 5:04:16join the upcoming we to get to get an
  7907. 5:04:18early insight and prepare their team
  7908. 5:04:20provide recorded versions of the webinar
  7909. 5:04:22exclusively to those in the initial roll
  7910. 5:04:24out phase all right now this question
  7911. 5:04:26plays on the concept of engaging your
  7912. 5:04:29stakeholders engage your stakeholders
  7913. 5:04:31how if you remember I say this in the
  7914. 5:04:32course often and early always remember
  7915. 5:04:35that often and early or I should say
  7916. 5:04:37early and often making see the best
  7917. 5:04:41answer here's why
  7918. 5:04:44so notice that this is a companywide
  7919. 5:04:47project and if you're scheduling a
  7920. 5:04:49series of educational webinars for
  7921. 5:04:51employees then who should you invite
  7922. 5:04:54right if you have a project that is
  7923. 5:04:56going to be affecting the entire company
  7924. 5:04:58means everybody's a stakeholder in this
  7925. 5:05:00project and you want to do a series of
  7926. 5:05:02educational thing about this then who
  7927. 5:05:04technically should you invite if you
  7928. 5:05:06said everyone because they're all your
  7929. 5:05:07stakeholders because you want to engage
  7930. 5:05:09all your Stak code is correct that's why
  7931. 5:05:10C is the answer you don't want to limit
  7932. 5:05:13it right off the bat you don't want to
  7933. 5:05:15tell them to wait uh previously recorded
  7934. 5:05:18versions while this is good maybe you
  7935. 5:05:21want to encourage them to come and if
  7936. 5:05:22they could great if not maybe then you
  7937. 5:05:24can do the making see the best answer
  7938. 5:05:27148 a project manager's tasked with
  7939. 5:05:30integrating Advanced artificial
  7940. 5:05:31intelligent features into an existent
  7941. 5:05:33software product however the current
  7942. 5:05:35project team lacks the AI expertise
  7943. 5:05:37required for successful implementation
  7944. 5:05:39what should the project manager do to
  7945. 5:05:40ensure the project success despite the
  7946. 5:05:42team's current skills
  7947. 5:05:45limitation initiated Target AI training
  7948. 5:05:48programs to the team okay partner with a
  7949. 5:05:50partner with an AI technology firm to
  7950. 5:05:52provide expert consultation facilitate
  7951. 5:05:54Workshop that in that innovates problem
  7952. 5:05:57solving
  7953. 5:05:57techniques deploy automated tools to
  7954. 5:06:01assist the team with AI related tasks
  7955. 5:06:03okay best answer here is going to be a
  7956. 5:06:07is correct now there were two good
  7957. 5:06:09answers here all right first of all you
  7958. 5:06:11don't want to just give away to work yet
  7959. 5:06:13let the team work and if they cannot
  7960. 5:06:15figure it out or we cannot get the right
  7961. 5:06:17training maybe then you can do B the
  7962. 5:06:20other one here you could have uh done
  7963. 5:06:23was d uh got rid of was D because you
  7964. 5:06:25don't want to just deploy to they don't
  7965. 5:06:27understand the technology you put in
  7966. 5:06:29more automation toolate just complex the
  7967. 5:06:30process more now you came down should
  7968. 5:06:33you facilitate workshops that encourages
  7969. 5:06:36problem solving techniques or should you
  7970. 5:06:38get in the right training now it it
  7971. 5:06:40tells you in the question they lack the
  7972. 5:06:44expertise so if they lack the expertise
  7973. 5:06:46them doing promise all is not going to
  7974. 5:06:48help them because they don't know how to
  7975. 5:06:49solve it in the first place the best
  7976. 5:06:51thing you can do when your team lacks a
  7977. 5:06:54particular knowledge that they don't
  7978. 5:06:55have the best thing to do the best thing
  7979. 5:06:57the project manager should do is get
  7980. 5:06:59them that
  7981. 5:07:02training by the way guys if you guys are
  7982. 5:07:04enjoying this can you give the video a
  7983. 5:07:06like click subscribe to the channel we
  7984. 5:07:08do spend a lot lot of time putting these
  7985. 5:07:10questions together and recording these
  7986. 5:07:12videos would be greatly
  7987. 5:07:13appreciated let's get back to it 149 a
  7988. 5:07:17project manager has coordinated a new
  7989. 5:07:18environmental research project involving
  7990. 5:07:20experts from various uh continents the
  7991. 5:07:24geographic geographical spread of the
  7992. 5:07:26team makes regular face-to-face uh
  7993. 5:07:28interactions impossible what should the
  7994. 5:07:30project manager do to ensure seamless
  7995. 5:07:32communication and collaboration across
  7996. 5:07:33the team now if you guys know me in the
  7997. 5:07:35class I always tell you guys face Toof
  7998. 5:07:37face is the best form of communication
  7999. 5:07:39adapt an Advan uh project management and
  8000. 5:07:42communication software okay set up
  8001. 5:07:45rotational schedule for team to adjust
  8002. 5:07:46their avability for occasional
  8003. 5:07:48synchronous meetings uh by the way
  8004. 5:07:51synchronous and asynchronous synchronous
  8005. 5:07:53communication is basically me talking to
  8006. 5:07:56you like on a zoom call or on a phone
  8007. 5:07:58call it's live it's real time
  8008. 5:08:00asynchronous is like what I'm doing here
  8009. 5:08:02this is asynchronous uh it's not real
  8010. 5:08:05time it's not
  8011. 5:08:06live create a cultural Exchange program
  8012. 5:08:09within team to facilitate better
  8013. 5:08:10understanding establish a system of
  8014. 5:08:12regular email updates and reports to
  8015. 5:08:14keep all team members informed best
  8016. 5:08:16answer here guys notice that we want the
  8017. 5:08:20question particularly points out this
  8018. 5:08:22thing of face-to-face communication and
  8019. 5:08:24if you can't do it if you can't do
  8020. 5:08:25face-to-face communication because of a
  8021. 5:08:28massive spread continent spread in
  8022. 5:08:30particular the best thing here to do is
  8023. 5:08:31to get the right technology to do it as
  8024. 5:08:34we have many options like Zoom or go to
  8025. 5:08:37meeting uh this here will solve the
  8026. 5:08:39problem because now they can have
  8027. 5:08:41seamless communication and consistent
  8028. 5:08:43not occasional communication we don't
  8029. 5:08:46need an exchange program as this may
  8030. 5:08:48take
  8031. 5:08:49time and you know what's better than
  8032. 5:08:52email this is asynchronous communication
  8033. 5:08:55synchronous communication is much better
  8034. 5:08:58all right so if you have good
  8035. 5:09:00communication software like Zoom that's
  8036. 5:09:02considered synchronous versus email is
  8037. 5:09:04asynchronous
  8038. 5:09:06communication
  8039. 5:09:07150 as the project manager for an
  8040. 5:09:10Innovative smart home device project you
  8041. 5:09:11receive a requests from the stakeholder
  8042. 5:09:14to incorporate Advanced AI capabilities
  8043. 5:09:18into capabilities to improve design
  8044. 5:09:21usability the addition is expected to
  8045. 5:09:24significantly enhance the product but
  8046. 5:09:25comes late in the cycle with a
  8047. 5:09:27challenging deadline all right so this
  8048. 5:09:28might delay the project here guys what
  8049. 5:09:30should the project manager do
  8050. 5:09:32next conduct an impact analysis to
  8051. 5:09:34determine how the integration of the
  8052. 5:09:36advanced AI capabilities affects the
  8053. 5:09:38timeline of budget okay suggest focusing
  8054. 5:09:41on launching the current version without
  8055. 5:09:42Ai and adding it as a feature in the
  8056. 5:09:45next product release okay uh increase
  8057. 5:09:48the team's working hours to meet the
  8058. 5:09:50demand of inte of integrating the new
  8059. 5:09:52feature within the timeline negotiate
  8060. 5:09:54for additional resource specifically
  8061. 5:09:55focus on developing and integrating the
  8062. 5:09:58function now I want to point out that
  8063. 5:10:00you notice this particular question says
  8064. 5:10:01what should we do next and if you
  8065. 5:10:03remember what I said earlier what should
  8066. 5:10:05you do next is going to be to analyze
  8067. 5:10:08something don't fix the prod problem yet
  8068. 5:10:09analyze something how is this going to
  8069. 5:10:11affect the project not just the timeline
  8070. 5:10:14but I want to point out that when you
  8071. 5:10:16affect time you're probably going to
  8072. 5:10:17affect cost making a the best answer you
  8073. 5:10:20shouldn't just add it
  8074. 5:10:22in uh or just reject it so B is like hey
  8075. 5:10:27just rejected we'll do that later never
  8076. 5:10:29do that to a customer never overwork
  8077. 5:10:32your team negotiate for additional
  8078. 5:10:35resources before you do that I would say
  8079. 5:10:38you would do a then B
  8080. 5:10:40um if the question was like Hey how do
  8081. 5:10:43you fix this what are we going to do to
  8082. 5:10:44fix this maybe then you might need more
  8083. 5:10:45resources to get it done but in this one
  8084. 5:10:47here they're asking what should you do
  8085. 5:10:49next in other words assess the situation
  8086. 5:10:51all right question
  8087. 5:10:53151 a project manager is leading the
  8088. 5:10:55development of a new Public Library
  8089. 5:10:57during the planning phase it come it
  8090. 5:10:59comes to light that the library's
  8091. 5:11:01proposed location is a popular site for
  8092. 5:11:03an annual book fair which was not
  8093. 5:11:06considered in the initial consultations
  8094. 5:11:08the oversight Rises concern about the
  8095. 5:11:10fear's future on libraries uh community
  8096. 5:11:13relations what should the project
  8097. 5:11:15manager do to ensure the project aligns
  8098. 5:11:17with Community interest and maintains
  8099. 5:11:19positive relations a redesign the
  8100. 5:11:22library layout to include a dedicated
  8101. 5:11:24space for the annual book fear without
  8102. 5:11:26additional speaker input organize a
  8103. 5:11:29discussion for with book organizers and
  8104. 5:11:32community members to explore how the
  8105. 5:11:34library project can accommodate the fear
  8106. 5:11:37prepare a risk management plan
  8107. 5:11:38specifically for mitigating the backlash
  8108. 5:11:41from the book fear enthusiasts suggest
  8109. 5:11:44relocating the book fear to a less
  8110. 5:11:45Central but still accessible location
  8111. 5:11:49without consulting the event organizers
  8112. 5:11:52this question plays the game of engaging
  8113. 5:11:56stakeholders a project manager should
  8114. 5:11:59not be modifying or editing the scope
  8115. 5:12:02without consulting your stakeholders and
  8116. 5:12:04that makes it one good answer which is B
  8117. 5:12:07here's why you see in a you're you as
  8118. 5:12:11the project manager you're just
  8119. 5:12:13redesigning the space just like that
  8120. 5:12:15without their input so is D you're just
  8121. 5:12:18moving things you're doing things
  8122. 5:12:19without cons Consulting the event
  8123. 5:12:22organizers no what you want to do is you
  8124. 5:12:24want to bring your stakeholders together
  8125. 5:12:26so they can work together and come up
  8126. 5:12:28with a scope or a solution that best
  8127. 5:12:30matches their requirements prepare risk
  8128. 5:12:34management plan in this one you're doing
  8129. 5:12:35nothing in this one you're basically
  8130. 5:12:37proceeding and you're saying well if
  8131. 5:12:38there's a backlash will deal with it at
  8132. 5:12:40some point so in this one here you're
  8133. 5:12:41taking no actions not the best answer
  8134. 5:12:44our best answer here is going to be
  8135. 5:12:47B 152 as the project manager for a
  8136. 5:12:51software development project you're
  8137. 5:12:53informed that due to budget relocations
  8138. 5:12:56reallocations several developers will be
  8139. 5:12:58reassigned to other projects create an
  8140. 5:13:01unease amount to your team about project
  8141. 5:13:03timelines and their roles what should
  8142. 5:13:05the project manager do
  8143. 5:13:07first Implement a Revis project schedule
  8144. 5:13:10that accelerates timelines to
  8145. 5:13:12demonstrate the project can proceed
  8146. 5:13:14without additional
  8147. 5:13:16resources facilitate a
  8148. 5:13:18discussion facilitate a session to
  8149. 5:13:21discuss the reassignments emphasizing
  8150. 5:13:23the Strategic vision and how team
  8151. 5:13:25contributions are critical to both the
  8152. 5:13:26project and broader company
  8153. 5:13:29objectives introduce a mentorship
  8154. 5:13:31program parent remaining team members
  8155. 5:13:33with experience mentors to bolster
  8156. 5:13:36confidence and set skills set and skill
  8157. 5:13:39sets in h in light of reduced staff and
  8158. 5:13:42levels sorry guys a lot of big words
  8159. 5:13:44here launch a cross training initiatives
  8160. 5:13:47to diversify the skill sets of remaining
  8161. 5:13:49team members ensuring the Project's
  8162. 5:13:51critical functions are covered now this
  8163. 5:13:53is pretty common especially on today's
  8164. 5:13:55world where all of a sudden they may cut
  8165. 5:13:59cut budgets or reduce your budgets and
  8166. 5:14:02other team members or particularly good
  8167. 5:14:04team members may have to be reassigned
  8168. 5:14:06to other projects what do you do well
  8169. 5:14:09you notice this question is what do you
  8170. 5:14:10do first and one of the first things you
  8171. 5:14:12do is to assess the
  8172. 5:14:14situation understand what's happening in
  8173. 5:14:17in light of what's budget cuts or people
  8174. 5:14:20leave and things like that notice b c
  8175. 5:14:25and d takes an action in this one you
  8176. 5:14:28shouldn't just revise a schedule like
  8177. 5:14:29that that will requires generally some
  8178. 5:14:32kind of change
  8179. 5:14:33request this is a mentorship program
  8180. 5:14:35this is a cross trining program in these
  8181. 5:14:38here
  8182. 5:14:39you're probably going to do these later
  8183. 5:14:41I would do B let's understand let's do a
  8184. 5:14:44discussion to understand what these
  8185. 5:14:45reassignment means how it affects the
  8186. 5:14:48projects how it affects the company's
  8187. 5:14:50objective let's do that first maybe then
  8188. 5:14:53we can do a mentorship program and and
  8189. 5:14:56or a cross trainining program so
  8190. 5:14:59remember on this exam watch that keyword
  8191. 5:15:02what should you do first what should you
  8192. 5:15:04do
  8193. 5:15:05next 153 during the implementation phase
  8194. 5:15:09of a Citywide public transportation
  8195. 5:15:11Improvement project a city council
  8196. 5:15:13member requests A specialized update
  8197. 5:15:16that goes beyond the scope of regular
  8198. 5:15:19briefing provided to the public and City
  8199. 5:15:21officials okay the team utilizes
  8200. 5:15:25Advanced so uh simulation software and
  8201. 5:15:29traffic flow analysis to plan and
  8202. 5:15:31monitor progress what should the project
  8203. 5:15:33manager
  8204. 5:15:34do provide a tutorial on how to
  8205. 5:15:36interpret the simulation software
  8206. 5:15:38results
  8207. 5:15:39invite the council member to workshop on
  8208. 5:15:41traffic flow analysis techniques using
  8209. 5:15:44the project engage directly with the
  8210. 5:15:46council member to clarify what specific
  8211. 5:15:49Data Insights are
  8212. 5:15:51needed compile a comprehensive report
  8213. 5:15:54using data from both simulation software
  8214. 5:15:57and traffic
  8215. 5:15:58analysis okay best answer here guys is
  8216. 5:16:01going to be by before I give it to you
  8217. 5:16:04remember what do you do next what do you
  8218. 5:16:06do first is going to help determine the
  8219. 5:16:08the answer of
  8220. 5:16:11C you see before taking this action
  8221. 5:16:14before giving them something meet with
  8222. 5:16:17them ask them when do you want it how
  8223. 5:16:22how would you like it in like what
  8224. 5:16:23format who should be giving it to
  8225. 5:16:26you um what time of day in what setting
  8226. 5:16:30would you like to get this basically
  8227. 5:16:31you're building that communication
  8228. 5:16:34management plan you notice a b
  8229. 5:16:39and D is giving them the data in a what
  8230. 5:16:43are you doing you're giving them a
  8231. 5:16:45tutorial you're telling them to come to
  8232. 5:16:48the workshop you're telling you're
  8233. 5:16:49giving them a report in this one here
  8234. 5:16:52let's clarify exactly what they want no
  8235. 5:16:55pinpoint the specific of what they want
  8236. 5:16:58and then you can better then you can
  8237. 5:17:01better give them what they want so first
  8238. 5:17:03clarify what they need 154 following a
  8239. 5:17:07critical review session of healthcare
  8240. 5:17:08software project a project manager notes
  8241. 5:17:11that the output of one software engineer
  8242. 5:17:13is not up to the project standards while
  8243. 5:17:17what is the most appropriate form of
  8244. 5:17:19communication for the project manager to
  8245. 5:17:21utilize in addressing the software
  8246. 5:17:23engineer performance
  8247. 5:17:26concerns send a group email highlighting
  8248. 5:17:29the importance of meeting project
  8249. 5:17:31standards without naming
  8250. 5:17:33individuals schedule a one-on-one
  8251. 5:17:35meeting to discuss the performance
  8252. 5:17:38issues and development plan all right
  8253. 5:17:41issue a formal performance Improvement
  8254. 5:17:43plan through the company's HR System
  8255. 5:17:45okay initiate a team-wide meeting to
  8256. 5:17:49discuss project
  8257. 5:17:50standards and individual contributions
  8258. 5:17:54collectively all right best answer here
  8259. 5:17:56guys is did you guys get that 101 here's
  8260. 5:18:00why anytime you have a problem on a
  8261. 5:18:04project where it deals with one person a
  8262. 5:18:07stakeholder a senior manager a sponsor a
  8263. 5:18:10team member it's just one person this
  8264. 5:18:13person is causing chaos this person
  8265. 5:18:15needs more information this person has
  8266. 5:18:18particular concerns the best thing to do
  8267. 5:18:20is don't do it in front of people deal
  8268. 5:18:22with that person right
  8269. 5:18:25on so what are we going to do we're
  8270. 5:18:28going to schedule a one-onone meeting
  8271. 5:18:29we're going to discuss the performance
  8272. 5:18:31issues and come up with a plan of how to
  8273. 5:18:32fix it we don't want to do this in a in
  8274. 5:18:35a group setting it's one person one
  8275. 5:18:38person that's having some of the
  8276. 5:18:40problems so the best way to deal with
  8277. 5:18:42this one person is going to be to ensure
  8278. 5:18:47that you meet with this person see what
  8279. 5:18:49the problem is and solve it instead of
  8280. 5:18:51bringing the team all in it so remember
  8281. 5:18:53that tip for your
  8282. 5:18:55test 155 leader in a software
  8283. 5:18:59development ad out project for a
  8284. 5:19:00multinational corporation a project
  8285. 5:19:02manager faces the challenge of managing
  8286. 5:19:04a team spread across multiple time zones
  8287. 5:19:07common nowadays right guys the project
  8288. 5:19:09manager has previously encountered
  8289. 5:19:11issues with such teams regarding
  8290. 5:19:13inconsistent work
  8291. 5:19:15quality and miss deadline what action
  8292. 5:19:18should the project manager take to
  8293. 5:19:19ensure high quality
  8294. 5:19:21deliverables and adherence to the
  8295. 5:19:25timeline initiative frequent virtual
  8296. 5:19:28stand-ups to clarify project goals
  8297. 5:19:29synchronize team efforts and address any
  8298. 5:19:31issues okay develop a comprehensive
  8299. 5:19:33trainer program on time management and
  8300. 5:19:35productivity tools distribute a detailed
  8301. 5:19:38weekly template for members to fill out
  8302. 5:19:40summarizing their progress organize a
  8303. 5:19:42quarterly in-person Meetup for team
  8304. 5:19:44building and detailed project reviews
  8305. 5:19:47best answer here guys is going to be a
  8306. 5:19:49this is correct first of all you should
  8307. 5:19:51be doing a virtual standup meetings on a
  8308. 5:19:53daily basis this is an adob project um I
  8309. 5:19:57wouldn't do weekly or quarterly because
  8310. 5:20:01quarterly may be too long maybe too far
  8311. 5:20:03apart
  8312. 5:20:04weekly may or may not be too long or Too
  8313. 5:20:07Short apart from from from their updates
  8314. 5:20:10but as a as an adob project the best
  8315. 5:20:13answer here is to do a standup meeting
  8316. 5:20:15you should be doing that anyhow notice a
  8317. 5:20:17training on time management this is a
  8318. 5:20:20decent answer I thought a and Bs were a
  8319. 5:20:22good answer and productivity tools for
  8320. 5:20:24all members but the best thing here is
  8321. 5:20:26just to fix the problem right what you
  8322. 5:20:29want to do is you want to make sure that
  8323. 5:20:31everybody understands their goals here
  8324. 5:20:33and the best answer is to do a frequent
  8325. 5:20:35daily standup meeting best answer was a
  8326. 5:20:40156 a project manager is tasked with
  8327. 5:20:43launching a new drug product which
  8328. 5:20:45requires adherence to strent health and
  8329. 5:20:48safety regulations it's crtical it's
  8330. 5:20:50critical for the launch to comply with
  8331. 5:20:52these regulations to avoid penalties and
  8332. 5:20:54ensure Public Safety what should the
  8333. 5:20:56project manager do next to guarantee
  8334. 5:20:58compliance with these regulations
  8335. 5:21:00arrange for regular training sessions on
  8336. 5:21:03Regulatory Compliance with the team all
  8337. 5:21:05right assess and document the potential
  8338. 5:21:07compliance risk related to health and
  8339. 5:21:09safety okay Implement a quality control
  8340. 5:21:12system to continuously monitor the
  8341. 5:21:14product against safety standard organize
  8342. 5:21:17a consultation with legal experts
  8343. 5:21:18specialized in regulations to review
  8344. 5:21:20project alignment this was a tough
  8345. 5:21:23question almost all of these answers
  8346. 5:21:25were pretty much correct best answer
  8347. 5:21:27here is going to be to assess it that's
  8348. 5:21:29correct notice what should you do
  8349. 5:21:33next assess and document potential
  8350. 5:21:35compliance risk that's the next thing
  8351. 5:21:37you want to do here
  8352. 5:21:39uh
  8353. 5:21:40notice you want to make sure that you
  8354. 5:21:42stay to it it's critical to comply well
  8355. 5:21:46what happens if you don't comply because
  8356. 5:21:47you want to avoid these penalties right
  8357. 5:21:50and ensure Public Safety what should you
  8358. 5:21:52be
  8359. 5:21:53doing well the best thing here is to
  8360. 5:21:57document potential compliance risk
  8361. 5:21:59related to safety put that in the plan
  8362. 5:22:01because it's from looking at the risks
  8363. 5:22:05then you can understand okay this is how
  8364. 5:22:06it can affect the schedule this is how
  8365. 5:22:08it can affect Public Safety this is how
  8366. 5:22:10it can affect the budget this is how it
  8367. 5:22:11can affect the scope uh arrange for
  8368. 5:22:14regular training let's do B then a so
  8369. 5:22:17we'll do remember it's what should you
  8370. 5:22:18do
  8371. 5:22:19next organize a consultation with legal
  8372. 5:22:22experts so let's understand how it
  8373. 5:22:23affects the project first Implement a
  8374. 5:22:26quality control this is something you're
  8375. 5:22:27going to implement later on not right
  8376. 5:22:29now best answer was
  8377. 5:22:31B
  8378. 5:22:33157 during the critical testing phase of
  8379. 5:22:35an Enterprise software upgrade the
  8380. 5:22:37project manager ident ifies that testing
  8381. 5:22:39is significantly behind schedule posing
  8382. 5:22:42a risk to the planned go live date what
  8383. 5:22:46should the project manager do first now
  8384. 5:22:47you notice the project this year
  8385. 5:22:49identified testing is significantly
  8386. 5:22:51behind what should you do escalate to
  8387. 5:22:54the company's executive management all
  8388. 5:22:55right conduct a detailed session with
  8389. 5:22:57the team to pinpoint causes for the
  8390. 5:22:59delay all right seek additional funding
  8391. 5:23:02to contract external testing services to
  8392. 5:23:04catch up Implement overtime hours for
  8393. 5:23:07the testing team this one here if you
  8394. 5:23:09follow along what I was saying uh at the
  8395. 5:23:11beginning of this video what you do
  8396. 5:23:13first don't take an action right away
  8397. 5:23:15let's go ahead and do a detail session
  8398. 5:23:17with the team let's go in there and uh
  8399. 5:23:20pinpoint what's causing this delay and
  8400. 5:23:22then we can go ahead and fix it you
  8401. 5:23:25never want to escalate project problems
  8402. 5:23:27especially to Senior Management the
  8403. 5:23:29company's executive management is there
  8404. 5:23:31to make decisions not to help you manage
  8405. 5:23:33your
  8406. 5:23:34project seek additional funding not yet
  8407. 5:23:38understand how it affects the project
  8408. 5:23:41don't Implement overtime one of the
  8409. 5:23:43things we want to resist on this exam is
  8410. 5:23:45implementation of overtime or
  8411. 5:23:47implementing overtime can overwork your
  8412. 5:23:49team members causing a significant drop
  8413. 5:23:52in productivity and overall quality of
  8414. 5:23:56deliverables
  8415. 5:23:58158 during the construction phase of a
  8416. 5:24:01new city park conflicts have emerged
  8417. 5:24:04between the landscape designers and
  8418. 5:24:07environmental consultant over the choice
  8419. 5:24:09of plant species and their environmental
  8420. 5:24:11impact what are the two most effective
  8421. 5:24:13actions for the project manager to take
  8422. 5:24:15to take first to resolve these conflicts
  8423. 5:24:18select
  8424. 5:24:19two delay any decisions on plant species
  8425. 5:24:23until further research can be conducted
  8426. 5:24:25okay organize individual meetings with
  8427. 5:24:28landscape designers and environmental
  8428. 5:24:30Consultants to understand each group's
  8429. 5:24:31concern initiate a workshop at all
  8430. 5:24:34stakeholders to democratically vote on
  8431. 5:24:35the species election escalate the
  8432. 5:24:38solution the issue to the city council
  8433. 5:24:40for final decision to avoid further
  8434. 5:24:43delay conduct private Target discussions
  8435. 5:24:45with key representative from both sides
  8436. 5:24:47to find a middle ground all right what
  8437. 5:24:49answers did you get the best answer here
  8438. 5:24:51I have is going to be B you want to
  8439. 5:24:54bring them together right you want to
  8440. 5:24:57understand what's going on so the first
  8441. 5:24:59thing I want to
  8442. 5:25:00do is let's do individual meetings with
  8443. 5:25:04the designers let's understand what's
  8444. 5:25:06going on understand their concerns
  8445. 5:25:09then what we want to do is we want to
  8446. 5:25:11conduct private targeted discussions
  8447. 5:25:14with the representative from both sides
  8448. 5:25:16to find that middle ground so in the
  8449. 5:25:17first one you meet them you meet you
  8450. 5:25:19meet the designers you meet the
  8451. 5:25:21Consultants then the next thing you
  8452. 5:25:22bring them together and see if there's a
  8453. 5:25:23middle ground hopefully we can solve the
  8454. 5:25:25problem you don't want to escalate it
  8455. 5:25:28not yet all right you don't want to
  8456. 5:25:30escalate this you have to try to solve
  8457. 5:25:32the problem now before you do a workshop
  8458. 5:25:35to vote on the pl species understand is
  8459. 5:25:37there a middle ground and never delay
  8460. 5:25:40anything delay any decision until
  8461. 5:25:42further research can be done no let's
  8462. 5:25:45work together and fix it just don't push
  8463. 5:25:46it off don't kick the can down the road
  8464. 5:25:48is what I generally say when answering
  8465. 5:25:50if you ever see a choice that looks like
  8466. 5:25:51it's going to kick the can down the road
  8467. 5:25:53it's probably not the
  8468. 5:25:55answer
  8469. 5:25:57159 during a critical software
  8470. 5:25:59implementation project the project
  8471. 5:26:01manager identifies a significant
  8472. 5:26:03slowdown in the integration phase
  8473. 5:26:05attributed to the team's unfamiliar
  8474. 5:26:08unfamiliarity with the new software's
  8475. 5:26:11API this issue threatens to delay
  8476. 5:26:13project Milestones what should the
  8477. 5:26:15project manager do first to address the
  8478. 5:26:17team's skill Gap without Rising the
  8479. 5:26:20budget initiate a collaborative problem
  8480. 5:26:23solving medum to identify Alternatives
  8481. 5:26:25integration strategies or Solutions okay
  8482. 5:26:28delegate the integration task to more
  8483. 5:26:29experienced team within the organization
  8484. 5:26:32reducing the learning curve all right
  8485. 5:26:34invest in FastTrack external training
  8486. 5:26:36program specifically focus on the new
  8487. 5:26:39software's API hire an external
  8488. 5:26:42consultant with expertise in s in the
  8489. 5:26:44software to lead the integration phase
  8490. 5:26:46and TR trainer team read the question
  8491. 5:26:49carefully you notice I highlight
  8492. 5:26:52this without Rising the budget so that
  8493. 5:26:56means you could have eliminated two
  8494. 5:26:57choices right you this here will
  8495. 5:26:59definitely rise the budget this here
  8496. 5:27:01will rise the budget and this here gives
  8497. 5:27:03away the work right so B gives away the
  8498. 5:27:05work the best thing here the best answer
  8499. 5:27:07all it's not the greatest answer ever
  8500. 5:27:10the best answer here is there any
  8501. 5:27:12alternative integration strategies or
  8502. 5:27:14Solutions we can go with we don't have
  8503. 5:27:16much choice because we cannot rise the
  8504. 5:27:18budget as for the question making a the
  8505. 5:27:21best
  8506. 5:27:24answer did you guys enjoy this video if
  8507. 5:27:26you did give this video a like subscribe
  8508. 5:27:28to the channel 160 during the planning
  8509. 5:27:31of a new development project a recently
  8510. 5:27:34enacted zoner Law changes the permis
  8511. 5:27:37building
  8512. 5:27:38the the permissible building Heights
  8513. 5:27:40within the Project's area the project
  8514. 5:27:43team has been informed of this change
  8515. 5:27:45what is the most effective course of
  8516. 5:27:47action for the project manager to take
  8517. 5:27:50proceed with planning until the legal
  8518. 5:27:51department informs you to update the
  8519. 5:27:54Plan update the project documentation to
  8520. 5:27:57reflect change in zonal laws impact on
  8521. 5:27:59the scope okay schedule a meeting with
  8522. 5:28:01local government officials to seek
  8523. 5:28:03exceptions uh for the current project
  8524. 5:28:05consult with legal councel and on
  8525. 5:28:07understand the implementation of Z Z and
  8526. 5:28:08law change on the project best answer
  8527. 5:28:10here this is a trick question by the way
  8528. 5:28:12best answer here guys is going to be B
  8529. 5:28:15why is
  8530. 5:28:16that well let's put it to you guys this
  8531. 5:28:19way they're still in
  8532. 5:28:22Planet I want to point that out they're
  8533. 5:28:24still in Planet and once you're in
  8534. 5:28:25planning you don't need a change request
  8535. 5:28:27to update the scope or anything like
  8536. 5:28:29that and if something is a law you have
  8537. 5:28:32to do it notice this isn't an active law
  8538. 5:28:36by not doing it you're breaking the law
  8539. 5:28:38making this a better answer proceed with
  8540. 5:28:40planning until the no you already know
  8541. 5:28:43the plan has to
  8542. 5:28:44change uh you don't need an ex exception
  8543. 5:28:47because it's a law now the other good
  8544. 5:28:49answer was D consult with legal counsel
  8545. 5:28:51understand uh this thing on on the zone
  8546. 5:28:54and law change to the project well you
  8547. 5:28:56already know that the height cannot be
  8548. 5:28:59done so you already know the impact of
  8549. 5:29:00it so now you just need to reassess your
  8550. 5:29:03plan um notice document the changes and
  8551. 5:29:07it document the impact on the entire
  8552. 5:29:10thing one of the things you have to
  8553. 5:29:11remember about law is if something is a
  8554. 5:29:13law you have to get it done it can be
  8555. 5:29:15the best answer and first question up in
  8556. 5:29:19the late stages of marketing launching a
  8557. 5:29:21marketing campaign project it's
  8558. 5:29:24identified that a critical piece of
  8559. 5:29:26content is not ready because a team
  8560. 5:29:27member fell behind schedule this issue
  8561. 5:29:30came to light during a presentation to
  8562. 5:29:31the marketing department causing concern
  8563. 5:29:34about launching about meeting the launch
  8564. 5:29:36date what should should what action
  8565. 5:29:38should the project manager do first have
  8566. 5:29:41a confidential discussion with the team
  8567. 5:29:44member to understand the reasons for the
  8568. 5:29:45delay and explore Solutions together all
  8569. 5:29:48right delegate the unfinished task to
  8570. 5:29:50another team member who has the capacity
  8571. 5:29:53to expedite completion all right
  8572. 5:29:55organize a session for the team to
  8573. 5:29:58collaboratively brainstorm ways to
  8574. 5:30:00expedite the remaining work seek advice
  8575. 5:30:02from a senior manager on how to handle
  8576. 5:30:04the team member's delay in task
  8577. 5:30:06completion now I want to point out to
  8578. 5:30:07you that anytime you get a question
  8579. 5:30:10where there's one person that may be
  8580. 5:30:12causing an issue one person delaying the
  8581. 5:30:15project one person wants something one
  8582. 5:30:17person uh callus on a commotion on the
  8583. 5:30:20project the best thing to do is to meet
  8584. 5:30:23with that
  8585. 5:30:24person and find out what the problem is
  8586. 5:30:27and how we can fix
  8587. 5:30:28it when somebody when somebody's causing
  8588. 5:30:31a problem and I'm talking one person or
  8589. 5:30:33maybe even a small group deal deal with
  8590. 5:30:35that person privately individually is
  8591. 5:30:38the way to do that don't push it out in
  8592. 5:30:40the group and embarrass people or cause
  8593. 5:30:41a bigger problem now one choice you guys
  8594. 5:30:45should have eliminated right off the bat
  8595. 5:30:47was senior manager senior manager is not
  8596. 5:30:49there to solve problems on your project
  8597. 5:30:51that's what they hire you for so let's
  8598. 5:30:53eliminate that one before you organize a
  8599. 5:30:56session to fix this issue right now or
  8600. 5:30:58assign someone to fix it the best thing
  8601. 5:31:00to do is to meet with this person and
  8602. 5:31:02see if you guys can work together to fix
  8603. 5:31:04it best answer was
  8604. 5:31:06a 162
  8605. 5:31:08the project manager for a renewable
  8606. 5:31:11energy initiative receives a suggestion
  8607. 5:31:14from an environmental consultant to
  8608. 5:31:16incorporate a new technology that can
  8609. 5:31:17improve project outcomes but also extend
  8610. 5:31:20the timelines and increase costs what
  8611. 5:31:22should you do first forward the
  8612. 5:31:24suggestions forward the suggestion to
  8613. 5:31:26the Project's CCB by the way this means
  8614. 5:31:29change control board for approval before
  8615. 5:31:31I go on I want to point out that on the
  8616. 5:31:33exam generally when they give you an
  8617. 5:31:34acronym they probably spell it out for
  8618. 5:31:36you you don't have to memorize acronyms
  8619. 5:31:37on your test generally speaking except
  8620. 5:31:40those formal acronyms those evm acronyms
  8621. 5:31:42you should know
  8622. 5:31:43those arrange a project team me in to
  8623. 5:31:47discuss the feasibility and implications
  8624. 5:31:50of integrating the new technology
  8625. 5:31:52consult with industry experts to gauge
  8626. 5:31:54the potential benefits and drawback con
  8627. 5:31:56uh conduct a preliminary risk analysis
  8628. 5:31:58to understand how the new technology
  8629. 5:32:00might affect the project risk best
  8630. 5:32:02answer here guys now before I give you
  8631. 5:32:05the answer I want to point out that
  8632. 5:32:06remember it's a suggestion from an
  8633. 5:32:08environmental consultant it may be good
  8634. 5:32:10it may be bad the best thing we can
  8635. 5:32:12do is to have the team come in and tell
  8636. 5:32:16us if this is a good or a bad idea
  8637. 5:32:18always utilize the expertise of the team
  8638. 5:32:21that's what they're there for so what we
  8639. 5:32:23want to do is you want to meet with the
  8640. 5:32:24team and we want to say hey what do you
  8641. 5:32:26guys think is this good how is this
  8642. 5:32:28going to affect the project they're the
  8643. 5:32:30expert not us you can't send it to the
  8644. 5:32:32Change Control Board for approval if you
  8645. 5:32:34haven't see how it's going to how it's
  8646. 5:32:36going to affect the project how much is
  8647. 5:32:38it going to extend that deadline how
  8648. 5:32:40much is it going to extend that
  8649. 5:32:42budget before going to Industry experts
  8650. 5:32:45remember what to do first we want to
  8651. 5:32:47meet with the team first and to do this
  8652. 5:32:50risk assessment your team should help
  8653. 5:32:52you uh your the team should help you
  8654. 5:32:56before you do a risk assessment and the
  8655. 5:32:58team should help you do a risk
  8656. 5:32:59assessment don't forget all changes must
  8657. 5:33:01be assessed before it can be approved by
  8658. 5:33:04CCB
  8659. 5:33:06163 in the midst of a renewable energy
  8660. 5:33:09project a team member notices a
  8661. 5:33:11significant risk related to equipment
  8662. 5:33:13procurement that could potentially D
  8663. 5:33:15derail the project timeline the concern
  8664. 5:33:18is promptly communicated to the project
  8665. 5:33:20sponsor who then request the project
  8666. 5:33:22manager for a detail assessment and
  8667. 5:33:24action plan all right which a document
  8668. 5:33:26should a project manager consult with
  8669. 5:33:27the team to outline predefined
  8670. 5:33:29approaches to assist to address this
  8671. 5:33:32procurement risk appropriately risk
  8672. 5:33:35register issue log risk respon strategy
  8673. 5:33:38and risk management plan so the question
  8674. 5:33:41is
  8675. 5:33:42asking basically what
  8676. 5:33:45document has predefined approaches to
  8677. 5:33:49risks did you get it best answer here
  8678. 5:33:52was risk register is correct the risk
  8679. 5:33:54register has the risk and the potential
  8680. 5:33:57responses to the risk this is a risk
  8681. 5:33:59this is not an issue so it does not
  8682. 5:34:01belong to issue log there really is no
  8683. 5:34:03such thing as a risk response strategy
  8684. 5:34:05that's actually in the that's there's no
  8685. 5:34:07such document like that the strategy is
  8686. 5:34:09in the risk
  8687. 5:34:11register the risk management plan
  8688. 5:34:13doesn't actually have risk or risk
  8689. 5:34:15responses making a the best
  8690. 5:34:19answer 164 in finalizing an
  8691. 5:34:22infrastructure upgrade project the
  8692. 5:34:24project manager needs to ensure that all
  8693. 5:34:26critical operation knowledge has been
  8694. 5:34:28transferred to the clients to the
  8695. 5:34:30client's maintenance
  8696. 5:34:32team efficiently or effectively what
  8697. 5:34:36approach should the project maner your
  8698. 5:34:37employee to confirm the thoroughness of
  8699. 5:34:40the knowledge transfer schedule
  8700. 5:34:42face-to-face sessions with the
  8701. 5:34:43maintenance team members and the project
  8702. 5:34:45team to validate understand and
  8703. 5:34:47application of operational knowledge
  8704. 5:34:49okay develop and administer a formal
  8705. 5:34:52assessment to the maintenance team on a
  8706. 5:34:53key operational procedure create an
  8707. 5:34:56interactive online module for the
  8708. 5:34:57maintenance team to complete uh covering
  8709. 5:34:59all necessary operational information
  8710. 5:35:02facilitate a Roundtable discussion with
  8711. 5:35:04key project and maintenance team members
  8712. 5:35:07to evaluate the depth of knowledge
  8713. 5:35:08transfer all right you want to uh let's
  8714. 5:35:12take a look at the question here uh what
  8715. 5:35:15approach to employ to confirm the
  8716. 5:35:17thoroughness of the knowledge transfer
  8717. 5:35:19this is the key here you want to confirm
  8718. 5:35:21that it was thoroughly done best answer
  8719. 5:35:23here guys is going to be a if you got a
  8720. 5:35:25you are correct one thing I do mention
  8721. 5:35:27in the course is anytime you see that
  8722. 5:35:29word face Toof face communication it's
  8723. 5:35:31probably good answer to choose
  8724. 5:35:33face-to-face communication is one of the
  8725. 5:35:35best ways and the richest way to
  8726. 5:35:36communicate
  8727. 5:35:38and I think face to-face communication
  8728. 5:35:40here just trumps or or is better than an
  8729. 5:35:44interactive online module or some kind
  8730. 5:35:46of formal
  8731. 5:35:47assessment uh the best thing here is to
  8732. 5:35:49have face tof face discussion let them
  8733. 5:35:52talk and let them validate your
  8734. 5:35:53understanding so they can both talk to
  8735. 5:35:55each other and see hey do you understand
  8736. 5:35:57this do you understand it's better than
  8737. 5:35:58that the other one here was more of a
  8738. 5:36:00round table but I think this face Toof
  8739. 5:36:02face is is better uh than actually just
  8740. 5:36:05going going through a round table
  8741. 5:36:09question 165 in a software development
  8742. 5:36:11project the project manager notices that
  8743. 5:36:14the various project teams have different
  8744. 5:36:17priorities and methodologies leading to
  8745. 5:36:20inconsistencies and delays in Project
  8746. 5:36:22Milestones the project manager realizes
  8747. 5:36:25the need for a unified approach to
  8748. 5:36:27streamline processes and improve
  8749. 5:36:29collaboration amongst the
  8750. 5:36:31team what is the most effective course
  8751. 5:36:34of action for the project manager to
  8752. 5:36:36ensure consistent progress across all
  8753. 5:36:40teams Implement a centralized project
  8754. 5:36:43management tool to enhance communication
  8755. 5:36:45and task tracking all right conduct a
  8756. 5:36:47workshop to align all teams on the
  8757. 5:36:50project objectives and establish a
  8758. 5:36:51shared methodology okay assign a liazon
  8759. 5:36:55from each team to facilitate better
  8760. 5:36:57understanding and integration of work
  8761. 5:36:59practices real uh reallocate project
  8762. 5:37:02resources to prioritize task according
  8763. 5:37:05to urgency and importance of the project
  8764. 5:37:07milestone
  8765. 5:37:08okay what did you guys get we have a
  8766. 5:37:10problem here what's the problem teams
  8767. 5:37:13having different priorities and
  8768. 5:37:15different methodologies this is what's
  8769. 5:37:17causing the problem you got to select
  8770. 5:37:19the answer that deals directly with this
  8771. 5:37:22and the best answer here is going to be
  8772. 5:37:24to bring them all
  8773. 5:37:26together make sure that the the choices
  8774. 5:37:30is going to deal with solving this
  8775. 5:37:33problem right this whole problem of
  8776. 5:37:36different priorities
  8777. 5:37:37and especially
  8778. 5:37:39methodologies one of the things we have
  8779. 5:37:41to do when we do this exam is you have
  8780. 5:37:42to read that question
  8781. 5:37:44carefully and say to yourself does that
  8782. 5:37:47answer actually solves the question
  8783. 5:37:50because you're going to have multiple
  8784. 5:37:51answers that sounds great but only one
  8785. 5:37:53of them may actually solve the problem
  8786. 5:37:56and this one does because if you notice
  8787. 5:37:58it establishes a shared methodology and
  8788. 5:38:00that's what we want a shared methodology
  8789. 5:38:04would lead to consistency right right
  8790. 5:38:06now to have inconsistency
  8791. 5:38:08ancies a centralized project management
  8792. 5:38:10tool is you choosing for them let the
  8793. 5:38:12team choose not you choosing for them in
  8794. 5:38:15all the other choices you're choosing so
  8795. 5:38:17is C you're saying hey let's do a
  8796. 5:38:19liaison between them now the entire
  8797. 5:38:22teams are not there reallocate project
  8798. 5:38:25resources to prioritize tasks now you're
  8799. 5:38:27doing it for them don't do that let the
  8800. 5:38:29team
  8801. 5:38:30choose next
  8802. 5:38:32question
  8803. 5:38:34166 while implementing an ER r p
  8804. 5:38:37enterprise resource planning the agile
  8805. 5:38:40project manager received several
  8806. 5:38:41requests for additional features from
  8807. 5:38:44department heads potentially affecting
  8808. 5:38:46the project scope and timeline what
  8809. 5:38:48should the project manager do to address
  8810. 5:38:50these feature requests efficiently or
  8811. 5:38:54effectively uh direct the department
  8812. 5:38:57heads to submit their request after the
  8813. 5:38:59Erp goes live all right have the product
  8814. 5:39:01owner integrate the feature request into
  8815. 5:39:04the product backlog for
  8816. 5:39:05prioritization Asa advise the Department
  8817. 5:39:08of Health that all project changes are
  8818. 5:39:10Frozen to avoid deviations from the plan
  8819. 5:39:13schedule request detailed business case
  8820. 5:39:15for each feature to assess the impact
  8821. 5:39:18before adding them to the product
  8822. 5:39:20project
  8823. 5:39:21plan so I want you guys to know that the
  8824. 5:39:23agile it's clearly states this this is
  8825. 5:39:26an agile project and somebody wants to
  8826. 5:39:28add something to Agile not difficult if
  8827. 5:39:30you understand AG practices because
  8828. 5:39:33there's one thing we know the only
  8829. 5:39:34person that can add something to the
  8830. 5:39:37scope put a project on an ad job project
  8831. 5:39:39is who is the correct the product owner
  8832. 5:39:42only the product owner can add features
  8833. 5:39:44to the product backlog and then
  8834. 5:39:45prioritize it not the department heads
  8835. 5:39:49needs to work with the product owner you
  8836. 5:39:51don't stop changes on an adob project
  8837. 5:39:53they never stop and you don't need a
  8838. 5:39:56detailed business case for each one
  8839. 5:39:58that's something between the product
  8840. 5:39:59owners and the uh people asking for
  8841. 5:40:02people asking for the
  8842. 5:40:05changes 167 in the implementation stage
  8843. 5:40:09of a critical network security project
  8844. 5:40:11it is revealed that a specialist
  8845. 5:40:14responsible for key parts of the
  8846. 5:40:16configuration will be taken emergency
  8847. 5:40:18leave what should the project manager do
  8848. 5:40:20to address this specialist absence
  8849. 5:40:22imminent absence and keep the project on
  8850. 5:40:25schedule facilitate a discussion with
  8851. 5:40:28the project team to redistribute the
  8852. 5:40:29specialist
  8853. 5:40:31responsibilities efficient effectively
  8854. 5:40:34uh efficiently among existing members
  8855. 5:40:37suggest pausing the project until the
  8856. 5:40:39specialist can return and resume their
  8857. 5:40:41duties contract an external consultant
  8858. 5:40:43firm to Temporary fill the specialist
  8859. 5:40:45role request an immediate extension of
  8860. 5:40:48the project deadline to accommodate the
  8861. 5:40:49delay all right somebody's leaving the
  8862. 5:40:53best thing here to do guys is meet with
  8863. 5:40:55the team and see how put up a discussion
  8864. 5:40:59and see hey can we spread this
  8865. 5:41:02responsibilities amst each other this is
  8866. 5:41:04what this is how you can do this really
  8867. 5:41:06quickly and just try to keep the project
  8868. 5:41:08on
  8869. 5:41:09schedule because it's saying that he
  8870. 5:41:12plays you know this person leaving plays
  8871. 5:41:14a key part in the configuration but
  8872. 5:41:16we'll be taking emergency leave work
  8873. 5:41:18with the team if the team tells you that
  8874. 5:41:21they need an additional person maybe
  8875. 5:41:24then you can go out and get a consultant
  8876. 5:41:26firm to give you someone I wouldn't
  8877. 5:41:28pause the project like that if the team
  8878. 5:41:30said it's okay
  8879. 5:41:31then I wouldn't ask for an extension if
  8880. 5:41:34the team says so then but let's see if
  8881. 5:41:37the the team can deal with this if you
  8882. 5:41:39notice you know we've been doing a lot
  8883. 5:41:40of questions 167 of them if you notice
  8884. 5:41:44the team has the power on the project
  8885. 5:41:46the team knows better they're the
  8886. 5:41:49experts next question 168 nearing the
  8887. 5:41:53completion of an extensive software
  8888. 5:41:55development project it is noticed that
  8889. 5:41:57one developers innovative solutions have
  8890. 5:41:59greatly enhanced the project outcome uh
  8891. 5:42:01distinguishing their contribution from
  8892. 5:42:03the rest of the team what is the most
  8893. 5:42:05appropriate way for the project manager
  8894. 5:42:07to acknowledge this outstanding
  8895. 5:42:09contribution create a feature in the
  8896. 5:42:11company newsletter highlighting the
  8897. 5:42:13developers Innovative work all right
  8898. 5:42:16organize a casual team lunch where
  8899. 5:42:18developers efforts can be uh informally
  8900. 5:42:20recognized by peers all right submit a
  8901. 5:42:23recommendation for the developer to be
  8902. 5:42:25considered for the prestigious industry
  8903. 5:42:27award I like that one that's a good one
  8904. 5:42:29identify a form of recognition that
  8905. 5:42:31aligns with the developers value most
  8906. 5:42:33whether it be professional development
  8907. 5:42:35opportunity specific for a or something
  8908. 5:42:37personal the best thing here guys if you
  8909. 5:42:39find that someone is doing a great job
  8910. 5:42:42and you want to award them the best
  8911. 5:42:44thing to do is to talk to them ask them
  8912. 5:42:47what do you think is the best way to
  8913. 5:42:48award you we like you and we want to
  8914. 5:42:50give you something what would be best so
  8915. 5:42:53work with them you notice in this one in
  8916. 5:42:57c b and a you're choosing the way to
  8917. 5:43:03acknowledge their
  8918. 5:43:05contribution right you you're choosing
  8919. 5:43:07the acknowledgement you're choosing the
  8920. 5:43:09method of acknowledgement the best way
  8921. 5:43:11is to work with the team member to let
  8922. 5:43:13them
  8923. 5:43:15choose as a project manager for 169 as a
  8924. 5:43:19project manager for a novel online
  8925. 5:43:21educational platform you're face with
  8926. 5:43:24different views Divergent views among
  8927. 5:43:27stakeholders regarding the balance
  8928. 5:43:28between interactive content and
  8929. 5:43:30accessibility features the development
  8930. 5:43:32team is split on uh which aspects to
  8931. 5:43:36prioritize potentially affecting the
  8932. 5:43:38project timeline what action should the
  8933. 5:43:40project manager take to navigate this
  8934. 5:43:41impath effic
  8935. 5:43:45effectively deploy conf deploy conflict
  8936. 5:43:48resolution method technique specifically
  8937. 5:43:50designed to address and navigate the
  8938. 5:43:52diverse viewpoints into a unified
  8939. 5:43:54strategy okay conduct a poll with the
  8940. 5:43:57team and among stakeholders to
  8941. 5:43:58democratically decide the Project's
  8942. 5:44:00Focus area facilitate discussion
  8943. 5:44:03facilitate a focus group discussion
  8944. 5:44:06leverages is design in principles to
  8945. 5:44:08Foster Innovative solution choose the
  8946. 5:44:10best solution all right suggest the team
  8947. 5:44:13separately debates and reaches a
  8948. 5:44:14consensus without managerial
  8949. 5:44:17intervention this one here has two good
  8950. 5:44:19answers let me see what you guys
  8951. 5:44:21got best answer was a here's why first
  8952. 5:44:24of all before we answer this it's
  8953. 5:44:26basically have different view amounts
  8954. 5:44:28the stakeholders you want to balance
  8955. 5:44:29this interactive method and the
  8956. 5:44:31accessibility
  8957. 5:44:33feature team is split what are we going
  8958. 5:44:35to do here guys well you don't want to
  8959. 5:44:38just do a poll amounts the stakeholders
  8960. 5:44:41because uh you might have to sometimes
  8961. 5:44:44software development these features
  8962. 5:44:45might be needed by law so you might have
  8963. 5:44:47to include them um don't just tell the
  8964. 5:44:50team to go and figure it out themselves
  8965. 5:44:53never tell the team to go figure it out
  8966. 5:44:55themselves it's part of your job to work
  8967. 5:44:56with the team now this one here you
  8968. 5:45:01notice that the team is split all right
  8969. 5:45:05on this how are you going to do it well
  8970. 5:45:07there's lots of different conflict
  8971. 5:45:08resolution techniques you can use and
  8972. 5:45:11because there are different views
  8973. 5:45:13amongst the people you're going to have
  8974. 5:45:15to work you're going to have to use
  8975. 5:45:17these techniques to manage the different
  8976. 5:45:20views into one strategy so the project
  8977. 5:45:22can progress this one here is more of a
  8978. 5:45:25design principle to come up with
  8979. 5:45:27innovative solutions although that
  8980. 5:45:30sounds great the best answer here is
  8981. 5:45:31going to be the company unified strategy
  8982. 5:45:34remember the project can't move on if if
  8983. 5:45:37we don't come up with a unified strategy
  8984. 5:45:38make it a better than
  8985. 5:45:41C last question
  8986. 5:45:44170 halfway through a critical website
  8987. 5:45:47development project it is revealed
  8988. 5:45:49during a Sprint review that an
  8989. 5:45:51unforeseen technical hurdle could
  8990. 5:45:53potentially delay the Project's
  8991. 5:45:54completion this Revelation came as a
  8992. 5:45:57surprise especially considering the
  8993. 5:46:00project manager prior weekly updates
  8994. 5:46:02indicated that the project was
  8995. 5:46:03proceeding according to
  8996. 5:46:05plan what could have been been done
  8997. 5:46:07differently to avoid being caught offu
  8998. 5:46:09by such a critical issue establish a
  8999. 5:46:12robust risk man risk management process
  9000. 5:46:14to identify monitor potential technical
  9001. 5:46:16challenges to our project all right
  9002. 5:46:18schedule mids Sprint reviews to assess
  9003. 5:46:21Pro uh progress and uncover hidden risk
  9004. 5:46:24before the escalate conduct regular
  9005. 5:46:26one-on-one meetings with the team to
  9006. 5:46:27identify potential risk that might not
  9007. 5:46:30surface in the group set all right use
  9008. 5:46:32project management tool to track
  9009. 5:46:33progress and flag potential risk based
  9010. 5:46:35on the time deviation
  9011. 5:46:38okay so I want you just to review this
  9012. 5:46:41question it says here it is revealed
  9013. 5:46:43that during a Sprint review on
  9014. 5:46:45foreseeing technical could potenti so we
  9015. 5:46:48know that this is a
  9016. 5:46:49risk right because this is something
  9017. 5:46:51that can stop it the best answer now
  9018. 5:46:54again this is a risk when you're
  9019. 5:46:55managing risk what should you be doing
  9020. 5:46:58all right in order to manage risk well
  9021. 5:47:00remember you want to do something to
  9022. 5:47:01avoid this from ever happening you know
  9023. 5:47:03what's going to avoid this from
  9024. 5:47:04happening manage risk throughout the
  9025. 5:47:07project correct risk is not something
  9026. 5:47:10that you may want to
  9027. 5:47:11do uh mid-print it's not something that
  9028. 5:47:15you're going to want to do maybe weekly
  9029. 5:47:17it's something that you're going to do
  9030. 5:47:18throughout the project every day every
  9031. 5:47:20minute every second of a project you're
  9032. 5:47:21doing risk assessment identify and
  9033. 5:47:23assess and risk because remember risk
  9034. 5:47:25happens all the time making this a lot
  9035. 5:47:27better answer one-on-one meetings I like
  9036. 5:47:30one-on-one meetings but risk management
  9037. 5:47:33risk assessment risk identification
  9038. 5:47:35should be done as a team not just just
  9039. 5:47:36as 101 we don't need a tool for this we
  9040. 5:47:40need everybody to work with it making a
  9041. 5:47:42the best answer question
  9042. 5:47:44171 as a project manager overseeing the
  9043. 5:47:47roll out of a new online banking
  9044. 5:47:49platform ensuring that customers can
  9045. 5:47:52seemlessly transition and utilize a
  9046. 5:47:53platform is
  9047. 5:47:54critical the project sponsor emphasizes
  9048. 5:47:57the importance of excellent customer
  9049. 5:47:59support following the launch what action
  9050. 5:48:01should the project manager take to
  9051. 5:48:02fulfill this requirement coordinate with
  9052. 5:48:05the customer service department to
  9053. 5:48:06extend their hours in the weeks
  9054. 5:48:08following the launch okay initiate a
  9055. 5:48:11temporary dedicated hotline for new
  9056. 5:48:13platform inquiries and issues all right
  9057. 5:48:15set up a series of self-paced webinars
  9058. 5:48:17for customers focusing on platform
  9059. 5:48:19features and common troubleshooting step
  9060. 5:48:22okay create a comprehensive online help
  9061. 5:48:25center that includes tutorial videos
  9062. 5:48:27searchable knowledge base and options
  9063. 5:48:29for Live support our this question is is
  9064. 5:48:31a tricky question right because it says
  9065. 5:48:34here that you want to ensure that
  9066. 5:48:35customers can seamlessly
  9067. 5:48:37transition uh and the importance of
  9068. 5:48:39excellent customer support the point of
  9069. 5:48:42this question was when you're dealing
  9070. 5:48:43with a lots of lots of different
  9071. 5:48:45stakeholders and you might not be able
  9072. 5:48:48to uh assess all their needs the best
  9073. 5:48:50thing here to do is to give them as much
  9074. 5:48:52options as possible you notice D talks
  9075. 5:48:55about tutorial videos knowledge based
  9076. 5:48:57and Live support versus this is more of
  9077. 5:49:00just a self-pace webinar this one here
  9078. 5:49:03is just a dedicated
  9079. 5:49:05hotline and this one is just keeping the
  9080. 5:49:07branches open longer the best thing here
  9081. 5:49:09to do would be to give as much options
  9082. 5:49:11to satisfy as many of those stakeholders
  9083. 5:49:14as you
  9084. 5:49:15could
  9085. 5:49:17172 at the at the outset of an
  9086. 5:49:21initiative to introduce Smart City
  9087. 5:49:23Technologies it is discovered that the
  9088. 5:49:25input from a CR from a crucial
  9089. 5:49:28environmental expert was not included
  9090. 5:49:30during the preliminary discussions on
  9091. 5:49:32the Project's environmental impact
  9092. 5:49:33assessment what document is most likely
  9093. 5:49:37in need of revision due to this
  9094. 5:49:39submission stakehold register engagement
  9095. 5:49:42plan project schedule or the
  9096. 5:49:44communication plan all right best answer
  9097. 5:49:46here guys is going to be the stakeholder
  9098. 5:49:49register here's why I want to point out
  9099. 5:49:52something you notice that the input from
  9100. 5:49:56this crucial environmental expert was
  9101. 5:49:59never gotten that means that this person
  9102. 5:50:01was probably not even identified keep in
  9103. 5:50:04mind that the stakeholder register has a
  9104. 5:50:07listing of all your
  9105. 5:50:08stakeholders and how they're going to
  9106. 5:50:11impact the project and what how they're
  9107. 5:50:13going to impact the project how the
  9108. 5:50:14project is going to impact them that's
  9109. 5:50:16in the stakeholder register so you would
  9110. 5:50:17need to know this before you even got
  9111. 5:50:19out before you went out and got their
  9112. 5:50:22opinion or got their statement the
  9113. 5:50:25engagement PL comes after the register
  9114. 5:50:28this is how you plan to engage with them
  9115. 5:50:29we never even know the existed the
  9116. 5:50:32project schedule is has nothing to do
  9117. 5:50:33with stakeholders the communication is
  9118. 5:50:35how we plan to communicate with them but
  9119. 5:50:37we didn't even know they exist because
  9120. 5:50:38we never even got their
  9121. 5:50:40input best answer stakeholder
  9122. 5:50:43register
  9123. 5:50:45173 just assigned to lead a new
  9124. 5:50:48technology integration project the
  9125. 5:50:49project manager Lawrence that no
  9126. 5:50:51foundational documentation exist leaving
  9127. 5:50:55the team uncertain about scope
  9128. 5:50:56deliverables and timeline what action
  9129. 5:50:58should the project manager take to
  9130. 5:51:00establish a solid solid
  9131. 5:51:04foundation initiate the project uh by
  9132. 5:51:07focusing on highle tasks and develop
  9133. 5:51:09documentation as these tasks progress
  9134. 5:51:11right instruct Department helps to
  9135. 5:51:13comply to respective sections of the
  9136. 5:51:15project documentation to streamline lock
  9137. 5:51:18in Industry standard project management
  9138. 5:51:20templates to quickly draft the necessary
  9139. 5:51:22documents engage the entire team in a
  9140. 5:51:24com comprehensive planning session to
  9141. 5:51:26collaboratively develop all critical
  9142. 5:51:29project management documents best answer
  9143. 5:51:31here now I want to point out I did
  9144. 5:51:32Circle this here I shouldn't have done
  9145. 5:51:34that because that makes it easier right
  9146. 5:51:36because in order to have the best
  9147. 5:51:38success on a project you must make sure
  9148. 5:51:40you have all the documents and you want
  9149. 5:51:42to engage your team while building these
  9150. 5:51:45documents
  9151. 5:51:47notice you can't just really go and do a
  9152. 5:51:50project if you do something that's like
  9153. 5:51:52high level you want to engage the team
  9154. 5:51:54the best answer here why this is one of
  9155. 5:51:57the best ansers because it engages the
  9156. 5:51:58team let the team help you let those
  9157. 5:52:00experts help you instruct departmental
  9158. 5:52:03heads know the project manager deals
  9159. 5:52:05with this templates are great I like
  9160. 5:52:07templates but you want to engage the
  9161. 5:52:10team here to help you build the plan
  9162. 5:52:12itself it can the best
  9163. 5:52:14answer 174 to enhance project
  9164. 5:52:17communication and address emerging
  9165. 5:52:19issues a project manager organizes by
  9166. 5:52:22weekly meetings with the development
  9167. 5:52:24team of a software project what should
  9168. 5:52:27the project manager prioritize at the
  9169. 5:52:29beginning of these meetings detail the
  9170. 5:52:31current status of the project schedule
  9171. 5:52:33and any deviations meet an agenda times
  9172. 5:52:35and topics to cover
  9173. 5:52:37reevaluate the scope in light of recent
  9174. 5:52:39developments gather feedback for
  9175. 5:52:41continuous Improvement now the first
  9176. 5:52:43thing you're going to do when you do a
  9177. 5:52:44meeting is what you guys should got this
  9178. 5:52:47what should prioritize at the beginning
  9179. 5:52:49of these meetings right beginning of
  9180. 5:52:52every meeting you guys should do what
  9181. 5:52:54talk about what you're going to be
  9182. 5:52:55covering how long uh and the topics to
  9183. 5:52:59go over that's the best
  9184. 5:53:00answer then later on in the meeting
  9185. 5:53:03you'll talk about schedule reevaluating
  9186. 5:53:05the scope if needed gather feedback
  9187. 5:53:07continuous Improvement these are all
  9188. 5:53:08things are going to cover in the meeting
  9189. 5:53:09but at the beginning of the meeting tell
  9190. 5:53:11people what this meeting is and the
  9191. 5:53:13times on the meeting that way the
  9192. 5:53:14meeting doesn't waste too too much
  9193. 5:53:17time
  9194. 5:53:19175 in the midst of executing a high
  9195. 5:53:22stake software development project
  9196. 5:53:24several unexpected software bugs and
  9197. 5:53:27team miscommunications have led to
  9198. 5:53:30delays causing tension within the team
  9199. 5:53:32and concern from the sponsor about
  9200. 5:53:35meeting key deliverable on time what
  9201. 5:53:37should the project manager do to
  9202. 5:53:39alleviate these issues and steer the
  9203. 5:53:40project back on
  9204. 5:53:42track conduct team building events focus
  9205. 5:53:45on enhancing team collaboration and open
  9206. 5:53:48communication okay host a problem
  9207. 5:53:50solving Workshop where team members can
  9208. 5:53:51collaborative identify solutions to
  9209. 5:53:53technical issues all right I like that
  9210. 5:53:56increase the frequency of progress
  9211. 5:53:57review meetings to closely monitor team
  9212. 5:53:59performance and progress H arrange for a
  9213. 5:54:02professional mediator to address and
  9214. 5:54:04resolve interpersonal conflict with in
  9215. 5:54:06the team I can eliminate one choice
  9216. 5:54:08right off the
  9217. 5:54:09bat but the others are pretty good let's
  9218. 5:54:13see what you got here's what I got the
  9219. 5:54:15one I could have eliminated right off
  9220. 5:54:17the bat was this one you are this person
  9221. 5:54:21you shouldn't hire a professional person
  9222. 5:54:23that's you let's get rid of that choice
  9223. 5:54:25I really lik to B and um see not so much
  9224. 5:54:30so let's let's get R to see the
  9225. 5:54:32frequency of the progress can increase
  9226. 5:54:34the frequency of progress meetings
  9227. 5:54:36they're not getting along here they
  9228. 5:54:37might this might lead to them not
  9229. 5:54:39getting along even
  9230. 5:54:40more now host problem solving where
  9231. 5:54:43teams can collaboratively identify
  9232. 5:54:45solutions to but this is to technical
  9233. 5:54:47issues that's not all of it notice
  9234. 5:54:50several unexpected software bugs and
  9235. 5:54:53team
  9236. 5:54:55miscommunication have led to delays and
  9237. 5:54:58concern so it's not just the software
  9238. 5:55:01bugs because this is technical it's also
  9239. 5:55:04miscommunication the best thing here is
  9240. 5:55:06to focus on their collaboration and open
  9241. 5:55:09communication this here can lead to less
  9242. 5:55:12miscommunication and hopefully leads to
  9243. 5:55:14fixing technical things always on this
  9244. 5:55:18exam it's not a technical exam try to be
  9245. 5:55:22a project manager that works with the
  9246. 5:55:24team in a way that is all about open
  9247. 5:55:28Communications and everybody can talk
  9248. 5:55:30anybody can get along just don't try to
  9249. 5:55:32fix one thing like technical issues I'm
  9250. 5:55:34pretty sure if you have open
  9251. 5:55:35Communications you're going to fix the
  9252. 5:55:37miscommunications and the technical
  9253. 5:55:40issues
  9254. 5:55:43176 during a key phase of an
  9255. 5:55:45infrastructure project the project
  9256. 5:55:47manager notices the notices a
  9257. 5:55:50significant slowdown and decision making
  9258. 5:55:52due to their need to approve numerous
  9259. 5:55:56minor project adjustments this has
  9260. 5:55:58started to impact the Project's momentum
  9261. 5:55:59as the project manager schedule is
  9262. 5:56:01dominated by stakeholder
  9263. 5:56:04meetings What in itive should the
  9264. 5:56:06project manager introduce to improve
  9265. 5:56:09decision-making
  9266. 5:56:10process organize weekly Roundup sessions
  9267. 5:56:13to address all accumulated decisions in
  9268. 5:56:15one go Implement a critical path
  9269. 5:56:18analysis to ENT to pinpoint decision
  9270. 5:56:20making as the the primary project delay
  9271. 5:56:24assign decision- making responsibility
  9272. 5:56:26for specific areas to trusted project
  9273. 5:56:29leads make all decisions to ensure it's
  9274. 5:56:32done in a timely
  9275. 5:56:34manner okay one choice here you can
  9276. 5:56:36eliminate the rest of this is a toss up
  9277. 5:56:39in the air in my opinion let's see what
  9278. 5:56:41you guys got here's what I got all
  9279. 5:56:45right let's go through these answers
  9280. 5:56:47this one here you got to eliminate
  9281. 5:56:49because this is the problem right here D
  9282. 5:56:51is not doing anything D is just saying
  9283. 5:56:52okay let's continue doing it you notice
  9284. 5:56:55the project might noce significant
  9285. 5:56:56slowdown due to the need to approve
  9286. 5:56:59numerous D is the same thing D is
  9287. 5:57:01basically say you just keep doing it so
  9288. 5:57:03we don't want that organize a weekly
  9289. 5:57:05we're not sure if weekly is
  9290. 5:57:07enough all right to address all the and
  9291. 5:57:11if you have to make these decisions it
  9292. 5:57:13might become a problem because in this
  9293. 5:57:15one you're going to be making them at
  9294. 5:57:17once a week and then teams might be
  9295. 5:57:20waiting what if they need a decision
  9296. 5:57:21Monday and you only do it on
  9297. 5:57:23Fridays a critical path well this one
  9298. 5:57:26here is not going to solve the problem
  9299. 5:57:28all right this is not this is going to
  9300. 5:57:29tell us where the delay is we don't need
  9301. 5:57:31to do this we already know where the
  9302. 5:57:33delay is it's in those decision making
  9303. 5:57:35the best here we can do is pass off some
  9304. 5:57:38of the
  9305. 5:57:39smaller right notice it says significant
  9306. 5:57:42slowdown due to numerous
  9307. 5:57:46minor right approve of these Minor
  9308. 5:57:49Adjustments give that over to the team
  9309. 5:57:51and Trust the team is going to do a good
  9310. 5:57:52job with them they can see the best
  9311. 5:57:56answer
  9312. 5:57:58177 in the midst of a complex IT project
  9313. 5:58:01feedback from an executive sponsor
  9314. 5:58:03indicates dissatisfaction with the
  9315. 5:58:05detailing nature of the project updates
  9316. 5:58:09which they find cumbersome and
  9317. 5:58:10distracting from Key insights what
  9318. 5:58:13measure should the project manager
  9319. 5:58:14Implement to refine the communication
  9320. 5:58:17process with the executive
  9321. 5:58:20sponsor transition to a streamline
  9322. 5:58:23weekly email summary highlighting
  9323. 5:58:25critical points and decisions needed all
  9324. 5:58:27right utilize a project management tool
  9325. 5:58:30that allows a sponsor to view realtime
  9326. 5:58:32updates that they're convenient okay uh
  9327. 5:58:36conduct a detailed discussion with a
  9328. 5:58:37sponsor identify their preference for
  9329. 5:58:39information and Report format
  9330. 5:58:41okay scheduled brief Focus update calls
  9331. 5:58:45with sponsor to review major milestones
  9332. 5:58:48and address any concern this one not too
  9333. 5:58:52difficult here's what if you notice in
  9334. 5:58:55this question the sponsor basically this
  9335. 5:59:00satisfaction with the project updates
  9336. 5:59:03the best thing here you can do is meet
  9337. 5:59:04with them and ask them what is it that
  9338. 5:59:07you want when do you want it how do you
  9339. 5:59:10want it who should send it to you in
  9340. 5:59:12what format do you want it in notice in
  9341. 5:59:15this one you're choosing for them you're
  9342. 5:59:17choosing for them and you're choosing
  9343. 5:59:19for them you know one of the tips I'm
  9344. 5:59:21going to give you guys to this test
  9345. 5:59:23is if you find choices are all the same
  9346. 5:59:26if you find like two choices that pretty
  9347. 5:59:28much doing the same thing it's probably
  9348. 5:59:29not the answer because you can only
  9349. 5:59:31choose one unless the question says
  9350. 5:59:32choose two of those in this one here
  9351. 5:59:35we're working with sponsorer we're
  9352. 5:59:37tailoring the communication to the
  9353. 5:59:39sponsorer preference Mak can C the best
  9354. 5:59:43answer
  9355. 5:59:44178 during an iterative development
  9356. 5:59:48project for a new software tool a
  9357. 5:59:50developer who was recently added to the
  9358. 5:59:53team suggests implementing a cut and
  9359. 5:59:56cutand Edge testing technique that diff
  9360. 5:59:58significantly from the project standard
  9361. 6:00:01practices the rest the rest of the team
  9362. 6:00:04has expressed reluctance to to deviate
  9363. 6:00:06from n methods what should the project
  9364. 6:00:08manager do to address the teams
  9365. 6:00:10reluctance and explore the potential of
  9366. 6:00:12the new method instruct the new
  9367. 6:00:14developer to maintain the status quo to
  9368. 6:00:16preserve team Harmony and project uh
  9369. 6:00:19Pace maybe assign the developer to less
  9370. 6:00:23critical task to avoid any potential
  9371. 6:00:24disruptions to the established
  9372. 6:00:26testing okay I'm not sure that I'm not
  9373. 6:00:29sure about that one facilitate a
  9374. 6:00:31discussion where the new developer can
  9375. 6:00:32present the proposed tesed method
  9376. 6:00:36detailing its advantages and imple and
  9377. 6:00:39implementation process all right
  9378. 6:00:41recommend the developer prepare a detail
  9379. 6:00:43report on the proposed method for review
  9380. 6:00:45at the Project's conclusion best answer
  9381. 6:00:48here guys is going to be that's right
  9382. 6:00:50don't shut the person down okay first of
  9383. 6:00:52all if you do
  9384. 6:00:54a you're telling developer hey I don't
  9385. 6:00:57want to hear you we're going to continue
  9386. 6:00:59doing this you have to do it our way
  9387. 6:01:01don't do that you see anytime people
  9388. 6:01:04want to change the world somebody comes
  9389. 6:01:05up with some crazy new idea the rest of
  9390. 6:01:07the world or majority of the world says
  9391. 6:01:09hey that's crazy we don't want to do
  9392. 6:01:10that but until that person proves it
  9393. 6:01:12they're probably going to get a lot of
  9394. 6:01:13push back even though it was an amazing
  9395. 6:01:15thing so in this one you don't want to
  9396. 6:01:17just tell the person
  9397. 6:01:19no and B I said hey I don't know about
  9398. 6:01:21that one because you're basically firing
  9399. 6:01:23the person from the task don't fire
  9400. 6:01:25anyone now notice although I D may not
  9401. 6:01:29look so bad but at the project
  9402. 6:01:30conclusion that means that this thing is
  9403. 6:01:32really beneficial no one gets to use it
  9404. 6:01:34have the developer meet to the team and
  9405. 6:01:36show them why this tool is amazing and
  9406. 6:01:39maybe the team will agree May con seeed
  9407. 6:01:41the best
  9408. 6:01:44answer
  9409. 6:01:45179 ahead of a uh crucial update
  9410. 6:01:50meeting uh a project manager learns
  9411. 6:01:54about a potential unforeseen delay in a
  9412. 6:01:56project segment that involves an
  9413. 6:01:58external
  9414. 6:01:59contractor the full extent of how this
  9415. 6:02:02will affect the project timeline is not
  9416. 6:02:04yet known what two action should the
  9417. 6:02:06project man take before addressing this
  9418. 6:02:07in meum
  9419. 6:02:09eight lays out with the external
  9420. 6:02:11contractor to understand the reasons
  9421. 6:02:13behind the delay perform a detailed
  9422. 6:02:15assessment to gauge the overall impact
  9423. 6:02:17of the delay on the project delay the
  9424. 6:02:19discussion until stakeholders notice to
  9425. 6:02:22delay themselves compare the situation
  9426. 6:02:25with a documented outcome from similar
  9427. 6:02:27incidents in all their projects record a
  9428. 6:02:30delay in the project risk register and
  9429. 6:02:32discuss it openly in the stakeholder
  9430. 6:02:33meeting all right let's see what answer
  9431. 6:02:35you you guys have notice it
  9432. 6:02:38says project law about an un potential
  9433. 6:02:41unforeseen delay all right with an
  9434. 6:02:44external contractor what are we going to
  9435. 6:02:45do
  9436. 6:02:46well the first thing here you want to do
  9437. 6:02:49is you want to perform a detail how is
  9438. 6:02:51this going to impact the delay on the
  9439. 6:02:53project and you want to record this in
  9440. 6:02:55the risk register why in the risk
  9441. 6:02:56register see this word potential this is
  9442. 6:02:59not an issue right you don't want to put
  9443. 6:03:01this this is nowhere near an issue this
  9444. 6:03:03is a the moment you see potential you
  9445. 6:03:05you know this is a
  9446. 6:03:07risk uh you don't want to lay on with
  9447. 6:03:09the external to understand the reason
  9448. 6:03:11well perform an assessment
  9449. 6:03:14first delay the discussion until the
  9450. 6:03:17stakeholders notice the delay no this
  9451. 6:03:20means you're just letting it be delayed
  9452. 6:03:21you're not taking proactive actions
  9453. 6:03:23compare this situation with documented
  9454. 6:03:25outcomes some similar incident although
  9455. 6:03:27I like that answer see how this is going
  9456. 6:03:29to affect this project first and of
  9457. 6:03:31course put in the risk register once you
  9458. 6:03:33do these two maybe then we can go back
  9459. 6:03:35and talk with the contractor and so on
  9460. 6:03:37making B and E the best best answer
  9461. 6:03:42180 at a conclusion of an Enterprise
  9462. 6:03:44software implementation project a
  9463. 6:03:47department head suggests the addition of
  9464. 6:03:49a new analytics feature to improve data
  9465. 6:03:52visualization capabilities the feature
  9466. 6:03:54was not covered in the Project's initial
  9467. 6:03:56scope but is considered by the
  9468. 6:03:58department head to be straight forward
  9469. 6:04:00enhancement that can be managed by the
  9470. 6:04:02current IT
  9471. 6:04:03staff what action should should the
  9472. 6:04:05project manager take in response to the
  9473. 6:04:07Department's head
  9474. 6:04:09suggestion a assess the feasibility of
  9475. 6:04:13incorporating new analytics feature
  9476. 6:04:15within the existing projects without
  9477. 6:04:17formalizing it consult with the finance
  9478. 6:04:20team to assess the potential financial
  9479. 6:04:23implications and budget adjustments
  9480. 6:04:26required for additional feature
  9481. 6:04:28coordinator meeting with the key
  9482. 6:04:29stakeholders to evaluate the added value
  9483. 6:04:32versus the effort and risk of
  9484. 6:04:34incorporating draft supplemental Charter
  9485. 6:04:36for an analytics feature addition
  9486. 6:04:38pending executive approval all right
  9487. 6:04:41guys best answer here is going to be did
  9488. 6:04:43you say that is
  9489. 6:04:45correct this is a straightforward
  9490. 6:04:47question lot of big words a lot of words
  9491. 6:04:49in this question it's a feature that
  9492. 6:04:52wasn't in the initial scope you want to
  9493. 6:04:54add it to the scope well then how
  9494. 6:04:57feasible is it how is it going to affect
  9495. 6:04:59the um how is it going to affect the
  9496. 6:05:02project but you don't want to formalize
  9497. 6:05:03it notice without formalizing it you
  9498. 6:05:06can't formalize a change to a scope if
  9499. 6:05:08it's a traditional project it needs to
  9500. 6:05:10change control needs to go through the
  9501. 6:05:11Change Control both project sponsors to
  9502. 6:05:13get approved if it's an agile project
  9503. 6:05:15you're going need to get it through the
  9504. 6:05:17product owner so assess it but don't
  9505. 6:05:20formalize it making that the best answer
  9506. 6:05:23consult with the team to assess I like
  9507. 6:05:25this one here but this one here looks at
  9508. 6:05:28the entire thing of the feature not just
  9509. 6:05:29a part of it this one here is looking
  9510. 6:05:31more for just budgets um this one here
  9511. 6:05:34is added value evaluate the added value
  9512. 6:05:37versus the efforts and risk you have to
  9513. 6:05:39look at not just that but the entire
  9514. 6:05:42thing uh draft a supplemental Charter
  9515. 6:05:45this doesn't need a chter project is
  9516. 6:05:46already started making a the best answer
  9517. 6:05:49181 as part of an initiative to upgrade
  9518. 6:05:53an educational institution digital
  9519. 6:05:55infrastructure a department head
  9520. 6:05:57proposes the integration of an AI based
  9521. 6:06:00learning assistant which was not
  9522. 6:06:02included the initial project scope the
  9523. 6:06:04department had also so is also unsure if
  9524. 6:06:07the Project's investors would agree to
  9525. 6:06:08the necessary budget increase what
  9526. 6:06:11initial all right initial action should
  9527. 6:06:13the project manager to take regarding
  9528. 6:06:15the proposed integration assess a
  9529. 6:06:17feasibility study to explore the
  9530. 6:06:18technical and financial aspect of addin
  9531. 6:06:20the I based lawning system estimate the
  9532. 6:06:23potential impact on the project budgets
  9533. 6:06:25timelines for
  9534. 6:06:26incorporating the AI laar assistant
  9535. 6:06:28consult with the team to assess how the
  9536. 6:06:30integration could affect the overall
  9537. 6:06:32project conduct an assessment of the
  9538. 6:06:34proposed addition impact on a project
  9539. 6:06:37all these answers are pretty good I
  9540. 6:06:39think they're all good but one of them
  9541. 6:06:41is better because if you notice one of
  9542. 6:06:44them includes the team in this one it
  9543. 6:06:47said what initial uh action should the
  9544. 6:06:50PM take in this one it seems like you're
  9545. 6:06:53doing it you're doing it and you're
  9546. 6:06:56doing it you know who's the best person
  9547. 6:06:59to tell you how something is going to
  9548. 6:07:01affect the project the experts and the
  9549. 6:07:04experts are the people people that's
  9550. 6:07:05working on the task the team
  9551. 6:07:09themselves so I would say definitely go
  9552. 6:07:11with the team here and notice this is
  9553. 6:07:12the overall project this one here is
  9554. 6:07:15looking at more Technical and financial
  9555. 6:07:17this is just budget and time but what
  9556. 6:07:19happens with quality what happens with
  9557. 6:07:21risk what happens with vendor and
  9558. 6:07:23procurement so there's a lot of other
  9559. 6:07:24areas that you need to look
  9560. 6:07:26at we can see the best
  9561. 6:07:29answer 182 in the roll out of a critical
  9562. 6:07:33update to an e-commerce platform the
  9563. 6:07:36project manager is presented with
  9564. 6:07:38several pressing issues there's an
  9565. 6:07:40immediate need for expertise in cyber
  9566. 6:07:42security due to new threats significant
  9567. 6:07:45Personnel shortages are on Horizon
  9568. 6:07:47including the exit of the product owner
  9569. 6:07:49okay this is a bad project right here
  9570. 6:07:51guys and a new data security law has
  9571. 6:07:53been passed o what should the project
  9572. 6:07:55manager's direct
  9573. 6:07:56Focus to ensure the project remains on
  9574. 6:08:00course uh initiate a search for a cyber
  9575. 6:08:03security expert to fortify the platform
  9576. 6:08:05against I like that begin the transition
  9577. 6:08:07process for a new product owner to
  9578. 6:08:09ensure strategic project oversight
  9579. 6:08:11continues good start the process to
  9580. 6:08:14secure a new it support contractor or
  9581. 6:08:17renew the existing one for
  9582. 6:08:18uninterruptible services resolve uh
  9583. 6:08:21identify Regulatory Compliance issu to
  9584. 6:08:23prevent any legal or operational
  9585. 6:08:26setbacks this question is difficult
  9586. 6:08:30because it's not there isn't a choice
  9587. 6:08:32here that really fixes them all right
  9588. 6:08:36you got a couple of choice here you have
  9589. 6:08:39cyber you you need a cyber security
  9590. 6:08:43expert there is a significant Personnel
  9591. 6:08:45change on the horizon right especially
  9592. 6:08:47your product owner and there's a new
  9593. 6:08:49cyber security law that's passed what
  9594. 6:08:51should you focus on right and the
  9595. 6:08:53choices are basically going to go into
  9596. 6:08:55and tell you there's like three or four
  9597. 6:08:57things here and they're going to tell
  9598. 6:08:59you all three or four things the one you
  9599. 6:09:00should focus on is the law no project
  9600. 6:09:04should be progressing if that project is
  9601. 6:09:06breaking the law This falls into the
  9602. 6:09:07domain
  9603. 6:09:09of business environment if a project is
  9604. 6:09:12out of compliance that project should be
  9605. 6:09:13stopped no project should be breaking
  9606. 6:09:15the law so if you're progressing on
  9607. 6:09:17something that's breaking the law that
  9608. 6:09:18project needs to get stopped in this
  9609. 6:09:20this is dealing with the cyber security
  9610. 6:09:23expert this is finding a new product
  9611. 6:09:25owner this here is something to do with
  9612. 6:09:27a contractor the best thing here you can
  9613. 6:09:29do is to check you know if you had to
  9614. 6:09:31choose one of these things would it be
  9615. 6:09:34insure the cyber security law would it
  9616. 6:09:37be getting the product owner or getting
  9617. 6:09:38the expert in cyber security best answer
  9618. 6:09:41was ensuring you're in
  9619. 6:09:44compliance
  9620. 6:09:46183 as a project unfolds for a global
  9621. 6:09:49Health Initiative the project manager
  9622. 6:09:51identifies the that the current online
  9623. 6:09:54collaboration tools are hindering
  9624. 6:09:56effective Communications across time
  9625. 6:09:59zones affecting the Project's progress
  9626. 6:10:02the team suggests that it CH that it
  9627. 6:10:04change in digital tools could
  9628. 6:10:06significantly improve Project Dynamics
  9629. 6:10:08and cross team interactions what should
  9630. 6:10:11the project manager do to ensure the
  9631. 6:10:13selection of the most effective tools
  9632. 6:10:16for the
  9633. 6:10:17team uh trial several top rated uh
  9634. 6:10:22collaboration tools on a small scale to
  9635. 6:10:25gauge Effectiveness before a full team
  9636. 6:10:27roll
  9637. 6:10:28out delegate the decision to the
  9638. 6:10:30organization technology Advisory board
  9639. 6:10:32for expert organize a series of Workshop
  9640. 6:10:34aimed that maximizing the current tools
  9641. 6:10:36capabilities before considering you one
  9642. 6:10:38organize a meeting with the entire team
  9643. 6:10:40to assess needs evaluate alternative
  9644. 6:10:42decide on the best collaboration tool
  9645. 6:10:44follow the mindset on this one this one
  9646. 6:10:45is not too difficult what's the best
  9647. 6:10:48tool work with the team let the team
  9648. 6:10:50tell you what's the best tool in this
  9649. 6:10:52one here this is more like you're you're
  9650. 6:10:55doing it yourself before you do a full
  9651. 6:10:57team roll out in this one here delegate
  9652. 6:11:00the decision to that you're giving away
  9653. 6:11:01the decision you're not incorporating
  9654. 6:11:03the team the best tool is dependent on
  9655. 6:11:05the person not everybody likes every
  9656. 6:11:07tool let the team tell you what they
  9657. 6:11:08like organize a series of Workshop
  9658. 6:11:11before considering noce maximizing
  9659. 6:11:13occurrent how about if we see what's out
  9660. 6:11:15there first bring the team in make
  9661. 6:11:17indeed the best
  9662. 6:11:19answer 184 for the Implement for the
  9663. 6:11:23implementation of a sophisticated
  9664. 6:11:25security software across multiple
  9665. 6:11:27departments the selected external
  9666. 6:11:30provider asserts that their solution is
  9667. 6:11:32plug andplay negating the need for any
  9668. 6:11:34in-depth involvement or validation
  9669. 6:11:37activities from the company the project
  9670. 6:11:39manager aiming to ensure the solutions
  9671. 6:11:41capability and Effectiveness decides to
  9672. 6:11:43confirm these assertions with the
  9673. 6:11:46organization stakeholders what initial
  9674. 6:11:49step should the project manager take to
  9675. 6:11:50guarantee alignment and meet the
  9676. 6:11:52organizational standards convey a
  9677. 6:11:54comprehensive briefing with key
  9678. 6:11:55stakeholders consolidate on standard and
  9679. 6:11:57set unified expectation for the project
  9680. 6:12:00draft a contingency plan to address
  9681. 6:12:04potential gaps that that might emerge
  9682. 6:12:06post implementation choose a preliminary
  9683. 6:12:09phase of collaboration between the
  9684. 6:12:10vendor's technical team and the
  9685. 6:12:12organization's it Department send out a
  9686. 6:12:14survey to department heads to collect
  9687. 6:12:17initial Impressions and concerns
  9688. 6:12:19regarding the vendor's claim all right
  9689. 6:12:22what are we going to do here guys the
  9690. 6:12:23best answer is going to be a that is
  9691. 6:12:26correct
  9692. 6:12:28notice I want a comprehensive briefing
  9693. 6:12:30right we want to consolidate your
  9694. 6:12:32understanding and set the expectations
  9695. 6:12:33on this project the is saying hey you
  9696. 6:12:36don't need to do anything we want to
  9697. 6:12:37make sure the stakeholders understand
  9698. 6:12:38that this one here draft a contingency
  9699. 6:12:41plan to address potential
  9700. 6:12:43gaps uh we're not sure what those gaps
  9701. 6:12:46are yet draft a preliminary propose a
  9702. 6:12:49preliminary phase of collaboration and
  9703. 6:12:51the organization's it well you got to
  9704. 6:12:53get not just it but the actual
  9705. 6:12:55stakeholders on top too sponsors and so
  9706. 6:12:57on we don't want just a survey a you
  9707. 6:13:00know what's better than a survey a good
  9708. 6:13:02comprehensive briefing with them versus
  9709. 6:13:05just a survey you can need a b
  9710. 6:13:08answer
  9711. 6:13:10185 a technology firm is transitioning
  9712. 6:13:14its software development practice to
  9713. 6:13:15Agile methodologies to improve its
  9714. 6:13:18productive its product development life
  9715. 6:13:21cycle the move aims to make the progress
  9716. 6:13:23more Dynamic and responsive to customer
  9717. 6:13:25needs and Market truns what is the
  9718. 6:13:27principal advantage of adapting agile in
  9719. 6:13:30this agile methodologies in this context
  9720. 6:13:33enhance the efficiency of the
  9721. 6:13:35development cycle to reduce time to
  9722. 6:13:37market for new features all right
  9723. 6:13:39Implement a structured risk management
  9724. 6:13:42approach to significantly uh decrease
  9725. 6:13:45project
  9726. 6:13:46uncertainties prioritize and deliver
  9727. 6:13:48product features in alignment with their
  9728. 6:13:50value on customer
  9729. 6:13:51demand reduce operation by by optimizing
  9730. 6:13:55team workflows on resources okay there's
  9731. 6:13:57two good answers and there's two bad
  9732. 6:13:59answers let's see what you guys got
  9733. 6:14:01let's Point them out first of all two
  9734. 6:14:03bad answers
  9735. 6:14:05adile really doesn't have a massive
  9736. 6:14:07structure approach so let's get rid of
  9737. 6:14:09this it may or may not increase or
  9738. 6:14:13decrease expenses is not something that
  9739. 6:14:16you can gauge right off the bat but
  9740. 6:14:20agile does do two
  9741. 6:14:22things it does lead to things get into
  9742. 6:14:26the market quicker and it also
  9743. 6:14:29prioritizes features leading to the most
  9744. 6:14:33valuable product coming out first so
  9745. 6:14:35that brings me to a or C if you choose a
  9746. 6:14:38or C you're probably if you got a you
  9747. 6:14:39probably say hey what is what did what
  9748. 6:14:42happened here well you have to ask
  9749. 6:14:45yourself what's better in agile is it
  9750. 6:14:48the whole concept of get things to
  9751. 6:14:51Market first or is it get the most
  9752. 6:14:53valuable things to Market first if you
  9753. 6:14:56said well let's get the most valuable
  9754. 6:14:57thing to Market first that's the value
  9755. 6:14:59of agile agile is about developing the
  9756. 6:15:01most valuable thing first not
  9757. 6:15:03necessarily to get it to the market
  9758. 6:15:06first it's to develop the most valuable
  9759. 6:15:08thing first making a a better c a better
  9760. 6:15:11answer than
  9761. 6:15:14a
  9762. 6:15:16186 during the critical phase of a green
  9763. 6:15:19energy plan construction project it
  9764. 6:15:22becomes evident that the project that
  9765. 6:15:24the project may not adhere to the
  9766. 6:15:26initially planned schedule this
  9767. 6:15:29situation arises even as the project
  9768. 6:15:31team has been performing efficiently
  9769. 6:15:33making their completion of several
  9770. 6:15:35important fa marking the completion of
  9771. 6:15:37several important
  9772. 6:15:38phases what is the first course of
  9773. 6:15:41action a project
  9774. 6:15:42manager what is the first course for the
  9775. 6:15:45project manager to address the Lumen
  9776. 6:15:46schedule delay inform Senior Management
  9777. 6:15:49and key stakeholders about the potential
  9778. 6:15:50delay suggesting a reassessment of the
  9779. 6:15:54project timeline summarize the project
  9780. 6:15:56achievements to date and expected imp
  9781. 6:15:59impact on the delay of the delay in
  9782. 6:16:02detailing in detailed breef briefing for
  9783. 6:16:05the project board revise the project
  9784. 6:16:07timeline with lead Engineers to pinpoint
  9785. 6:16:09specific tasks that are causing the
  9786. 6:16:11delay and their potential remedies
  9787. 6:16:14review the project the current project
  9788. 6:16:17timelines um with I should say with the
  9789. 6:16:19entire team what answer do you guys have
  9790. 6:16:21here guys the best answer guys is going
  9791. 6:16:23to be
  9792. 6:16:25D all right I did miss a word here it
  9793. 6:16:27should be with the entire team here okay
  9794. 6:16:30sorry about that one word we missed
  9795. 6:16:31there okay so notice the first course of
  9796. 6:16:36action all right you really got to put
  9797. 6:16:39this thing in order anytime you guys see
  9798. 6:16:40this thing that
  9799. 6:16:42says uh what do you do first Sometimes
  9800. 6:16:45they going to be choices and you got to
  9801. 6:16:46say okay which one am I going to do
  9802. 6:16:47first of those four choices because you
  9803. 6:16:50may say well I have to assess something
  9804. 6:16:51first yeah but um I have to revise
  9805. 6:16:55something you're absolutely correct and
  9806. 6:16:56that's what we're doing here you notice
  9807. 6:16:58in this one before you inform senior
  9808. 6:16:59manager you have to assess the problem
  9809. 6:17:02summarize the achievement and the
  9810. 6:17:03expected impact before you do that you
  9811. 6:17:06would have you should meet with the team
  9812. 6:17:08first right you should meet with the
  9813. 6:17:10team before you do
  9814. 6:17:12this revise the timeline no you just
  9815. 6:17:16can't revise the timeline you just can't
  9816. 6:17:17change the time this requires a whole
  9817. 6:17:19change request so D is the best option
  9818. 6:17:21here not you just can't go and change an
  9819. 6:17:23entire timeline like that and always
  9820. 6:17:26meet with the team revise reassess
  9821. 6:17:29assess the situation before taking an
  9822. 6:17:32action 187
  9823. 6:17:36aim the roll out of a new software
  9824. 6:17:37platform designed to enhance customer
  9825. 6:17:40engagement for a retail chain the lead
  9826. 6:17:43role transitions due to a
  9827. 6:17:45promotion the lead role transition due
  9828. 6:17:48to
  9829. 6:17:49promotion the incoming project manager
  9830. 6:17:51tasks with guid in the project to its
  9831. 6:17:53completion under a hybrid management
  9832. 6:17:55framework what document should the new
  9833. 6:17:57manage manager review first to
  9834. 6:18:00understand the Strategic benefits and
  9835. 6:18:01objective of a project the road map the
  9836. 6:18:04business case strategic alignment
  9837. 6:18:05documents technical design documents
  9838. 6:18:08now this question you see you're going
  9839. 6:18:11to get questions on your exam where like
  9840. 6:18:13a whole portion of the question is not
  9841. 6:18:14even needed the real question is here
  9842. 6:18:17all of this is just saying that there's
  9843. 6:18:18a new project manager that's what this
  9844. 6:18:20is saying so I'm going to throw that
  9845. 6:18:21paragraph out the real thing is what
  9846. 6:18:24should the project what what should a
  9847. 6:18:25new project manager review first you
  9848. 6:18:29want to understand the benefits and
  9849. 6:18:31objectives of this project and that is
  9850. 6:18:33stored in a document we call all correct
  9851. 6:18:35the business case the business case will
  9852. 6:18:38store that the program road map is not
  9853. 6:18:41even a project road map the program
  9854. 6:18:42roadmap are all the different projects
  9855. 6:18:44on the program to accomplish its
  9856. 6:18:46strategic
  9857. 6:18:48goal strategic alignment document really
  9858. 6:18:51no such thing or technical design
  9859. 6:18:52document this is how it will be
  9860. 6:18:53technically developed use the business
  9861. 6:18:55case in this
  9862. 6:18:58one
  9863. 6:19:00188 embarking on an enterprise-wide
  9864. 6:19:02software upgrade project this distinct
  9865. 6:19:05distinct
  9866. 6:19:07distinctively different from the
  9867. 6:19:09organization's usual it initiatives the
  9868. 6:19:12project manager's task with selecting
  9869. 6:19:14project management methodologies and
  9870. 6:19:16tools that best align with this specific
  9871. 6:19:19venture's needs who should be the
  9872. 6:19:21primary responsibility for choosing the
  9873. 6:19:22project management methodologies and
  9874. 6:19:24tools tailored to this distinctive
  9875. 6:19:26project it's a good
  9876. 6:19:27question the LA really it's in the last
  9877. 6:19:30part right like who's really responsible
  9878. 6:19:32for choosing a project management
  9879. 6:19:33methodology you should be key
  9880. 6:19:36stakeholders excuse me on that uh from
  9881. 6:19:38each department should collaboratively
  9882. 6:19:40determine the methodology and tools for
  9883. 6:19:42the project the project manager and the
  9884. 6:19:44team are to strictly utilize the
  9885. 6:19:46industry standard set of methodologies
  9886. 6:19:48and
  9887. 6:19:49tools the chief technology officer is
  9888. 6:19:52the highest Authority on the technology
  9889. 6:19:53project should set the methodologies and
  9890. 6:19:56tools the project manager and the
  9891. 6:19:58project team should identify and select
  9892. 6:20:00the methodologies and tools that best
  9893. 6:20:02suit the project so this really is who
  9894. 6:20:04should choose the right methodology well
  9895. 6:20:05I'll tell you guys right off the bat it
  9896. 6:20:07is not key stakeholders from departments
  9897. 6:20:11it you shouldn't just use industry
  9898. 6:20:12standards or the CTO you and your team
  9899. 6:20:15should work together to select the best
  9900. 6:20:18methodology for your
  9901. 6:20:19project only the team really understands
  9902. 6:20:22the work and the project manager is
  9903. 6:20:24going to work with the team so work
  9904. 6:20:25together on that every project is unique
  9905. 6:20:28every project is
  9906. 6:20:30different in spearheading a ground
  9907. 6:20:33ground breaking environmental let me
  9908. 6:20:36stop right here for a second guys if you
  9909. 6:20:37hear me mispronouncing words I've been
  9910. 6:20:39doing this all day yes these videos are
  9911. 6:20:41recorded in one session and these words
  9912. 6:20:44are massively
  9913. 6:20:46large it's easy to read it in your mind
  9914. 6:20:49when you're reading it nonstop like this
  9915. 6:20:52it's tough it it's tough it's tough
  9916. 6:20:55uh it's tough let's get back to this
  9917. 6:20:57video man don't don't take this out you
  9918. 6:20:59know what let me give you guys a quick
  9919. 6:21:01lesson we got time in this um when
  9920. 6:21:04you're reading this exam I have been
  9921. 6:21:07added right now for about a 100 of these
  9922. 6:21:11that it's recorded all in one day and
  9923. 6:21:13I'm going to tell you guys something uh
  9924. 6:21:15it is very very difficult uh to do this
  9925. 6:21:20I imagine on a real test and me reading
  9926. 6:21:22out me read see I can't even pronounce
  9927. 6:21:24it anymore I need to take a break now me
  9928. 6:21:26reading the words out loud is even more
  9929. 6:21:28difficult on the real exam take breaks
  9930. 6:21:30you're going to get breaks take it I'm
  9931. 6:21:31telling you guys I can't sit here and do
  9932. 6:21:34this and I wrote these questions you
  9933. 6:21:36guys are going to see these questions
  9934. 6:21:37for the first time you're going to be
  9935. 6:21:38critical thinking I'm not critical
  9936. 6:21:40thinking I'm just memorizing the answer
  9937. 6:21:41because I I wrote them for you guys take
  9938. 6:21:43your breaks I'm telling you guys you
  9939. 6:21:45need them like I need it right now I'm
  9940. 6:21:46going to have a real hard time at 189
  9941. 6:21:48190 I'm gon to have to take a break come
  9942. 6:21:50back to to the last set
  9943. 6:21:52here editor don't cut this section out
  9944. 6:21:55this is me uh being real with them let's
  9945. 6:21:59get back to this finish this up inspir
  9946. 6:22:01headen a groundbreaking environmental
  9947. 6:22:04initiative within a large organization a
  9948. 6:22:06lot of words there the project manager
  9949. 6:22:08faces the challenge of ensuring clear
  9950. 6:22:11and effective communication amongst team
  9951. 6:22:12members from various disciplines
  9952. 6:22:14including engineering environmental
  9953. 6:22:16science and project management what
  9954. 6:22:19should the project manager do develop
  9955. 6:22:22individualized communication management
  9956. 6:22:24plans that cater to the specific
  9957. 6:22:26informational needs preference to each
  9958. 6:22:28project team
  9959. 6:22:29discipline inst Institute a centralized
  9960. 6:22:33project information dashboard for
  9961. 6:22:34realtime updates and transparen and
  9962. 6:22:36across the team
  9963. 6:22:38disciplines conduct interdisciplinary
  9964. 6:22:41workshops to Foster Mutual understanding
  9965. 6:22:43and collaborative problem solving
  9966. 6:22:45problem solving skills amongst team
  9967. 6:22:46members all right assigning
  9968. 6:22:47communication Le Aon within each
  9969. 6:22:50discipline to streamline the workflow of
  9970. 6:22:53project information and facilitate
  9971. 6:22:56interdepartmental understanding okay
  9972. 6:22:58guys best answer here all right notice
  9973. 6:23:01you got teams from various discipline
  9974. 6:23:03the best answer answer here guys is you
  9975. 6:23:06want to have a communication management
  9976. 6:23:08plan that is very catered to everyone on
  9977. 6:23:11a project keep in mind the communication
  9978. 6:23:13is tailored to the stakeholders it's not
  9979. 6:23:15just a centralized thing or it's not
  9980. 6:23:17just one method to everything like this
  9981. 6:23:19here this is one
  9982. 6:23:21method this here is interdisciplinary
  9983. 6:23:24Workshop this one here is bringing
  9984. 6:23:26people more like together but it should
  9985. 6:23:27be customized we don't want just a
  9986. 6:23:29liaison we want to have everyone get in
  9987. 6:23:32the right form of communication make hey
  9988. 6:23:34the best
  9989. 6:23:36answer oh thank God it's a short
  9990. 6:23:39question 190 following the approval of
  9991. 6:23:42the project Charter the project manager
  9992. 6:23:43begins working with the team to organize
  9993. 6:23:46the project Scopes into smaller detailed
  9994. 6:23:48components what is a project manager
  9995. 6:23:51primally working on creating a project
  9996. 6:23:53racy chart so this stands for
  9997. 6:23:55responsible accountable consultant
  9998. 6:23:56inform form a project schedule Network
  9999. 6:23:59diagram work breakdown structure
  10000. 6:24:02WBS uh already
  10001. 6:24:04scheduling the uh execution phases for
  10002. 6:24:07the project task best answer guys is of
  10003. 6:24:09course the WBS if you are
  10004. 6:24:12decomposing uh the scope when you
  10005. 6:24:14decompose the scope you're basically
  10006. 6:24:16creating the work packages that builds
  10007. 6:24:19up on the WPS this is to assign people
  10008. 6:24:21to work they're not doing that here this
  10009. 6:24:24is to build a schedule you got to finish
  10010. 6:24:27the plan before you build a schedule you
  10011. 6:24:29can see the best answer all right 191
  10012. 6:24:31here we go on a high stakes software
  10013. 6:24:33development at out project the project
  10014. 6:24:35manager notices a pattern where numerous
  10015. 6:24:37team members are either late or entirely
  10016. 6:24:39missed the virtual entirely missed the
  10017. 6:24:42daily virtual scrum designed to
  10018. 6:24:44facilitate project cohesion what action
  10019. 6:24:47should the project manager take to
  10020. 6:24:48enhance the efficiency and attendance of
  10021. 6:24:51these
  10022. 6:24:53sessions work with the team to identify
  10023. 6:24:55a project communication protocol that
  10024. 6:24:57will work with them to ensure timely
  10025. 6:24:59participation in the daily scrum all
  10026. 6:25:01right identify time that could
  10027. 6:25:03potentially incre increase attendance
  10028. 6:25:05and punctuality transition to an
  10029. 6:25:07asynchronous communication model to
  10030. 6:25:09allow team members to update their
  10031. 6:25:10status at their convenient solicit input
  10032. 6:25:13from stakeholders on efficient methods
  10033. 6:25:14to improve team engagement and meeting
  10034. 6:25:17with attendants now it really comes down
  10035. 6:25:19to two P two good questions first of all
  10036. 6:25:22which one should you there's two answers
  10037. 6:25:23you could eliminate first of all which
  10038. 6:25:25one can you eliminate did you get it
  10039. 6:25:27first one you should have eliminated was
  10040. 6:25:29B because you just can't Identify some a
  10041. 6:25:32time for the team it's an agile project
  10042. 6:25:34these are the daily standup meetings the
  10043. 6:25:35daily scrum is a daily standup meetings
  10044. 6:25:38work with the team on this an
  10045. 6:25:40asynchronous method doesn't work for a
  10046. 6:25:42daily scrum a daily scrum technically
  10047. 6:25:44should be a standup where everybody
  10048. 6:25:45talks it should be if it's virtual
  10049. 6:25:47everybody should be there now it really
  10050. 6:25:51came down to a or b and in this one
  10051. 6:25:54you're getting input from stakeholders
  10052. 6:25:55but it doesn't particularly say the team
  10053. 6:25:58maybe you're getting inputs from the
  10054. 6:26:00project uh the product owner or maybe
  10055. 6:26:01even the customers the best answer here
  10056. 6:26:03is to work with the team all right work
  10057. 6:26:04with the team come up with a good
  10058. 6:26:06protocol or a set of rules that they are
  10059. 6:26:08willing to follow that ensures that they
  10060. 6:26:11come and show up to the Sprint either on
  10061. 6:26:12time or just sh up so the best thing is
  10062. 6:26:14to work with the team don't just get an
  10063. 6:26:16input from everybody else get input from
  10064. 6:26:18the team in particular making a a better
  10065. 6:26:22answer than
  10066. 6:26:24D 192 a project manager discovers that
  10067. 6:26:27recent legislative updates necessitate
  10068. 6:26:30additional security enhancement to the
  10069. 6:26:31project although the development team is
  10070. 6:26:33incorpor prop these enhance enhancements
  10071. 6:26:36without exceeding their budget the
  10072. 6:26:38project manager realizes that the
  10073. 6:26:40allocated budget for quality insurance
  10074. 6:26:41and testing is quickly being depleted
  10075. 6:26:44due to these unplan requirements what
  10076. 6:26:46action should the project manager take
  10077. 6:26:49what actions should the project manager
  10078. 6:26:51take to manage the escalating cost
  10079. 6:26:53associated with the increased scope of
  10080. 6:26:55testing a propose a temporary
  10081. 6:26:58reallocation of resources from less
  10082. 6:27:00critical activities to support the
  10083. 6:27:02expanded testing requirements have the
  10084. 6:27:05sponsor analyze potential cost-saving
  10085. 6:27:07measures within the project to
  10086. 6:27:09reallocate funds towards the testing
  10087. 6:27:11budget submit a formal change request to
  10088. 6:27:13revive the cost based on accommodating
  10089. 6:27:15the extra expense incurred in the
  10090. 6:27:17testing adjust the Project's Financial
  10091. 6:27:19strategy to ensure the newly identified
  10092. 6:27:22testing needs are adequately funded
  10093. 6:27:24without compromising quality guys the
  10094. 6:27:26best answer here is going to be did you
  10095. 6:27:28get it yes so if there is something that
  10096. 6:27:32needs the project to in increase its
  10097. 6:27:34schedule increase its budget it's
  10098. 6:27:37important to get that approved you just
  10099. 6:27:40can't do it that's what a d is doing you
  10100. 6:27:43just can't adjust the financial Str you
  10101. 6:27:46just can't add money to the project and
  10102. 6:27:48this is not a job of the sponsor sponsor
  10103. 6:27:50is there to approve or disapprove not to
  10104. 6:27:52help you with
  10105. 6:27:53assessment and noticed a temporary
  10106. 6:27:56reallocation of resources this may
  10107. 6:27:57require change request the best thing
  10108. 6:27:59here to do submit a formal change
  10109. 6:28:01request to update that cost Baseline so
  10110. 6:28:04you can get those testing done C is the
  10111. 6:28:06best
  10112. 6:28:07answer 193 in the development stage of
  10113. 6:28:11an Innovative mobile application the
  10114. 6:28:13agile the agile project team discovers
  10115. 6:28:16the need for an advanced software
  10116. 6:28:18library that wasn't initially
  10117. 6:28:20anticipated which is critical for
  10118. 6:28:22enhancing the apps functionality what
  10119. 6:28:24should the project manager do to
  10120. 6:28:26effectively uh manage this unforeseen
  10121. 6:28:28requirement organize a strategic meeting
  10122. 6:28:30with the product owner to reassess the
  10123. 6:28:33project priorities and integrate the new
  10124. 6:28:34software Library update the project
  10125. 6:28:37timeline to reflect the expected delay
  10126. 6:28:39to the uh due to the integration of the
  10127. 6:28:41new software Library identify this new
  10128. 6:28:45need this new need as this new need
  10129. 6:28:48asset project risk seek immediate advice
  10130. 6:28:50from steering committee delegate the
  10131. 6:28:53task of integrating the new software
  10132. 6:28:54library to a specialist within within
  10133. 6:28:57the project Team without delay best
  10134. 6:28:59answer here guys if there is any kind of
  10135. 6:29:02things that needs to get added to an
  10136. 6:29:05adob project how do we know it's an adob
  10137. 6:29:07project it literally says the adob
  10138. 6:29:08project team if there's something that
  10139. 6:29:10needs to get added to the adob project
  10140. 6:29:12and particularly something added to the
  10141. 6:29:14scope it must go through the project the
  10142. 6:29:16product owner they have to agree with it
  10143. 6:29:18they have to add it in and then it has
  10144. 6:29:20to be reprioritized and the product
  10145. 6:29:23backlog you just can't update the
  10146. 6:29:25timeline you would need approval from
  10147. 6:29:27product owner identify this as a
  10148. 6:29:30identify this need as a project risk
  10149. 6:29:32well you notice they need need they need
  10150. 6:29:35this in order to keep going far is
  10151. 6:29:36critical for their to function the best
  10152. 6:29:39thing the best way to get this
  10153. 6:29:40Incorporated would be to added to the
  10154. 6:29:42product backlog delegate the task well
  10155. 6:29:45you never give away your task never just
  10156. 6:29:46give away your work make an a the best
  10157. 6:29:49answer
  10158. 6:29:51194 while working on a project the
  10159. 6:29:54client's request for additional changes
  10160. 6:29:56threaten to extend the Project's
  10161. 6:29:58timeline significantly the project
  10162. 6:30:00manager is exploring options to
  10163. 6:30:02accelerate the project time timeline to
  10164. 6:30:04accommodate these changes but there's
  10165. 6:30:06concerned about the potential for
  10166. 6:30:08increase overtime for the team what what
  10167. 6:30:11action should the project manager take
  10168. 6:30:12to keep the team motivated despite these
  10169. 6:30:14challenges offer a monetary incentive to
  10170. 6:30:17team members who agree to work extended
  10171. 6:30:18hours to meet the
  10172. 6:30:20deadline attempt to meet the timeline
  10173. 6:30:22regularly recognize team efforts
  10174. 6:30:24celebrate Milestones to maintain moral
  10175. 6:30:27challenges uh during during challenges
  10176. 6:30:30during challenging period reassigned
  10177. 6:30:32task to focus on high priority
  10178. 6:30:34deliverable and reduce the team workload
  10179. 6:30:36introduce monetary team building
  10180. 6:30:38activities to encourage collaboration
  10181. 6:30:40and increase motivation the best answer
  10182. 6:30:44here guys is going to be did you get it
  10183. 6:30:46yes this is the best answer here's
  10184. 6:30:48why
  10185. 6:30:50now read the question carefully the
  10186. 6:30:53question is what will keep them
  10187. 6:30:57motivated that's the question right the
  10188. 6:30:59question is what keeps your team
  10189. 6:31:00motivated they may have to work overtime
  10190. 6:31:04notice introduce mandatory team building
  10191. 6:31:07anything that's mandatory is probably
  10192. 6:31:09not going to be motivating it might lead
  10193. 6:31:12to more
  10194. 6:31:13demoralization Reign task to focus on
  10195. 6:31:16high PRI and reduce the team workload
  10196. 6:31:18although I like this it may not be
  10197. 6:31:20feasible in times like
  10198. 6:31:22this offer now it really I was thinking
  10199. 6:31:25A or B keep in mind that everyone is
  10200. 6:31:28incentivized by money and what if it's
  10201. 6:31:31the entire team and not just a few
  10202. 6:31:33people then a is not going to work but
  10203. 6:31:35what you could do is celebrate Milestone
  10204. 6:31:37recognize their effort just try to keep
  10205. 6:31:39them motivated which is what B is
  10206. 6:31:43doing 195 in a major software
  10207. 6:31:46development project the project manager
  10208. 6:31:48finds that several team members are
  10209. 6:31:50reluctant to to use new project
  10210. 6:31:52management software believing it to be
  10211. 6:31:54overly comp complicated and not
  10212. 6:31:56beneficial for their task what should
  10213. 6:31:58the project manager have done initially
  10214. 6:32:00to facilitate the adaptation of the new
  10215. 6:32:02software by the team encourage team
  10216. 6:32:04leaders to use the software in their
  10217. 6:32:06meetings to set an example for the rest
  10218. 6:32:07of the team Implement a reward system
  10219. 6:32:10for early adapters who effectively
  10220. 6:32:13integrate the soft integrate the
  10221. 6:32:15software into their
  10222. 6:32:17workflow conduct one-on-one sessions to
  10223. 6:32:19understand individual resistance and
  10224. 6:32:21tailor support
  10225. 6:32:23accordingly organize a comprehensive
  10226. 6:32:25training session to demonstrate the
  10227. 6:32:26functional benefits of the new software
  10228. 6:32:28best answer guys is going to be D that
  10229. 6:32:31is correct here's why
  10230. 6:32:34you got to read the question carefully
  10231. 6:32:35it says have initially done what you're
  10232. 6:32:40trying to do is prevent the problem not
  10233. 6:32:43fix the problem see fixes the problem we
  10234. 6:32:47don't want to fix the problem right now
  10235. 6:32:49we want to prevent it from
  10236. 6:32:51happening the others now encourage team
  10237. 6:32:54leaders this is not going to not because
  10238. 6:32:57of team leaders doing doesn't mean that
  10239. 6:32:59the other members see the benefits of it
  10240. 6:33:02versus the
  10241. 6:33:04inde everybody is seeing the benefits of
  10242. 6:33:07this thing maybe they're resistant
  10243. 6:33:08because they just don't know the
  10244. 6:33:09benefits of it Implement a reward system
  10245. 6:33:12not because you offer someone a reward
  10246. 6:33:14doesn't mean they see the benefit of it
  10247. 6:33:15they'll just use it just to get their
  10248. 6:33:16reward the best thing to do is to show
  10249. 6:33:19them the benefit let them see how it's
  10250. 6:33:20going to help them and they're more
  10251. 6:33:22likely to take in the software make and
  10252. 6:33:24deem the best
  10253. 6:33:27answer
  10254. 6:33:28196 on an infrastructure project to
  10255. 6:33:31upgrade City Water Systems the project
  10256. 6:33:33manager struggling to finalize the
  10257. 6:33:35project schedule due to unpredictable
  10258. 6:33:38regulatory review times and potential
  10259. 6:33:40delays in securing necessary
  10260. 6:33:42equipment what schedule and technique
  10261. 6:33:44should the project man adapt to to
  10262. 6:33:46manage the planet effectively under
  10263. 6:33:48these terms Rolland wave planning
  10264. 6:33:51backwards pass analysis uh dependency
  10265. 6:33:54structuring lag lead and lag
  10266. 6:33:56optimization now notice let's go over
  10267. 6:34:00this here for a
  10268. 6:34:01second unpredictable regulatory review
  10269. 6:34:05times and potential if something is
  10270. 6:34:07unpredictable review times if something
  10271. 6:34:09is
  10272. 6:34:10unpredictable you may not be able to
  10273. 6:34:13break down the work you may not be able
  10274. 6:34:14to schedule it right away you may not be
  10275. 6:34:16able to build a plan right away so you
  10276. 6:34:18have the plan to replan that's called
  10277. 6:34:21rolling wave plan and you plan as time
  10278. 6:34:23is progressing as time is progressing
  10279. 6:34:25things becomes more
  10280. 6:34:27clear that's basically the definition of
  10281. 6:34:30rolling wave planner
  10282. 6:34:31everyone uh backwards pass is to
  10283. 6:34:34calculate the critical path we not
  10284. 6:34:36that's not going to help us here
  10285. 6:34:38dependency structure is showing you what
  10286. 6:34:40task depends on what is
  10287. 6:34:43it uh finish to start start to start
  10288. 6:34:45type thing uh lags and Lead shows you
  10289. 6:34:49there any delays or overlap between tals
  10290. 6:34:51that's not going to help us here what we
  10291. 6:34:52need to do is we need to understand that
  10292. 6:34:53we can't plan for everything right away
  10293. 6:34:55let time progress and then we can plan
  10294. 6:34:57for
  10295. 6:34:57them 197 during the roll out of a new it
  10296. 6:35:01system within a large corporation the
  10297. 6:35:03project manager observes that
  10298. 6:35:05discussions and stakeholder meetings are
  10299. 6:35:07frequently derailed by a participant
  10300. 6:35:10who the the the can't pronounce that
  10301. 6:35:14word right now stop right here guys I'm
  10302. 6:35:16way too tired on this into technical
  10303. 6:35:19details uh irrelevant to the to the
  10304. 6:35:21meetings objectives the behavior is
  10305. 6:35:23causing meetings to overrun and is
  10306. 6:35:25reducing the time available to cover all
  10307. 6:35:27agenda items leading to dissatisfaction
  10308. 6:35:30about stakeholders so let's see what's
  10309. 6:35:32going on here we got one team member
  10310. 6:35:34that is going into too much technical
  10311. 6:35:36detail is probably not needed what
  10312. 6:35:38action should the project manager take
  10313. 6:35:39to ensure meetings are more focused and
  10314. 6:35:43productive emphasize the meeting agenda
  10315. 6:35:45at the start and kindly remind
  10316. 6:35:47participants to keep discussions on
  10317. 6:35:50topic allocate specific time for open
  10318. 6:35:52discussions at the end of the meeting to
  10319. 6:35:53cater to additional
  10320. 6:35:55topics introduce a me and co-
  10321. 6:35:58facilitator to help steer conversation
  10322. 6:35:59back to the agenda when they go off
  10323. 6:36:01course Implement a suggestion by for
  10324. 6:36:04topics that require further discussions
  10325. 6:36:05outside of the scheduled meeting this is
  10326. 6:36:07a good question actually because it has
  10327. 6:36:09quite a good set of tasks uh what should
  10328. 6:36:11you do to ensure meetings are more
  10329. 6:36:13focused and productive the best answer
  10330. 6:36:16here guys is going to be correct
  10331. 6:36:19emphasize the agenda say this is what
  10332. 6:36:21we're covering we don't want to cover uh
  10333. 6:36:24and do this at the beginning you may
  10334. 6:36:25have to do this throughout the meeting
  10335. 6:36:26too and tell people hey you know what
  10336. 6:36:29let's try to stay on topic this here
  10337. 6:36:31would solve the
  10338. 6:36:32problem although the other answers are
  10339. 6:36:35not bad I don't think the other answers
  10340. 6:36:36are terrible like a suggestion
  10341. 6:36:38box um I'm not sure about this co-
  10342. 6:36:41facilitator you should be the
  10343. 6:36:43facilitator you need another one and
  10344. 6:36:45even allocating extra time with the end
  10345. 6:36:46Delo this can speed up meetings or
  10346. 6:36:49sometimes this can make the meeting go
  10347. 6:36:50over so I think a here is the best
  10348. 6:36:54answer 198 on an agricultural
  10349. 6:36:57development project a key team member
  10350. 6:37:00expresses dissatisfaction with the
  10351. 6:37:01current risk management strategy
  10352. 6:37:04feel feeling it doesn't adequately
  10353. 6:37:06address the potential for unpredictable
  10354. 6:37:07weather conditions affecting crop
  10355. 6:37:10trials what action should the project
  10356. 6:37:12manager take first Implement a
  10357. 6:37:14contingency fund specifically for
  10358. 6:37:16weather related delays consult with the
  10359. 6:37:18external agriculture expert to gain
  10360. 6:37:20insights on managing weather related rks
  10361. 6:37:22reevaluate the risk management plan and
  10362. 6:37:24risk register with the entire team to
  10363. 6:37:25incorporate feedback on the weather
  10364. 6:37:26related risks adjust the timeline and
  10365. 6:37:29Milestone to allow for greater
  10366. 6:37:30flexibility and response to weather
  10367. 6:37:32changes best here guys is going to
  10368. 6:37:35be C is correct why is that well if
  10369. 6:37:40somebody brings up something to you
  10370. 6:37:42they're saying hey we're not adequately
  10371. 6:37:44managing risk we may not have the right
  10372. 6:37:46responses we're not be identifying them
  10373. 6:37:48fast enough for all of them what can we
  10374. 6:37:51do well bring it to the team work with
  10375. 6:37:53the entire team let them re help us
  10376. 6:37:55rebuild maybe the RIS management plan
  10377. 6:37:58let them add it to the risk register and
  10378. 6:37:59let's get their feedback in there let's
  10379. 6:38:02do this first before we go to the
  10380. 6:38:04agricultural expert or get some kind of
  10381. 6:38:07contingency fund or don't just change a
  10382. 6:38:09timeline like that that might need a
  10383. 6:38:11change request so do c before you do a b
  10384. 6:38:14or d making that the best
  10385. 6:38:17answer
  10386. 6:38:18199 a project team in a digital
  10387. 6:38:21marketing project discovers that their
  10388. 6:38:24key design software license has expired
  10389. 6:38:27Halton the team work on a critical
  10390. 6:38:29critical campaign visuals what is the
  10391. 6:38:32most effective initial action for the
  10392. 6:38:34project manager to
  10393. 6:38:36take request that the team manually
  10394. 6:38:39sketch the campaign Concepts while
  10395. 6:38:41awaiting uh this the license
  10396. 6:38:44renewal have the team work with the IT
  10397. 6:38:46department to renew the license
  10398. 6:38:47prioritize other aspects of campaign
  10399. 6:38:49that doesn't require software doesn't
  10400. 6:38:51require uh design software according
  10401. 6:38:54with it Department prompt to renew the
  10402. 6:38:55software license best answer here guys
  10403. 6:38:57is going to be D now part of being a
  10404. 6:38:59servant leader is
  10405. 6:39:02removing imp
  10406. 6:39:03removing obstacles from the team this is
  10407. 6:39:06clearly not something that's project
  10408. 6:39:08related this is more computer it related
  10409. 6:39:11computer errors and when you have
  10410. 6:39:12something like that it's your job or it
  10411. 6:39:14should be your job to help remove this
  10412. 6:39:16obstacle from the team remember the
  10413. 6:39:19concept of servant
  10414. 6:39:21leadership so in this one here you're
  10415. 6:39:23telling the team this is not optimizing
  10416. 6:39:25the work you're not giving them the
  10417. 6:39:26right tools you're see to manually do it
  10418. 6:39:29in this one here you're telling the team
  10419. 6:39:30to fix it prioritize other aspects
  10420. 6:39:33you're not addressing the problem in
  10421. 6:39:34this one here making D the best answer
  10422. 6:39:38question 200 during a during a critical
  10423. 6:39:42uh phase of a software development
  10424. 6:39:43project the key developer notifies the
  10425. 6:39:45project manager that they will need to
  10426. 6:39:47take an unexpected leave impa in the
  10427. 6:39:49completion of a crucial backlog item
  10428. 6:39:52schedule for demonstration in the
  10429. 6:39:54upcoming Sprint review what should the
  10430. 6:39:56project manager do and since the
  10431. 6:39:58developer work remotely during their
  10432. 6:40:00leave to ensure the backlog item is
  10433. 6:40:02completed on time escalate the issue to
  10434. 6:40:05Senior Management and demand the assign
  10435. 6:40:07an additional resource immediately
  10436. 6:40:09reevaluate the Sprint goals and backlog
  10437. 6:40:11priorities consult with the team about
  10438. 6:40:13adjustments
  10439. 6:40:14and communicate the revised plan to
  10440. 6:40:17stakeholders cancel the upcoming Sprint
  10441. 6:40:19review stting the lack of progress on
  10442. 6:40:21the crit on the crucial backlog item the
  10443. 6:40:24best answer here guys is going to be C
  10444. 6:40:26that is correct here's
  10445. 6:40:28why so one thing we want to talk about
  10446. 6:40:31here is you notice somebody left right
  10447. 6:40:34so they need to take expensively don't
  10448. 6:40:37make them work if they're leaving for an
  10449. 6:40:39emergency or family issues they got to
  10450. 6:40:42go you can't just tell up to work
  10451. 6:40:44remotely that might not be possible just
  10452. 6:40:47don't go to Senior Management and demand
  10453. 6:40:49things from Senior Management this just
  10454. 6:40:50sounds wrong first of all you might be
  10455. 6:40:52fired for that that leavs two things you
  10456. 6:40:55can't just cancel the Sprint the best
  10457. 6:40:56thing here is to work with the team now
  10458. 6:40:58you're re-evaluating the goals you're
  10459. 6:41:00not some people say hey Andrew you're re
  10460. 6:41:02no we're not re prioritizing the backlog
  10461. 6:41:04you're reevaluating it the only person
  10462. 6:41:07that
  10463. 6:41:08can uh rep prioritize a product owner
  10464. 6:41:11but you're Consulting with the team
  10465. 6:41:13right maybe we need to change the Sprint
  10466. 6:41:14goal that's within the team so you can
  10467. 6:41:16adjust the Sprint goals because you know
  10468. 6:41:18what you might not be able to get that
  10469. 6:41:19done with this team member
  10470. 6:41:21gone and that guys ends the 200 practice
  10471. 6:41:24questions hopefully you guys enjoyed
  10472. 6:41:26this journey hopefully you guys uh
  10473. 6:41:29really like these 200 practice questions
  10474. 6:41:31it would mean a lot to me it took me a a
  10475. 6:41:33lot of time to write this took me a lot
  10476. 6:41:34of time to present it as you can see the
  10477. 6:41:36length in this video If you
  10478. 6:41:39guys uh really enjoyed this type of
  10479. 6:41:41content give the video a like subscribe
  10480. 6:41:43to the channel would be absolutely
  10481. 6:41:44amazing it really helps us out it really
  10482. 6:41:47helps us to make our content I guess
  10483. 6:41:49gain a bigger audience which would
  10484. 6:41:51really help us out and if you want more
  10485. 6:41:53questions like this check the link below
  10486. 6:41:56we have the ti exam Simulator the
  10487. 6:41:58closest to the real exam tons of people
  10488. 6:42:00have used it over 30,000 people have
  10489. 6:42:02used that to pass their PMP exam and
  10490. 6:42:05also my 35-hour course my study guide my
  10491. 6:42:08books are all below you guys can all
  10492. 6:42:09check that out and with that in mind
  10493. 6:42:11guys hopefully you guys learned a lot in
  10494. 6:42:13this in this video and in the
  10495. 6:42:15compilation of when it's a bigger video
  10496. 6:42:17hopefully you guys learned a lot and
  10497. 6:42:19I'll see you in the next video

About this transcript

This page contains the full transcript of 200 Ultra Hard PMP Questions 1-200 by Andrew Ramdayal, generated from the public captions YouTube serves with the video. The transcript has 66,848 words across 10,497 segments, with the original timestamps preserved so you can click any line to jump to that moment in the embedded player.

What you can do with it

Use the transcript to take notes, quote the speaker, build a study guide, generate a summary with ChatGPT or Claude via the YouTube Summary tool, or export it as a timed subtitle file with YouTube to SRT. You can also re-open it in the transcriber to translate the transcript into 100+ languages.

Free YouTube transcript tool

YouTube2Text is a free YouTube transcript generator — no signup, no daily limit. Paste any YouTube link and get the full transcript instantly, with timestamps, click-to-jump, translation to 100+ languages, AI prompts for ChatGPT, Claude, and Gemini, and exports to TXT, SRT, VTT, or Markdown.